TITLE 83: PUBLIC UTILITIES
CHAPTER I: ILLINOIS COMMERCE COMMISSION SUBCHAPTER b: PROVISIONS APPLICABLE TO MORE THAN ONE KIND OF UTILITY PART 285 STANDARD INFORMATION REQUIREMENTS FOR PUBLIC UTILITIES AND TELECOMMUNICATIONS CARRIERS IN FILING FOR AN INCREASE IN RATES SECTION 285.2060 SCHEDULE B-7.1: CONSTRUCTION WORK IN PROGRESS PERCENT COMPLETE Section 285.2060 Schedule B-7.1: Construction Work in Progress Percent Complete
a) For the projects identified in Schedule B-7, provide information to determine the estimated percent complete, or for a future test year, expected to be complete, at the end of the test year.
b) Information provided shall include:
1) Project number;
2) Description of project;
3) Date project started;
4) Most recent estimated project completion date;
5) Original budget estimate;
6) Most recent revised estimate;
7) Accumulated construction costs; and
8) Percent complete (the amount in subsection (b)(7) divided by the amount in subsection (b)(6) x 100).
|