| | SB2591 Engrossed | | LRB100 17172 SLF 32327 b |
|
|
1 | | AN ACT concerning agriculture.
|
2 | | Be it enacted by the People of the State of Illinois,
|
3 | | represented in the General Assembly:
|
4 | | Section 5. The Counties Code is amended by changing Section |
5 | | 5-12020 as follows: |
6 | | (55 ILCS 5/5-12020) |
7 | | Sec. 5-12020. Wind farms. Notwithstanding any other |
8 | | provision of law, a county may establish standards for wind |
9 | | farms and electric-generating wind devices. The standards may |
10 | | include, without limitation, the height of the devices and the |
11 | | number of devices that may be located within a geographic area. |
12 | | A county may also regulate the siting of wind farms and |
13 | | electric-generating wind devices in unincorporated areas of |
14 | | the county outside of the zoning jurisdiction of a municipality |
15 | | and the 1.5 mile radius surrounding the zoning jurisdiction of |
16 | | a municipality. There shall be at least one public hearing not |
17 | | more than 30 days prior to a siting decision by the county |
18 | | board. Notice of the hearing shall be published in a newspaper |
19 | | of general circulation in the county. A commercial wind energy |
20 | | facility owner, as defined in the Renewable Wind Energy |
21 | | Facilities Agricultural Impact Mitigation Act, must enter into |
22 | | an agricultural impact mitigation agreement with the |
23 | | Department of Agriculture prior to the date of the required |
|
| | SB2591 Engrossed | - 2 - | LRB100 17172 SLF 32327 b |
|
|
1 | | public hearing. A commercial wind energy facility owner seeking |
2 | | an extension of a permit granted by a county prior to July 24, |
3 | | 2015 (the effective date of Public Act 99-132) must enter into |
4 | | an agricultural impact mitigation agreement with the |
5 | | Department of Agriculture prior to a decision by the county to |
6 | | grant the permit extension. Counties may allow test wind towers |
7 | | to be sited without formal approval by the county board. Any |
8 | | provision of a county zoning ordinance pertaining to wind farms |
9 | | that is in effect before August 16, 2007 (the effective date of |
10 | | Public Act 95-203) may continue in effect notwithstanding any |
11 | | requirements of this Section. |
12 | | A county may not require a wind tower or other renewable |
13 | | energy system that is used exclusively by an end user to be |
14 | | setback more than 1.1 times the height of the renewable energy |
15 | | system from the end user's property line.
|
16 | | (Source: P.A. 99-123, eff. 1-1-16; 99-132, eff. 7-24-15; |
17 | | 99-642, eff. 7-28-16.) |
18 | | Section 10. The Illinois Municipal Code is amended by |
19 | | changing Section 11-13-26 as follows: |
20 | | (65 ILCS 5/11-13-26) |
21 | | Sec. 11-13-26. Wind farms. Notwithstanding any other |
22 | | provision of law: |
23 | | (a) A municipality may regulate wind farms and |
24 | | electric-generating wind devices within its zoning |
|
| | SB2591 Engrossed | - 3 - | LRB100 17172 SLF 32327 b |
|
|
1 | | jurisdiction and within the 1.5 mile radius surrounding its |
2 | | zoning jurisdiction. There shall be at least one public |
3 | | hearing not more than 30 days prior to a siting decision by |
4 | | the corporate authorities of a municipality. Notice of the |
5 | | hearing shall be published in a newspaper of general |
6 | | circulation in the municipality. A commercial wind energy |
7 | | facility owner, as defined in the Renewable Wind Energy |
8 | | Facilities Agricultural Impact Mitigation Act, must enter |
9 | | into an agricultural impact mitigation agreement with the |
10 | | Department of Agriculture prior to the date of the required |
11 | | public hearing. A commercial wind energy facility owner |
12 | | seeking an extension of a permit granted by a municipality |
13 | | prior to July 24, 2015 (the effective date of Public Act |
14 | | 99-132) must enter into an agricultural impact mitigation |
15 | | agreement with the Department of Agriculture prior to a |
16 | | decision by the municipality to grant the permit extension. |
17 | | A municipality may allow test wind towers to be sited |
18 | | without formal approval by the corporate authorities of the |
19 | | municipality. Test wind towers must be dismantled within 3 |
20 | | years of installation. For the purposes of this Section, |
21 | | "test wind towers" are wind towers that are designed solely |
22 | | to collect wind generation data.
