| | SB0104 Engrossed | | LRB101 04773 RJF 49782 b |
|
|
1 | | AN ACT concerning finance.
|
2 | | Be it enacted by the People of the State of Illinois,
|
3 | | represented in the General Assembly:
|
4 | | Section 5. The State Prompt Payment Act is amended by |
5 | | changing Sections 1 and 7 as follows:
|
6 | | (30 ILCS 540/1) (from Ch. 127, par. 132.401)
|
7 | | Sec. 1.
This Act applies to any State official or agency |
8 | | authorized to
provide for payment from State funds, by virtue |
9 | | of any appropriation of the
General Assembly, for goods or |
10 | | services furnished to the State.
|
11 | | For purposes of this Act, "goods or
services furnished to |
12 | | the State" include but are not limited to (i) covered health
|
13 | | care provided to eligible members and their covered dependents |
14 | | in accordance
with the State Employees Group Insurance Act of |
15 | | 1971, including coverage
through a physician-owned health |
16 | | maintenance organization under Section 6.1 of
that Act, (ii) |
17 | | prevention, intervention, or treatment services and supports |
18 | | for persons with developmental disabilities, mental health |
19 | | services, alcohol and substance abuse services, rehabilitation |
20 | | services, and early intervention services provided by a vendor, |
21 | | and (iii) prevention, intervention, or treatment services and |
22 | | supports for youth provided by a vendor by virtue of a |
23 | | contractual grant agreement. For the purposes of items (ii) and |
|
| | SB0104 Engrossed | - 2 - | LRB101 04773 RJF 49782 b |
|
|
1 | | (iii), a vendor includes but is not limited to sellers of goods |
2 | | and services, including community-based organizations that are |
3 | | licensed to provide prevention, intervention, or treatment |
4 | | services and supports for persons with developmental |
5 | | disabilities, mental illness, and substance abuse problems, or |
6 | | that provides prevention, intervention, or treatment services |
7 | | and supports for youth.
|
8 | | For the purposes of this Act, "appropriate State official |
9 | | or agency" is
defined as the Director or Chief Executive or his |
10 | | designee of that State
agency or department or facility of such |
11 | | agency or department.
With respect to covered health care |
12 | | provided to eligible members and
their dependents in accordance |
13 | | with the State Employees Group Insurance Act
of 1971, |
14 | | "appropriate State official or agency" also includes an
|
15 | | administrator of a program of health benefits under that Act.
|
16 | | As used in this Act, "eligible member" means a member who |
17 | | is eligible for
health benefits under the State Employees Group |
18 | | Insurance Act of 1971, and
"member" and "dependent" have the |
19 | | meanings ascribed to those terms in that Act.
|
20 | | As used in this Act, "a proper bill or invoice" means a |
21 | | bill or invoice, including, but not limited to, an invoice |
22 | | issued under a contractual grant agreement,
that
includes the
|
23 | | information necessary for processing the payment as may be |
24 | | specified by a State
agency and in rules adopted in accordance |
25 | | with this Act. Beginning on and after July 1, 2021, "a proper |
26 | | bill or invoice" shall also include the names of all |
|
| | SB0104 Engrossed | - 3 - | LRB101 04773 RJF 49782 b |
|
|
1 | | subcontractors or subconsultants to be paid from the bill or |
2 | | invoice and the amounts due to each of them, if any.
|
3 | | (Source: P.A. 100-549, eff. 1-1-18 .)
|
4 | | (30 ILCS 540/7)
(from Ch. 127, par. 132.407)
|
5 | | Sec. 7. Payments to subcontractors and material suppliers. |
6 | | (a) When a State official or agency responsible for |
7 | | administering a
contract submits a voucher to the Comptroller |
8 | | for
payment to a contractor, that State official or agency |
9 | | shall promptly make
available electronically
the voucher |
10 | | number, the date of the voucher, and
the amount of the voucher.
|
11 | | The State official or agency responsible for administering the |
12 | | contract shall
provide subcontractors and material suppliers, |
13 | | known to the State official or
agency, with instructions on how |
14 | | to access the electronic information. |
15 | | (a-5) When a
contractor receives any payment, the |
16 | | contractor shall
pay each subcontractor and material supplier |
17 | | electronically within 7 business days or, if paid by a printed |
18 | | check, the printed check must be postmarked within 7 business |
19 | | days after receiving payment in proportion to the work
|
20 | | completed by each subcontractor and material supplier its |
21 | | application or pay estimate, plus interest received under this |
22 | | Act. When a contractor receives any payment, the contractor |
23 | | shall pay each lower-tiered subcontractor and material |
24 | | supplier and each subcontractor and material supplier shall |
25 | | make payment to its own respective subcontractors and material |
|
| | SB0104 Engrossed | - 4 - | LRB101 04773 RJF 49782 b |
|
|
1 | | suppliers. If the contractor receives less than the full |
2 | | payment
due under the public construction contract, the |
3 | | contractor shall be
obligated to disburse on a pro rata basis |
4 | | those funds received, plus interest received under this Act, |
5 | | with the
contractor, subcontractors and material suppliers |
6 | | each receiving a prorated
portion based on the amount of |
7 | | payment each has earned. When, however, the State official or |
8 | | agency
does not release the full payment due under the contract |
9 | | because there are
specific areas of work or materials the State |
10 | | agency or official has determined are not suitable for
payment, |
11 | | then those specific subcontractors or material suppliers |
12 | | involved shall not
be paid for that portion of work rejected or |
13 | | deemed not suitable for
payment and all other subcontractors |
14 | | and suppliers shall be paid based upon the amount of payment |
15 | | each has earned, plus interest received under this Act.
