|
| | 10400HB4803ham002 | - 2 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | "High-voltage electric service line" has the meaning given |
| 2 | | to that term in Section 8-406 of the Public Utilities Act. |
| 3 | | "High-voltage transmission infrastructure" means poles, |
| 4 | | wires, cable, or any physical infrastructure associated with a |
| 5 | | high-voltage electric service line. |
| 6 | | "Public utility" has the meaning given to that term in |
| 7 | | Section 3-105 of the Public Utilities Act. |
| 8 | | "Secretary" means the Secretary of Transportation. |
| 9 | | Section 10. High-voltage transmission line colocation |
| 10 | | requests. |
| 11 | | (a) A public utility may construct, place, or maintain a |
| 12 | | high-voltage electric service line on a public right-of-way or |
| 13 | | along a highway if (i) the public utility submits to the |
| 14 | | Secretary or the Authority a colocation request for the |
| 15 | | high-voltage electric service line, (ii) the Secretary or the |
| 16 | | Authority reviews and approves the colocation request, and |
| 17 | | (iii) the Federal Highway Administration does not express |
| 18 | | objection to the request. |
| 19 | | (b) The Secretary or the Authority may deny a colocation |
| 20 | | request under this Section if the Secretary or the Authority |
| 21 | | determines that the construction, placement, or maintenance of |
| 22 | | a high-voltage electric service line on a public right-of-way |
| 23 | | or along a highway would endanger public safety, would |
| 24 | | decrease the efficacy or efficiency of the State's |
| 25 | | transportation network, would prevent possible system |
|
| | 10400HB4803ham002 | - 3 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | expansion, would interfere with other public assets, would |
| 2 | | interfere with the optimal function of the highway, or would |
| 3 | | interfere with any current or future Agency project. |
| 4 | | (c) If the Secretary or the Authority denies a colocation |
| 5 | | request under this Section, the Secretary or the Authority |
| 6 | | shall submit the reasons for the denial to the Director of the |
| 7 | | Environmental Protection Agency, the Executive Director of the |
| 8 | | Commission, and the Director of Commerce and Economic |
| 9 | | Opportunity within 90 days after the issuance of the denial. |
| 10 | | Section 15. Consultation and constructability report. |
| 11 | | (a) A public utility may submit a written request, signed |
| 12 | | by a professional engineer who is qualified to perform |
| 13 | | engineering design with the Agency, to the Department or the |
| 14 | | Authority for an evaluation of corridors for possible |
| 15 | | locations for a high-voltage electric service line. The Agency |
| 16 | | shall evaluate each request and respond to the applicable |
| 17 | | public utility. |
| 18 | | (b) The Department or the Authority shall inform a public |
| 19 | | utility about any of the Department's or the Authority's |
| 20 | | current plans or projects that could impact the public |
| 21 | | utility's potential construction or placement of a |
| 22 | | high-voltage electric service line within a corridor. |
| 23 | | (c) After an evaluation under subsection (a) identifies an |
| 24 | | acceptable location within a corridor, a public utility, in |
| 25 | | consultation with the Department or the Authority, shall |
|
| | 10400HB4803ham002 | - 4 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | develop a constructability report. The public utility shall be |
| 2 | | assisted by a professional engineer who is qualified to |
| 3 | | perform engineering design with the Agency. The |
| 4 | | constructability report shall include (i) the terms and |
| 5 | | conditions for the siting of the high-voltage electric service |
| 6 | | line to account for the safety, operability, and maintenance |
| 7 | | of highways operated by the Department and the Authority, (ii) |
| 8 | | a plan for addressing and mitigating the impacts of induced |
| 9 | | voltage, and (iii) a plan for the maintenance of the |
| 10 | | high-voltage transmission infrastructure, including access, |
| 11 | | traffic control, vegetation control, and restoration of the |
| 12 | | right-of-way. The Department or the Authority shall issue a |
