104TH GENERAL ASSEMBLY
State of Illinois
2025 and 2026
HB4803

 

Introduced , by Rep. Dave Vella

 

SYNOPSIS AS INTRODUCED:
 
New Act

    Creates the Electric Transmission Colocation and Siting Priority Act. Defines terms. Requires that, in the siting of new electric transmission facilities, available corridors be used in the following order of priority: (1) existing public utility corridors; (2) State highway corridors; and (3) new corridors. Provides that a public utility or transmission developer may construct, place, or maintain a high-voltage transmission line on a public right-of-way or along a highway if (i) the public utility or transmission developer submits a colocation request for the high-voltage transmission line to the Secretary of Transportation and (ii) the Secretary reviews and approves the colocation request. Provides that the Secretary may deny a colocation request if the Secretary determines that the construction, placement, or maintenance of a high-voltage transmission line on a public right-of-way or along a highway would endanger public safety or would interfere with the proper function of the highway. Provides that a public utility or transmission developer may submit a written request to the Department of Transportation for an evaluation of certain corridors for possible locations for a high-voltage transmission line. Provides that, within 30 days after receipt of a written request, the Secretary shall assign a project coordinator to the request. Provides that a project coordinator, upon assignment to a request, shall begin the evaluation in coordination with the applicable public utility or transmission developer. Requires a public utility or transmission developer to develop a constructability report in consultation with the Department and requires the public utility or transmission developer and the Department to follow the terms and conditions of the constructability report during the planning and approval process for the siting of a high-voltage transmission line. Sets forth requirements for the content of the constructability report. Provides that, if the Department requires that a high-voltage transmission line on a public right-of-way be relocated by a specific date, the Department shall give the applicable public utility or transmission developer notice of the required relocation no less than 10 years before the date of the required relocation. Makes other changes. Effective January 1, 2027.


LRB104 16923 AAS 30337 b

 

 

A BILL FOR

 

HB4803LRB104 16923 AAS 30337 b

1    AN ACT concerning regulation.
 
2    Be it enacted by the People of the State of Illinois,
3represented in the General Assembly:
 
4    Section 1. Short title. This Act may be cited as the
5Electric Transmission Colocation and Siting Priority Act.
 
6    Section 5. Definitions.As used in this Section:
7    "Commission" means the Illinois Commerce Commission.
8    "Department" means the Illinois Department of
9Transportation.
10    "Electric transmission facility" means an electrical
11transmission system designed and constructed with the
12capability of being safely and reliably energized at 69
13kilovolts or more, including transmission lines, transmission
14towers, conductors, insulators, foundations, grounding
15systems, access roads, and all associated transmission
16facilities, including transmission substations. "Electric
17transmission facility" does not include a project located on
18the electric generating side of a facility's point of
19interconnection.
20    "Highway" has the meaning given to that term in Section
212-202 of the Illinois Highway Code.
22    "High-voltage transmission line" means any line for the
23transmission of electric current with a nominal voltage of at

 

 

HB4803- 2 -LRB104 16923 AAS 30337 b

1least 115 kilovolts that is colocated longitudinally in a
2public right-of-way or a corridor, including all supporting
3structures and accessories necessary for such line.
4"High-voltage transmission line" does not include any line for
5the transmission of electric current that crosses through but
6is not wholly contained within a State highway right-of-way.
7    "Public utility" has the meaning given to that term in
8Section 3-105 of the Public Utilities Act.
9    "Public utility corridor" means the land, or interest
10therein, acquired for or devoted to a public utility to place
11and maintain infrastructure for electricity, water, gas, or
12internet service.
13    "Secretary" means the Secretary of Transportation.
14    "State highway corridor" means the land, or interest
15therein, acquired for or devoted to a State highway.
16    "Transmission developer" means any company that (i) has
17been issued a certificate of public convenience and necessity
18in this State that authorizes the company to own and operate an
19electric transmission line and (ii) is a State electric
20utility, as defined in Section 16-102 of the Public Utilities
21Act, or an affiliate of a State electric utility through a
22common ownership structure.
 
