| ||||||||||||||||||||
| ||||||||||||||||||||
| ||||||||||||||||||||
| ||||||||||||||||||||
| ||||||||||||||||||||
| 1 | AN ACT concerning animals.
| |||||||||||||||||||
| 2 | Be it enacted by the People of the State of Illinois,
| |||||||||||||||||||
| 3 | represented in the General Assembly:
| |||||||||||||||||||
| 4 | Section 5. The Livestock Management Facilities Act is | |||||||||||||||||||
| 5 | amended by changing Section 12 as follows:
| |||||||||||||||||||
| 6 | (510 ILCS 77/12)
| |||||||||||||||||||
| 7 | Sec. 12. Public informational meeting; lagoons and | |||||||||||||||||||
| 8 | non-lagoon structures.
| |||||||||||||||||||
| 9 | (a) Beginning on the effective date of this amendatory Act | |||||||||||||||||||
| 10 | of 1999, within 7
days after
receiving a form giving notice of | |||||||||||||||||||
| 11 | intent to construct (i) a new livestock
management facility or
| |||||||||||||||||||
| 12 | livestock waste handling facility serving 1,000 or more animal | |||||||||||||||||||
| 13 | units that does
not propose to
utilize a lagoon or (ii) a | |||||||||||||||||||
| 14 | livestock waste management facility or livestock
waste | |||||||||||||||||||
| 15 | handling facility
that does propose to utilize a lagoon, the | |||||||||||||||||||
| 16 | Department shall send a copy of the
notice form to the
county | |||||||||||||||||||
| 17 | board of the county in which the facility is to be located and | |||||||||||||||||||
| 18 | shall
publish a public notice in
a newspaper of general | |||||||||||||||||||
| 19 | circulation within the county. After receiving a copy
of the | |||||||||||||||||||
| 20 | notice form
from the Department, the county board may, at its | |||||||||||||||||||
| 21 | discretion and within 30 days
after receipt of
the notice, | |||||||||||||||||||
| 22 | request that the Department conduct an informational meeting
| |||||||||||||||||||
| 23 | concerning the
proposed construction that is subject to this | |||||||||||||||||||
| |||||||
| |||||||
| 1 | Section. In addition, during the
county's 30-day
review period, | ||||||
| 2 | county residents may petition the county board of the county
| ||||||
| 3 | where the proposed
new facility will be located to request that | ||||||
| 4 | the Department conduct an
informational meeting.
When | ||||||
| 5 | petitioned by 75 or more of the county's residents who are | ||||||
| 6 | registered
voters, the county
board shall request that the | ||||||
| 7 | Department conduct an informational meeting. If
the county | ||||||
| 8 | board
requests that the Department conduct the informational | ||||||
| 9 | meeting, the Department
shall conduct
the informational | ||||||
| 10 | meeting within 15 days of the county board's request. If the
| ||||||
| 11 | Department
conducts such a meeting, it shall cause notice of | ||||||
| 12 | the meeting to be published
in a newspaper of
general | ||||||
| 13 | circulation in the county and in the State newspaper and shall | ||||||
| 14 | send a
copy of the notice to the County Board. Upon receipt of | ||||||
| 15 | the notice, the County
Board shall post the notice
on the | ||||||
| 16 | public
informational board at the county courthouse at least 10 | ||||||
| 17 | days before the
meeting. The owner or
operator who submitted | ||||||
| 18 | the notice of intent to construct to the Department
shall | ||||||
| 19 | appear at the
meeting. At the meeting, the Department shall | ||||||
| 20 | afford members of the public an
opportunity to ask
questions | ||||||
| 21 | and present oral or written comments concerning the proposed
| ||||||
| 22 | construction.
| ||||||
| 23 | (b) The county board shall submit at the informational | ||||||
| 24 | meeting or within 30
days following
the meeting a binding an | ||||||
| 25 | advisory, non-binding recommendation to the Department about | ||||||
| 26 | the
proposed
new facility's construction in accordance with the | ||||||
| |||||||
| |||||||
| 1 | applicable requirements of
this Act. The
binding advisory, | ||||||
| 2 | non-binding recommendation shall contain at a minimum:
| ||||||
| 3 | (1) a statement of whether the proposed facility | ||||||
| 4 | achieves or fails to
achieve any each
of the 8 siting | ||||||
| 5 | criteria as outlined in subsection (d); and
| ||||||
| 6 | (2) a statement of the information and criteria used by | ||||||
| 7 | the county board
in
determining that the proposed facility | ||||||
| 8 | met or failed to meet any of the
criteria
described in | ||||||
| 9 | subsection (d).