|
23 | | (b) A municipality may not require a wind tower or |
24 | | other renewable energy system that is used exclusively by |
25 | | an end user to be setback more than 1.1 times the height of |
26 | | the renewable energy system from the end user's property |
|
| | SB2591 Engrossed | - 4 - | LRB100 17172 SLF 32327 b |
|
|
1 | | line. A setback requirement imposed by a municipality on a |
2 | | renewable energy system may not be more restrictive than as |
3 | | provided under this subsection. This subsection is a |
4 | | limitation of home rule powers and functions under |
5 | | subsection (i) of Section 6 of Article VII of the Illinois |
6 | | Constitution on the concurrent exercise by home rule units |
7 | | of powers and functions exercised by the State. |
8 | | (Source: P.A. 99-123, eff. 1-1-16; 99-132, eff. 7-24-15; |
9 | | 99-642, eff. 7-28-16.) |
10 | | Section 15. The Wind Energy Facilities Agricultural Impact |
11 | | Mitigation Act is amended by changing Sections 1, 5, 10, and 15 |
12 | | as follows: |
13 | | (505 ILCS 147/1)
|
14 | | Sec. 1. Short title. This Act may be cited as the Renewable |
15 | | Wind Energy Facilities Agricultural Impact Mitigation Act.
|
16 | | (Source: P.A. 99-132, eff. 7-24-15.) |
17 | | (505 ILCS 147/5)
|
18 | | Sec. 5. Purpose. The primary purpose of this Act is to |
19 | | promote the State's welfare by protecting landowners during the |
20 | | construction and deconstruction of commercial renewable wind |
21 | | energy facilities.
|
22 | | (Source: P.A. 99-132, eff. 7-24-15.) |
|
| | SB2591 Engrossed | - 5 - | LRB100 17172 SLF 32327 b |
|
|
1 | | (505 ILCS 147/10)
|
2 | | Sec. 10. Definitions.
As used in this Act:
|
3 | | "Abandonment of a commercial wind energy facility " means |
4 | | when deconstruction has not been completed within 18 months |
5 | | after the commercial wind energy facility reaches the end of |
6 | | its useful life. For purposes of this definition, a commercial |
7 | | wind energy facility will be presumed to have reached the end |
8 | | of its useful life if (1) no electricity is generated for a |
9 | | continuous period of 12 months and (2) the commercial wind |
10 | | energy facility owner fails, for a period of 6 consecutive |
11 | | months, to pay the landowner amounts owed in accordance with |
12 | | the underlying agreement. |
13 | | "Abandonment of a commercial solar energy facility" means |
14 | | when deconstruction has not been completed within 12 months |
15 | | after the commercial solar energy facility reaches the end of |
16 | | its useful life. For purposes of this definition, a commercial |
17 | | solar energy facility shall be presumed to have reached the end |
18 | | of its useful life if the commercial solar energy facility |
19 | | owner fails, for a period of 6 consecutive months, to pay the |
20 | | landowner amounts owed in accordance with the underlying |
21 | | agreement. |
22 | | "Agricultural impact mitigation agreement" means an |
23 | | agreement between the commercial wind energy facility owner or |
24 | | the commercial solar energy facility owner and the Department |
25 | | of Agriculture described in Section 15 of this Act.
|
26 | | "Commercial renewable energy facility " means a commercial |
|
| | SB2591 Engrossed | - 6 - | LRB100 17172 SLF 32327 b |
|
|
1 | | wind energy facility or commercial solar energy facility as |
2 | | defined in this Act. |
3 | | "Commercial solar energy facility" means a solar energy |
4 | | conversion facility equal to or greater than 500 kilowatts in |
5 | | total nameplate capacity, including a solar energy conversion |
6 | | facility seeking an extension of a permit to construct granted |
7 | | by a county or municipality before the effective date of this |
8 | | amendatory Act of the 100th General Assembly. "Commercial solar |
9 | | energy facility" does not include a solar energy conversion |
10 | | facility: (1) for which a permit to construct has been issued |
11 | | before the effective date of this amendatory Act of the 100th |
12 | | General Assembly; (2) that is located on land owned by the |
13 | | commercial solar energy facility owner; (3) that was |
14 | | constructed before the effective date of this amendatory Act of |
15 | | the 100th General Assembly; or (4) that is located on the |
16 | | customer side of the customer's electric meter and is primarily |
17 | | used to offset that customer's electricity load and is limited |
18 | | in nameplate capacity to less than or equal to 2,000 kilowatts. |
19 | | "Commercial solar energy facility owner" means a private |
20 | | commercial enterprise that owns a commercial solar energy |
21 | | facility. A commercial solar energy facility owner is not nor |
22 | | shall it be deemed to be a public utility as defined in the |
23 | | Public Utilities Act. |
24 | | "Commercial wind energy facility" means a wind energy |
25 | | conversion facility of equal or greater than 500 kilowatts in |
26 | | total nameplate generating capacity. "Commercial wind energy |
|
| | SB2591 Engrossed | - 7 - | LRB100 17172 SLF 32327 b |
|
|
1 | | facility" includes a wind energy conversion facility seeking an |
2 | | extension of a permit to construct granted by a county or |
3 | | municipality before the effective date of this Act. "Commercial |
4 | | wind energy facility" does not include a wind energy conversion |
5 | | facility: (1) that has submitted a complete permit application |
6 | | to a county or municipality and for which the hearing on the |
7 | | completed application has commenced on the date provided in the |
8 | | public hearing notice, which must be before the effective date |
9 | | of this Act; (2) for which a permit to construct has been |
10 | | issued before the effective date of this Act; or (3) that was |
11 | | constructed before the effective date of this Act. |
12 | | "Commercial wind energy facility owner" means a private |
13 | | commercial enterprise that owns or operates a commercial wind |
14 | | energy facility.
