Rep. Mark L. Walker
Filed: 5/14/2021
| | 10200SB2182ham001 | | LRB102 16377 JWD 26541 a |
|
|
1 | | AMENDMENT TO SENATE BILL 2182
|
2 | | AMENDMENT NO. ______. Amend Senate Bill 2182 by replacing |
3 | | everything after the enacting clause with the following:
|
4 | | "Section 5. The Department of Commerce and Economic |
5 | | Opportunity Law of the
Civil Administrative Code of Illinois |
6 | | is amended by changing Section 605-1025 as follows: |
7 | | (20 ILCS 605/605-1025) |
8 | | Sec. 605-1025. Data center investment. |
9 | | (a) The Department shall issue certificates of exemption |
10 | | from the Retailers' Occupation Tax Act, the Use Tax Act, the |
11 | | Service Use Tax Act, and the Service Occupation Tax Act, all |
12 | | locally-imposed retailers' occupation taxes administered and |
13 | | collected by the Department, the Chicago non-titled Use Tax, |
14 | | and a credit certification against the taxes imposed under |
15 | | subsections (a) and (b) of Section 201 of the Illinois Income |
16 | | Tax Act to qualifying Illinois data centers. |
|
| | 10200SB2182ham001 | - 2 - | LRB102 16377 JWD 26541 a |
|
|
1 | | (b) For taxable years beginning on or after January 1, |
2 | | 2019, the Department shall award credits against the taxes |
3 | | imposed under subsections (a) and (b) of Section 201 of the |
4 | | Illinois Income Tax Act as provided in Section 229 of the |
5 | | Illinois Income Tax Act. |
6 | | (c) For purposes of this Section: |
7 | | "Data center" means a facility: (1) whose primary |
8 | | services are the storage, management, and processing of |
9 | | digital data; and (2) that is used to house (i) computer |
10 | | and network systems, including associated components such |
11 | | as servers, network equipment and appliances, |
12 | | telecommunications, and data storage systems, (ii) systems |
13 | | for monitoring and managing infrastructure performance, |
14 | | (iii) Internet-related equipment and services, (iv) data |
15 | | communications connections, (v) environmental controls, |
16 | | (vi) fire protection systems, and (vii) security systems |
17 | | and services. |
18 | | "Qualifying Illinois data center" means a new or |
19 | | existing data center that: |
20 | | (1) is located in the State of Illinois , is |
21 | | located within a 5-mile geographic radius, and is |
22 | | connected by common infrastructure ; |
23 | | (2) in the case of an existing data center, made a |
24 | | capital investment of at least $250,000,000 |
25 | | collectively by the data center operator and the |
26 | | tenants of the data center over the 60-month period |
|
| | 10200SB2182ham001 | - 3 - | LRB102 16377 JWD 26541 a |
|
|
1 | | immediately prior to January 1, 2020 or committed to |
2 | | make a capital investment of at least $250,000,000 |
3 | | over a 60-month period commencing before January 1, |
4 | | 2020 and ending after January 1, 2020; or |
5 | | (3) in the case of a new data center, or an |
6 | | existing data center making an upgrade, makes a |
7 | | capital investment of at least $250,000,000 over a |
8 | | 60-month period beginning on or after January 1, 2020; |
9 | | and |
10 | | (4) in the case of both existing and new data |
11 | | centers, results in the creation of at least 20 |
12 | | full-time or full-time equivalent new jobs over a |
13 | | period of 60 months by the data center operator and the |
14 | | tenants of the data center, collectively, associated |
15 | | with the operation or maintenance of the data center; |
16 | | all jobs associated with a qualifying data center |
17 | | meeting its job creation requirements those jobs must |
18 | | have a total compensation equal to or greater than |
19 | | 120% of the average wage paid to full-time employees |
20 | | in the county where the data center is located, as |
21 | | determined by the U.S. Bureau of Labor Statistics; and |
22 | | (5) within 2 years 90 days after being placed in |
23 | | service, certifies to the Department that it is carbon |
24 | | neutral or has attained certification under one or |
25 | | more of the following green building standards: |
26 | | (A) BREEAM for New Construction or BREEAM |
|
| | 10200SB2182ham001 | - 4 - | LRB102 16377 JWD 26541 a |
|
|
1 | | In-Use; |
2 | | (B) ENERGY STAR; |
3 | | (C) Envision; |
4 | | (D) ISO 50001-energy management; |
5 | | (E) LEED for Building Design and Construction |
6 | | or LEED for Operations and Maintenance; |
7 | | (F) Green Globes for New Construction or Green |
