3everything after the enacting clause with the following:
 
4    "Section 5. The State Prompt Payment Act is amended by
5changing Section 7 as follows:
 
6    (30 ILCS 540/7)  (from Ch. 127, par. 132.407)
7    Sec. 7. Payments to subcontractors and material suppliers.
8    (a) When a State official or agency responsible for
9administering a contract submits a voucher to the Comptroller
10for payment to a contractor, that State official or agency
11shall promptly make available electronically the voucher
12number, the date of the voucher, and the amount of the voucher.
13The State official or agency responsible for administering the
14contract shall provide subcontractors and material suppliers,
15known to the State official or agency, with instructions on
16how to access the electronic information.

 

 

10400HB0879ham001- 2 -LRB104 04777 HLH 36879 a

1    (a-5) When a contractor receives any payment, the
2contractor shall pay each subcontractor and material supplier
3electronically within 10 business days or 15 calendar days,
4whichever occurs earlier, or, if paid by a printed check, the
5printed check must be postmarked within 10 business days or 15
6calendar days, whichever occurs earlier, after receiving
7payment in proportion to the work completed by each
8subcontractor and material supplier its application or pay
9estimate, plus interest received under this Act. When a
10contractor receives any payment, the contractor shall pay each
11lower-tiered subcontractor and material supplier and each
12subcontractor and material supplier shall make payment to its
13own respective subcontractors and material suppliers. If the
14contractor receives less than the full payment due under the
15public construction contract, the contractor shall be
16obligated to disburse on a pro rata basis those funds
17received, plus interest received under this Act, with the
18contractor, subcontractors and material suppliers each
19receiving a prorated portion based on the amount of payment
20each has earned. When, however, the State official or agency
21does not release the full payment due under the contract
22because there are specific areas of work or materials the
23State agency or official has determined are not suitable for
24payment, then those specific subcontractors or material
25suppliers involved shall not be paid for that portion of work
26rejected or deemed not suitable for payment and all other

 

 

10400HB0879ham001- 3 -LRB104 04777 HLH 36879 a

1subcontractors and suppliers shall be paid based upon the
2amount of payment each has earned, plus interest received
3under this Act.
4    (a-10) For construction contracts with the Department of
5Transportation or the Capital Development Board, the
6contractor, subcontractor, or material supplier, regardless of
7tier, shall not offset, decrease, or diminish payment or
8payments that are due to its subcontractors or material
9suppliers without reasonable cause.
10    A contractor, who refuses to make prompt payment within 10
11business days or 15 calendar days, whichever occurs earlier,
12after receiving payment, in whole or in part, shall provide to
13the subcontractor or material supplier and the public owner or
14its agent, a written notice of that refusal. The written
15notice shall be made by a contractor no later than 5 calendar
16days after payment is received by the contractor. The written
17notice shall identify the Department of Transportation's or
18the Capital Development Board's contract, any subcontract or
19material purchase agreement, a detailed reason for refusal,
20the value of the payment to be withheld, and the specific
21remedial actions required of the subcontractor or material
22supplier so that payment may be made. Written notice of
23refusal may be given in a form and method which is acceptable
24to the parties and public owner.
25    (b) If the contractor, without reasonable cause, fails to
26make full payment of amounts due under subsection (a) to its

 

 

10400HB0879ham001- 4 -LRB104 04777 HLH 36879 a

1subcontractors and material suppliers within 10 business days
2or 15 calendar days, whichever occurs earlier, after receipt
3of payment from the State official or agency, the contractor
4shall pay to its subcontractors and material suppliers, in
5addition to the payment due them, interest in the amount of 2%
6per month, calculated from the expiration of the
710-business-day period or the 15-calendar-day period until
8fully paid. This subsection shall further apply to any
9payments made by subcontractors and material suppliers to
10their subcontractors and material suppliers and to all
11payments made to lower tier subcontractors and material
12suppliers throughout the contracting chain.
13        (1) If a contractor, without reasonable cause, fails
14    to make payment in full as provided in subsection (a-5)
15    within 10 business days or 15 calendar days, whichever
16    occurs earlier, after receipt of payment under the public
17    construction contract, any subcontractor or material
18    supplier to whom payments are owed may file a written
19    notice and request for administrative hearing with the
20    State official or agency setting forth the amount owed by
21    the contractor and the contractor's failure to timely pay
22    the amount owed. The written notice and request for
23    administrative hearing shall identify the public
24    construction contract, the contractor, and the amount
25    owed, and shall contain a sworn statement or attestation
26    to verify the accuracy of the notice. The notice and

 

 

