1 | AN ACT concerning finance.
| |||||||||||||||||||
2 | Be it enacted by the People of the State of Illinois,
| |||||||||||||||||||
3 | represented in the General Assembly:
| |||||||||||||||||||
4 | Section 5. The State Prompt Payment Act is amended by | |||||||||||||||||||
5 | changing Section 7 as follows:
| |||||||||||||||||||
6 | (30 ILCS 540/7)
(from Ch. 127, par. 132.407)
| |||||||||||||||||||
7 | Sec. 7. Payments to subcontractors and material suppliers. | |||||||||||||||||||
8 | (a) When a State official or agency responsible for | |||||||||||||||||||
9 | administering a
contract submits a voucher to the Comptroller | |||||||||||||||||||
10 | for
payment to a contractor, that State official or agency | |||||||||||||||||||
11 | shall promptly make
available electronically
the voucher | |||||||||||||||||||
12 | number, the date of the voucher, and
the amount of the voucher.
| |||||||||||||||||||
13 | The State official or agency responsible for administering the | |||||||||||||||||||
14 | contract shall
provide subcontractors and material suppliers, | |||||||||||||||||||
15 | known to the State official or
agency, with instructions on how | |||||||||||||||||||
16 | to access the electronic information. When a
contractor | |||||||||||||||||||
17 | receives any payment, the contractor shall
pay each | |||||||||||||||||||
18 | subcontractor and material supplier in proportion to the work
| |||||||||||||||||||
19 | completed by each subcontractor and material supplier their | |||||||||||||||||||
20 | application, plus interest received under this Act,
less any | |||||||||||||||||||
21 | retention. If the contractor receives less than the full | |||||||||||||||||||
22 | payment
due under the public construction contract, the | |||||||||||||||||||
23 | contractor shall be
obligated to disburse on a pro rata basis |
| |||||||
| |||||||
1 | those funds received, plus interest received under this Act, | ||||||
2 | with the
contractor, subcontractors and material suppliers | ||||||
3 | each receiving a prorated
portion based on the amount of | ||||||
4 | payment. When, however, the public owner
does not release the | ||||||
5 | full payment due under the contract because there are
specific | ||||||
6 | areas of work or materials the contractor is rejecting or | ||||||
7 | because
the contractor has otherwise determined such areas are | ||||||
8 | not suitable for
payment, then those specific subcontractors or | ||||||
9 | suppliers involved shall not
be paid for that portion of work | ||||||
10 | rejected or deemed not suitable for
payment and all other | ||||||
11 | subcontractors and suppliers shall be paid in full, plus | ||||||
12 | interest received under this Act.
| ||||||
13 | A contractor may require either a performance bond or | ||||||
14 | retention of payment of a subcontractor as part of the | ||||||
15 | subcontract. However, a contractor may not require both. | ||||||
16 | (b) If the contractor, without reasonable cause, fails to | ||||||
17 | make full payment of amounts due under subsection (a) to
his | ||||||
18 | subcontractors and material suppliers within 15 days after
| ||||||
19 | receipt of
payment under the public construction contract, the | ||||||
20 | contractor shall pay to
his subcontractors and material | ||||||
21 | suppliers, in addition to the payment due
them, interest in the | ||||||
22 | amount of
2% per month, calculated from the
expiration of the | ||||||
23 | 15-day period until fully paid. This subsection shall
also | ||||||
24 | apply to any payments made by subcontractors and material | ||||||
25 | suppliers to
their subcontractors and material suppliers and to | ||||||
26 | all payments made to
lower tier subcontractors and material |
| |||||||
| |||||||
1 | suppliers throughout the contracting
chain.
| ||||||
2 | (1) If a contractor, without reasonable cause, fails to | ||||||
3 | make payment in
full as
provided in subsection (a) within | ||||||
4 | 15 days after receipt of payment under the
public
| ||||||
5 | construction contract, any subcontractor or material | ||||||
6 | supplier to whom payments
are owed
may file a written | ||||||
7 | notice with the State official or agency setting forth the
| ||||||
8 | amount owed by
the contractor and the contractor's failure | ||||||
9 | to timely pay the amount owed.
| ||||||
10 | (2) The State official or agency, within 15 days after | ||||||
11 | receipt of a
subcontractor's
or material supplier's | ||||||
12 | written notice of the failure to receive payment from
the | ||||||
13 | contractor,
shall hold a hearing convened by an | ||||||
14 | administrative law judge to determine whether the | ||||||
15 | contractor withheld payment,
without
reasonable cause, | ||||||
16 | from the subcontractors and material suppliers and what
| ||||||
17 | amount, if any,
is due to the subcontractors and material | ||||||
18 | suppliers. The State official or
agency shall
provide | ||||||
19 | appropriate notice to the parties of the date, time, and | ||||||
20 | location of
the hearing. Each contractor, subcontractor, | ||||||
21 | and material supplier has the right to be represented by | ||||||
22 | counsel at the hearing and to cross-examine witnesses and | ||||||
23 | challenge documents.
| ||||||
24 | (3) If there is a finding by the administrative law | ||||||
25 | judge that the contractor failed
to make
payment in full, | ||||||
26 | without reasonable cause, as provided in subsection (a), |
| |||||||
| |||||||
1 | then
the administrative law judge shall, in writing, direct | ||||||
2 | the contractor to pay the amount
owed to the
subcontractors | ||||||
3 | and material suppliers plus interest within 15 days after | ||||||
4 | the
finding.
| ||||||
5 | (4) If a contractor fails to make full payment within | ||||||
6 | 15 days after the
administrative law judge's finding, then | ||||||
7 | the contractor shall be barred from
entering into a State
| ||||||
8 | public construction contract for a period of one year | ||||||
9 | beginning on the date of
the administrative law judge's | ||||||
10 | finding.
| ||||||
11 | (Source: P.A. 94-672, eff. 1-1-06; 94-972, eff. 7-1-07 .)
|