| 13 | | permit to the public utility for the use of a public |
| 14 | | right-of-way within the corridor for the siting of a |
| 15 | | high-voltage electric service line only after a |
| 16 | | constructability report is approved by the Department or the |
| 17 | | Authority and the public utility. |
| 18 | | (d) A public utility and the Agency shall follow the terms |
| 19 | | and conditions of the approved constructability report during |
| 20 | | the planning and approval process for the siting of a |
| 21 | | high-voltage electric service line. |
| 22 | | Section 20. Relocation and removal. If at any point the |
| 23 | | Agency finds that a public utility is not meeting prescribed |
| 24 | | standards set out in a constructability report, the public |
| 25 | | utility must take corrective action within a timely manner, as |
|
| | 10400HB4803ham002 | - 5 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | set out in the constructability report. If the Agency is not |
| 2 | | satisfied with the public utility's corrective action and |
| 3 | | progress, the Agency may revoke the permit provided to the |
| 4 | | public utility and any operation of the high-voltage |
| 5 | | transmission infrastructure must cease. |
| 6 | | Section 25. Project labor agreements. High-voltage |
| 7 | | electric service lines and related facilities constructed or |
| 8 | | placed on a public right-of-way or along a highway in |
| 9 | | accordance with this Act shall be built by general contractors |
| 10 | | who have entered into a project labor agreement prior to |
| 11 | | construction. |
| 12 | | Section 30. Rules. The Department and the Authority may |
| 13 | | adopt rules for the implementation of this Act. |
| 14 | | Section 35. The Public Utilities Act is amended by |
| 15 | | changing Sections 8-406 and 8-406.1 as follows: |
| 16 | | (220 ILCS 5/8-406) (from Ch. 111 2/3, par. 8-406) |
| 17 | | (Text of Section before amendment by P.A. 104-458) |
| 18 | | Sec. 8-406. Certificate of public convenience and |
| 19 | | necessity. |
| 20 | | (a) No public utility not owning any city or village |
| 21 | | franchise nor engaged in performing any public service or in |
| 22 | | furnishing any product or commodity within this State as of |
|
| | 10400HB4803ham002 | - 6 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | July 1, 1921 and not possessing a certificate of public |
| 2 | | convenience and necessity from the Illinois Commerce |
| 3 | | Commission, the State Public Utilities Commission, or the |
| 4 | | Public Utilities Commission, at the time Public Act 84-617 |
| 5 | | goes into effect (January 1, 1986), shall transact any |
| 6 | | business in this State until it shall have obtained a |
| 7 | | certificate from the Commission that public convenience and |
| 8 | | necessity require the transaction of such business. A |
| 9 | | certificate of public convenience and necessity requiring the |
| 10 | | transaction of public utility business in any area of this |
| 11 | | State shall include authorization to the public utility |
| 12 | | receiving the certificate of public convenience and necessity |
| 13 | | to construct such plant, equipment, property, or facility as |
| 14 | | is provided for under the terms and conditions of its tariff |
| 15 | | and as is necessary to provide utility service and carry out |
| 16 | | the transaction of public utility business by the public |
| 17 | | utility in the designated area. |
| 18 | | (b) No public utility shall begin the construction of any |
| 19 | | new plant, equipment, property, or facility which is not in |
| 20 | | substitution of any existing plant, equipment, property, or |
| 21 | | facility, or any extension or alteration thereof or in |
| 22 | | addition thereto, unless and until it shall have obtained from |
| 23 | | the Commission a certificate that public convenience and |
| 24 | | necessity require such construction. Whenever after a hearing |
| 25 | | the Commission determines that any new construction or the |
| 26 | | transaction of any business by a public utility will promote |
|
| | 10400HB4803ham002 | - 7 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | the public convenience and is necessary thereto, it shall have |
| 2 | | the power to issue certificates of public convenience and |
