| 1 | AN ACT concerning finance.
| ||||||||||||||||||||||||
| 2 | Be it enacted by the People of the State of Illinois,
| ||||||||||||||||||||||||
| 3 | represented in the General Assembly:
| ||||||||||||||||||||||||
| 4 | Section 5. The Public Construction Bond Act is amended by | ||||||||||||||||||||||||
| 5 | changing Section 1 as follows:
| ||||||||||||||||||||||||
| 6 | (30 ILCS 550/1) (from Ch. 29, par. 15)
| ||||||||||||||||||||||||
| 7 | Sec. 1. Except as otherwise provided by this Act, all | ||||||||||||||||||||||||
| 8 | officials, boards,
commissions, or agents of this State, or of | ||||||||||||||||||||||||
| 9 | any political subdivision thereof, in making contracts for | ||||||||||||||||||||||||
| 10 | public work of
any kind costing over $50,000 to be performed | ||||||||||||||||||||||||
| 11 | for the State, or of any political subdivision thereof,
shall | ||||||||||||||||||||||||
| 12 | require every contractor for the work to furnish, supply and | ||||||||||||||||||||||||
| 13 | deliver
a bond to the State, or to the political subdivision | ||||||||||||||||||||||||
| 14 | thereof entering into
the contract, as the case may be, with | ||||||||||||||||||||||||
| 15 | good and sufficient sureties. The surety on the bond shall be a | ||||||||||||||||||||||||
| 16 | company that is licensed by the Department of Insurance | ||||||||||||||||||||||||
| 17 | authorizing it to execute surety bonds and the company shall | ||||||||||||||||||||||||
| 18 | have a financial strength rating of at least A- as rated by | ||||||||||||||||||||||||
| 19 | A.M. Best Company, Inc., Moody's Investors Service, Standard & | ||||||||||||||||||||||||
| 20 | Poor's Corporation, or a similar rating agency. The
amount of | ||||||||||||||||||||||||
| 21 | the bond shall be fixed by the officials, boards, commissions,
| ||||||||||||||||||||||||
| 22 | commissioners or agents, and the bond, among other conditions,
| ||||||||||||||||||||||||
| 23 | shall be
conditioned for the completion of the contract, for | ||||||||||||||||||||||||
| |||||||
| |||||||
| 1 | the payment of material, apparatus, fixtures, and machinery
| ||||||
| 2 | used in the work and for all labor performed in the work, | ||||||
| 3 | whether by
subcontractor or otherwise.
| ||||||
| 4 | If the contract is for emergency repairs as provided in | ||||||
| 5 | the Illinois
Procurement
Code, proof of payment for all labor, | ||||||
| 6 | materials, apparatus, fixtures, and
machinery may be
furnished | ||||||
| 7 | in lieu of the bond required by this Section.
| ||||||
| 8 | Each such bond is deemed to contain the following | ||||||
| 9 | provisions whether
such provisions are inserted in such bond | ||||||
| 10 | or not:
| ||||||
| 11 | "The principal and sureties on this bond agree that all | ||||||
| 12 | the
undertakings, covenants, terms, conditions and agreements | ||||||
| 13 | of the contract
or contracts entered into between the | ||||||
| 14 | principal and the State or any
political subdivision thereof | ||||||
| 15 | will be performed and fulfilled and to pay
all persons, firms | ||||||
| 16 | and corporations having contracts with the principal or
with | ||||||
| 17 | subcontractors, all just claims due them under the provisions | ||||||
| 18 | of such
contracts for labor performed or materials furnished | ||||||
| 19 | in the performance of
the contract on account of which this | ||||||
| 20 | bond is given, when such claims are
not satisfied out of the | ||||||
| 21 | contract price of the contract on account of which
this bond is | ||||||
| 22 | given, after final settlement between the officer, board,
| ||||||
| 23 | commission or agent of the State or of any political | ||||||
| 24 | subdivision thereof
and the principal has been made.". | ||||||
| 25 | Each bond securing contracts between the Capital | ||||||
| 26 | Development Board or any board of a public institution of | ||||||
| |||||||
| |||||||
| 1 | higher education and a contractor shall contain the following | ||||||
| 2 | provisions, whether the provisions are inserted in the bond or | ||||||
| 3 | not: | ||||||
| 4 | "Upon the default of the principal with respect to | ||||||
| 5 | undertakings, covenants, terms, conditions, and agreements, | ||||||
| 6 | the termination of the contractor's right to proceed with the | ||||||
