TITLE 35: ENVIRONMENTAL PROTECTION
SUBTITLE G: WASTE DISPOSAL
CHAPTER I: POLLUTION CONTROL BOARD
SUBCHAPTER b: PERMITS
PART 705 PROCEDURES FOR PERMIT ISSUANCE
SECTION 705.126 DECISION SCHEDULE


 

Section 705.126  Decision Schedule

 

For each permit application from a major new HWM facility or major new UIC injection well, the Agency must, no later than the effective date of the application, prepare and mail to the applicant a projected decision schedule.  The schedule must specify target dates by which the Agency intends to do the following:

 

a)         Prepare a draft permit pursuant to Subpart C;

 

b)         Give public notice pursuant to Subpart D;

 

c)         Complete the public comment period, including any public hearing pursuant to Subpart E; and

 

d)         Issue a final permit pursuant to Subpart F.

 

BOARD NOTE:  Derived from 40 CFR 124.3(g) (2017).

 

(Source:  Amended at 42 Ill. Reg. 21179, effective November 19, 2018)