Rep. Dave Vella

Filed: 4/15/2026

 

 


 

 


 
10400HB4803ham002LRB104 16923 AAS 36827 a

1
AMENDMENT TO HOUSE BILL 4803

2    AMENDMENT NO. ______. Amend House Bill 4803, AS AMENDED,
3by replacing everything after the enacting clause with the
4following:
 
5    "Section 1. Short title. This Act may be cited as the
6Electric Transmission Highway Colocation Act.
 
7    Section 5. Definitions. As used in this Section:
8    "Agency" means the Department of Transportation or the
9Illinois State Toll Highway Authority, depending on which
10entity a public utility is seeking a right-of-way from.
11    "Authority" means the Illinois State Toll Highway
12Authority.
13    "Department" means the Illinois Department of
14Transportation.
15    "Highway" has the meaning given to that term in Section
162-202 of the Illinois Highway Code.

 

 

10400HB4803ham002- 2 -LRB104 16923 AAS 36827 a

1    "High-voltage electric service line" has the meaning given
2to that term in Section 8-406 of the Public Utilities Act.
3    "High-voltage transmission infrastructure" means poles,
4wires, cable, or any physical infrastructure associated with a
5high-voltage electric service line.
6    "Public utility" has the meaning given to that term in
7Section 3-105 of the Public Utilities Act.
8    "Secretary" means the Secretary of Transportation.
 
9    Section 10. High-voltage transmission line colocation
10requests.
11    (a) A public utility may construct, place, or maintain a
12high-voltage electric service line on a public right-of-way or
13along a highway if (i) the public utility submits to the
14Secretary or the Authority a colocation request for the
15high-voltage electric service line, (ii) the Secretary or the
16Authority reviews and approves the colocation request, and
17(iii) the Federal Highway Administration does not express
18objection to the request.
19    (b) The Secretary or the Authority may deny a colocation
20request under this Section if the Secretary or the Authority
21determines that the construction, placement, or maintenance of
22a high-voltage electric service line on a public right-of-way
23or along a highway would endanger public safety, would
24decrease the efficacy or efficiency of the State's
25transportation network, would prevent possible system

 

 

10400HB4803ham002- 3 -LRB104 16923 AAS 36827 a

1expansion, would interfere with other public assets, would
2interfere with the optimal function of the highway, or would
3interfere with any current or future Agency project.
4    (c) If the Secretary or the Authority denies a colocation
5request under this Section, the Secretary or the Authority
6shall submit the reasons for the denial to the Director of the
7Environmental Protection Agency, the Executive Director of the
8Commission, and the Director of Commerce and Economic
9Opportunity within 90 days after the issuance of the denial.
 
10    Section 15. Consultation and constructability report.
11    (a) A public utility may submit a written request, signed
12by a professional engineer who is qualified to perform
13engineering design with the Agency, to the Department or the
14Authority for an evaluation of corridors for possible
15locations for a high-voltage electric service line. The Agency
16shall evaluate each request and respond to the applicable
17public utility.
18    (b) The Department or the Authority shall inform a public
19utility about any of the Department's or the Authority's
20current plans or projects that could impact the public
21utility's potential construction or placement of a
22high-voltage electric service line within a corridor.
23    (c) After an evaluation under subsection (a) identifies an
24acceptable location within a corridor, a public utility, in
25consultation with the Department or the Authority, shall

 

 

10400HB4803ham002- 4 -LRB104 16923 AAS 36827 a

1develop a constructability report. The public utility shall be
2assisted by a professional engineer who is qualified to
3perform engineering design with the Agency. The
4constructability report shall include (i) the terms and
5conditions for the siting of the high-voltage electric service
6line to account for the safety, operability, and maintenance
7of highways operated by the Department and the Authority, (ii)
8a plan for addressing and mitigating the impacts of induced
9voltage, and (iii) a plan for the maintenance of the
10high-voltage transmission infrastructure, including access,
11traffic control, vegetation control, and restoration of the
12right-of-way. The Department or the Authority shall issue a
13permit to the public utility for the use of a public
14right-of-way within the corridor for the siting of a
15high-voltage electric service line only after a
16constructability report is approved by the Department or the
17Authority and the public utility.
18    (d) A public utility and the Agency shall follow the terms
19and conditions of the approved constructability report during
20the planning and approval process for the siting of a
21high-voltage electric service line.
 
22    Section 20. Relocation and removal. If at any point the
23Agency finds that a public utility is not meeting prescribed
24standards set out in a constructability report, the public
25utility must take corrective action within a timely manner, as

 

 

10400HB4803ham002- 5 -LRB104 16923 AAS 36827 a

1set out in the constructability report. If the Agency is not
2satisfied with the public utility's corrective action and
3progress, the Agency may revoke the permit provided to the
4public utility and any operation of the high-voltage
5transmission infrastructure must cease.
 
6    Section 25. Project labor agreements. High-voltage
7electric service lines and related facilities constructed or
8placed on a public right-of-way or along a highway in
9accordance with this Act shall be built by general contractors
10who have entered into a project labor agreement prior to
11construction.
 
