|
| | HB3185 Engrossed | | LRB104 10629 HLH 20706 b |
|
|
| 1 | | AN ACT concerning finance. |
| 2 | | Be it enacted by the People of the State of Illinois, |
| 3 | | represented in the General Assembly: |
| 4 | | Section 5. The State Prompt Payment Act is amended by |
| 5 | | changing Section 7 as follows: |
| 6 | | (30 ILCS 540/7) (from Ch. 127, par. 132.407) |
| 7 | | Sec. 7. Payments to subcontractors and material suppliers. |
| 8 | | (a) When a State official or agency responsible for |
| 9 | | administering a contract submits a voucher to the Comptroller |
| 10 | | for payment to a contractor, that State official or agency |
| 11 | | shall promptly make available electronically the voucher |
| 12 | | number, the date of the voucher, and the amount of the voucher. |
| 13 | | The State official or agency responsible for administering the |
| 14 | | contract shall provide subcontractors and material suppliers, |
| 15 | | known to the State official or agency, with instructions on |
| 16 | | how to access the electronic information. |
| 17 | | (a-5) When a contractor receives any payment, the |
| 18 | | contractor shall pay each subcontractor and material supplier |
| 19 | | electronically within 10 business days or 15 calendar days, |
| 20 | | whichever occurs earlier, or, if paid by a printed check, the |
| 21 | | printed check must be postmarked within 10 business days or 15 |
| 22 | | calendar days, whichever occurs earlier, after receiving |
| 23 | | payment in proportion to the work completed by each |
|
| | HB3185 Engrossed | - 2 - | LRB104 10629 HLH 20706 b |
|
|
| 1 | | subcontractor and material supplier its application or pay |
| 2 | | estimate, plus interest received under this Act. When a |
| 3 | | contractor receives any payment, the contractor shall pay each |
| 4 | | lower-tiered subcontractor and material supplier and each |
| 5 | | subcontractor and material supplier shall make payment to its |
| 6 | | own respective subcontractors and material suppliers. If the |
| 7 | | contractor receives less than the full payment due under the |
| 8 | | public construction contract, the contractor shall be |
| 9 | | obligated to disburse on a pro rata basis those funds |
| 10 | | received, plus interest received under this Act, with the |
| 11 | | contractor, subcontractors and material suppliers each |
| 12 | | receiving a prorated portion based on the amount of payment |
| 13 | | each has earned. When, however, the State official or agency |
| 14 | | does not release the full payment due under the contract |
| 15 | | because there are specific areas of work or materials the |
| 16 | | State agency or official has determined are not suitable for |
| 17 | | payment, then those specific subcontractors or material |
| 18 | | suppliers involved shall not be paid for that portion of work |
| 19 | | rejected or deemed not suitable for payment and all other |
| 20 | | subcontractors and suppliers shall be paid based upon the |
| 21 | | amount of payment each has earned, plus interest received |
| 22 | | under this Act. |
| 23 | | (a-10) For construction contracts with the Department of |
| 24 | | Transportation or the Capital Development Board, the |
| 25 | | contractor, subcontractor, or material supplier, regardless of |
| 26 | | tier, shall not offset, decrease, or diminish payment or |
|
| | HB3185 Engrossed | - 3 - | LRB104 10629 HLH 20706 b |
|
|
| 1 | | payments that are due to its subcontractors or material |
| 2 | | suppliers without reasonable cause. |
| 3 | | A contractor, who refuses to make prompt payment within 10 |
| 4 | | business days or 15 calendar days, whichever occurs earlier, |
| 5 | | after receiving payment, in whole or in part, shall provide to |
| 6 | | the subcontractor or material supplier and the public owner or |
| 7 | | its agent, a written notice of that refusal. The written |
| 8 | | notice shall be made by a contractor no later than 5 calendar |
| 9 | | days after payment is received by the contractor. The written |
| 10 | | notice shall identify the Department of Transportation's or |
| 11 | | the Capital Development Board's contract, any subcontract or |
| 12 | | material purchase agreement, a detailed reason for refusal, |
| 13 | | the value of the payment to be withheld, and the specific |
| 14 | | remedial actions required of the subcontractor or material |
| 15 | | supplier so that payment may be made. Written notice of |
| 16 | | refusal may be given in a form and method which is acceptable |
| 17 | | to the parties and public owner. |
| 18 | | (b) If the contractor, without reasonable cause, fails to |