| 7 | work, and written notice of that default and termination by | ||||||
| 8 | the State or any political subdivision to the surety | ||||||
| 9 | ("Notice"), the surety shall promptly remedy the default by | ||||||
| 10 | taking one of the following actions: | ||||||
| 11 | (1) The surety shall complete the work pursuant to a | ||||||
| 12 | written takeover agreement, using a completing contractor | ||||||
| 13 | jointly selected by the surety and the State or any | ||||||
| 14 | political subdivision; or | ||||||
| 15 | (2) The surety shall pay a sum of money to the obligee, | ||||||
| 16 | up to the penal sum of the bond, that represents the | ||||||
| 17 | reasonable cost to complete the work that exceeds the | ||||||
| 18 | unpaid balance of the contract sum. | ||||||
| 19 | The surety shall respond to the Notice within 15 working | ||||||
| 20 | days of receipt indicating the course of action that it | ||||||
| 21 | intends to take or advising that it requires more time to | ||||||
| 22 | investigate the default and select a course of action. If the | ||||||
| 23 | surety requires more than 15 working days to investigate the | ||||||
| 24 | default and select a course of action or if the surety elects | ||||||
| 25 | to complete the work with a completing contractor that is not | ||||||
| 26 | prepared to commence performance within 15 working days after | ||||||
| |||||||
| |||||||
| 1 | receipt of Notice, and if the State or any political | ||||||
| 2 | subdivision determines it is in the best interest of the State | ||||||
| 3 | to maintain the progress of the work, the State or any | ||||||
| 4 | political subdivision may continue to work until the | ||||||
| 5 | completing contractor is prepared to commence performance. | ||||||
| 6 | Unless otherwise agreed to by the procuring agency, in no case | ||||||
| 7 | may the surety take longer than 30 working days to advise the | ||||||
| 8 | State or political subdivision on the course of action it | ||||||
| 9 | intends to take. The surety shall be liable for reasonable | ||||||
| 10 | costs incurred by the State or any political subdivision to | ||||||
| 11 | maintain the progress to the extent the costs exceed the | ||||||
| 12 | unpaid balance of the contract sum, subject to the penal sum of | ||||||
| 13 | the bond.".
| ||||||
| 14 | The surety bond required by this Section may be acquired | ||||||
| 15 | from the
company, agent or broker of the contractor's choice. | ||||||
| 16 | The bond and sureties
shall
be subject to the right of | ||||||
| 17 | reasonable approval or disapproval, including
suspension, by | ||||||
| 18 | the State or political subdivision thereof concerned. In the
| ||||||
| 19 | case of State construction contracts, a contractor shall not | ||||||
| 20 | be required to
post a cash bond or letter of credit in addition | ||||||
| 21 | to or as a substitute for the
surety bond required by this | ||||||
| 22 | Section.
| ||||||
| 23 | No retainage may be withheld by a unit of local | ||||||
| 24 | government, as specified under Section 2 of the Local | ||||||
| 25 | Government Prompt Payment Act, from a contractor who furnishes | ||||||
| 26 | the bond or bond substitute required by this Act, nor may a | ||||||
| |||||||
| |||||||
| 1 | contractor withhold retainage from its subcontractors. | ||||||
| 2 | When other than motor fuel tax funds, federal-aid funds, | ||||||
| 3 | or other
funds received from the State are used, a political | ||||||
| 4 | subdivision may allow
the contractor to provide a | ||||||
| 5 | non-diminishing irrevocable bank letter of
credit, in lieu of | ||||||
| 6 | the bond required by this Section, on contracts under
$100,000 | ||||||
| 7 | to comply with the requirements of this Section. Any such bank
| ||||||
| 8 | letter of credit shall contain all provisions required for | ||||||
| 9 | bonds by this
Section.
| ||||||
| 10 | For the purposes of this Section, the terms "material", | ||||||
| 11 | "labor", "apparatus", "fixtures", and "machinery" include | ||||||
| 12 | those rented items that are on the construction site and those | ||||||
| 13 | rented tools that are used or consumed on the construction | ||||||
| 14 | site in the performance of the contract on account of which the | ||||||
| 15 | bond is given. | ||||||
| 16 | (Source: P.A. 101-65, eff. 1-1-20.)
| ||||||