12    Section 30. Rules. The Department and the Authority may
13adopt rules for the implementation of this Act.
 
14    Section 35. The Public Utilities Act is amended by
15changing Sections 8-406 and 8-406.1 as follows:
 
16    (220 ILCS 5/8-406)  (from Ch. 111 2/3, par. 8-406)
17    (Text of Section before amendment by P.A. 104-458)
18    Sec. 8-406. Certificate of public convenience and
19necessity.
20    (a) No public utility not owning any city or village
21franchise nor engaged in performing any public service or in
22furnishing any product or commodity within this State as of

 

 

10400HB4803ham002- 6 -LRB104 16923 AAS 36827 a

1July 1, 1921 and not possessing a certificate of public
2convenience and necessity from the Illinois Commerce
3Commission, the State Public Utilities Commission, or the
4Public Utilities Commission, at the time Public Act 84-617
5goes into effect (January 1, 1986), shall transact any
6business in this State until it shall have obtained a
7certificate from the Commission that public convenience and
8necessity require the transaction of such business. A
9certificate of public convenience and necessity requiring the
10transaction of public utility business in any area of this
11State shall include authorization to the public utility
12receiving the certificate of public convenience and necessity
13to construct such plant, equipment, property, or facility as
14is provided for under the terms and conditions of its tariff
15and as is necessary to provide utility service and carry out
16the transaction of public utility business by the public
17utility in the designated area.
18    (b) No public utility shall begin the construction of any
19new plant, equipment, property, or facility which is not in
20substitution of any existing plant, equipment, property, or
21facility, or any extension or alteration thereof or in
22addition thereto, unless and until it shall have obtained from
23the Commission a certificate that public convenience and
24necessity require such construction. Whenever after a hearing
25the Commission determines that any new construction or the
26transaction of any business by a public utility will promote

 

 

10400HB4803ham002- 7 -LRB104 16923 AAS 36827 a

1the public convenience and is necessary thereto, it shall have
2the power to issue certificates of public convenience and
3necessity. The Commission shall determine that proposed
4construction will promote the public convenience and necessity
5only if the utility demonstrates: (1) that the proposed
6construction is necessary to provide adequate, reliable, and
7efficient service to its customers and is the least-cost means
8of satisfying the service needs of its customers or that the
9proposed construction will promote the development of an
10effectively competitive electricity market that operates
11efficiently, is equitable to all customers, and is the least
12cost means of satisfying those objectives; (2) that the
13utility is capable of efficiently managing and supervising the
14construction process and has taken sufficient action to ensure
15adequate and efficient construction and supervision thereof;
16and (3) that the utility is capable of financing the proposed
17construction without significant adverse financial
18consequences for the utility or its customers.
19    (b-5) As used in this subsection (b-5):
20    "Qualifying direct current applicant" means an entity that
21seeks to provide direct current bulk transmission service for
22the purpose of transporting electric energy in interstate
23commerce.
24    "Qualifying direct current project" means a high voltage
25direct current electric service line that crosses at least one
26Illinois border, the Illinois portion of which is physically

 

 

10400HB4803ham002- 8 -LRB104 16923 AAS 36827 a

1located within the region of the Midcontinent Independent
2System Operator, Inc., or its successor organization, and runs
3through the counties of Pike, Scott, Greene, Macoupin,
4Montgomery, Christian, Shelby, Cumberland, and Clark, is
5capable of transmitting electricity at voltages of 345
6kilovolts or above, and may also include associated
7interconnected alternating current interconnection facilities
8in this State that are part of the proposed project and
9reasonably necessary to connect the project with other
10portions of the grid.
11    Notwithstanding any other provision of this Act, a
12qualifying direct current applicant that does not own,
13control, operate, or manage, within this State, any plant,
14equipment, or property used or to be used for the transmission
15of electricity at the time of its application or of the
16Commission's order may file an application on or before
17December 31, 2023 with the Commission pursuant to this Section
18or Section 8-406.1 for, and the Commission may grant, a
19certificate of public convenience and necessity to construct,
20operate, and maintain a qualifying direct current project. The
21qualifying direct current applicant may also include in the
22application requests for authority under Section 8-503. The
23Commission shall grant the application for a certificate of
24public convenience and necessity and requests for authority
25under Section 8-503 if it finds that the qualifying direct
26current applicant and the proposed qualifying direct current

 

 

10400HB4803ham002- 9 -LRB104 16923 AAS 36827 a

1project satisfy the requirements of this subsection and
2otherwise satisfy the criteria of this Section or Section
38-406.1 and the criteria of Section 8-503, as applicable to
4the application and to the extent such criteria are not
5superseded by the provisions of this subsection. The
6Commission's order on the application for the certificate of
7public convenience and necessity shall also include the
8Commission's findings and determinations on the request or
9requests for authority pursuant to Section 8-503. Prior to
10filing its application under either this Section or Section
118-406.1, the qualifying direct current applicant shall conduct
123 public meetings in accordance with subsection (h) of this
13Section. If the qualifying direct current applicant
14demonstrates in its application that the proposed qualifying
15direct current project is designed to deliver electricity to a
16point or points on the electric transmission grid in either or
17both the PJM Interconnection, LLC or the Midcontinent
18Independent System Operator, Inc., or their respective
19successor organizations, the proposed qualifying direct
20current project shall be deemed to be, and the Commission
21shall find it to be, for public use. If the qualifying direct
22current applicant further demonstrates in its application that
23the proposed transmission project has a capacity of 1,000
24megawatts or larger and a voltage level of 345 kilovolts or
25greater, the proposed transmission project shall be deemed to
26satisfy, and the Commission shall find that it satisfies, the

 

 

10400HB4803ham002- 10 -LRB104 16923 AAS 36827 a

1criteria stated in item (1) of subsection (b) of this Section
2or in paragraph (1) of subsection (f) of Section 8-406.1, as
3applicable to the application, without the taking of
4additional evidence on these criteria. Prior to the transfer
5of functional control of any transmission assets to a regional
6transmission organization, a qualifying direct current
7applicant shall request Commission approval to join a regional
8transmission organization in an application filed pursuant to
9this subsection (b-5) or separately pursuant to Section 7-102
10of this Act. The Commission may grant permission to a
11qualifying direct current applicant to join a regional
12transmission organization if it finds that the membership, and
13associated transfer of functional control of transmission
14assets, benefits Illinois customers in light of the attendant
15costs and is otherwise in the public interest. Nothing in this
16subsection (b-5) requires a qualifying direct current
17applicant to join a regional transmission organization.
18Nothing in this subsection (b-5) requires the owner or
19operator of a high voltage direct current transmission line
20that is not a qualifying direct current project to obtain a
21certificate of public convenience and necessity to the extent
22it is not otherwise required by this Section 8-406 or any other
23provision of this Act.
24    (c) As used in this subsection (c):
25    "Decommissioning" has the meaning given to that term in
26subsection (a) of Section 8-508.1.

