| | 104TH GENERAL ASSEMBLY
State of Illinois
2025 and 2026 SB1597 Introduced 2/4/2025, by Sen. Sally J. Turner SYNOPSIS AS INTRODUCED: | | | Amends the Renewable Energy Facilities Agricultural Impact Mitigation Act. In a provision regarding agricultural impact mitigation agreements, provides that an agricultural impact mitigation agreement for a commercial energy facility shall include a provision for the prevention and remediation of soil and water contamination from the release of oil, lubricant, hydraulic fluid, transformer solvent, insulation fluid, cleaning fluid, or any other similar fluid. |
| |
| | A BILL FOR |
|
|
| | SB1597 | | LRB104 05980 BDA 16013 b |
|
|
| 1 | | AN ACT concerning agriculture. |
| 2 | | Be it enacted by the People of the State of Illinois, |
| 3 | | represented in the General Assembly: |
| 4 | | Section 5. The Renewable Energy Facilities Agricultural |
| 5 | | Impact Mitigation Act is amended by changing Section 15 as |
| 6 | | follows: |
| 7 | | (505 ILCS 147/15) |
| 8 | | Sec. 15. Agricultural impact mitigation agreement. |
| 9 | | (a) A commercial renewable energy facility owner of a |
| 10 | | commercial wind energy facility or a commercial solar energy |
| 11 | | facility that is located on landowner property shall enter |
| 12 | | into an agricultural impact mitigation agreement with the |
| 13 | | Department outlining construction and deconstruction standards |
| 14 | | and policies designed to preserve the integrity of any |
| 15 | | agricultural land that is impacted by commercial renewable |
| 16 | | energy facility construction and deconstruction. The |
| 17 | | construction and deconstruction of any commercial solar energy |
| 18 | | facility shall be in conformance with the Department's |
| 19 | | standard agricultural impact mitigation agreement referenced |
| 20 | | in subsection (f) of this Section. Except as provided in |
| 21 | | subsection (a-5) of this Section, the terms and conditions of |
| 22 | | the Department's standard agricultural impact mitigation |
| 23 | | agreement are subject to and may be modified by an underlying |
|
| | SB1597 | - 2 - | LRB104 05980 BDA 16013 b |
|
|
| 1 | | agreement between the landowner and the commercial solar |
| 2 | | energy facility owner. |
| 3 | | (a-5) Prior to the commencement of construction, a |
| 4 | | commercial solar energy facility owner shall submit to the |
| 5 | | county in which the commercial solar facility is to be located |
| 6 | | a deconstruction plan. A commercial solar energy facility |
| 7 | | owner shall provide the county with an appropriate financial |
| 8 | | assurance mechanism consistent with the Department's standard |
| 9 | | agricultural impact mitigation agreement for and to assure |
| 10 | | deconstruction in the event of an abandonment of a commercial |
| 11 | | solar energy facility. |
| 12 | | (b) The agricultural impact mitigation agreement for a |
| 13 | | commercial wind energy facility shall include, but is not |
| 14 | | limited to, such items as restoration of agricultural land |
| 15 | | affected by construction, deconstruction (including upon |
| 16 | | abandonment of a commercial wind energy facility), |
| 17 | | construction staging, and storage areas; support structures; |
| 18 | | aboveground facilities; guy wires and anchors; underground |
| 19 | | cabling depth; topsoil replacement; protection and repair of |
| 20 | | agricultural drainage tiles; rock removal; repair of |
| 21 | | compaction and rutting; land leveling; prevention of soil |
| 22 | | erosion; repair of damaged soil conservation practices; |
| 23 | | prevention and remediation of soil and water contamination |
| 24 | | from the release of oil, lubricant, hydraulic fluid, |
| 25 | | transformer solvent, insulation fluid, cleaning fluid, or any |
| 26 | | other similar fluid; compensation for damages to private |
|
| | SB1597 | - 3 - | LRB104 05980 BDA 16013 b |
|
|
| 1 | | property; clearing of trees and brush; interference with |
| 2 | | irrigation systems; access roads; weed control; pumping of |
| 3 | | water from open excavations; advance notice of access to |
| 4 | | private property; indemnification of landowners; and |
| 5 | | deconstruction plans and financial assurance for |
| 6 | | deconstruction (including upon abandonment of a commercial |
| 7 | | wind energy facility). |
| 8 | | (b-5) The agricultural impact mitigation agreement for a |