|
16 | | (a-10) For construction contracts with the Department of |
17 | | Transportation, the contractor, subcontractor, or material |
18 | | supplier, regardless of tier, shall not offset, decrease, or |
19 | | diminish payment or payments that are due to its subcontractors |
20 | | or material suppliers without reasonable cause. |
21 | | A contractor, who refuses to make prompt payment within 7 |
22 | | business days after receiving payment , in whole or in part, |
23 | | shall provide to the subcontractor or material supplier and the |
24 | | public owner or its agent, a written notice of that refusal. |
25 | | The written notice shall be made by a contractor no later than |
26 | | 5 calendar days after payment is received by the contractor. |
|
| | SB0104 Engrossed | - 5 - | LRB101 04773 RJF 49782 b |
|
|
1 | | The written notice shall identify the Department of |
2 | | Transportation's contract, any subcontract or material |
3 | | purchase agreement, a detailed reason for refusal, the value of |
4 | | the payment to be withheld, and the specific remedial actions |
5 | | required of the subcontractor or material supplier so that |
6 | | payment may be made. Written notice of refusal may be given in |
7 | | a form and method which is acceptable to the parties and public |
8 | | owner. |
9 | | (b) If the contractor, without reasonable cause, fails to |
10 | | make full payment of amounts due under subsection (a) to its
|
11 | | subcontractors and material suppliers within 7 business days 15 |
12 | | calendar days after
receipt of
payment from the State official |
13 | | or agency, the contractor shall pay to its
subcontractors and |
14 | | material suppliers, in addition to the payment due
them, |
15 | | interest in the amount of
2% per month, calculated from the
|
16 | | expiration of the 7-business-day 15-day period until fully |
17 | | paid. This subsection shall further
apply to any payments made |
18 | | by subcontractors and material suppliers to
their |
19 | | subcontractors and material suppliers and to all payments made |
20 | | to
lower tier subcontractors and material suppliers throughout |
21 | | the contracting
chain.
|
22 | | (1) If a contractor, without reasonable cause, fails to |
23 | | make payment in
full as
provided in subsection (a-5) within |
24 | | 7 business days 15 calendar days after receipt of payment |
25 | | under the
public
construction contract, any subcontractor |
26 | | or material supplier to whom payments
are owed
may file a |
|
| | SB0104 Engrossed | - 6 - | LRB101 04773 RJF 49782 b |
|
|
1 | | written notice and request for administrative hearing with |
2 | | the State official or agency setting forth the
amount owed |
3 | | by
the contractor and the contractor's failure to timely |
4 | | pay the amount owed. The written notice and request for |
5 | | administrative hearing shall identify the public |
6 | | construction contract, the contractor, and the amount |
7 | | owed, and shall contain a sworn statement or attestation to |
8 | | verify the accuracy of the notice. The notice and request |
9 | | for administrative hearing shall be filed with the State |
10 | | official for the public construction contract, with a copy |
11 | | of the notice concurrently provided to the contractor. |
12 | | Notice to the State official may be made by certified or |
13 | | registered mail, messenger service, or personal service, |
14 | | and must include proof of delivery to the State official.
|
15 | | (2) The State official or agency, within 15 calendar |
16 | | days after receipt of a
subcontractor's
or material |
17 | | supplier's written notice and request for administrative |
18 | | hearing,
shall hold a hearing convened by an administrative |
19 | | law judge to determine whether the contractor withheld |
20 | | payment,
without
reasonable cause, from the subcontractors |
21 | | or material suppliers and what
amount, if any,
is due to |
22 | | the subcontractors or material suppliers, and the |
23 | | reasonable cause or causes asserted by the contractor. The |
24 | | State official or
agency shall
provide appropriate notice |
25 | | to the parties of the date, time, and location of
the |
26 | | hearing. Each contractor, subcontractor, or material |
|
| | SB0104 Engrossed | - 7 - | LRB101 04773 RJF 49782 b |
|
|
1 | | supplier has the right to be represented by counsel at a |
2 | | hearing and to cross-examine witnesses and challenge |
3 | | documents. Upon the request of the subcontractor or |
4 | | material supplier and a showing of good cause, reasonable |
5 | | continuances may be granted by the administrative law |
6 | | judge.
|
7 | | (3) Upon a finding by the administrative law judge that |
8 | | the contractor failed
to make
payment in full, without |
9 | | reasonable cause, as provided in subsection (a-10), then
|
10 | | the administrative law judge shall, in writing, order the |
11 | | contractor to pay the amount
owed to the
subcontractors or |
12 | | material suppliers plus interest within 15 calendar days |
13 | | after the order.