 

 

10400HB4803ham002- 11 -LRB104 16923 AAS 36827 a

1    "Nuclear power reactor" has the meaning given to that term
2in Section 8 of the Nuclear Safety Law of 2004.
3    After the effective date of this amendatory Act of the
4103rd General Assembly, no construction shall commence on any
5new nuclear power reactor with a nameplate capacity of more
6than 300 megawatts of electricity to be located within this
7State, and no certificate of public convenience and necessity
8or other authorization shall be issued therefor by the
9Commission, until the Illinois Emergency Management Agency and
10Office of Homeland Security, in consultation with the Illinois
11Environmental Protection Agency and the Illinois Department of
12Natural Resources, finds that the United States Government,
13through its authorized agency, has identified and approved a
14demonstrable technology or means for the disposal of high
15level nuclear waste, or until such construction has been
16specifically approved by a statute enacted by the General
17Assembly. Beginning January 1, 2026, construction may commence
18on a new nuclear power reactor with a nameplate capacity of 300
19megawatts of electricity or less within this State if the
20entity constructing the new nuclear power reactor has obtained
21all permits, licenses, permissions, or approvals governing the
22construction, operation, and funding of decommissioning of
23such nuclear power reactors required by: (1) this Act; (2) any
24rules adopted by the Illinois Emergency Management Agency and
25Office of Homeland Security under the authority of this Act;
26(3) any applicable federal statutes, including, but not

 

 

10400HB4803ham002- 12 -LRB104 16923 AAS 36827 a

1limited to, the Atomic Energy Act of 1954, the Energy
2Reorganization Act of 1974, the Low-Level Radioactive Waste
3Policy Amendments Act of 1985, and the Energy Policy Act of
41992; (4) any regulations promulgated or enforced by the U.S.
5Nuclear Regulatory Commission, including, but not limited to,
6those codified at Title X, Parts 20, 30, 40, 50, 70, and 72 of
7the Code of Federal Regulations, as from time to time amended;
8and (5) any other federal or State statute, rule, or
9regulation governing the permitting, licensing, operation, or
10decommissioning of such nuclear power reactors. None of the
11rules developed by the Illinois Emergency Management Agency
12and Office of Homeland Security or any other State agency,
13board, or commission pursuant to this Act shall be construed
14to supersede the authority of the U.S. Nuclear Regulatory
15Commission. The changes made by this amendatory Act of the
16103rd General Assembly shall not apply to the uprate, renewal,
17or subsequent renewal of any license for an existing nuclear
18power reactor that began operation prior to the effective date
19of this amendatory Act of the 103rd General Assembly.
20    None of the changes made in this amendatory Act of the
21103rd General Assembly are intended to authorize the
22construction of nuclear power plants powered by nuclear power
23reactors that are not either: (1) small modular nuclear
24reactors; or (2) nuclear power reactors licensed by the U.S.
25Nuclear Regulatory Commission to operate in this State prior
26to the effective date of this amendatory Act of the 103rd

 

 

10400HB4803ham002- 13 -LRB104 16923 AAS 36827 a

1General Assembly.
2    (d) In making its determination under subsection (b) of
3this Section, the Commission shall attach primary weight to
4the cost or cost savings to the customers of the utility. The
5Commission may consider any or all factors which will or may
6affect such cost or cost savings, including the public
7utility's engineering judgment regarding the materials used
8for construction.
9    (e) The Commission may issue a temporary certificate which
10shall remain in force not to exceed one year in cases of
11emergency, to assure maintenance of adequate service or to
12serve particular customers, without notice or hearing, pending
13the determination of an application for a certificate, and may
14by regulation exempt from the requirements of this Section
15temporary acts or operations for which the issuance of a
16certificate will not be required in the public interest.
17    A public utility shall not be required to obtain but may
18apply for and obtain a certificate of public convenience and
19necessity pursuant to this Section with respect to any matter
20as to which it has received the authorization or order of the
21Commission under the Electric Supplier Act, and any such
22authorization or order granted a public utility by the
23Commission under that Act shall as between public utilities be
24deemed to be, and shall have except as provided in that Act the
25same force and effect as, a certificate of public convenience
26and necessity issued pursuant to this Section.

 

 

10400HB4803ham002- 14 -LRB104 16923 AAS 36827 a

1    No electric cooperative shall be made or shall become a
2party to or shall be entitled to be heard or to otherwise
3appear or participate in any proceeding initiated under this
4Section for authorization of power plant construction and as
5to matters as to which a remedy is available under the Electric
6Supplier Act.
7    (f) Such certificates may be altered or modified by the
8Commission, upon its own motion or upon application by the
9person or corporation affected. Unless exercised within a
10period of 2 years from the grant thereof, authority conferred
11by a certificate of convenience and necessity issued by the
12Commission shall be null and void.
13    No certificate of public convenience and necessity shall
14be construed as granting a monopoly or an exclusive privilege,
15immunity or franchise.
16    (g) A public utility that undertakes any of the actions
17described in items (1) through (3) of this subsection (g) or
18that has obtained approval pursuant to Section 8-406.1 of this
19Act shall not be required to comply with the requirements of
20this Section to the extent such requirements otherwise would
21apply. For purposes of this Section and Section 8-406.1 of
22this Act, "high voltage electric service line" means an
23electric line having a design voltage of 100,000 or more. For
24purposes of this subsection (g), a public utility may do any of
25the following:
26        (1) replace or upgrade any existing high voltage