| 19 | | make full payment of amounts due under subsection (a) to its |
| 20 | | subcontractors and material suppliers within 10 business days |
| 21 | | or 15 calendar days, whichever occurs earlier, after receipt |
| 22 | | of payment from the State official or agency, the contractor |
| 23 | | shall pay to its subcontractors and material suppliers, in |
| 24 | | addition to the payment due them, interest in the amount of 2% |
| 25 | | per month, calculated from the expiration of the |
| 26 | | 10-business-day period or the 15-calendar-day period until |
|
| | HB3185 Engrossed | - 4 - | LRB104 10629 HLH 20706 b |
|
|
| 1 | | fully paid. This subsection shall further apply to any |
| 2 | | payments made by subcontractors and material suppliers to |
| 3 | | their subcontractors and material suppliers and to all |
| 4 | | payments made to lower tier subcontractors and material |
| 5 | | suppliers throughout the contracting chain. |
| 6 | | (1) If a contractor, without reasonable cause, fails |
| 7 | | to make payment in full as provided in subsection (a-5) |
| 8 | | within 10 business days or 15 calendar days, whichever |
| 9 | | occurs earlier, after receipt of payment under the public |
| 10 | | construction contract, any subcontractor or material |
| 11 | | supplier to whom payments are owed may file a written |
| 12 | | notice and request for administrative hearing with the |
| 13 | | State official or agency setting forth the amount owed by |
| 14 | | the contractor and the contractor's failure to timely pay |
| 15 | | the amount owed. The written notice and request for |
| 16 | | administrative hearing shall identify the public |
| 17 | | construction contract, the contractor, and the amount |
| 18 | | owed, and shall contain a sworn statement or attestation |
| 19 | | to verify the accuracy of the notice. The notice and |
| 20 | | request for administrative hearing shall be filed with the |
| 21 | | State official for the public construction contract, with |
| 22 | | a copy of the notice concurrently provided to the |
| 23 | | contractor. Notice to the State official may be made by |
| 24 | | certified or registered mail, messenger service, or |
| 25 | | personal service, and must include proof of delivery to |
| 26 | | the State official. |
|
| | HB3185 Engrossed | - 5 - | LRB104 10629 HLH 20706 b |
|
|
| 1 | | (2) The State official or agency, within 15 calendar |
| 2 | | days after receipt of a subcontractor's or material |
| 3 | | supplier's written notice and request for administrative |
| 4 | | hearing, shall hold a hearing convened by an |
| 5 | | administrative law judge to determine whether the |
| 6 | | contractor withheld payment, without reasonable cause, |
| 7 | | from the subcontractors or material suppliers and what |
| 8 | | amount, if any, is due to the subcontractors or material |
| 9 | | suppliers, and the reasonable cause or causes asserted by |
| 10 | | the contractor. The State official or agency shall provide |
| 11 | | appropriate notice to the parties of the date, time, and |
| 12 | | location of the hearing. Each contractor, subcontractor, |
| 13 | | or material supplier has the right to be represented by |
| 14 | | counsel at a hearing and to cross-examine witnesses and |
| 15 | | challenge documents. Upon the request of the subcontractor |
| 16 | | or material supplier and a showing of good cause, |
| 17 | | reasonable continuances may be granted by the |
| 18 | | administrative law judge. |
| 19 | | (3) Upon a finding by the administrative law judge |
| 20 | | that the contractor failed to make payment in full, |
| 21 | | without reasonable cause, as provided in subsection |
| 22 | | (a-10), then the administrative law judge shall, in |
| 23 | | writing, order the contractor to pay the amount owed to |
| 24 | | the subcontractors or material suppliers plus interest |
| 25 | | within 15 calendar days after the order. |
| 26 | | (4) If a contractor fails to make full payment as |
|
| | HB3185 Engrossed | - 6 - | LRB104 10629 HLH 20706 b |
|
|
| 1 | | ordered under paragraph (3) of this subsection (b) within |
| 2 | | 15 days after the administrative law judge's order, then |
| 3 | | the contractor shall be barred from entering into a State |
| 4 | | public construction contract for a period of one year |
| 5 | | beginning on the date of the administrative law judge's |
| 6 | | order. |
| 7 | | (5) If, on 2 or more occasions within a |
| 8 | | 3-calendar-year period, there is a finding by an |
| 9 | | administrative law judge that the contractor failed to |
