4    "Section 5. The State Prompt Payment Act is amended by
5changing Sections 3-2, 3-6, and 7 as follows:
 
6    (30 ILCS 540/3-2)
7    Sec. 3-2. Beginning July 1, 1993, in any instance where a
8State official or agency is late in payment of a vendor's bill
9or invoice for goods or services furnished to the State, as
10defined in Section 1, properly approved in accordance with
11rules promulgated under Section 3-3, the State official or
12agency shall pay interest to the vendor in accordance with the
13following:
14        (1) (Blank). Any bill, except a bill submitted under
15    Article V of the Illinois Public Aid Code and except as
16    provided under paragraph (1.05) of this Section, approved

 

 

10400HB4288ham001- 2 -LRB104 17163 HLH 35361 a

1    for payment under this Section must be paid or the payment
2    issued to the payee within 60 days of receipt of a proper
3    bill or invoice. If payment is not issued to the payee
4    within this 60-day period, an interest penalty of 1.0% of
5    any amount approved and unpaid shall be added for each
6    month or fraction thereof after the end of this 60-day
7    period, until final payment is made. Any bill, except a
8    bill for pharmacy or nursing facility services or goods,
9    and except as provided under paragraph (1.05) of this
10    Section, submitted under Article V of the Illinois Public
11    Aid Code approved for payment under this Section must be
12    paid or the payment issued to the payee within 60 days
13    after receipt of a proper bill or invoice, and, if payment
14    is not issued to the payee within this 60-day period, an
15    interest penalty of 2.0% of any amount approved and unpaid
16    shall be added for each month or fraction thereof after
17    the end of this 60-day period, until final payment is
18    made. Any bill for pharmacy or nursing facility services
19    or goods submitted under Article V of the Illinois Public
20    Aid Code, except as provided under paragraph (1.05) of
21    this Section, and approved for payment under this Section
22    must be paid or the payment issued to the payee within 60
23    days of receipt of a proper bill or invoice. If payment is
24    not issued to the payee within this 60-day period, an
25    interest penalty of 1.0% of any amount approved and unpaid
26    shall be added for each month or fraction thereof after

 

 

10400HB4288ham001- 3 -LRB104 17163 HLH 35361 a

1    the end of this 60-day period, until final payment is
2    made.
3        (1.05) For State fiscal year 2012 and future fiscal
4    years, any bill approved for payment under this Section
5    must be paid or the payment issued to the payee within 90
6    days of receipt of a proper bill or invoice. If payment is
7    not issued to the payee within this 90-day period, an
8    interest penalty of 1.0% of any amount approved and unpaid
9    shall be added for each month, or 0.033% (one-thirtieth of
10    one percent) of any amount approved and unpaid for each
11    day, after the end of this 90-day period, until final
12    payment is made.
13        (1.1) A State agency shall review in a timely manner
14    each bill or invoice within 30 days after its receipt. If
15    the State agency determines that the bill or invoice
16    contains a defect making it unable to process the payment
17    request, the agency shall notify the vendor requesting
18    payment as soon as possible after discovering the defect
19    pursuant to rules promulgated under Section 3-3; provided,
20    however, that the notice for construction related bills or
21    invoices must be given not later than 30 days after the
22    bill or invoice was first submitted. The notice shall
23    identify the defect and any additional information
24    necessary to correct the defect. If one or more items on a
25    construction related bill or invoice are disapproved, but
26    not the entire bill or invoice, then the portion that is

 

 

10400HB4288ham001- 4 -LRB104 17163 HLH 35361 a

1    not disapproved shall be paid in accordance with the
2    requirements of this Act.
3        (2) Where a State official or agency is late in
4    payment of a vendor's bill or invoice properly approved in
5    accordance with this Act, and different late payment terms
6    are not reduced to writing as a contractual agreement, the
7    State official or agency shall automatically pay interest
8    penalties required by this Section amounting to $50 or
9    more to the appropriate vendor. Each agency shall be
10    responsible for determining whether an interest penalty is
11    owed and for paying the interest to the vendor. Except as
12    provided in paragraph (4), an individual interest payment
13    amounting to $5 or less shall not be paid by the State.
14    Interest due to a vendor that amounts to greater than $5
15    and less than $50 shall not be paid but shall be accrued
16    until all interest due the vendor for all similar warrants
17    exceeds $50, at which time the accrued interest shall be
18    payable and interest will begin accruing again, except
19    that interest accrued as of the end of the fiscal year that
20    does not exceed $50 shall be payable at that time. In the
21    event an individual has paid a vendor for services in
22    advance, the provisions of this Section shall apply until
23    payment is made to that individual.
24        (3) The provisions of Public Act 96-1501 reducing the
25    interest rate on pharmacy claims under Article V of the
26    Illinois Public Aid Code to 1.0% per month shall apply to

