TITLE 35: ENVIRONMENTAL PROTECTION
SUBTITLE B: AIR POLLUTION
CHAPTER I: POLLUTION CONTROL BOARD
SUBCHAPTER c: EMISSIONS STANDARDS AND LIMITATIONS FOR STATIONARY SOURCES
PART 215 ORGANIC MATERIAL EMISSION STANDARDS AND LIMITATIONS
SECTION 215.407 COMPLIANCE PLAN


 

Section 215.407  Compliance Plan

 

a)         The owner or operator of an emission source subject to Section 215.405(a)(1) shall submit to the Agency a compliance plan, pursuant to 35 Ill. Adm. Code 201, Subpart H, including a project completion schedule where applicable, no later than April 21, 1983.

 

b)         The owner or operator of an emission source subject to Section 215.405(b) shall submit to the Agency a compliance plan, including a project completion schedule where applicable, no later than December 31, 1986.

 

c)         The owner or operator of an emission source subject to Section 215.405(c) shall submit a compliance plan, including a project completion schedule within 90 days after the date of redesignation, but in no case later than December 31, 1986.

 

d)         Unless the submitted compliance plan or schedule is disapproved by the Agency, the owner or operator of a facility or emission source subject to the rules specified in subsections (a), (b) or (c) may operate the emission source according to the plan and schedule as submitted.

 

e)         The plan and schedule shall meet the requirements of 35 Ill. Adm. Code 201, Subpart H, including specific interim dates as required in 35 Ill. Adm. Code 201.242.

 

(Source:  Amended at 11 Ill. Reg. 16706, effective September 30, 1987)