 

 

10400HB4803ham002- 15 -LRB104 16923 AAS 36827 a

1    electric service line and related facilities,
2    notwithstanding its length;
3        (2) relocate any existing high voltage electric
4    service line and related facilities, notwithstanding its
5    length, to accommodate construction or expansion of a
6    roadway or other transportation infrastructure; or
7        (3) construct a high voltage electric service line and
8    related facilities that is constructed solely to serve a
9    single customer's premises or to provide a generator
10    interconnection to the public utility's transmission
11    system and that will pass under or over the premises owned
12    by the customer or generator to be served or under or over
13    premises for which the customer or generator has secured
14    the necessary right of way.
15    (h) A public utility seeking to construct a high-voltage
16electric service line and related facilities (Project) must
17show that the utility has held a minimum of 2 pre-filing public
18meetings to receive public comment concerning the Project in
19each county where the Project is to be located, no earlier than
206 months prior to filing an application for a certificate of
21public convenience and necessity from the Commission. Notice
22of the public meeting shall be published in a newspaper of
23general circulation within the affected county once a week for
243 consecutive weeks, beginning no earlier than one month prior
25to the first public meeting. If the Project traverses 2
26contiguous counties and where in one county the transmission

 

 

10400HB4803ham002- 16 -LRB104 16923 AAS 36827 a

1line mileage and number of landowners over whose property the
2proposed route traverses is one-fifth or less of the
3transmission line mileage and number of such landowners of the
4other county, then the utility may combine the 2 pre-filing
5meetings in the county with the greater transmission line
6mileage and affected landowners. All other requirements
7regarding pre-filing meetings shall apply in both counties.
8Notice of the public meeting, including a description of the
9Project, must be provided in writing to the clerk of each
10county where the Project is to be located. A representative of
11the Commission shall be invited to each pre-filing public
12meeting.
13    (h-5) A public utility seeking to construct a high-voltage
14electric service line and related facilities must also show
15that the Project has complied with training and competence
16requirements under subsection (b) of Section 15 of the
17Electric Transmission Systems Construction Standards Act.
18    (h-10) A public utility may be permitted to use highway
19corridors for the purposes of constructing a high-voltage
20electric service line and related facilities.
21    (h-15) A public utility seeking to construct a
22high-voltage electric service line and related facilities must
23consider corridors of development in the following order of
24priority:
25        (1) existing utility corridors, where adding new lines
26    or making improvements to existing lines can achieve

 

 

10400HB4803ham002- 17 -LRB104 16923 AAS 36827 a

1    expanded electric capacity at the lowest possible cost;
2        (2) highway corridors; and
3        (3) new utility corridors.
4    Consideration of corridors shall be done, to the greatest
5extent possible, in a manner that accounts for economic and
6engineering considerations, the reliability of the electric
7system, and the protection of the environment.
8    (i) For applications filed after August 18, 2015 (the
9effective date of Public Act 99-399), the Commission shall, by
10certified mail, notify each owner of record of land, as
11identified in the records of the relevant county tax assessor,
12included in the right-of-way over which the utility seeks in
13its application to construct a high-voltage electric line of
14the time and place scheduled for the initial hearing on the
15public utility's application. The utility shall reimburse the
16Commission for the cost of the postage and supplies incurred
17for mailing the notice.
18(Source: P.A. 102-609, eff. 8-27-21; 102-662, eff. 9-15-21;
19102-813, eff. 5-13-22; 102-931, eff. 5-27-22; 103-569, eff.
206-1-24; 103-1066, eff. 2-20-25.)
 
21    (Text of Section after amendment by P.A. 104-458)
22    Sec. 8-406. Certificate of public convenience and
23necessity.
24    (a) No public utility not owning any city or village
25franchise nor engaged in performing any public service or in

 

 

10400HB4803ham002- 18 -LRB104 16923 AAS 36827 a

1furnishing any product or commodity within this State as of
2July 1, 1921 and not possessing a certificate of public
3convenience and necessity from the Illinois Commerce
4Commission, the State Public Utilities Commission, or the
5Public Utilities Commission, at the time Public Act 84-617
6goes into effect (January 1, 1986), shall transact any
7business in this State until it shall have obtained a
8certificate from the Commission that public convenience and
9necessity require the transaction of such business. A
10certificate of public convenience and necessity requiring the
11transaction of public utility business in any area of this
12State shall include authorization to the public utility
13receiving the certificate of public convenience and necessity
14to construct such plant, equipment, property, or facility as
15is provided for under the terms and conditions of its tariff
16and as is necessary to provide utility service and carry out
17the transaction of public utility business by the public
18utility in the designated area.
19    (b) No public utility shall begin the construction of any
20new plant, equipment, property, or facility which is not in
21substitution of any existing plant, equipment, property, or
22facility, or any extension or alteration thereof or in
23addition thereto, unless and until it shall have obtained from
24the Commission a certificate that public convenience and
25necessity require such construction. Whenever after a hearing
26the Commission determines that any new construction or the

 

 

10400HB4803ham002- 19 -LRB104 16923 AAS 36827 a

1transaction of any business by a public utility will promote
2the public convenience and is necessary thereto, it shall have
3the power to issue certificates of public convenience and
4necessity. The Commission shall determine that proposed
5construction will promote the public convenience and necessity
6only if the utility demonstrates: (1) that the proposed
7construction is necessary to provide adequate, reliable, and
8efficient service to its customers and is the least-cost means
9of satisfying the service needs of its customers or that the
10proposed construction will promote the development of an
11effectively competitive electricity market that operates
12efficiently, is equitable to all customers, and is the
13least-cost means of satisfying those objectives; (2) that the
14utility is capable of efficiently managing and supervising the
15construction process and has taken sufficient action to ensure
16adequate and efficient construction and supervision thereof;
17and (3) that the utility is capable of financing the proposed
18construction without significant adverse financial
19consequences for the utility or its customers.
20    (b-5) As used in this subsection (b-5):
21    "Qualifying direct current applicant" means an entity that
22seeks to provide direct current bulk transmission service for
23the purpose of transporting electric energy in interstate
24commerce.
25    "Qualifying direct current project" means a high voltage
26direct current electric service line that crosses at least one

