SECTION 285.2060 SCHEDULE B-7.1: CONSTRUCTION WORK IN PROGRESS PERCENT COMPLETE


Section 285.2060  Schedule B-7.1: Construction Work in Progress Percent Complete

 

a)         For the projects identified in Schedule B-7, provide information to determine the estimated percent complete, or for a future test year, expected to be complete, at the end of the test year.

 

b)         Information provided shall include:

 

1)         Project number;

 

2)         Description of project;

 

3)         Date project started;

 

4)         Most recent estimated project completion date;

 

5)         Original budget estimate;

 

6)         Most recent revised estimate;

 

7)         Accumulated construction costs; and

 

8)         Percent complete (the amount in subsection (b)(7) divided by the amount in subsection (b)(6) x 100).