|
| | 103RD GENERAL ASSEMBLY
State of Illinois
2023 and 2024 HB3491 Introduced 2/17/2023, by Rep. Matt Hanson SYNOPSIS AS INTRODUCED: |
| 820 ILCS 130/4 | from Ch. 48, par. 39s-4 | 820 ILCS 130/11 | from Ch. 48, par. 39s-11 |
|
Amends the Prevailing Wage Act. Provides that any laborer, worker, or mechanic who is employed by the contractor or by any lower tier sub-contractor and is paid for services in a sum less than the prevailing wage rates for work performed on a project shall have a right of action for whatever difference there may be between the amount so paid and the prevailing rates required to be paid for work performed on the project. Makes other changes.
|
| |
| | A BILL FOR |
|
|
| | HB3491 | | LRB103 26348 SPS 52709 b |
|
|
1 | | AN ACT concerning employment.
|
2 | | Be it enacted by the People of the State of Illinois,
|
3 | | represented in the General Assembly:
|
4 | | Section 5. The Prevailing Wage Act is amended by changing |
5 | | Sections 4 and 11 as follows:
|
6 | | (820 ILCS 130/4) (from Ch. 48, par. 39s-4)
|
7 | | Sec. 4. Ascertaining prevailing wage. |
8 | | (a) The prevailing rate of wages paid to individuals |
9 | | covered under this Act shall not be less than the
rate that |
10 | | prevails for work of a similar character on public works in the |
11 | | locality in which the
work is performed under collective |
12 | | bargaining agreements or understandings between employers
or |
13 | | employer associations and bona fide labor organizations |
14 | | relating to each craft or type of
worker or mechanic needed to |
15 | | execute the contract or perform such work, and collective
|
16 | | bargaining agreements or understandings successor thereto, |
17 | | provided that said employers or
members of said employer |
18 | | associations employ at least 30% of the laborers, workers, or
|
19 | | mechanics in the same trade or occupation in the locality |
20 | | where the work is being performed. |
21 | | (b) If the prevailing rates of wages and fringe benefits |
22 | | cannot reasonably and fairly be applied
in any locality |
23 | | because no such agreements or understandings exist, the |
|
| | HB3491 | - 2 - | LRB103 26348 SPS 52709 b |
|
|
1 | | Department of Labor
shall determine the rates and fringe |
2 | | benefits for the same or most similar work in the nearest and
|
3 | | most similar neighboring locality in which such agreements or |
4 | | understandings exist. The
Department of Labor shall keep a |
5 | | record of its findings available for inspection by any |
6 | | interested
party in the office of the Department of Labor. |
7 | | (c) In the event it is determined, after a written |
8 | | objection is filed and hearing is held in
accordance with |
9 | | Section 9 of this Act, that less than 30% of the laborers, |
10 | | workers, or
mechanics in a particular trade or occupation in |
11 | | the locality where the work is performed receive
a |
12 | | collectively bargained rate of wage, then the average wage |
13 | | paid to such laborers, workers, or
mechanics in the same trade |
14 | | or occupation in the locality for the 12-month period |
15 | | preceding
the Department of Labor's annual determination shall |
16 | | be the prevailing rate of wage. |
17 | | (d) The public body awarding any contract for public work |
18 | | or
otherwise undertaking any public works shall
specify in the |
19 | | call for bids for the
contract, or where the public body |
20 | | performs the work without letting the contract in a written |
21 | | instrument provided to the contractor, that the general |
22 | | prevailing rate of wages in the locality for
each craft or type |
23 | | of worker or mechanic needed to execute the contract
or |
24 | | perform such work, also the general prevailing rate for legal |
25 | | holiday
and overtime work, as ascertained by the
Department of |
26 | | Labor shall be paid for each craft or type of worker
needed to |
|
| | HB3491 | - 3 - | LRB103 26348 SPS 52709 b |
|
|
1 | | execute the contract or to perform such work, and it shall be
|
2 | | mandatory upon the contractor to whom the contract is awarded |
3 | | and upon
any subcontractor under him, and where the public |
4 | | body performs the
work, upon the public body, to pay not less |
5 | | than the specified rates to
all laborers, workers and |
6 | | mechanics employed by them in the execution of
the contract or |
7 | | such work. Compliance with this Act is a matter of statewide |
8 | | concern, and a public body may not opt out of any provisions |
9 | | herein. |
10 | | (e) The public body or other entity awarding the
contract |
11 | | shall cause to be inserted in the project specifications and |
12 | | the
contract a stipulation to the
effect that not less than the |
13 | | prevailing rate of wages as found by the
Department of Labor or |
14 | | determined by the court on review
shall be paid to all |
15 | | laborers, workers and mechanics performing work
under the |
16 | | contract.