| 3 | | necessity. The Commission shall determine that proposed |
| 4 | | construction will promote the public convenience and necessity |
| 5 | | only if the utility demonstrates: (1) that the proposed |
| 6 | | construction is necessary to provide adequate, reliable, and |
| 7 | | efficient service to its customers and is the least-cost means |
| 8 | | of satisfying the service needs of its customers or that the |
| 9 | | proposed construction will promote the development of an |
| 10 | | effectively competitive electricity market that operates |
| 11 | | efficiently, is equitable to all customers, and is the least |
| 12 | | cost means of satisfying those objectives; (2) that the |
| 13 | | utility is capable of efficiently managing and supervising the |
| 14 | | construction process and has taken sufficient action to ensure |
| 15 | | adequate and efficient construction and supervision thereof; |
| 16 | | and (3) that the utility is capable of financing the proposed |
| 17 | | construction without significant adverse financial |
| 18 | | consequences for the utility or its customers. |
| 19 | | (b-5) As used in this subsection (b-5): |
| 20 | | "Qualifying direct current applicant" means an entity that |
| 21 | | seeks to provide direct current bulk transmission service for |
| 22 | | the purpose of transporting electric energy in interstate |
| 23 | | commerce. |
| 24 | | "Qualifying direct current project" means a high voltage |
| 25 | | direct current electric service line that crosses at least one |
| 26 | | Illinois border, the Illinois portion of which is physically |
|
| | 10400HB4803ham002 | - 8 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | located within the region of the Midcontinent Independent |
| 2 | | System Operator, Inc., or its successor organization, and runs |
| 3 | | through the counties of Pike, Scott, Greene, Macoupin, |
| 4 | | Montgomery, Christian, Shelby, Cumberland, and Clark, is |
| 5 | | capable of transmitting electricity at voltages of 345 |
| 6 | | kilovolts or above, and may also include associated |
| 7 | | interconnected alternating current interconnection facilities |
| 8 | | in this State that are part of the proposed project and |
| 9 | | reasonably necessary to connect the project with other |
| 10 | | portions of the grid. |
| 11 | | Notwithstanding any other provision of this Act, a |
| 12 | | qualifying direct current applicant that does not own, |
| 13 | | control, operate, or manage, within this State, any plant, |
| 14 | | equipment, or property used or to be used for the transmission |
| 15 | | of electricity at the time of its application or of the |
| 16 | | Commission's order may file an application on or before |
| 17 | | December 31, 2023 with the Commission pursuant to this Section |
| 18 | | or Section 8-406.1 for, and the Commission may grant, a |
| 19 | | certificate of public convenience and necessity to construct, |
| 20 | | operate, and maintain a qualifying direct current project. The |
| 21 | | qualifying direct current applicant may also include in the |
| 22 | | application requests for authority under Section 8-503. The |
| 23 | | Commission shall grant the application for a certificate of |
| 24 | | public convenience and necessity and requests for authority |
| 25 | | under Section 8-503 if it finds that the qualifying direct |
| 26 | | current applicant and the proposed qualifying direct current |
|
| | 10400HB4803ham002 | - 9 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | project satisfy the requirements of this subsection and |
| 2 | | otherwise satisfy the criteria of this Section or Section |
| 3 | | 8-406.1 and the criteria of Section 8-503, as applicable to |
| 4 | | the application and to the extent such criteria are not |
| 5 | | superseded by the provisions of this subsection. The |
| 6 | | Commission's order on the application for the certificate of |
| 7 | | public convenience and necessity shall also include the |
| 8 | | Commission's findings and determinations on the request or |
| 9 | | requests for authority pursuant to Section 8-503. Prior to |
| 10 | | filing its application under either this Section or Section |
| 11 | | 8-406.1, the qualifying direct current applicant shall conduct |
