TITLE 8: AGRICULTURE AND ANIMALS
CHAPTER I: DEPARTMENT OF AGRICULTURE SUBCHAPTER t: WASTE MANAGEMENT PART 900 LIVESTOCK MANAGEMENT FACILITY REGULATIONS SECTION 900.703 LEVEL OF SURETY
Section 900.703 Level of Surety
a) The level of surety is determined by the following formula:
Level of Surety = (V x CF) + EC
where:
b) The cost factor is obtained from the following:
1) Through December 31, 2002, the cost factor is 10 cents per cubic foot of lagoon volume.
2) On and after January 1, 2003 through December 31, 2007, the cost factor is 12 cents per cubic foot of lagoon volume.
3) On and after January 1, 2008, the cost factor is 15 cents per cubic foot of lagoon volume.
c) The engineering contingency is equal to 10% of (V x CF). |