|
17 | | (f) When a public body or other entity covered by this Act |
18 | | has awarded work to a contractor without a public bid, |
19 | | contract or project specification, such public body or other |
20 | | entity shall comply with subsection (e) by providing the |
21 | | contractor with written notice on the purchase order related |
22 | | to the work to be done or on a separate document indicating |
23 | | that not less than the prevailing rate of wages ascertained by |
24 | | the Department of Labor or determined by the court on review |
25 | | shall be paid to all laborers, workers, and mechanics |
26 | | performing work on the project. |
|
| | HB3491 | - 4 - | LRB103 26348 SPS 52709 b |
|
|
1 | | (g) Where a complaint is made and the Department of Labor |
2 | | determines that a violation occurred, the Department of Labor |
3 | | shall determine if proper written notice under this Section 4 |
4 | | was given. If proper written notice was not provided to the |
5 | | contractor by the public body or other entity, the Department |
6 | | of Labor shall order the public body or other entity to pay any |
7 | | interest, penalties or fines that would have been owed by the |
8 | | contractor if proper written notice were provided. The failure |
9 | | by a public body or other entity to provide written notice does |
10 | | not relieve the contractor of the duty to comply with the |
11 | | prevailing wage rate, nor of the obligation to pay any back |
12 | | wages, as determined under this Act. For the purposes of this |
13 | | subsection, back wages shall be limited to the difference |
14 | | between the actual amount paid and the prevailing rate of |
15 | | wages required to be paid for the project. The failure of a |
16 | | public body or other entity to provide written notice under |
17 | | this Section 4 does not diminish the right of a laborer, |
18 | | worker, or mechanic to the prevailing rate of wages as |
19 | | determined under this Act. |
20 | | Any laborer, worker, or mechanic who is employed by the |
21 | | contractor or by any sub-contractor and is paid for services |
22 | | in a sum less than the prevailing wage rates for work performed |
23 | | on a project shall have a right of action for whatever |
24 | | difference there may be between (i) the amount so paid and (ii) |
25 | | the prevailing rates required to be paid for work performed on |
26 | | the project. |
|
| | HB3491 | - 5 - | LRB103 26348 SPS 52709 b |
|
|
1 | | (h) It shall also be mandatory upon the contractor to whom |
2 | | the contract is
awarded
to insert into each subcontract and |
3 | | into the project specifications for each
subcontract a written |
4 | | stipulation to the effect that not less than the
prevailing
|
5 | | rate of wages shall be paid to all laborers, workers, and |
6 | | mechanics performing
work under the contract. It shall also be |
7 | | mandatory upon each subcontractor to
cause to be inserted into |
8 | | each lower tiered subcontract
and into the project |
9 | | specifications for each lower tiered subcontract a
stipulation |
10 | | to the effect that not less
than the prevailing rate of wages |
11 | | shall be paid to all laborers, workers, and
mechanics |
12 | | performing work under the contract. A contractor or |
13 | | subcontractor who
fails to comply with this subsection is in |
14 | | violation of this Act.