| 12 | | 3 public meetings in accordance with subsection (h) of this |
| 13 | | Section. If the qualifying direct current applicant |
| 14 | | demonstrates in its application that the proposed qualifying |
| 15 | | direct current project is designed to deliver electricity to a |
| 16 | | point or points on the electric transmission grid in either or |
| 17 | | both the PJM Interconnection, LLC or the Midcontinent |
| 18 | | Independent System Operator, Inc., or their respective |
| 19 | | successor organizations, the proposed qualifying direct |
| 20 | | current project shall be deemed to be, and the Commission |
| 21 | | shall find it to be, for public use. If the qualifying direct |
| 22 | | current applicant further demonstrates in its application that |
| 23 | | the proposed transmission project has a capacity of 1,000 |
| 24 | | megawatts or larger and a voltage level of 345 kilovolts or |
| 25 | | greater, the proposed transmission project shall be deemed to |
| 26 | | satisfy, and the Commission shall find that it satisfies, the |
|
| | 10400HB4803ham002 | - 10 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | criteria stated in item (1) of subsection (b) of this Section |
| 2 | | or in paragraph (1) of subsection (f) of Section 8-406.1, as |
| 3 | | applicable to the application, without the taking of |
| 4 | | additional evidence on these criteria. Prior to the transfer |
| 5 | | of functional control of any transmission assets to a regional |
| 6 | | transmission organization, a qualifying direct current |
| 7 | | applicant shall request Commission approval to join a regional |
| 8 | | transmission organization in an application filed pursuant to |
| 9 | | this subsection (b-5) or separately pursuant to Section 7-102 |
| 10 | | of this Act. The Commission may grant permission to a |
| 11 | | qualifying direct current applicant to join a regional |
| 12 | | transmission organization if it finds that the membership, and |
| 13 | | associated transfer of functional control of transmission |
| 14 | | assets, benefits Illinois customers in light of the attendant |
| 15 | | costs and is otherwise in the public interest. Nothing in this |
| 16 | | subsection (b-5) requires a qualifying direct current |
| 17 | | applicant to join a regional transmission organization. |
| 18 | | Nothing in this subsection (b-5) requires the owner or |
| 19 | | operator of a high voltage direct current transmission line |
| 20 | | that is not a qualifying direct current project to obtain a |
| 21 | | certificate of public convenience and necessity to the extent |
| 22 | | it is not otherwise required by this Section 8-406 or any other |
| 23 | | provision of this Act. |
| 24 | | (c) As used in this subsection (c): |
| 25 | | "Decommissioning" has the meaning given to that term in |
| 26 | | subsection (a) of Section 8-508.1. |
|
| | 10400HB4803ham002 | - 11 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | "Nuclear power reactor" has the meaning given to that term |
| 2 | | in Section 8 of the Nuclear Safety Law of 2004. |
| 3 | | After the effective date of this amendatory Act of the |
| 4 | | 103rd General Assembly, no construction shall commence on any |
| 5 | | new nuclear power reactor with a nameplate capacity of more |
| 6 | | than 300 megawatts of electricity to be located within this |
| 7 | | State, and no certificate of public convenience and necessity |
| 8 | | or other authorization shall be issued therefor by the |
| 9 | | Commission, until the Illinois Emergency Management Agency and |
| 10 | | Office of Homeland Security, in consultation with the Illinois |
| 11 | | Environmental Protection Agency and the Illinois Department of |
| 12 | | Natural Resources, finds that the United States Government, |
| 13 | | through its authorized agency, has identified and approved a |
| 14 | | demonstrable technology or means for the disposal of high |
| 15 | | level nuclear waste, or until such construction has been |
| 16 | | specifically approved by a statute enacted by the General |
| 17 | | Assembly. Beginning January 1, 2026, construction may commence |
| 18 | | on a new nuclear power reactor with a nameplate capacity of 300 |
| 19 | | megawatts of electricity or less within this State if the |
| 20 | | entity constructing the new nuclear power reactor has obtained |