 

 

10400HB4803ham002- 20 -LRB104 16923 AAS 36827 a

1Illinois border, the Illinois portion of which is physically
2located within the region of the Midcontinent Independent
3System Operator, Inc., or its successor organization, and runs
4through the counties of Pike, Scott, Greene, Macoupin,
5Montgomery, Christian, Shelby, Cumberland, and Clark, is
6capable of transmitting electricity at voltages of 345
7kilovolts or above, and may also include associated
8interconnected alternating current interconnection facilities
9in this State that are part of the proposed project and
10reasonably necessary to connect the project with other
11portions of the grid.
12    Notwithstanding any other provision of this Act, a
13qualifying direct current applicant that does not own,
14control, operate, or manage, within this State, any plant,
15equipment, or property used or to be used for the transmission
16of electricity at the time of its application or of the
17Commission's order may file an application on or before
18December 31, 2023 with the Commission pursuant to this Section
19or Section 8-406.1 for, and the Commission may grant, a
20certificate of public convenience and necessity to construct,
21operate, and maintain a qualifying direct current project. The
22qualifying direct current applicant may also include in the
23application requests for authority under Section 8-503. The
24Commission shall grant the application for a certificate of
25public convenience and necessity and requests for authority
26under Section 8-503 if it finds that the qualifying direct

 

 

10400HB4803ham002- 21 -LRB104 16923 AAS 36827 a

1current applicant and the proposed qualifying direct current
2project satisfy the requirements of this subsection and
3otherwise satisfy the criteria of this Section or Section
48-406.1 and the criteria of Section 8-503, as applicable to
5the application and to the extent such criteria are not
6superseded by the provisions of this subsection. The
7Commission's order on the application for the certificate of
8public convenience and necessity shall also include the
9Commission's findings and determinations on the request or
10requests for authority pursuant to Section 8-503. Prior to
11filing its application under either this Section or Section
128-406.1, the qualifying direct current applicant shall conduct
133 public meetings in accordance with subsection (h) of this
14Section. If the qualifying direct current applicant
15demonstrates in its application that the proposed qualifying
16direct current project is designed to deliver electricity to a
17point or points on the electric transmission grid in either or
18both the PJM Interconnection, LLC or the Midcontinent
19Independent System Operator, Inc., or their respective
20successor organizations, the proposed qualifying direct
21current project shall be deemed to be, and the Commission
22shall find it to be, for public use. If the qualifying direct
23current applicant further demonstrates in its application that
24the proposed transmission project has a capacity of 1,000
25megawatts or larger and a voltage level of 345 kilovolts or
26greater, the proposed transmission project shall be deemed to

 

 

10400HB4803ham002- 22 -LRB104 16923 AAS 36827 a

1satisfy, and the Commission shall find that it satisfies, the
2criteria stated in item (1) of subsection (b) of this Section
3or in paragraph (1) of subsection (f) of Section 8-406.1, as
4applicable to the application, without the taking of
5additional evidence on these criteria. Prior to the transfer
6of functional control of any transmission assets to a regional
7transmission organization, a qualifying direct current
8applicant shall request Commission approval to join a regional
9transmission organization in an application filed pursuant to
10this subsection (b-5) or separately pursuant to Section 7-102
11of this Act. The Commission may grant permission to a
12qualifying direct current applicant to join a regional
13transmission organization if it finds that the membership, and
14associated transfer of functional control of transmission
15assets, benefits Illinois customers in light of the attendant
16costs and is otherwise in the public interest. Nothing in this
17subsection (b-5) requires a qualifying direct current
18applicant to join a regional transmission organization.
19Nothing in this subsection (b-5) requires the owner or
20operator of a high voltage direct current transmission line
21that is not a qualifying direct current project to obtain a
22certificate of public convenience and necessity to the extent
23it is not otherwise required by this Section 8-406 or any other
24provision of this Act.
25    (c) As used in this subsection (c):
26    "Decommissioning" has the meaning given to that term in

 

 

10400HB4803ham002- 23 -LRB104 16923 AAS 36827 a

1subsection (a) of Section 8-508.1.
2    "Nuclear power reactor" has the meaning given to that term
3in Section 8 of the Nuclear Safety Law of 2004.
4    Beginning January 1, 2026, construction may commence on a
5new nuclear power reactor within this State if the entity
6constructing the new nuclear power reactor has obtained all
7permits, licenses, permissions, or approvals governing the
8construction, operation, and funding of decommissioning of
9such nuclear power reactors required by: (1) this Act; (2) any
10rules adopted by the Illinois Emergency Management Agency and
11Office of Homeland Security under the authority of this Act;
12(3) any applicable federal statutes, including, but not
13limited to, the Atomic Energy Act of 1954, the Energy
14Reorganization Act of 1974, the Low-Level Radioactive Waste
15Policy Amendments Act of 1985, and the Energy Policy Act of
161992; (4) any regulations promulgated or enforced by the U.S.
17Nuclear Regulatory Commission, including, but not limited to,
18those codified at Title X, Parts 20, 30, 40, 50, 70, and 72 of
19the Code of Federal Regulations, as from time to time amended;
20and (5) any other federal or State statute, rule, or
21regulation governing the permitting, licensing, operation, or
22decommissioning of such nuclear power reactors. None of the
23rules developed by the Illinois Emergency Management Agency
24and Office of Homeland Security or any other State agency,
25board, or commission pursuant to this Act shall be construed
26to supersede the authority of the U.S. Nuclear Regulatory