| 9 | | commercial solar energy facility shall include, but is not |
| 10 | | limited to, such items as restoration of agricultural land |
| 11 | | affected by construction, deconstruction (including upon |
| 12 | | abandonment of a commercial solar energy facility); support |
| 13 | | structures; aboveground facilities; guy wires and anchors; |
| 14 | | underground cabling depth; topsoil removal and replacement; |
| 15 | | rerouting and permanent repair of agricultural drainage tiles; |
| 16 | | rock removal; repair of compaction and rutting; construction |
| 17 | | during wet weather; land leveling; prevention of soil erosion; |
| 18 | | repair of damaged soil conservation practices; compensation |
| 19 | | for damages to private property; clearing of trees and brush; |
| 20 | | access roads; weed control; advance notice of access to |
| 21 | | private property; indemnification of landowners; and |
| 22 | | deconstruction plans and financial assurance for |
| 23 | | deconstruction (including upon abandonment of a commercial |
| 24 | | solar energy facility). The commercial solar energy facility |
| 25 | | owner shall enter into one agricultural impact mitigation |
| 26 | | agreement for each commercial solar energy facility. |
|
| | SB1597 | - 4 - | LRB104 05980 BDA 16013 b |
|
|
| 1 | | (c) For commercial wind energy facility owners seeking a |
| 2 | | permit from a county or municipality for the construction of a |
| 3 | | commercial wind energy facility, the agricultural impact |
| 4 | | mitigation agreement shall be entered into prior to the public |
| 5 | | hearing required prior to a siting decision of a county or |
| 6 | | municipality regarding the commercial wind energy facility. |
| 7 | | The agricultural impact mitigation agreement is binding on any |
| 8 | | subsequent commercial wind energy facility owner that takes |
| 9 | | ownership of the commercial wind energy facility that is the |
| 10 | | subject of the agreement. |
| 11 | | (c-5) A commercial solar energy facility owner shall, not |
| 12 | | less than 45 days prior to commencement of actual |
| 13 | | construction, submit to the Department a standard agricultural |
| 14 | | impact mitigation agreement as referenced in subsection (f) of |
| 15 | | this Section signed by the commercial solar energy facility |
| 16 | | owner and including all information required by the |
| 17 | | Department. The commercial solar energy facility owner shall |
| 18 | | provide either a copy of that submitted agreement or a copy of |
| 19 | | the fully executed project-specific agricultural impact |
| 20 | | mitigation agreement to the landowner not less than 30 days |
| 21 | | prior to the commencement of construction. The agricultural |
| 22 | | impact mitigation agreement is binding on any subsequent |
| 23 | | commercial solar energy facility owner that takes ownership of |
| 24 | | the commercial solar energy facility that is the subject of |
| 25 | | the agreement. |
| 26 | | (d) If a commercial renewable energy facility owner seeks |
|
| | SB1597 | - 5 - | LRB104 05980 BDA 16013 b |
|
|
| 1 | | an extension of a permit granted by a county or municipality |
| 2 | | for the construction of a commercial wind energy facility |
| 3 | | prior to the effective date of this Act, the agricultural |
| 4 | | impact mitigation agreement shall be entered into prior to a |
| 5 | | decision by the county or municipality to grant the permit |
| 6 | | extension. |
| 7 | | (e) The Department may adopt rules that are necessary and |
| 8 | | appropriate for the implementation and administration of |
| 9 | | agricultural impact mitigation agreements as required under |
| 10 | | this Act. |
| 11 | | (f) The Department shall make available on its website a |
| 12 | | standard agricultural impact mitigation agreement applicable |
| 13 | | to all commercial solar energy facilities within 60 days after |
| 14 | | the effective date of this amendatory Act of the 100th General |
| 15 | | Assembly. |
| 16 | | (g) Nothing in this amendatory Act of the 100th General |
| 17 | | Assembly and nothing in an agricultural impact mitigation |
| 18 | | agreement shall be construed to apply to or otherwise impair |
| 19 | | an underlying agreement for a commercial solar energy facility |
| 20 | | entered into prior to the effective date of this amendatory |
| 21 | | Act of the 100th General Assembly. |
| 22 | | (Source: P.A. 99-132, eff. 7-24-15; 100-598, eff. 6-29-18.) |