TITLE 44: GOVERNMENT CONTRACTS, GRANTMAKING, PROCUREMENT AND PROPERTY MANAGEMENT
SUBTITLE B: SUPPLEMENTAL PROCUREMENT
CHAPTER XII: CAPITAL DEVELOPMENT BOARD
PART 990 PREQUALIFICATION OF CONSTRUCTION MANAGERS
SUBPART A: RESPONSIBILITY
Section 990.110 Purpose
Section 990.120 Definitions
Section 990.130 Prequalification Required
Section 990.140 Special Projects
Section 990.150 Confidentiality
Section 990.160 Sources for Determining Responsibility
Section 990.180 Prequalification of Firms and Office Locations
Section 990.200 Processing of Construction Manager Prequalification Application
SUBPART B: SUSPENSION, DEBARMENT, MODIFICATION OF PREQUALIFICATION, AND CONDITIONAL PREQUALIFICATION
Section 990.300 Actions Affecting Responsibility and Prequalification
Section 990.310 Causes for Suspension, Debarment, Modification of Prequalification, and Conditional Prequalification
Section 990.320 Nullification of Prequalification
Section 990.330 Failure to Satisfactorily Perform Work on or Breach of the Terms of CDB Contracts, Private Contracts, or Other Governmental Contracts
Section 990.340 Interim or Emergency Suspension or Modification Pursuant to Section 16 of the Capital Development Board Act
Section 990.350 Denial of Prequalification
SUBPART C: APPLICATION OF CDB ACTION
Section 990.400 General
Section 990.410 Violation of CDB Order
Section 990.420 Denial of Award of Contract
Section 990.430 Debarment
Section 990.440 Reapplication for Prequalification
Section 990.450 Extension of CDB Action
Section 990.460 Effect on Current Contracts
Section 990.470 Basis of Decisions
Section 990.480 Settlement
SUBPART D: PROCEDURES
Section 990.500 Review
Section 990.510 Notice of CDB Action
Section 990.520 Executive Director Decision and Request for Reconsideration
Section 990.530 Hearings
Section 990.540 Burden of Proof
AUTHORITY: Implementing the Capital Development Board Act [20 ILCS 3105] and authorized by Section 16 of that Act and Sections 5-25, 30-20 and 33-5 of the Illinois Procurement Code [30 ILCS 500/5-25, 30-20 and 33-5].
SOURCE: Adopted at 31 Ill. Reg. 12173, effective August 2, 2007; recodified Title of the Part at 39 Ill. Reg. 5903.
SUBPART A: RESPONSIBILITY
Section 990.110 Purpose
The Capital Development Board construction management agreements shall be awarded only to prequalified construction managers. An applicant for prequalification must affirmatively demonstrate its responsibility. In the absence of information clearly indicating that the applicant is responsible, CDB shall make a determination of non-responsibility. Only responsible construction managers shall be prequalified and permitted to make submittals on CDB projects.