 

 

10400HB4803ham002- 24 -LRB104 16923 AAS 36827 a

1Commission. The changes made by this amendatory Act of the
2103rd General Assembly shall not apply to the uprate, renewal,
3or subsequent renewal of any license for an existing nuclear
4power reactor that began operation prior to the effective date
5of this amendatory Act of the 103rd General Assembly.
6    None of the changes made in this amendatory Act of the
7104th General Assembly are intended to authorize the
8construction of nuclear power plants powered by nuclear power
9reactors that are not nuclear power reactors licensed by the
10U.S. Nuclear Regulatory Commission to operate in this State.
11    (d) In making its determination under subsection (b) of
12this Section, the Commission shall attach primary weight to
13the cost or cost savings to the customers of the utility. The
14Commission may consider any or all factors which will or may
15affect such cost or cost savings, including the public
16utility's engineering judgment regarding the materials used
17for construction.
18    (e) The Commission may issue a temporary certificate which
19shall remain in force not to exceed one year in cases of
20emergency, to assure maintenance of adequate service or to
21serve particular customers, without notice or hearing, pending
22the determination of an application for a certificate, and may
23by regulation exempt from the requirements of this Section
24temporary acts or operations for which the issuance of a
25certificate will not be required in the public interest.
26    A public utility shall not be required to obtain but may

 

 

10400HB4803ham002- 25 -LRB104 16923 AAS 36827 a

1apply for and obtain a certificate of public convenience and
2necessity pursuant to this Section with respect to any matter
3as to which it has received the authorization or order of the
4Commission under the Electric Supplier Act, and any such
5authorization or order granted a public utility by the
6Commission under that Act shall as between public utilities be
7deemed to be, and shall have except as provided in that Act the
8same force and effect as, a certificate of public convenience
9and necessity issued pursuant to this Section.
10    No electric cooperative shall be made or shall become a
11party to or shall be entitled to be heard or to otherwise
12appear or participate in any proceeding initiated under this
13Section for authorization of power plant construction and as
14to matters as to which a remedy is available under the Electric
15Supplier Act.
16    (f) Such certificates may be altered or modified by the
17Commission, upon its own motion or upon application by the
18person or corporation affected. Unless exercised within a
19period of 2 years from the grant thereof, authority conferred
20by a certificate of convenience and necessity issued by the
21Commission shall be null and void.
22    No certificate of public convenience and necessity shall
23be construed as granting a monopoly or an exclusive privilege,
24immunity or franchise.
25    (g) A public utility that undertakes any of the actions
26described in items (1) through (3) of this subsection (g) or

 

 

10400HB4803ham002- 26 -LRB104 16923 AAS 36827 a

1that has obtained approval pursuant to Section 8-406.1 of this
2Act shall not be required to comply with the requirements of
3this Section to the extent such requirements otherwise would
4apply. For purposes of this Section and Section 8-406.1 of
5this Act, "high voltage electric service line" means an
6electric line having a design voltage of 69,000 or more. For
7purposes of this subsection (g), a public utility may do any of
8the following:
9        (1) replace or upgrade any existing high voltage
10    electric service line and related facilities,
11    notwithstanding its length or, subject to applicable
12    Article VII requirements, ownership;
13        (2) relocate any existing high voltage electric
14    service line and related facilities, notwithstanding its
15    length, to accommodate construction or expansion of a
16    roadway or other transportation infrastructure; or
17        (3) construct a high voltage electric service line and
18    related facilities that is constructed solely to serve a
19    single customer's premises or to provide a generator
20    interconnection to the public utility's transmission
21    system and that will (i) pass under or over the premises
22    owned by the customer or generator to be served; (ii) pass
23    under or over premises for which the customer or generator
24    has secured the necessary right-of-way; or (iii) be
25    multi-circuited with the facilities of the public utility.
26    (h) A public utility seeking to construct a high-voltage

 

 

10400HB4803ham002- 27 -LRB104 16923 AAS 36827 a

1electric service line and related facilities (Project) must
2show that the utility has held a minimum of 2 pre-filing public
3meetings to receive public comment concerning the Project in
4each county where the Project is to be located, no earlier than
56 months prior to filing an application for a certificate of
6public convenience and necessity from the Commission. Notice
7of the public meeting shall be published in a newspaper of
8general circulation within the affected county once a week for
93 consecutive weeks, beginning no earlier than one month prior
10to the first public meeting. If the Project traverses 2
11contiguous counties and where in one county the transmission
12line mileage and number of landowners over whose property the
13proposed route traverses is one-fifth or less of the
14transmission line mileage and number of such landowners of the
15other county, then the utility may combine the 2 pre-filing
16meetings in the county with the greater transmission line
17mileage and affected landowners. All other requirements
18regarding pre-filing meetings shall apply in both counties.
19Notice of the public meeting, including a description of the
20Project, must be provided in writing to the clerk of each
21county where the Project is to be located. A representative of
22the Commission shall be invited to each pre-filing public
23meeting.
24    (h-5) A public utility seeking to construct a high-voltage
25electric service line and related facilities must also show
26that the Project has complied with training and competence

 

 