|
14 | | (4) If a contractor fails to make full payment as |
15 | | ordered under paragraph (3) of this subsection (b) within |
16 | | 15 days after the
administrative law judge's order, then |
17 | | the contractor shall be barred from
entering into a State
|
18 | | public construction contract for a period of one year |
19 | | beginning on the date of
the administrative law judge's |
20 | | order.
|
21 | | (5) If, on 2 or more occasions within a 3-calendar-year |
22 | | period, there is a finding by an administrative law judge |
23 | | that the contractor failed to make payment in full, without |
24 | | reasonable cause, and a written order was issued to a |
25 | | contractor under paragraph (3) of this subsection (b), then |
26 | | the contractor shall be barred from entering into a State |
|
| | SB0104 Engrossed | - 8 - | LRB101 04773 RJF 49782 b |
|
|
1 | | public construction contract for a period of 6 months |
2 | | beginning on the date of the administrative law judge's |
3 | | second written order, even if the payments required under |
4 | | the orders were made in full. |
5 | | (6) If a contractor fails to make full payment as |
6 | | ordered under paragraph (4) of this subsection (b), the |
7 | | subcontractor or material supplier may, within 30 days of |
8 | | the date of that order, petition the State agency for an |
9 | | order for reasonable attorney's fees and costs incurred in |
10 | | the prosecution of the action under this subsection (b). |
11 | | Upon that petition and taking of additional evidence, as |
12 | | may be required, the administrative law judge may issue a |
13 | | supplemental order directing the contractor to pay those |
14 | | reasonable attorney's fees and costs. |
15 | | (7) The written order of the administrative law judge |
16 | | shall be final and appealable under the Administrative |
17 | | Review Law. |
18 | | (b-5) On or before July 2021, the Department of |
19 | | Transportation shall publish on its website a searchable |
20 | | database that allows for queries for each active construction |
21 | | contract by the name of a subcontractor or the pay item such |
22 | | that each pay item is associated with either the prime |
23 | | contractor or a subcontractor. |
24 | | (c) This Section shall not be construed to in any manner |
25 | | diminish, negate, or interfere with the |
26 | | contractor-subcontractor or contractor-material supplier |
|
| | SB0104 Engrossed | - 9 - | LRB101 04773 RJF 49782 b |
|
|
1 | | relationship or commercially useful function. |
2 | | (d) This Section shall not preclude, bar, or stay the |
3 | | rights, remedies, and defenses available to the parties by way |
4 | | of the operation of their contract, purchase agreement, the |
5 | | Mechanics Lien Act, or the Public Construction Bond Act. |
6 | | (e) State officials and agencies may adopt rules as may be |
7 | | deemed necessary in order to establish the formal procedures |
8 | | required under this Section. |
9 | | (f) As used in this Section: |
10 | | "Payment" means the discharge of an obligation in money or |
11 | | other valuable consideration or thing delivered in full or |
12 | | partial satisfaction of an obligation to pay. "Payment" shall |
13 | | include interest paid pursuant to this Act. |
14 | | "Reasonable cause" may include, but is not limited to, |
15 | | unsatisfactory workmanship or materials; failure to provide |
16 | | documentation required by the contract, subcontract, or |
17 | | material purchase agreement; claims made against the |
18 | | Department of Transportation or the subcontractor pursuant to |
19 | | subsection (c) of Section 23 of the Mechanics Lien Act or the |
20 | | Public Construction Bond Act; judgments, levies, garnishments, |
21 | | or other court-ordered assessments or offsets in favor of the |
22 | | Department of Transportation or other State agency entered |
23 | | against a subcontractor or material supplier. "Reasonable |
24 | | cause" does not include payments issued to the contractor that |
25 | | create a negative or reduced valuation pay application or pay |
26 | | estimate due to a reduction of contract quantities or work not |
|
| | SB0104 Engrossed | - 10 - | LRB101 04773 RJF 49782 b |
|
|
1 | | performed or provided by the subcontractor or material |
2 | | supplier; the interception or withholding of funds for reasons |
3 | | not related to the subcontractor's or material supplier's work |
4 | | on the contract; anticipated claims or assessments of third |
5 | | parties not a party related to the contract or subcontract; |
6 | | asserted claims or assessments of third parties that are not |
7 | | authorized by court order, administrative tribunal, or |
8 | | statute. "Reasonable cause" further does not include the |
9 | | withholding, offset, or reduction of payment, in whole or in |
10 | | part, due to the assessment of liquidated damages or penalties |
11 | | assessed by the Department of Transportation against the |
12 | | contractor, unless the subcontractor's performance or supplied |
13 | | materials were the sole and proximate cause of the liquidated |
14 | | damage or penalty. |
15 | | (Source: P.A. 100-43, eff. 8-9-17; 100-376, eff. 1-1-18; |
16 | | 100-863, eff. 8-14-18.)
|