| ||||||
| 10 | (c) When the county board requests an informational | ||||||
| 11 | meeting, construction
shall not
begin until after the | ||||||
| 12 | informational meeting has been held, the Department has
| ||||||
| 13 | reviewed the
county board's recommendation and replied to the | ||||||
| 14 | recommendation indicating if
the proposed
new livestock | ||||||
| 15 | management facility or the new livestock waste handling | ||||||
| 16 | facility
is or will be in
compliance with the requirements of | ||||||
| 17 | the Act, and the owner, operator, or
certified manager and
| ||||||
| 18 | operator has received the Department's notice that the setbacks | ||||||
| 19 | and all
applicable requirements
of this Act have been met.
| ||||||
| 20 | (d) At the informational meeting for the proposed facility, | ||||||
| 21 | the Department
of
Agriculture
shall receive evidence by | ||||||
| 22 | testimony or otherwise on the following subjects:
| ||||||
| 23 | (1) Whether registration and livestock waste | ||||||
| 24 | management plan certification
requirements, if required, | ||||||
| 25 | are met by the notice of intent to construct.
| ||||||
| 26 | (2) Whether the design, location, or proposed | ||||||
| |||||||
| |||||||
| 1 | operation will protect the
environment
by being consistent | ||||||
| 2 | with this Act.
| ||||||
| 3 | (3) Whether the location minimizes any incompatibility | ||||||
| 4 | with the
surrounding area's
character by being located in | ||||||
| 5 | any area zoned for agriculture where the county
has zoning | ||||||
| 6 | or where the county is not zoned, the setback requirements
| ||||||
| 7 | established by this Act are complied with.
| ||||||
| 8 | (4) Whether the facility is located within a 100-year | ||||||
| 9 | floodplain or an
otherwise
environmentally sensitive area | ||||||
| 10 | (defined as an area of karst area or with
aquifer
material | ||||||
| 11 | within 5 feet of the bottom of the livestock waste handling | ||||||
| 12 | facility)
and
whether construction standards set forth in | ||||||
| 13 | the notice of intent to construct
are
consistent with the | ||||||
| 14 | goal of protecting the safety of the area.
| ||||||
| 15 | (5) Whether the owner or operator has submitted plans | ||||||
| 16 | for operation that
minimize
the likelihood of any | ||||||
| 17 | environmental damage to the surrounding area from spills,
| ||||||
| 18 | runoff, and leaching.
| ||||||
| 19 | (6) Whether odor control plans are reasonable and | ||||||
| 20 | incorporate reasonable
or
innovative odor reduction | ||||||
| 21 | technologies given the current state of such
technologies.
| ||||||
| 22 | (7) Whether traffic patterns minimize the effect on | ||||||
| 23 | existing traffic
flows.
| ||||||
| 24 | (8) Whether construction or modification of a new | ||||||
| 25 | facility is consistent
with existing
community growth, | ||||||
| 26 | tourism, recreation, or economic development or with | ||||||
| |||||||
| |||||||
| 1 | specific
projects involving community growth, tourism, | ||||||
| 2 | recreation, or economic
development that have been | ||||||
| 3 | identified by government action for development or
| ||||||
| 4 | operation within one year through compliance with | ||||||
| 5 | applicable zoning and setback
requirements for populated | ||||||
| 6 | areas as established by this Act.
| ||||||
| 7 | (e) After reviewing the binding recommendation submitted | ||||||
| 8 | to the county, the Department shall deny any permit to | ||||||
| 9 | construct if the county recommends that the facility not be | ||||||
| 10 | constructed. | ||||||
| 11 | (Source: P.A. 91-110, eff. 7-13-99.)
| ||||||
| 12 | Section 99. Effective date. This Act takes effect upon | ||||||
| 13 | becoming law.
| ||||||