10400HB4803ham002- 28 -LRB104 16923 AAS 36827 a

1requirements under subsection (b) of Section 15 of the
2Electric Transmission Systems Construction Standards Act.
3    (h-10) A public utility may be permitted to use highway
4corridors for the purposes of constructing a high-voltage
5electric service line and related facilities.
6    (h-15) A public utility seeking to construct a
7high-voltage electric service line and related facilities must
8consider corridors of development in the following order of
9priority:
10        (1) existing utility corridors, where adding new lines
11    or making improvements to existing lines can achieve
12    expanded electric capacity at the lowest possible cost;
13        (2) highway corridors; and
14        (3) new utility corridors.
15    Consideration of corridors shall be done, to the greatest
16extent possible, in a manner that accounts for economic and
17engineering considerations, the reliability of the electric
18system, and the protection of the environment.
19    (i) For applications filed after August 18, 2015 (the
20effective date of Public Act 99-399), the Commission shall, by
21certified mail, notify each owner of record of land, as
22identified in the records of the relevant county tax assessor,
23included in the right-of-way over which the utility seeks in
24its application to construct a high-voltage electric line of
25the time and place scheduled for the initial hearing on the
26public utility's application. The utility shall reimburse the

 

 

10400HB4803ham002- 29 -LRB104 16923 AAS 36827 a

1Commission for the cost of the postage and supplies incurred
2for mailing the notice.
3    (j) In determining whether to issue a certificate of
4public convenience for a new electric generation facility to a
5municipal power agency that is required to obtain such a
6certificate to exercise its power of eminent domain pursuant
7to Section 11-119.1-10 of the Illinois Municipal Code, the
8Commission shall give due consideration to whether a
9generation unit of similar size and type is part of the
10municipal power agency's preferred portfolio or least-cost
11plan for achieving renewable energy goals in its most recent
12integrated resource plan, as described in subsection (d) of
13Section 1-15 of the Municipal and Cooperative Electric Utility
14Transparent Planning Act.
15(Source: P.A. 103-569, eff. 6-1-24; 103-1066, eff. 2-20-25;
16104-458, eff. 6-1-26.)
 
17    (220 ILCS 5/8-406.1)
18    Sec. 8-406.1. Certificate of public convenience and
19necessity; expedited procedure.
20    (a) A public utility may apply for a certificate of public
21convenience and necessity pursuant to this Section for the
22construction of any new high voltage electric service line and
23related facilities (Project). To facilitate the expedited
24review process of an application filed pursuant to this
25Section, an application shall include all of the following:

 

 

10400HB4803ham002- 30 -LRB104 16923 AAS 36827 a

1        (1) Information in support of the application that
2    shall include the following:
3            (A) A detailed description of the Project,
4        including location maps and plot plans to scale
5        showing all major components.
6            (B) The following engineering data:
7                (i) a detailed Project description including:
8                    (I) name and destination of the Project;
9                    (II) design voltage rating (kV);
10                    (III) operating voltage rating (kV); and
11                    (IV) normal peak operating current rating;
12                (ii) a conductor, structures, and substations
13            description including:
14                    (I) conductor size and type;
15                    (II) type of structures;
16                    (III) height of typical structures;
17                    (IV) an explanation why these structures
18                were selected;
19                    (V) dimensional drawings of the typical
20                structures to be used in the Project; and
21                    (VI) a list of the names of all new (and
22                existing if applicable) substations or
23                switching stations that will be associated
24                with the proposed new high voltage electric
25                service line;
26                (iii) the location of the site and

 

 

10400HB4803ham002- 31 -LRB104 16923 AAS 36827 a

1            right-of-way including:
2                    (I) miles of right-of-way;
3                    (II) miles of circuit;
4                    (III) width of the right-of-way; and
5                    (IV) a brief description of the area
6                traversed by the proposed high voltage
7                electric service line, including a description
8                of the general land uses in the area and the
9                type of terrain crossed by the proposed line;
10                (iv) assumptions, bases, formulae, and methods
11            used in the development and preparation of the
12            diagrams and accompanying data, and a technical
13            description providing the following information:
14                    (I) number of circuits, with
15                identification as to whether the circuit is
16                overhead or underground;
17                    (II) the operating voltage and frequency;
18                and
19                    (III) conductor size and type and number
20                of conductors per phase;
21                (v) if the proposed interconnection is an
22            overhead line, the following additional
23            information also must be provided:
24                    (I) the wind and ice loading design
25                parameters;
26                    (II) a full description and drawing of a

 

 

10400HB4803ham002- 32 -LRB104 16923 AAS 36827 a

1                typical supporting structure, including
2                strength specifications;
3                    (III) structure spacing with typical
4                ruling and maximum spans;
5                    (IV) conductor (phase) spacing; and
6                    (V) the designed line-to-ground and
7                conductor-side clearances;
8                (vi) if an underground or underwater
9            interconnection is proposed, the following
10            additional information also must be provided:
11                    (I) burial depth;
12                    (II) type of cable and a description of
13                any required supporting equipment, such as
14                insulation medium pressurizing or forced
15                cooling;
16                    (III) cathodic protection scheme; and
17                    (IV) type of dielectric fluid and
18                safeguards used to limit potential spills in
19                waterways;
20                (vii) technical diagrams that provide
21            clarification of any item under this item (1)
22            should be included; and
23                (viii) applicant shall provide and identify a
24            primary right-of-way and one or more alternate
25            rights-of-way for the Project as part of the
26            filing. To the extent applicable, for each

 

 

10400HB4803ham002- 33 -LRB104 16923 AAS 36827 a

1            right-of-way, an applicant shall provide the
2            information described in this subsection (a). Upon
3            a showing of good cause in its filing, an
4            applicant may be excused from providing and
5            identifying alternate rights-of-way.
6        (2) An application fee of $100,000, which shall be
7    paid into the Public Utility Fund at the time the Chief
8    Clerk of the Commission deems it complete and accepts the
9    filing.
10        (3) Information showing that the utility has held a
11    minimum of 3 pre-filing public meetings to receive public
12    comment concerning the Project in each county where the
13    Project is to be located, no earlier than 6 months prior to
14    the filing of the application. Notice of the public
15    meeting shall be published in a newspaper of general
16    circulation within the affected county once a week for 3
17    consecutive weeks, beginning no earlier than one month
18    prior to the first public meeting. If the Project
19    traverses 2 contiguous counties and where in one county
20    the transmission line mileage and number of landowners
21    over whose property the proposed route traverses is 1/5 or
22    less of the transmission line mileage and number of such
23    landowners of the other county, then the utility may
24    combine the 3 pre-filing meetings in the county with the
25    greater transmission line mileage and affected landowners.
26    All other requirements regarding pre-filing meetings shall