A commercial wind energy facility owner is not |
15 | | nor shall it be deemed to be a public utility as defined in the |
16 | | Public Utilities Act. |
17 | | "Construction" means the installation, preparation for |
18 | | installation, or repair of a commercial renewable wind energy |
19 | | facility.
|
20 | | "County" means the county where the commercial renewable |
21 | | wind energy facility is located.
|
22 | | "Deconstruction" means the removal of a commercial |
23 | | renewable wind energy facility from the property of a landowner |
24 | | and the restoration of that property as provided in the |
25 | | agricultural impact mitigation agreement.
|
26 | | "Department" means the Department of Agriculture.
|
|
| | SB2591 Engrossed | - 8 - | LRB100 17172 SLF 32327 b |
|
|
1 | | "Landowner" means any person (1) with an ownership interest |
2 | | in property that is used for agricultural purposes and (2) that |
3 | | is a party to an underlying agreement.
|
4 | | "Underlying agreement" means the written agreement with a |
5 | | landowner, including, but not limited to, an easement, option, |
6 | | lease, or license, under the terms of which another person has |
7 | | constructed, constructs, or intends to construct a commercial |
8 | | wind energy facility or commercial solar energy facility on the |
9 | | property of the landowner.
|
10 | | (Source: P.A. 99-132, eff. 7-24-15.) |
11 | | (505 ILCS 147/15)
|
12 | | Sec. 15. Agricultural impact mitigation agreement.
|
13 | | (a) A commercial renewable wind energy facility owner of a |
14 | | commercial wind energy facility or a commercial solar energy |
15 | | facility that is located on landowner property shall enter into |
16 | | an agricultural impact mitigation agreement with the |
17 | | Department outlining construction and deconstruction standards |
18 | | and policies designed to preserve the integrity of any |
19 | | agricultural land that is impacted by commercial renewable wind |
20 | | energy facility construction and deconstruction. The |
21 | | construction and deconstruction of any commercial solar energy |
22 | | facility shall be in conformance with the Department's standard |
23 | | agricultural impact mitigation agreement referenced in |
24 | | subsection (f) of this Section. Except as provided in |
25 | | subsection (a-5) of this Section, the terms and conditions of |
|
| | SB2591 Engrossed | - 9 - | LRB100 17172 SLF 32327 b |
|
|
1 | | the Department's standard agricultural impact mitigation |
2 | | agreement are subject to and may be modified by an underlying |
3 | | agreement between the landowner and the commercial solar energy |
4 | | facility owner. |
5 | | (a-5) Prior to the commencement of construction, a |
6 | | commercial solar energy facility owner shall submit to the |
7 | | county in which the commercial solar facility is to be located |
8 | | a deconstruction plan. A commercial solar energy facility owner |
9 | | shall provide the county with an appropriate financial |
10 | | assurance mechanism consistent with the Department's standard |
11 | | agricultural impact mitigation agreement for and to assure |
12 | | deconstruction in the event of an abandonment of a commercial |
13 | | solar energy facility. |
14 | | (b) The agricultural impact mitigation agreement for a |
15 | | commercial wind energy facility shall include, but is not |
16 | | limited to, such items as restoration of agricultural land |
17 | | affected by construction, deconstruction (including upon |
18 | | abandonment of a commercial wind energy facility ), |
19 | | construction staging, and storage areas; support structures; |
20 | | aboveground facilities; guy wires and anchors; underground |
21 | | cabling depth; topsoil replacement; protection and repair of |
22 | | agricultural drainage tiles; rock removal; repair of |
23 | | compaction and rutting; land leveling; prevention of soil |
24 | | erosion; repair of damaged soil conservation practices; |
25 | | compensation for damages to private property; clearing of trees |
26 | | and brush; interference with irrigation systems; access roads; |
|
| | SB2591 Engrossed | - 10 - | LRB100 17172 SLF 32327 b |
|
|
1 | | weed control; pumping of water from open excavations; advance |
2 | | notice of access to private property; indemnification of |
3 | | landowners; and deconstruction plans and financial assurance |
4 | | for deconstruction (including upon abandonment of a commercial |
5 | | wind energy facility ).
