| 1 | AN ACT concerning safety. | |||||||||||||||||||
| 2 | Be it enacted by the People of the State of Illinois, | |||||||||||||||||||
| 3 | represented in the General Assembly: | |||||||||||||||||||
| 4 | Section 5. The Environmental Protection Act is amended by | |||||||||||||||||||
| 5 | adding Section 22.40c as follows: | |||||||||||||||||||
| 6 | (415 ILCS 5/22.40c new) | |||||||||||||||||||
| 7 | Sec. 22.40c. Gas Collection and Control System | |||||||||||||||||||
| 8 | Requirements. Each owner or operator of a municipal solid | |||||||||||||||||||
| 9 | waste landfill that meets 40 CFR 60.33c and relevant federal | |||||||||||||||||||
| 10 | regulatory requirements to install a gas collection and | |||||||||||||||||||
| 11 | control system must fulfill the following requirements: | |||||||||||||||||||
| 12 | (1) The owner or operator must, in the case of an | |||||||||||||||||||
| 13 | active municipal solid waste landfill, operate the gas | |||||||||||||||||||
| 14 | collection and control system so that gas is collected | |||||||||||||||||||
| 15 | from each area, cell, or group of cells in the municipal | |||||||||||||||||||
| 16 | solid waste landfill in which solid waste has been in | |||||||||||||||||||
| 17 | place for one year or more. | |||||||||||||||||||
| 18 | (2) The owner or operator must estimate when the | |||||||||||||||||||
| 19 | landfill will reach the thresholds identified in 40 CFR | |||||||||||||||||||
| 20 | 60.33c and relevant federal regulatory requirements | |||||||||||||||||||
| 21 | requiring installation of a gas collection and control | |||||||||||||||||||
| 22 | system, install a gas collection and control system within | |||||||||||||||||||
| 23 | 12 months after that estimated date, and operate the gas | |||||||||||||||||||
| |||||||
| |||||||
| 1 | collection and control system in accordance with 40 CFR | ||||||
| 2 | 60.34f. | ||||||
| 3 | (3) The gas collection and control design plan must | ||||||
| 4 | provide for whether other measures to control gas, | ||||||
| 5 | including horizontal collectors, connections to the | ||||||
| 6 | leachate control system, and electric systems that will | ||||||
| 7 | eventually connect to control devices, the vacuum system, | ||||||
| 8 | and other gas collection and control system elements, can | ||||||
| 9 | be installed before the full gas collection and control | ||||||
| 10 | system is required. | ||||||
| 11 | (4) The gas collection and control system, if it uses | ||||||
| 12 | a flare, must achieve a methane destruction efficiency of | ||||||
| 13 | at least 99% by weight. | ||||||
| 14 | (5) The gas collection system must be designed and | ||||||
| 15 | operated to draw all the gas toward the gas control device | ||||||
| 16 | or devices. | ||||||