|
Public Act 100-0376 |
HB2664 Enrolled | LRB100 08773 MLM 18912 b |
|
|
AN ACT concerning finance.
|
Be it enacted by the People of the State of Illinois,
|
represented in the General Assembly:
|
Section 5. The State Prompt Payment Act is amended by |
changing Section 7 as follows:
|
(30 ILCS 540/7)
(from Ch. 127, par. 132.407)
|
Sec. 7. Payments to subcontractors and material suppliers. |
(a) When a State official or agency responsible for |
administering a
contract submits a voucher to the Comptroller |
for
payment to a contractor, that State official or agency |
shall promptly make
available electronically
the voucher |
number, the date of the voucher, and
the amount of the voucher.
|
The State official or agency responsible for administering the |
contract shall
provide subcontractors and material suppliers, |
known to the State official or
agency, with instructions on how |
to access the electronic information. |
(a-5) When a
contractor receives any payment, the |
contractor shall
pay each subcontractor and material supplier |
in proportion to the work
completed by each subcontractor and |
material supplier its their application or pay estimate , plus |
interest received under this Act ,
less any retention . When a |
contractor receives any payment, the contractor shall pay each |
lower-tiered subcontractor and material supplier and each |
|
subcontractor and material supplier shall make payment to its |
own respective subcontractors and material suppliers. If the |
contractor receives less than the full payment
due under the |
public construction contract, the contractor shall be
|
obligated to disburse on a pro rata basis those funds received, |
plus interest received under this Act, with the
contractor, |
subcontractors and material suppliers each receiving a |
prorated
portion based on the amount of payment each has |
earned . When, however, the State official or agency public |
owner
does not release the full payment due under the contract |
because there are
specific areas of work or materials the State |
agency or official has determined contractor is rejecting or |
because
the contractor has otherwise determined such areas are |
not suitable for
payment, then those specific subcontractors or |
material suppliers involved shall not
be paid for that portion |
of work rejected or deemed not suitable for
payment and all |
other subcontractors and suppliers shall be paid based upon the |
amount of payment each has earned in full , plus interest |
received under this Act.
|
(a-10) For construction contracts with the Department of |
Transportation, the contractor, subcontractor, or material |
supplier, regardless of tier, shall not offset, decrease, or |
diminish payment or payments that are due to its subcontractors |
or material suppliers without reasonable cause. |
A contractor, who refuses to make prompt payment, in whole |
or in part, shall provide to the subcontractor or material |
|
supplier and the public owner or its agent, a written notice of |
that refusal. The written notice shall be made by a contractor |
no later than 5 calendar days after payment is received by the |
contractor. The written notice shall identify the Department of |
Transportation's contract, any subcontract or material |
purchase agreement, a detailed reason for refusal, the value of |
the payment to be withheld, and the specific remedial actions |
required of the subcontractor or material supplier so that |
payment may be made. Written notice of refusal may be given in |
a form and method which is acceptable to the parties and public |
owner. |
(b) If the contractor, without reasonable cause, fails to |
make full payment of amounts due under subsection (a) to its
|
his subcontractors and material suppliers within 15 calendar |
days after
receipt of
payment from the State official or agency |
under the public construction contract , the contractor shall |
pay to its
his subcontractors and material suppliers, in |
addition to the payment due
them, interest in the amount of
2% |
per month, calculated from the
expiration of the 15-day period |
until fully paid. This subsection shall further
also apply to |
any payments made by subcontractors and material suppliers to
|
their subcontractors and material suppliers and to all payments |
made to
lower tier subcontractors and material suppliers |
throughout the contracting
chain.
|
(1) If a contractor, without reasonable cause, fails to |
make payment in
full as
provided in subsection (a-5) (a) |
|
within 15 calendar days after receipt of payment under the
|
public
construction contract, any subcontractor or |
material supplier to whom payments
are owed
may file a |
written notice and request for administrative hearing with |
the State official or agency setting forth the
amount owed |
by
the contractor and the contractor's failure to timely |
pay the amount owed. The written notice and request for |
administrative hearing shall identify the public |
construction contract, the contractor, and the amount |
owed, and shall contain a sworn statement or attestation to |
verify the accuracy of the notice. The notice and request |
for administrative hearing shall be filed with the State |
official for the public construction contract, with a copy |
of the notice concurrently provided to the contractor. |
Notice to the State official may be made by certified or |
registered mail, messenger service, or personal service, |
and must include proof of delivery to the State official.