10400HB0879ham001- 5 -LRB104 04777 HLH 36879 a

1    request for administrative hearing shall be filed with the
2    State official for the public construction contract, with
3    a copy of the notice concurrently provided to the
4    contractor. Notice to the State official may be made by
5    certified or registered mail, messenger service, or
6    personal service, and must include proof of delivery to
7    the State official.
8        (2) The State official or agency, within 15 calendar
9    days after receipt of a subcontractor's or material
10    supplier's written notice and request for administrative
11    hearing, shall hold a hearing convened by an
12    administrative law judge to determine whether the
13    contractor withheld payment, without reasonable cause,
14    from the subcontractors or material suppliers and what
15    amount, if any, is due to the subcontractors or material
16    suppliers, and the reasonable cause or causes asserted by
17    the contractor. The State official or agency shall provide
18    appropriate notice to the parties of the date, time, and
19    location of the hearing. Each contractor, subcontractor,
20    or material supplier has the right to be represented by
21    counsel at a hearing and to cross-examine witnesses and
22    challenge documents. Upon the request of the subcontractor
23    or material supplier and a showing of good cause,
24    reasonable continuances may be granted by the
25    administrative law judge.
26        (3) Upon a finding by the administrative law judge

 

 

10400HB0879ham001- 6 -LRB104 04777 HLH 36879 a

1    that the contractor failed to make payment in full,
2    without reasonable cause, as provided in subsection
3    (a-10), then the administrative law judge shall, in
4    writing, order the contractor to pay the amount owed to
5    the subcontractors or material suppliers plus interest
6    within 15 calendar days after the order.
7        (4) If a contractor fails to make full payment as
8    ordered under paragraph (3) of this subsection (b) within
9    15 days after the administrative law judge's order, then
10    the contractor shall be barred from entering into a State
11    public construction contract for a period of one year
12    beginning on the date of the administrative law judge's
13    order.
14        (5) If, on 2 or more occasions within a
15    3-calendar-year period, there is a finding by an
16    administrative law judge that the contractor failed to
17    make payment in full, without reasonable cause, and a
18    written order was issued to a contractor under paragraph
19    (3) of this subsection (b), then the contractor shall be
20    barred from entering into a State public construction
21    contract for a period of 6 months beginning on the date of
22    the administrative law judge's second written order, even
23    if the payments required under the orders were made in
24    full.
25        (6) If a contractor fails to make full payment as
26    ordered under paragraph (4) of this subsection (b), the

 

 

10400HB0879ham001- 7 -LRB104 04777 HLH 36879 a

1    subcontractor or material supplier may, within 30 days of
2    the date of that order, petition the State agency for an
3    order for reasonable attorney's fees and costs incurred in
4    the prosecution of the action under this subsection (b).
5    Upon that petition and taking of additional evidence, as
6    may be required, the administrative law judge may issue a
7    supplemental order directing the contractor to pay those
8    reasonable attorney's fees and costs.
9        (7) The written order of the administrative law judge
10    shall be final and appealable under the Administrative
11    Review Law.
12    (b-5) On or before July 2021, the Department of
13Transportation shall publish on its website a searchable
14database that allows for queries for each active construction
15contract by the name of a subcontractor or the pay item such
16that each pay item is associated with either the prime
17contractor or a subcontractor.
18    (c) This Section shall not be construed to in any manner
19diminish, negate, or interfere with the
20contractor-subcontractor or contractor-material supplier
21relationship or commercially useful function.
22    (d) This Section shall not preclude, bar, or stay the
23rights, remedies, and defenses available to the parties by way
24of the operation of their contract, purchase agreement, the
25Mechanics Lien Act, or the Public Construction Bond Act.
26    (e) State officials and agencies may adopt rules as may be

 

 

10400HB0879ham001- 8 -LRB104 04777 HLH 36879 a

1deemed necessary in order to establish the formal procedures
2required under this Section.
3    (f) As used in this Section:
4    "Payment" means the discharge of an obligation in money or
5other valuable consideration or thing delivered in full or
6partial satisfaction of an obligation to pay. "Payment" shall
7include interest paid pursuant to this Act.
8    "Reasonable cause" may include, but is not limited to,
9unsatisfactory workmanship or materials; failure to provide
10documentation required by the contract, subcontract, or
11material purchase agreement; claims made against the
12Department of Transportation, the Capital Development Board,
13or the subcontractor pursuant to subsection (c) of Section 23
14of the Mechanics Lien Act or the Public Construction Bond Act;
15judgments, levies, garnishments, or other court-ordered
16assessments or offsets in favor of the Department of
17Transportation, the Capital Development Board, or other State
18agency entered against a subcontractor or material supplier.
19"Reasonable cause" does not include payments issued to the
20contractor that create a negative or reduced valuation pay
21application or pay estimate due to a reduction of contract
22quantities or work not performed or provided by the
23subcontractor or material supplier; the interception or
24withholding of funds for reasons not related to the
25subcontractor's or material supplier's work on the contract;
26anticipated claims or assessments of third parties not a party

 

 

10400HB0879ham001- 9 -LRB104 04777 HLH 36879 a

1related to the contract or subcontract; asserted claims or
2assessments of third parties that are not authorized by court
3order, administrative tribunal, or statute. "Reasonable cause"
4further does not include the withholding, offset, or reduction
5of payment, in whole or in part, due to the assessment of
6liquidated damages or penalties assessed by the Department of
7Transportation or the Capital Development Board against the
8contractor, unless the subcontractor's performance or supplied
9materials were the sole and proximate cause of the liquidated
10damage or penalty.
11(Source: P.A. 100-43, eff. 8-9-17; 100-376, eff. 1-1-18;
12100-863, eff. 8-14-18; 101-524, eff. 1-1-20.)".