 

 

10400HB4803ham002- 34 -LRB104 16923 AAS 36827 a

1    apply in both counties. Notice of the public meeting,
2    including a description of the Project, must be provided
3    in writing to the clerk of each county where the Project is
4    to be located. A representative of the Commission shall be
5    invited to each pre-filing public meeting.
6    For applications filed after the effective date of this
7amendatory Act of the 99th General Assembly, the Commission
8shall, by certified mail, notify each owner of record of the
9land, as identified in the records of the relevant county tax
10assessor, included in the primary or alternate rights-of-way
11identified in the utility's application of the time and place
12scheduled for the initial hearing upon the public utility's
13application. The utility shall reimburse the Commission for
14the cost of the postage and supplies incurred for mailing the
15notice.
16    (b) At the first status hearing the administrative law
17judge shall set a schedule for discovery that shall take into
18consideration the expedited nature of the proceeding.
19    (c) Nothing in this Section prohibits a utility from
20requesting, or the Commission from approving, protection of
21confidential or proprietary information under applicable law.
22The public utility may seek confidential protection of any of
23the information provided pursuant to this Section, subject to
24Commission approval.
25    (d) The public utility shall publish notice of its
26application in the official State newspaper within 10 days

 

 

10400HB4803ham002- 35 -LRB104 16923 AAS 36827 a

1following the date of the application's filing.
2    (e) The public utility shall establish a dedicated website
3for the Project 3 weeks prior to the first public meeting and
4maintain the website until construction of the Project is
5complete. The website address shall be included in all public
6notices.
7    (f) The Commission shall, after notice and hearing, grant
8a certificate of public convenience and necessity filed in
9accordance with the requirements of this Section if, based
10upon the application filed with the Commission and the
11evidentiary record, it finds the Project will promote the
12public convenience and necessity and that all of the following
13criteria are satisfied:
14        (1) That the Project is necessary to provide adequate,
15    reliable, and efficient service to the public utility's
16    customers and is the least-cost means of satisfying the
17    service needs of the public utility's customers or that
18    the Project will promote the development of an effectively
19    competitive electricity market that operates efficiently,
20    is equitable to all customers, and is the least cost means
21    of satisfying those objectives.
22        (2) That the public utility is capable of efficiently
23    managing and supervising the construction process and has
24    taken sufficient action to ensure adequate and efficient
25    construction and supervision of the construction.
26        (3) That the public utility is capable of financing

 

 

10400HB4803ham002- 36 -LRB104 16923 AAS 36827 a

1    the proposed construction without significant adverse
2    financial consequences for the utility or its customers.
3        (4) That the Project has complied with training and
4    competence and Diversity Plan requirements under
5    subsections (b) and (d) of Section 15 of the Electric
6    Transmission Systems Construction Standards Act.
7    (g) The Commission shall issue its decision with findings
8of fact and conclusions of law granting or denying the
9application no later than 150 days after the application is
10filed. The Commission may extend the 150-day deadline upon
11notice by an additional 75 days if, on or before the 30th day
12after the filing of the application, the Commission finds that
13good cause exists to extend the 150-day period.
14    (h) In the event the Commission grants a public utility's
15application for a certificate pursuant to this Section, the
16public utility shall pay a one-time construction fee to each
17county in which the Project is constructed within 30 days
18after the completion of construction. The construction fee
19shall be $20,000 per mile of high voltage electric service
20line constructed in that county, or a proportionate fraction
21of that fee. The fee shall be in lieu of any permitting fees
22that otherwise would be imposed by a county. Counties
23receiving a payment under this subsection (h) may distribute
24all or portions of the fee to local taxing districts in that
25county.
26    (i) Notwithstanding any other provisions of this Act, a

 

 

10400HB4803ham002- 37 -LRB104 16923 AAS 36827 a

1decision granting a certificate under this Section shall
2include an order pursuant to Section 8-503 of this Act
3authorizing or directing the construction of the high voltage
4electric service line and related facilities as approved by
5the Commission, in the manner and within the time specified in
6said order.
7    (j) A public utility may be permitted to use highway
8corridors for the purposes of constructing a high-voltage
9electric service line and related facilities for the purposes
10of this Section.
11    (j-5) A public utility seeking to construct a high-voltage
12electric service line and related facilities must consider
13corridors of development in the following order of priority:
14        (1) existing utility corridors, where adding new lines
15    or making improvements to existing lines can achieve
16    expanded electric capacity at the lowest possible cost;
17        (2) highway corridors; and
18        (3) new utility corridors.
19    Consideration of corridors shall be done, to the greatest
20extent possible, in a manner that accounts for economic and
21engineering considerations, the reliability of the electric
22system, and the protection of the environment.
23(Source: P.A. 102-931, eff. 5-27-22; 103-1066, eff. 2-20-25.)
 
24    Section 95. No acceleration or delay. Where this Act makes
25changes in a statute that is represented in this Act by text

 

 

10400HB4803ham002- 38 -LRB104 16923 AAS 36827 a

1that is not yet or no longer in effect (for example, a Section
2represented by multiple versions), the use of that text does
3not accelerate or delay the taking effect of (i) the changes
4made by this Act or (ii) provisions derived from any other
5Public Act.
 
6    Section 99. Effective date. This Act takes effect upon
7becoming law.".