 

 

10400HB4288ham001- 5 -LRB104 17163 HLH 35361 a

1    any pharmacy bills for services and goods under Article V
2    of the Illinois Public Aid Code received on or after the
3    date 60 days before January 25, 2011 (the effective date
4    of Public Act 96-1501) except as provided under paragraph
5    (1.05) of this Section.
6        (4) Interest amounting to less than $5 shall not be
7    paid by the State, except for claims (i) to the Department
8    of Healthcare and Family Services or the Department of
9    Human Services, (ii) pursuant to Article V of the Illinois
10    Public Aid Code, the Covering ALL KIDS Health Insurance
11    Act, or the Children's Health Insurance Program Act, and
12    (iii) made (A) by pharmacies for prescriptive services or
13    (B) by any federally qualified health center for
14    prescriptive services or any other services.
15    Notwithstanding any provision to the contrary, interest
16may not be paid under this Act when: (1) a Chief Procurement
17Officer has voided the underlying contract for goods or
18services under Article 50 of the Illinois Procurement Code; or
19(2) the Auditor General is conducting a performance or program
20audit and the Comptroller has held or is holding for review a
21related contract or vouchers for payment of goods or services
22in the exercise of duties under Section 9 of the State
23Comptroller Act. In such event, interest shall not accrue
24during the pendency of the Auditor General's review.
25(Source: P.A. 100-1064, eff. 8-24-18.)
 

 

 

10400HB4288ham001- 6 -LRB104 17163 HLH 35361 a

1    (30 ILCS 540/3-6)
2    Sec. 3-6. Federal funds; lack of authority. If an agency
3incurs an interest liability under this Act that cannot be
4charged to the same expenditure authority account to which the
5related goods or services were charged due to federal
6prohibitions, the agency is authorized to pay the interest
7from its available appropriations from the General Revenue
8Fund or from any other fund in the State Treasury that is not
9otherwise prohibited from being used to pay interest, except
10that the Department of Transportation is authorized to pay the
11interest from its available appropriations from the Road Fund,
12as long as the original goods or services were for purposes
13consistent with Section 11 of Article IX of the Illinois
14Constitution.
15(Source: P.A. 103-588, eff. 6-5-24.)
 
16    (30 ILCS 540/7)  (from Ch. 127, par. 132.407)
17    Sec. 7. Payments to subcontractors and material suppliers.
18    (a) When a State official or agency responsible for
19administering a contract receives a proper bill or invoice
20from a contractor, that State official or agency shall
21transmit any approved amount to the Comptroller within 30 days
22of receipt.
23    (a-1) When a State official or agency responsible for
24administering a contract submits a voucher to the Comptroller
25for payment to a contractor, that State official or agency

 

 

10400HB4288ham001- 7 -LRB104 17163 HLH 35361 a

1shall promptly make available electronically the voucher
2number, the date of the voucher, and the amount of the voucher.
3The State official or agency responsible for administering the
4contract shall provide subcontractors and material suppliers,
5known to the State official or agency, with instructions on
6how to access the electronic information on the Comptroller's
7website.
8    (a-5) When a contractor receives any payment, the
9contractor shall pay each subcontractor and material supplier
10electronically within 10 business days or 15 calendar days,
11whichever occurs earlier, or, if paid by a printed check, the
12printed check must be postmarked within 10 business days or 15
13calendar days, whichever occurs earlier, after receiving
14payment in proportion to the work completed by each
15subcontractor and material supplier its application or pay
16estimate, plus interest received under this Act. When a
17contractor receives any payment, the contractor shall pay each
18lower-tiered subcontractor and material supplier and each
19subcontractor and material supplier shall make payment to its
20own respective subcontractors and material suppliers. If the
21contractor receives less than the full payment due under the
22public construction contract, the contractor shall be
23obligated to disburse on a pro rata basis those funds
24received, plus interest received under this Act, with the
25contractor, subcontractors and material suppliers each
26receiving a prorated portion based on the amount of payment