8 | | Globes for Existing Buildings; |
9 | | (G) UL 3223; or |
10 | | (H) an equivalent program approved by the |
11 | | Department of Commerce and Economic Opportunity , |
12 | | except that entering into an agreement with an |
13 | | independent business or entity unrelated to the |
14 | | data center for the purchase, sale, or transfer of |
15 | | carbon credits that would not result in carbon |
16 | | neutral outcomes at the actual site of the data |
17 | | center shall not qualify as an eligible program |
18 | | for the purposes of this Section . |
19 | | "Full-time equivalent job" means a job in which the |
20 | | new employee works for the owner, operator, contractor, or |
21 | | tenant of a data center or for a corporation under |
22 | | contract with the owner, operator or tenant of a data |
23 | | center at a rate of at least 35 hours per week. An owner, |
24 | | operator or tenant who employs labor or services at a |
25 | | specific site or facility under contract with another may |
26 | | declare one full-time, permanent job for every 1,820 man |
|
| | 10200SB2182ham001 | - 5 - | LRB102 16377 JWD 26541 a |
|
|
1 | | hours worked per year under that contract. Vacations, paid |
2 | | holidays, and sick time are included in this computation. |
3 | | Overtime is not considered a part of regular hours. |
4 | | "Qualified tangible personal property" means: |
5 | | electrical systems and equipment; climate control and |
6 | | chilling equipment and systems; mechanical systems and |
7 | | equipment; monitoring and secure systems; emergency |
8 | | generators; hardware; computers; servers; data storage |
9 | | devices; network connectivity equipment; racks; cabinets; |
10 | | telecommunications cabling infrastructure; raised floor |
11 | | systems; peripheral components or systems; software; |
12 | | mechanical, electrical, or plumbing systems; battery |
13 | | systems; cooling systems and towers; temperature control |
14 | | systems; other cabling; and other data center |
15 | | infrastructure equipment and systems necessary to operate |
16 | | qualified tangible personal property, including fixtures; |
17 | | and component parts of any of the foregoing, including |
18 | | installation, maintenance, repair, refurbishment, and |
19 | | replacement of qualified tangible personal property to |
20 | | generate, transform, transmit, distribute, or manage |
21 | | electricity necessary to operate qualified tangible |
22 | | personal property; and all other tangible personal |
23 | | property that is essential to the operations of a computer |
24 | | data center. "Qualified tangible personal property" also |
25 | | includes building materials physically incorporated in to |
26 | | the qualifying data center. |
|
| | 10200SB2182ham001 | - 6 - | LRB102 16377 JWD 26541 a |
|
|
1 | | "Tenant" means an entity that leases, subleases, or |
2 | | licenses with the owner or operator of a qualified data |
3 | | center that is certified under this Section to use or |
4 | | occupy all or part of the data center for a period of at |
5 | | least one year. |
6 | | To document the exemption allowed under this Section, the |
7 | | retailer must obtain from the purchaser a copy of the |
8 | | certificate of eligibility issued by the Department. |
9 | | (d) New and existing data centers seeking a certificate of |
10 | | exemption for new or existing facilities shall apply to the |
11 | | Department in the manner specified by the Department. The |
12 | | Department shall determine the duration of the certificate of |
13 | | exemption awarded under this Act. The duration of the |
14 | | certificate of exemption may not exceed 20 calendar years. The |
15 | | Department and any data center seeking the exemption, |
16 | | including a data center operator on behalf of itself and its |
17 | | tenants, must enter into a memorandum of understanding that at |
18 | | a minimum provides: |
19 | | (1) the details for determining the amount of capital |
20 | | investment to be made; |
21 | | (2) the number of new jobs created; |
22 | | (3) the timeline for achieving the capital investment |
23 | | and new job goals; |
24 | | (4) the repayment obligation should those goals not be |
25 | | achieved and any conditions under which repayment by the |
26 | | qualifying data center or data center tenant claiming the |
|
| | 10200SB2182ham001 | - 7 - | LRB102 16377 JWD 26541 a |
|
|
1 | | exemption will be required; |