| 10 | | make payment in full, without reasonable cause, and a |
| 11 | | written order was issued to a contractor under paragraph |
| 12 | | (3) of this subsection (b), then the contractor shall be |
| 13 | | barred from entering into a State public construction |
| 14 | | contract for a period of 6 months beginning on the date of |
| 15 | | the administrative law judge's second written order, even |
| 16 | | if the payments required under the orders were made in |
| 17 | | full. |
| 18 | | (6) If a contractor fails to make full payment as |
| 19 | | ordered under paragraph (4) of this subsection (b), the |
| 20 | | subcontractor or material supplier may, within 30 days of |
| 21 | | the date of that order, petition the State agency for an |
| 22 | | order for reasonable attorney's fees and costs incurred in |
| 23 | | the prosecution of the action under this subsection (b). |
| 24 | | Upon that petition and taking of additional evidence, as |
| 25 | | may be required, the administrative law judge may issue a |
| 26 | | supplemental order directing the contractor to pay those |
|
| | HB3185 Engrossed | - 7 - | LRB104 10629 HLH 20706 b |
|
|
| 1 | | reasonable attorney's fees and costs. |
| 2 | | (7) The written order of the administrative law judge |
| 3 | | shall be final and appealable under the Administrative |
| 4 | | Review Law. |
| 5 | | (b-5) On or before July 2021, the Department of |
| 6 | | Transportation shall publish on its website a searchable |
| 7 | | database that allows for queries for each active construction |
| 8 | | contract by the name of a subcontractor or the pay item such |
| 9 | | that each pay item is associated with either the prime |
| 10 | | contractor or a subcontractor. |
| 11 | | (c) This Section shall not be construed to in any manner |
| 12 | | diminish, negate, or interfere with the |
| 13 | | contractor-subcontractor or contractor-material supplier |
| 14 | | relationship or commercially useful function. |
| 15 | | (d) This Section shall not preclude, bar, or stay the |
| 16 | | rights, remedies, and defenses available to the parties by way |
| 17 | | of the operation of their contract, purchase agreement, the |
| 18 | | Mechanics Lien Act, or the Public Construction Bond Act. |
| 19 | | (e) State officials and agencies may adopt rules as may be |
| 20 | | deemed necessary in order to establish the formal procedures |
| 21 | | required under this Section. |
| 22 | | (f) As used in this Section: |
| 23 | | "Payment" means the discharge of an obligation in money or |
| 24 | | other valuable consideration or thing delivered in full or |
| 25 | | partial satisfaction of an obligation to pay. "Payment" shall |
| 26 | | include interest paid pursuant to this Act. |
|
| | HB3185 Engrossed | - 8 - | LRB104 10629 HLH 20706 b |
|
|
| 1 | | "Reasonable cause" may include, but is not limited to, |
| 2 | | unsatisfactory workmanship or materials; failure to provide |
| 3 | | documentation required by the contract, subcontract, or |
| 4 | | material purchase agreement; claims made against the |
| 5 | | Department of Transportation, the Capital Development Board, |
| 6 | | or the subcontractor pursuant to subsection (c) of Section 23 |
| 7 | | of the Mechanics Lien Act or the Public Construction Bond Act; |
| 8 | | judgments, levies, garnishments, or other court-ordered |
| 9 | | assessments or offsets in favor of the Department of |
| 10 | | Transportation, the Capital Development Board, or other State |
| 11 | | agency entered against a subcontractor or material supplier. |
| 12 | | "Reasonable cause" does not include payments issued to the |
| 13 | | contractor that create a negative or reduced valuation pay |
| 14 | | application or pay estimate due to a reduction of contract |
| 15 | | quantities or work not performed or provided by the |
| 16 | | subcontractor or material supplier; the interception or |
| 17 | | withholding of funds for reasons not related to the |
| 18 | | subcontractor's or material supplier's work on the contract; |
| 19 | | anticipated claims or assessments of third parties not a party |
| 20 | | related to the contract or subcontract; asserted claims or |
| 21 | | assessments of third parties that are not authorized by court |
| 22 | | order, administrative tribunal, or statute. "Reasonable cause" |
| 23 | | further does not include the withholding, offset, or reduction |
| 24 | | of payment, in whole or in part, due to the assessment of |
| 25 | | liquidated damages or penalties assessed by the Department of |
| 26 | | Transportation or the Capital Development Board against the |