 

 

10400HB4288ham001- 8 -LRB104 17163 HLH 35361 a

1each has earned. When, however, the State official or agency
2does not release the full payment due under the contract
3because there are specific areas of work or materials the
4State agency or official has determined are not suitable for
5payment, then those specific subcontractors or material
6suppliers involved shall not be paid for that portion of work
7rejected or deemed not suitable for payment and all other
8subcontractors and suppliers shall be paid based upon the
9amount of payment each has earned, plus interest received
10under this Act.
11    (a-10) For construction contracts with the Department of
12Transportation, the contractor, subcontractor, or material
13supplier, regardless of tier, shall not offset, decrease, or
14diminish payment or payments that are due to its
15subcontractors or material suppliers without reasonable cause.
16    A contractor, who refuses to make prompt payment within 10
17business days or 15 calendar days, whichever occurs earlier,
18after receiving payment, in whole or in part, shall provide to
19the subcontractor or material supplier and the public owner or
20its agent, a written notice of that refusal. The written
21notice shall be made by a contractor no later than 5 calendar
22days after payment is received by the contractor. The written
23notice shall identify the Department of Transportation's
24contract, any subcontract or material purchase agreement, a
25detailed reason for refusal, the value of the payment to be
26withheld, and the specific remedial actions required of the

 

 

10400HB4288ham001- 9 -LRB104 17163 HLH 35361 a

1subcontractor or material supplier so that payment may be
2made. Written notice of refusal may be given in a form and
3method which is acceptable to the parties and public owner.
4    (b) If the contractor, without reasonable cause, fails to
5make full payment of amounts due under subsection (a) to its
6subcontractors and material suppliers within 10 business days
7or 15 calendar days, whichever occurs earlier, after receipt
8of payment from the State official or agency, the contractor
9shall pay to its subcontractors and material suppliers, in
10addition to the payment due them, interest in the amount of 2%
11per month, calculated from the expiration of the
1210-business-day period or the 15-calendar-day period until
13fully paid. This subsection shall further apply to any
14payments made by subcontractors and material suppliers to
15their subcontractors and material suppliers and to all
16payments made to lower tier subcontractors and material
17suppliers throughout the contracting chain.
18        (1) If a contractor, without reasonable cause, fails
19    to make payment in full as provided in subsection (a-5)
20    within 10 business days or 15 calendar days, whichever
21    occurs earlier, after receipt of payment under the public
22    construction contract, any subcontractor or material
23    supplier to whom payments are owed may file a written
24    notice and request for administrative hearing with the
25    State official or agency setting forth the amount owed by
26    the contractor and the contractor's failure to timely pay

 

 

10400HB4288ham001- 10 -LRB104 17163 HLH 35361 a

1    the amount owed. The written notice and request for
2    administrative hearing shall identify the public
3    construction contract, the contractor, and the amount
4    owed, and shall contain a sworn statement or attestation
5    to verify the accuracy of the notice. The notice and
6    request for administrative hearing shall be filed with the
7    State official for the public construction contract, with
8    a copy of the notice concurrently provided to the
9    contractor. Notice to the State official may be made by
10    certified or registered mail, messenger service, or
11    personal service, and must include proof of delivery to
12    the State official.
13        (2) The State official or agency, within 15 calendar
14    days after receipt of a subcontractor's or material
15    supplier's written notice and request for administrative
16    hearing, shall hold a hearing convened by an
17    administrative law judge to determine whether the
18    contractor withheld payment, without reasonable cause,
19    from the subcontractors or material suppliers and what
20    amount, if any, is due to the subcontractors or material
21    suppliers, and the reasonable cause or causes asserted by
22    the contractor. The State official or agency shall provide
23    appropriate notice to the parties of the date, time, and
24    location of the hearing. Each contractor, subcontractor,
25    or material supplier has the right to be represented by
26    counsel at a hearing and to cross-examine witnesses and

 

 

