TITLE 83: PUBLIC UTILITIES
|
AUTHORITY: Implementing Section 9-201 and authorized by Section 10-101 of the Public Utilities Act [220 ILCS 5/9-201 and 10-101].
SOURCE: Adopted at 27 Ill. Reg. 12380, effective August 1, 2003.
Section 287.10 Applicability
This Part shall apply to all public utilities as defined in Section 3-105 of the Public Utilities Act (Act) [220 ILCS 5/3-105] and to those telecommunications carriers as defined in Section 13-202 of the Act [220 ILCS 5/13-202] that are subject to the requirements of Section 9-201 of the Act [220 ILCS 5/9-201] and 83 Ill. Adm. Code 285. As used in this Part, "utility" shall include both public utilities and those telecommunications carriers to which this Part is applicable.
Section 287.20 Test Year Options
A utility, at its option, may propose either one of the following periods as its proposed test year:
a) Historical. Any consecutive 12 month period, beginning no more than 24 months prior to the date of the utility's filing, for which actual data are available at the time of filing new tariffs; or
b) Future. Any consecutive 12 month period of forecasted data beginning no earlier than the date new tariffs are filed and ending no later than 24 months after the date new tariffs are filed.