| | 10200HB4384ham001 | - 2 - | LRB102 22727 RJF 36733 a |
|
|
| 1 | | on some of the terms of the change order or extra work; or (vi) |
| 2 | | explain in writing that an additional 30 days are necessary to |
| 3 | | make a determination. |
| 4 | | (b) If an additional 30 days is requested under subsection |
| 5 | | (a), then, after the 30 additional days have elapsed, the |
| 6 | | State agency shall: (i) issue the change order with an |
| 7 | | agreement on price; (ii) agree on price for the authorization |
| 8 | | for extra work; (iii) counter on price in writing; (iv) give |
| 9 | | written notice to the contractor of the reasons why the change |
| 10 | | order is unreasonable; (v) accept a partial agreement on price |
| 11 | | on some of the terms of the change order or extra work; or (vi) |
| 12 | | explain in writing that an additional 15 days are necessary to |
| 13 | | make a determination. If an additional 15 days is requested |
| 14 | | under this subsection (b), then, after every 15 additional |
| 15 | | days that elapse, as necessary, the State agency shall perform |
| 16 | | one of the actions specified in items (i) through (vi) of this |
| 17 | | subsection (b). |
| 18 | | (c) The State agency shall report quarterly on its website |
| 19 | | the total number of times the State agency requested |
| 20 | | additional time to make a determination under this Section and |
| 21 | | the total number of times the State agency requested |
| 22 | | additional time for such determination for each contract.
|
| 23 | | Section 99. Effective date. This Act takes effect upon |
| 24 | | becoming law.".
|