(220 ILCS 50/6) (from Ch. 111 2/3, par. 1606)
    Sec. 6. Emergency excavation or demolition.
    (a) Every person who engages in emergency excavation or demolition outside of the boundaries of a municipality of at least one million persons which operates its own one-call notice system shall take all reasonable precautions to avoid or minimize interference between the emergency work and existing underground utility facilities in and near the excavation or demolition area, through the State-Wide One-Call Notice System, and shall notify, as far in advance as possible, the owners or operators of such underground utility facilities in and near the emergency excavation or demolition area, through the State-Wide One-Call Notice System. At a minimum, the notice required under this subsection (a) shall provide:
        (1) the person's name, address, and (i) phone number at which a person can be reached
    
and (ii) fax number, if available;
        (2) the start date of the planned emergency excavation or demolition;
        (3) the address at which the excavation or demolition will take place; and
        (4) the type and extent of the work involved.
    There is a wait time of 2 hours or the date and time requested on the notice, whichever is longer, after an emergency locate notification request is made through the State-Wide One-Call Notice System. If the conditions at the site dictate an earlier start than the required wait time, it is the responsibility of the excavator to demonstrate that site conditions warranted this earlier start time.
    Upon notice by the person engaged in emergency excavation or demolition, the owner or operator of an underground utility facility in or near the excavation or demolition area shall communicate with the person engaged in emergency excavation or demolition within 2 hours or by the date and time requested on the notice, whichever is longer by (1) marking the approximate location of underground facilities; (2) advising the person excavating that their underground facilities are not in conflict with the emergency excavation; or (3) notifying the person excavating that the owner or operator shall be delayed in marking because of conditions as referenced in subsection (g) of Section 11 of this Act.
    The notice by the owner or operator to the person engaged in emergency excavation or demolition may be provided by phone or phone message or by marking the excavation or demolition area. The owner or operator has discharged the owner's or operator's obligation to provide notice under this Section if the owner or operator attempts to provide notice by telephone but is unable to do so because the person engaged in the emergency excavation or demolition does not answer his or her telephone or does not have an answering machine or answering service to receive the telephone call. If the owner or operator attempts to provide notice by telephone or by facsimile but receives a busy signal, that attempt shall not discharge the owner or operator from the obligation to provide notice under this Section.
    (b) Every person who engages in emergency excavation or demolition within the boundaries of a municipality of at least one million persons which operates its own one-call notice system shall take all reasonable precautions to avoid or minimize interference between the emergency work and existing underground utility facilities in and near the excavation or demolition area, through the municipality's one-call notice system, and shall notify, as far in advance as possible, the owners and operators of underground utility facilities in and near the emergency excavation or demolition area, through the municipality's one-call notice system.
    (c) The reinstallation of traffic control devices shall be deemed an emergency for purposes of this Section.
    (d) An open cut utility locate shall be deemed an emergency for purposes of this Section.
(Source: P.A. 96-714, eff. 1-1-10.)