|
6 | | (b-5) The agricultural impact mitigation agreement for a |
7 | | commercial solar energy facility shall include, but is not |
8 | | limited to, such items as restoration of agricultural land |
9 | | affected by construction, deconstruction (including upon |
10 | | abandonment of a commercial solar energy facility); support |
11 | | structures; aboveground facilities; guy wires and anchors; |
12 | | underground cabling depth; topsoil removal and replacement; |
13 | | rerouting and permanent repair of agricultural drainage tiles; |
14 | | rock removal; repair of compaction and rutting; construction |
15 | | during wet weather; land leveling; prevention of soil erosion; |
16 | | repair of damaged soil conservation practices; compensation |
17 | | for damages to private property; clearing of trees and brush; |
18 | | access roads; weed control; advance notice of access to private |
19 | | property; indemnification of landowners; and deconstruction |
20 | | plans and financial assurance for deconstruction (including |
21 | | upon abandonment of a commercial solar energy facility). The |
22 | | commercial solar energy facility owner shall enter into one |
23 | | agricultural impact mitigation agreement for each commercial |
24 | | solar energy facility. |
25 | | (c) For commercial wind energy facility owners seeking a |
26 | | permit from a county or municipality for the construction of a |
|
| | SB2591 Engrossed | - 11 - | LRB100 17172 SLF 32327 b |
|
|
1 | | commercial wind energy facility, the agricultural impact |
2 | | mitigation agreement shall be entered into prior to the public |
3 | | hearing required prior to a siting decision of a county or |
4 | | municipality regarding the commercial wind energy facility. |
5 | | The agricultural impact mitigation agreement is binding on any |
6 | | subsequent commercial wind energy facility owner that takes |
7 | | ownership of the commercial wind energy facility that is the |
8 | | subject of the agreement.
|
9 | | (c-5) A commercial solar energy facility owner shall, not |
10 | | less than 45 days prior to commencement of actual construction, |
11 | | submit to the Department a standard agricultural impact |
12 | | mitigation agreement as referenced in subsection (f) of this |
13 | | Section signed by the commercial solar energy facility owner |
14 | | and including all information required by the Department. The |
15 | | commercial solar energy facility owner shall provide either a |
16 | | copy of that submitted agreement or a copy of the fully |
17 | | executed project-specific agricultural impact mitigation |
18 | | agreement to the landowner not less than 30 days prior to the |
19 | | commencement of construction. The agricultural impact |
20 | | mitigation agreement is binding on any subsequent commercial |
21 | | solar energy facility owner that takes ownership of the |
22 | | commercial solar energy facility that is the subject of the |
23 | | agreement. |
24 | | (d) If a commercial renewable wind energy facility owner |
25 | | seeks an extension of a permit granted by a county or |
26 | | municipality for the construction of a commercial wind energy |
|
| | SB2591 Engrossed | - 12 - | LRB100 17172 SLF 32327 b |
|
|
1 | | facility prior to the effective date of this Act, the |
2 | | agricultural impact mitigation agreement shall be entered into |
3 | | prior to a decision by the county or municipality to grant the |
4 | | permit extension.
|
5 | | (e) The Department may shall adopt rules that are necessary |
6 | | and appropriate for the implementation and administration of |
7 | | agricultural impact mitigation agreements as required under |
8 | | this Act.
|
9 | | (f) The Department shall make available on its website a |
10 | | standard agricultural impact mitigation agreement applicable |
11 | | to all commercial solar energy facilities within 60 days after |
12 | | the effective date of this amendatory Act of the 100th General |
13 | | Assembly. |
14 | | (g) Nothing in this amendatory Act of the 100th General |
15 | | Assembly and nothing in an agricultural impact mitigation |
16 | | agreement shall be construed to apply to or otherwise impair an |
17 | | underlying agreement for a commercial solar energy facility |
18 | | entered into prior to the effective date of this amendatory Act |
19 | | of the 100th General Assembly. |
20 | | (Source: P.A. 99-132, eff. 7-24-15.)
|
21 | | Section 99. Effective date. This Act takes effect upon |
22 | | becoming law.
|