|
15 | | (i) When a contractor has awarded work to a subcontractor |
16 | | without a contract or contract specification, the contractor |
17 | | shall comply with subsection (h) by providing a subcontractor |
18 | | with a written statement indicating that not less than the |
19 | | prevailing rate of wages shall be paid to all laborers, |
20 | | workers, and mechanics performing work on the project. A |
21 | | contractor or subcontractor who fails to comply with this |
22 | | subsection is in violation of this Act. |
23 | | (j) Where a complaint is made and the Department of Labor |
24 | | determines that a violation has occurred, the Department of |
25 | | Labor shall determine if proper written notice under this |
26 | | Section 4 was given. If proper written notice was not provided |
|
| | HB3491 | - 6 - | LRB103 26348 SPS 52709 b |
|
|
1 | | to the subcontractor by the contractor, the Department of |
2 | | Labor shall order the contractor to pay any interest, |
3 | | penalties, or fines that would have been owed by the |
4 | | subcontractor if proper written notice were provided. The |
5 | | failure by a contractor to provide written notice to a |
6 | | subcontractor does not relieve the subcontractor of the duty |
7 | | to comply with the prevailing wage rate, nor of the obligation |
8 | | to pay any back wages, as determined under this Act. For the |
9 | | purposes of this subsection, back wages shall be limited to |
10 | | the difference between the actual amount paid and the |
11 | | prevailing rate of wages required for the project. However, if |
12 | | proper written notice was not provided to the contractor by |
13 | | the public body or other entity under this Section 4, the |
14 | | Department of Labor shall order the public body or other |
15 | | entity to pay any interest, penalties, or fines that would |
16 | | have been owed by the subcontractor if proper written notice |
17 | | were provided. The failure by a public body or other entity to |
18 | | provide written notice does not relieve the subcontractor of |
19 | | the duty to comply with the prevailing wage rate, nor of the |
20 | | obligation to pay any back wages, as determined under this |
21 | | Act. For the purposes of this subsection, back wages shall be |
22 | | limited to the difference between the actual amount paid and |
23 | | the prevailing rate of wages required for the project. The |
24 | | failure to provide written notice by a public body, other |
25 | | entity, or contractor does not diminish the right of a |
26 | | laborer, worker, or mechanic to the prevailing rate of wages |
|
| | HB3491 | - 7 - | LRB103 26348 SPS 52709 b |
|
|
1 | | as determined under this Act. |
2 | | (k) A public body or other entity shall also require in all |
3 | | contractor's and subcontractor's bonds
that the contractor or |
4 | | subcontractor include such provision as will guarantee the
|
5 | | faithful performance of such prevailing wage clause as |
6 | | provided by
contract or other written instrument. All bid |
7 | | specifications shall list the specified rates to all
laborers, |
8 | | workers and mechanics in the locality for each craft or type of
|
9 | | worker or mechanic needed to execute the contract.
|
10 | | (l) If the Department of Labor
revises the prevailing rate |
11 | | of hourly wages to be paid by the public body or other entity, |
12 | | the
revised rate shall apply to such contract, and the public |
13 | | body or other entity shall be
responsible to notify the |
14 | | contractor and each subcontractor, of the revised
rate.
|
15 | | The public body or other entity shall discharge its duty |
16 | | to notify of the revised rates by inserting a written |
17 | | stipulation in all contracts or other written instruments that |
18 | | states the prevailing rate of wages are revised by the |
19 | | Department of Labor and are available on the Department's |
20 | | official website. This shall be deemed to be proper |
21 | | notification of any rate changes under this subsection. |
22 | | (m) Two or more investigatory hearings under this Section |
23 | | on the issue
of establishing a new prevailing wage |
24 | | classification for a particular craft
or type of worker shall |
25 | | be consolidated in a single hearing before the
Department. The |
26 | | party requesting
a consolidated investigatory hearing shall |
|
| | HB3491 | - 8 - | LRB103 26348 SPS 52709 b |
|
|
1 | | have the burden of establishing that
there is no existing |
2 | | prevailing wage classification for the particular craft or
|
3 | | type of worker in any of the localities under consideration.
|
4 | | (n) It shall be mandatory upon the contractor or |
5 | | construction manager
to whom a contract for public works is |
6 | | awarded to post, at a
location on the project site of the |
7 | | public works that is
easily accessible to the workers engaged |
8 | | on the project,
the prevailing wage rates for each craft or |
9 | | type of worker
or mechanic needed to execute the contract or |
10 | | project or
work to be performed. In lieu of posting on the |
11 | | project site of the public works, a contractor which has a |
12 | | business location where laborers, workers, and mechanics |
13 | | regularly visit may: (1) post in a conspicuous location at |
14 | | that business the current prevailing wage rates for each |
15 | | county in which the contractor is performing work; or (2) |
16 | | provide such laborer, worker, or mechanic engaged on the |
17 | | public works project a written notice indicating the |
18 | | prevailing wage rates for the public works project. A failure |
19 | | to post or provide a prevailing wage
rate as required by this |
20 | | Section is a violation of this Act.