23    Section 10. Electric transmission siting priorities.
24    (a) In the siting of new electric transmission facilities,
25including high-voltage transmission lines, available corridors

 

 

HB4803- 3 -LRB104 16923 AAS 30337 b

1shall be used in the following order of priority:
2        (1) Existing public utility corridors.
3        (2) State highway corridors.
4        (3) New corridors.
5    (b) Permitting on the corridors listed in subsection (a)
6shall be done, to the greatest extent possible, in a manner
7that accounts for economic and engineering considerations, the
8reliability of the electric system, and the protection of the
9environment.
 
10    Section 15. High-voltage transmission line colocation
11requests.
12    (a) A public utility or transmission developer may
13construct, place, or maintain a high-voltage transmission line
14on a public right-of-way or along a highway if (i) the public
15utility or transmission developer submits to the Secretary a
16colocation request for the high-voltage transmission line and
17(ii) the Secretary reviews and approves the colocation
18request.
19    (b) The Secretary may deny a colocation request under this
20Section if the Secretary determines that the construction,
21placement, or maintenance of a high-voltage transmission line
22on a public right-of-way or along a highway would endanger
23public safety or would interfere with the proper function of
24the highway.
25    (c) If the Secretary denies a colocation request under

 

 

HB4803- 4 -LRB104 16923 AAS 30337 b

1this Section, the Secretary shall submit the reasons for the
2denial to the Director of the Environmental Protection Agency,
3the Executive Director of the Commission, and the Director of
4Commerce and Economic Opportunity within 90 days after the
5issuance of the denial.
 
6    Section 20. Consultation and constructability report.
7    (a) A public utility or transmission developer may submit
8a written request to the Department for an evaluation of the
9corridors described in subsection (a) of Section 10 for
10possible locations for a high-voltage transmission line.
11Within 30 days after receipt of a written request under this
12subsection (a), the Secretary shall assign a project
13coordinator to the request. A project coordinator, upon
14assignment to a request, shall begin the evaluation in
15coordination with the applicable public utility or
16transmission developer.
17    (b) The Department shall inform a public utility or
18transmission developer about any of the Department's current
19plans or projects that could impact the public utility's or
20transmission developer's potential construction or placement
21of a high-voltage transmission line within a corridor.
22    (c) After an evaluation under subsection (a) identifies an
23acceptable location within a corridor, a public utility or
24transmission developer, in consultation with the Department,
25shall develop a constructability report. The constructability

 

 

HB4803- 5 -LRB104 16923 AAS 30337 b

1report shall include (i) the terms and conditions for the
2siting of the high-voltage transmission line and (ii) an
3agreed-upon time frame during which the Department may not
4request the relocation of the high-voltage transmission line.
5The Department shall issue a permit to the public utility or
6transmission developer for the use of a public right-of-way
7within the corridor for the siting of a high-voltage
8transmission line only after a constructability report is
9approved by both the Department and the public utility or
10transmission developer.
11    (d) A public utility or transmission developer and the
12Department shall follow the terms and conditions of the
13approved constructability report during the planning and
14approval process for the siting of a high-voltage transmission
15line. If the Department requires the relocation of a
16high-voltage transmission line on a public right-of-way by a
17specific date, the Department shall give the applicable public
18utility or transmission developer notice of the required
19relocation no less than 10 years before the date of the
20required relocation.
 
21    Section 25. Relocation notice and cost responsibility
22    (a) If the Department requires the relocation of a
23high-voltage transmission line during the prohibited time
24frame specified in the constructability report or the
25Department provides notice of the required relocation of a

 

 

HB4803- 6 -LRB104 16923 AAS 30337 b

1high-voltage transmission line to a public utility or
2transmission developer less than 10 years before the date of
3the required relocation, the Department shall be responsible
4for 75% of the costs incurred by the public utility or
5transmission developer in the relocation of the high-voltage
6transmission line.
 
7    Section 99. Effective date. This Act takes effect on
8January 1, 2027.