2 | | (5) the duration of the exemption; and |
3 | | (6) other provisions as deemed necessary by the |
4 | | Department. |
5 | | A data center and an associated tenant may also enter into |
6 | | an ancillary memorandum of understanding, as prescribed by the |
7 | | Department, for purposes of receipt of the exemption. |
8 | | (e) Beginning July 1, 2021, and each year thereafter, the |
9 | | Department shall annually report to the Governor and the |
10 | | General Assembly on the outcomes and effectiveness of Public |
11 | | Act 101-31 that shall include the following: |
12 | | (1) the name of each recipient business; |
13 | | (2) the location of the project; |
14 | | (3) the estimated value of the credit; |
15 | | (4) the number of new jobs and, if applicable, |
16 | | retained jobs pledged as a result of the project; and |
17 | | (5) whether or not the project is located in an |
18 | | underserved area. |
19 | | (f) New and existing data centers seeking a certificate of |
20 | | exemption related to the rehabilitation or construction of |
21 | | data centers in the State shall require the contractor and all |
22 | | subcontractors to comply with the requirements of Section |
23 | | 30-22 of the Illinois Procurement Code as they apply to |
24 | | responsible bidders and to present satisfactory evidence of |
25 | | that compliance to the Department. |
26 | | (g) New and existing data centers seeking a certificate of |
|
| | 10200SB2182ham001 | - 8 - | LRB102 16377 JWD 26541 a |
|
|
1 | | exemption for the rehabilitation or construction of data |
2 | | centers in the State shall require the contractor to enter |
3 | | into a project labor agreement approved by the Department. |
4 | | Within 180 days after the effective date of this amendatory |
5 | | Act of the 120nd General Assembly, all new and existing data |
6 | | centers seeking a certificate of exemption under this Section |
7 | | shall require the contractor to enter into a labor peace |
8 | | agreement with any union representing workers who operate and |
9 | | maintain a critical system or equipment used or maintained by |
10 | | the data center. For purposes of this subsection, "critical |
11 | | system or equipment" includes, but is not limited to, pumps, |
12 | | chillers and coolers, fire line safety equipment, backup power |
13 | | generators, building automation system controls, and water |
14 | | treatment systems. |
15 | | (h) Any qualifying data center issued a certificate of |
16 | | exemption under this Section must annually report to the |
17 | | Department the total data center tax benefits that are |
18 | | received by the business. Reports are due no later than May 31 |
19 | | of each year and shall cover the previous calendar year. The |
20 | | first report is for the 2019 calendar year and is due no later |
21 | | than May 31, 2020. |
22 | | To the extent that a business issued a certificate of |
23 | | exemption under this Section has obtained an Enterprise Zone |
24 | | Building Materials Exemption Certificate or a High Impact |
25 | | Business Building Materials Exemption Certificate, no |
26 | | additional reporting for those building materials exemption |
|
| | 10200SB2182ham001 | - 9 - | LRB102 16377 JWD 26541 a |
|
|
1 | | benefits is required under this Section. |
2 | | Failure to file a report under this subsection (h) may |
3 | | result in suspension or revocation of the certificate of |
4 | | exemption. Factors to be considered in determining whether a |
5 | | data center certificate of exemption shall be suspended or |
6 | | revoked include, but are not limited to, prior compliance with |
7 | | the reporting requirements, cooperation in discontinuing and |
8 | | correcting violations, the extent of the violation, and |
9 | | whether the violation was willful or inadvertent. |
10 | | (i) The Department shall not issue any new certificates of |
11 | | exemption under the provisions of this Section after July 1, |
12 | | 2029. This sunset shall not affect any existing certificates |
13 | | of exemption in effect on July 1, 2029.
|
14 | | (j) The Department shall adopt rules to implement and |
15 | | administer this Section. |
16 | | (k) The Department is authorized to conform existing |
17 | | memorandums of understanding with the provisions of this |
18 | | Section. |
19 | | (Source: P.A. 101-31, eff. 6-28-19; 101-604, eff. 12-13-19.)
|
20 | | Section 99. Effective date. This Act takes effect upon |
21 | | becoming law.".
|