|
(2) The State official or agency, within 15 calendar |
days after receipt of a
subcontractor's
or material |
supplier's written notice and request for administrative |
hearing of the failure to receive payment from
the |
contractor ,
shall hold a hearing convened by an |
administrative law judge to determine whether the |
contractor withheld payment,
without
reasonable cause, |
from the subcontractors or and material suppliers and what
|
amount, if any,
is due to the subcontractors or and |
|
material suppliers , and the reasonable cause or causes |
asserted by the contractor . The State official or
agency |
shall
provide appropriate notice to the parties of the |
date, time, and location of
the hearing. Each contractor, |
subcontractor, or and material supplier has the right to be |
represented by counsel at a the hearing and to |
cross-examine witnesses and challenge documents. Upon the |
request of the subcontractor or material supplier and a |
showing of good cause, reasonable continuances may be |
granted by the administrative law judge.
|
(3) Upon If there is a finding by the administrative |
law judge that the contractor failed
to make
payment in |
full, without reasonable cause, as provided in subsection |
(a-10) (a) , then
the administrative law judge shall, in |
writing, order direct the contractor to pay the amount
owed |
to the
subcontractors or and material suppliers plus |
interest within 15 calendar days after the order
finding .
|
(4) If a contractor fails to make full payment as |
ordered under paragraph (3) of this subsection (b) within |
15 days after the
administrative law judge's order finding , |
then the contractor shall be barred from
entering into a |
State
public construction contract for a period of one year |
beginning on the date of
the administrative law judge's |
order finding .
|
(5) If, on 2 or more occasions within a 3-calendar-year |
period, there is a finding by an administrative law judge |
|
that the contractor failed to make payment in full, without |
reasonable cause, and a written order was issued to a |
contractor under paragraph (3) of this subsection (b), then |
the contractor shall be barred from entering into a State |
public construction contract for a period of 6 months |
beginning on the date of the administrative law judge's |
second written order, even if the payments required under |
the orders were made in full. |
(6) If a contractor fails to make full payment as |
ordered under paragraph (4) of this subsection (b), the |
subcontractor or material supplier may, within 30 days of |
the date of that order, petition the State agency for an |
order for reasonable attorney's fees and costs incurred in |
the prosecution of the action under this subsection (b). |
Upon that petition and taking of additional evidence, as |
may be required, the administrative law judge may issue a |
supplemental order directing the contractor to pay those |
reasonable attorney's fees and costs. |
(7) The written order of the administrative law judge |
shall be final and appealable under the Administrative |
Review Law. |
(c) This Section shall not be construed to in any manner |
diminish, negate, or interfere with the |
contractor-subcontractor or contractor-material supplier |
relationship or commercially useful function. |
(d) This Section shall not preclude, bar, or stay the |
|
rights, remedies, and defenses available to the parties by way |
of the operation of their contract, purchase agreement, the |
Mechanics Lien Act, or the Public Construction Bond Act. |
(e) State officials and agencies may adopt rules as may be |
deemed necessary in order to establish the formal procedures |
required under this Section. |
(f) As used in this Section, |
"Payment" means the discharge of an obligation in money or |
other valuable consideration or thing delivered in full or |
partial satisfaction of an obligation to pay. "Payment" shall |
include interest paid pursuant to this Act. |
"Reasonable cause" may include, but is not limited to, |
unsatisfactory workmanship or materials; failure to provide |
documentation required by the contract, subcontract, or |
material purchase agreement; claims made against the |
Department of Transportation or the subcontractor pursuant to |
subsection (c) of Section 23 of the Mechanics Lien Act or the |
Public Construction Bond Act; judgments, levies, garnishments, |
or other court-ordered assessments or offsets in favor of the |
Department of Transportation or other State agency entered |
against a subcontractor or material supplier. "Reasonable |
cause" does not include payments issued to the contractor that |
create a negative or reduced valuation pay application or pay |
estimate due to a reduction of contract quantities or work not |
performed or provided by the subcontractor or material |
supplier; the interception or withholding of funds for reasons |
|
not related to the subcontractor's or material supplier's work |
on the contract; anticipated claims or assessments of third |
parties not a party related to the contract or subcontract; |
asserted claims or assessments of third parties that are not |
authorized by court order, administrative tribunal, or |
statute. "Reasonable cause" further does not include the |
withholding, offset, or reduction of payment, in whole or in |
part, due to the assessment of liquidated damages or penalties |
assessed by the Department of Transportation against the |
contractor, unless the subcontractor's performance or supplied |
materials were the sole and proximate cause of the liquidated |
damage or penalty. |
(Source: P.A. 94-672, eff. 1-1-06; 94-972, eff. 7-1-07 .)
|