TITLE 35: ENVIRONMENTAL PROTECTION
SUBTITLE B: AIR POLLUTION CHAPTER I: POLLUTION CONTROL BOARD SUBCHAPTER a: PERMITS AND GENERAL PROVISIONS PART 201 PERMITS AND GENERAL PROVISIONS SECTION 201.APPENDIX C PART COMPLIANCE DATES
Section 201.APPENDIX C Part Compliance Dates
Rule 103(b)(2)
Operating permits were required as follows:
(B) All applications for Operating Permits shall be submitted to the Agency at least 90 days prior to the date on which an Operating Permit is required. Provided, however, the Agency may waive this 90 day requirement when appropriate. If necessary, to prevent an unmanageable workload as may be deemed appropriate, the Agency may extend the dates by which Operating Permits are required under Section 103(b)(2)(A) for a period not to exceed four months. The Agency shall notify the persons affected and the Board in writing of the extension at least four months before the dates set forth in Section 103(b)(2)(A). (C) Nothing in this Rule shall preclude any person from applying for an Operating Permit earlier than the dates specified in part (b)(2)(A) of this Rule 103.
Rule 103(b)(6)(G)
No operating permit could be granted unless the applicant submitted proof to the Agency that:
if subject to a future compliance date, the applicant was, on the effective date of this Chapter, and is at the time of application for an Operating Permit pursuant to Rule 103(b)(2), in compliance with any applicable emission standards of the Rules and Regulations Governing the Control of Air Pollution of the former State of Illinois Air Pollution Control Board; or was, on the effective date of this Chapter, in full compliance with any variance from those regulations granted by the Pollution Control Board; or has been, since the effective date of this Chapter, granted a variance from those regulations, and is in full compliance with such variance.
Rule 104(g)
Submission and Approval Dates. The owner or operator of an emission source subject to the following rules was required to have a Compliance Plan and a Project Completion Schedule, where applicable, approved by the Agency by the following dates. A Compliance Plan and a Project Completion Schedule, where applicable, shall be submitted at least 90 days before the following dates. (1) By February 1, 1980. Gasoline Dispensing facilities subject to Rule 205(p) and degreasers subject to Rule 205(k) located in Cook, DuPage, Lake, Kane, McHenry and Will counties. (2) By March 1, 1980. Petroleum refineries subject to Rule 205(1), except (1) (4)-(10). Gasoline dispensing facilities subject to Rule 205(p) in Boone, Madison, St. Clair, Peoria, Tazewell, Rock Island and Winnebago counties. (3) By April 1, 1980. Degreasers subject to Rule 205(k) located in counties other than Cook, DuPage, Lake, Kane, McHenry or Will. Bulk gasoline plants, bulk gasoline terminals and petroleum liquid storage tanks subject to Rule 205(o), except (o) (3), located in Cook, DuPage, Lake, Kane, McHenry and Will counties. (4) By April 1, 1980. Coating lines subject to Rule 205(n), except (n)(1)(J), and (K). Bulk gasoline plants, bulk gasoline terminals and petroleum liquid storage tanks subject to Rule 205(o), except (o)(3), which are located in counties other than Cook, Lake, DuPage, Kane, McHenry or Will. |