10400HB4288ham001- 11 -LRB104 17163 HLH 35361 a

1    challenge documents. Upon the request of the subcontractor
2    or material supplier and a showing of good cause,
3    reasonable continuances may be granted by the
4    administrative law judge.
5        (3) Upon a finding by the administrative law judge
6    that the contractor failed to make payment in full,
7    without reasonable cause, as provided in subsection
8    (a-10), then the administrative law judge shall, in
9    writing, order the contractor to pay the amount owed to
10    the subcontractors or material suppliers plus interest
11    within 15 calendar days after the order.
12        (4) If a contractor fails to make full payment as
13    ordered under paragraph (3) of this subsection (b) within
14    15 days after the administrative law judge's order, then
15    the contractor shall be barred from entering into a State
16    public construction contract for a period of one year
17    beginning on the date of the administrative law judge's
18    order.
19        (5) If, on 2 or more occasions within a
20    3-calendar-year period, there is a finding by an
21    administrative law judge that the contractor failed to
22    make payment in full, without reasonable cause, and a
23    written order was issued to a contractor under paragraph
24    (3) of this subsection (b), then the contractor shall be
25    barred from entering into a State public construction
26    contract for a period of 6 months beginning on the date of

 

 

10400HB4288ham001- 12 -LRB104 17163 HLH 35361 a

1    the administrative law judge's second written order, even
2    if the payments required under the orders were made in
3    full.
4        (6) If a contractor fails to make full payment as
5    ordered under paragraph (4) of this subsection (b), the
6    subcontractor or material supplier may, within 30 days of
7    the date of that order, petition the State agency for an
8    order for reasonable attorney's fees and costs incurred in
9    the prosecution of the action under this subsection (b).
10    Upon that petition and taking of additional evidence, as
11    may be required, the administrative law judge may issue a
12    supplemental order directing the contractor to pay those
13    reasonable attorney's fees and costs.
14        (7) The written order of the administrative law judge
15    shall be final and appealable under the Administrative
16    Review Law.
17    (b-5) On or before July 2021, the Department of
18Transportation shall publish on its website a searchable
19database that allows for queries for each active construction
20contract by the name of a subcontractor or the pay item such
21that each pay item is associated with either the prime
22contractor or a subcontractor.
23    (c) This Section shall not be construed to in any manner
24diminish, negate, or interfere with the
25contractor-subcontractor or contractor-material supplier
26relationship or commercially useful function.

 

 

10400HB4288ham001- 13 -LRB104 17163 HLH 35361 a

1    (d) This Section shall not preclude, bar, or stay the
2rights, remedies, and defenses available to the parties by way
3of the operation of their contract, purchase agreement, the
4Mechanics Lien Act, or the Public Construction Bond Act.
5    (e) State officials and agencies may adopt rules as may be
6deemed necessary in order to establish the formal procedures
7required under this Section.
8    (f) As used in this Section:
9    "Payment" means the discharge of an obligation in money or
10other valuable consideration or thing delivered in full or
11partial satisfaction of an obligation to pay. "Payment" shall
12include interest paid pursuant to this Act.
13    "Reasonable cause" may include, but is not limited to,
14unsatisfactory workmanship or materials; failure to provide
15documentation required by the contract, subcontract, or
16material purchase agreement; claims made against the
17Department of Transportation or the subcontractor pursuant to
18subsection (c) of Section 23 of the Mechanics Lien Act or the
19Public Construction Bond Act; judgments, levies, garnishments,
20or other court-ordered assessments or offsets in favor of the
21Department of Transportation or other State agency entered
22against a subcontractor or material supplier. "Reasonable
23cause" does not include payments issued to the contractor that
24create a negative or reduced valuation pay application or pay
25estimate due to a reduction of contract quantities or work not
26performed or provided by the subcontractor or material

 

 

10400HB4288ham001- 14 -LRB104 17163 HLH 35361 a

1supplier; the interception or withholding of funds for reasons
2not related to the subcontractor's or material supplier's work
3on the contract; anticipated claims or assessments of third
4parties not a party related to the contract or subcontract;
5asserted claims or assessments of third parties that are not
6authorized by court order, administrative tribunal, or
7statute. "Reasonable cause" further does not include the
8withholding, offset, or reduction of payment, in whole or in
9part, due to the assessment of liquidated damages or penalties
10assessed by the Department of Transportation against the
11contractor, unless the subcontractor's performance or supplied
12materials were the sole and proximate cause of the liquidated
13damage or penalty.
14(Source: P.A. 100-43, eff. 8-9-17; 100-376, eff. 1-1-18;
15100-863, eff. 8-14-18; 101-524, eff. 1-1-20.)
 
16    Section 99. Effective date. This Act takes effect July 1,
172027.".