TITLE 35: ENVIRONMENTAL PROTECTION
SUBTITLE J: CLEAN CONSTRUCTION OR DEMOLITION DEBRIS
CHAPTER II: ENVIRONMENTAL PROTECTION AGENCY
PART 1150 PROCEDURES FOR OPERATION OF THE CLEAN CONSTRUCTION OR DEMOLITION DEBRIS FILL OPERATION FEE SYSTEM
SECTION 1150.300 QUARTERLY SUBMISSION OF PAYMENT


 

Section 1150.300  Quarterly Submission of Payment

 

a)         Payment of the fee due under Section 22.51b of the Act must be made on a quarterly basis with the submission of the Quarterly Fill Summary. The payment must be received by the Agency on or before April 15, July 15, October 15 and January 15 of each year and must cover the preceding three calendar months.

 

b)         The fee payment due must be calculated by multiplying the quantity of CCDD and uncontaminated soil accepted for use as fill material, in tons weighed or cubic yards measured, as reported on the Quarterly Fill Summary, times the applicable rate in Section 22.51b of the Act.