|
21 | | (Source: P.A. 100-1177, eff. 6-1-19 .)
|
22 | | (820 ILCS 130/11) (from Ch. 48, par. 39s-11)
|
23 | | Sec. 11. No public works project shall be instituted |
24 | | unless the
provisions of this Act have been complied with. The |
25 | | provisions of this
Act shall not be applicable to Federal |
|
| | HB3491 | - 9 - | LRB103 26348 SPS 52709 b |
|
|
1 | | construction projects which
require a prevailing wage |
2 | | determination by the United States Secretary
of Labor. The |
3 | | Illinois Department of Labor represented by the Attorney
|
4 | | General is empowered to sue for injunctive relief against the |
5 | | awarding of
any contract or the continuation of work under any |
6 | | contract for public works
at a time when the prevailing wage |
7 | | prerequisites have not been met. Any
contract for public works |
8 | | awarded at a time when the prevailing wage prerequisites
had |
9 | | not been met shall be void as against public policy and the |
10 | | contractor
is prohibited from recovering any damages
for the |
11 | | voiding of the contract or pursuant to the terms of the |
12 | | contract.
The contractor is limited to a claim for amounts |
13 | | actually paid for labor
and materials supplied to the public |
14 | | body. Where objections to a determination
of the prevailing |
15 | | rate of
wages or a court action relative thereto is pending, |
16 | | the public body
shall not continue work on the project unless |
17 | | sufficient funds are
available to pay increased wages if such |
18 | | are finally determined or
unless the Department of Labor |
19 | | certifies such determination of the
prevailing rate of wages |
20 | | as correct.
|
21 | | Any laborer, worker or mechanic employed by the contractor |
22 | | or by any sub-contractor
under him who is paid for his services |
23 | | in a sum less than the prevailing stipulated
rates for work |
24 | | done under such contract, shall
have a right of action for |
25 | | whatever difference there may be between the
amount so paid, |
26 | | and the rates provided by the contract together with
costs and |
|
| | HB3491 | - 10 - | LRB103 26348 SPS 52709 b |
|
|
1 | | such reasonable attorney's fees as
shall be allowed by the |
2 | | court. Such contractor or subcontractor shall also
be liable |
3 | | to the
Department of Labor for
20% of
such underpayments and |
4 | | shall be additionally liable to the laborer, worker
or |
5 | | mechanic for punitive damages in the amount of
2% of the amount |
6 | | of any
such penalty to the
State for underpayments for each |
7 | | month following the date of payment during
which such |
8 | | underpayments
remain unpaid. Where a second or subsequent |
9 | | action to recover underpayments is brought against a |
10 | | contractor or subcontractor and the contractor or |
11 | | subcontractor is found liable for underpayments to any |
12 | | laborer, worker, or mechanic, the contractor or subcontractor |
13 | | shall also be liable to the Department of Labor for 50% of the |
14 | | underpayments payable as a result of the second or subsequent |
15 | | action, and shall be additionally liable for 5% of the amount |
16 | | of any such penalty to the State for underpayments for each |
17 | | month following the date of payment during which the |
18 | | underpayments remain unpaid. The Department shall also have a |
19 | | right of action on behalf
of any individual who has a right of |
20 | | action under this Section. An action brought
to recover same |
21 | | shall be deemed to be a suit for wages, and any and all
|
22 | | judgments entered therein shall have the same force and effect |
23 | | as other
judgments for wages.
The action shall be brought |
24 | | within 5 years from the date of the failure to pay the wages or |
25 | | compensation. At the request of any laborer, workman or |
26 | | mechanic
employed by the contractor or by any subcontractor |
|
| | HB3491 | - 11 - | LRB103 26348 SPS 52709 b |
|
|
1 | | under him who is paid
less than the prevailing wage rate |
2 | | required by this Act, the Department
of Labor may take an |
3 | | assignment of such wage claim in trust for the assigning
|
4 | | laborer, workman or mechanic and may bring any legal action |
5 | | necessary to
collect such claim, and the contractor or |
6 | | subcontractor shall be required
to pay the costs incurred in |
7 | | collecting such claim.
|
8 | | (Source: P.A. 98-328, eff. 1-1-14.)
|