Public Act 096-0306 |
||||
| ||||
| ||||
AN ACT concerning local government.
| ||||
Be it enacted by the People of the State of Illinois,
| ||||
represented in the General Assembly:
| ||||
Section 5. The Counties Code is amended by changing Section | ||||
5-12020 as follows: | ||||
(55 ILCS 5/5-12020) | ||||
Sec. 5-12020. Wind farms. A county may establish standards | ||||
for wind farms and electric-generating wind devices. The | ||||
standards may include, without limitation, the height of the | ||||
devices and the number of devices that may be located within a | ||||
geographic area. A county may also regulate the siting of wind | ||||
farms and electric-generating wind devices in unincorporated | ||||
areas of the county outside of the zoning jurisdiction of a | ||||
municipality and the 1.5 mile radius surrounding the zoning | ||||
jurisdiction of a municipality. There shall be at least one | ||||
public hearing not more than 30 days prior to a siting decision | ||||
by the county board. Notice of the hearing shall be published | ||||
in a newspaper of general circulation in the county. Counties | ||||
may allow test wind towers to be sited without formal approval | ||||
by the county board. Test wind towers must be dismantled within | ||||
3 years of installation. For the purposes of this Section, | ||||
"test wind towers" are wind towers that are designed solely to | ||||
collect wind generation data. Any provision of a county zoning |
ordinance pertaining to wind farms that is in effect before the | ||
effective date of this amendatory Act of the 95th General | ||
Assembly may continue in effect notwithstanding any | ||
requirements of this Section. | ||
A county may not require a wind tower or other renewable | ||
energy system that is used exclusively by an end user to be | ||
setback more than 1.1 times the height of the renewable energy | ||
system from the end user's property line.
| ||
(Source: P.A. 95-203, eff. 8-16-07.) | ||
Section 10. The Illinois Municipal Code is amended by | ||
changing Section 11-13-26 as follows: | ||
(65 ILCS 5/11-13-26) | ||
Sec. 11-13-26. Wind farms. | ||
(a) A municipality may regulate wind farms and | ||
electric-generating wind devices within its zoning | ||
jurisdiction and within the 1.5 mile radius surrounding its | ||
zoning jurisdiction. There shall be at least one public hearing | ||
not more than 30 days prior to a siting decision by the | ||
corporate authorities of a municipality. Notice of the hearing | ||
shall be published in a newspaper of general circulation in the | ||
municipality. A municipality may allow test wind towers to be | ||
sited without formal approval by the corporate authorities of | ||
the municipality. Test wind towers must be dismantled within 3 | ||
years of installation. For the purposes of this Section, "test |
wind towers" are wind towers that are designed solely to | ||
collect wind generation data.
| ||
(b) A municipality may not require a wind tower or other | ||
renewable energy system that is used exclusively by an end user | ||
to be setback more than 1.1 times the height of the renewable | ||
energy system from the end user's property line. A setback | ||
requirement imposed by a municipality on a renewable energy | ||
system may not be more restrictive than as provided under this | ||
subsection. This subsection is a limitation of home rule powers | ||
and functions under subsection (i) of Section 6 of Article VII | ||
of the Illinois Constitution on the concurrent exercise by home | ||
rule units of powers and functions exercised by the State. | ||
(Source: P.A. 95-203, eff. 8-16-07.)
|