| 21 | | all permits, licenses, permissions, or approvals governing the |
| 22 | | construction, operation, and funding of decommissioning of |
| 23 | | such nuclear power reactors required by: (1) this Act; (2) any |
| 24 | | rules adopted by the Illinois Emergency Management Agency and |
| 25 | | Office of Homeland Security under the authority of this Act; |
| 26 | | (3) any applicable federal statutes, including, but not |
|
| | 10400HB4803ham002 | - 12 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | limited to, the Atomic Energy Act of 1954, the Energy |
| 2 | | Reorganization Act of 1974, the Low-Level Radioactive Waste |
| 3 | | Policy Amendments Act of 1985, and the Energy Policy Act of |
| 4 | | 1992; (4) any regulations promulgated or enforced by the U.S. |
| 5 | | Nuclear Regulatory Commission, including, but not limited to, |
| 6 | | those codified at Title X, Parts 20, 30, 40, 50, 70, and 72 of |
| 7 | | the Code of Federal Regulations, as from time to time amended; |
| 8 | | and (5) any other federal or State statute, rule, or |
| 9 | | regulation governing the permitting, licensing, operation, or |
| 10 | | decommissioning of such nuclear power reactors. None of the |
| 11 | | rules developed by the Illinois Emergency Management Agency |
| 12 | | and Office of Homeland Security or any other State agency, |
| 13 | | board, or commission pursuant to this Act shall be construed |
| 14 | | to supersede the authority of the U.S. Nuclear Regulatory |
| 15 | | Commission. The changes made by this amendatory Act of the |
| 16 | | 103rd General Assembly shall not apply to the uprate, renewal, |
| 17 | | or subsequent renewal of any license for an existing nuclear |
| 18 | | power reactor that began operation prior to the effective date |
| 19 | | of this amendatory Act of the 103rd General Assembly. |
| 20 | | None of the changes made in this amendatory Act of the |
| 21 | | 103rd General Assembly are intended to authorize the |
| 22 | | construction of nuclear power plants powered by nuclear power |
| 23 | | reactors that are not either: (1) small modular nuclear |
| 24 | | reactors; or (2) nuclear power reactors licensed by the U.S. |
| 25 | | Nuclear Regulatory Commission to operate in this State prior |
| 26 | | to the effective date of this amendatory Act of the 103rd |
|
| | 10400HB4803ham002 | - 13 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | General Assembly. |
| 2 | | (d) In making its determination under subsection (b) of |
| 3 | | this Section, the Commission shall attach primary weight to |
| 4 | | the cost or cost savings to the customers of the utility. The |
| 5 | | Commission may consider any or all factors which will or may |
| 6 | | affect such cost or cost savings, including the public |
| 7 | | utility's engineering judgment regarding the materials used |
| 8 | | for construction. |
| 9 | | (e) The Commission may issue a temporary certificate which |
| 10 | | shall remain in force not to exceed one year in cases of |
| 11 | | emergency, to assure maintenance of adequate service or to |
| 12 | | serve particular customers, without notice or hearing, pending |
| 13 | | the determination of an application for a certificate, and may |
| 14 | | by regulation exempt from the requirements of this Section |
| 15 | | temporary acts or operations for which the issuance of a |
| 16 | | certificate will not be required in the public interest. |
| 17 | | A public utility shall not be required to obtain but may |
| 18 | | apply for and obtain a certificate of public convenience and |
| 19 | | necessity pursuant to this Section with respect to any matter |
| 20 | | as to which it has received the authorization or order of the |
| 21 | | Commission under the Electric Supplier Act, and any such |
| 22 | | authorization or order granted a public utility by the |
| 23 | | Commission under that Act shall as between public utilities be |
| 24 | | deemed to be, and shall have except as provided in that Act the |
| 25 | | same force and effect as, a certificate of public convenience |
| 26 | | and necessity issued pursuant to this Section. |
|
| | 10400HB4803ham002 | - 14 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | No electric cooperative shall be made or shall become a |
| 2 | | party to or shall be entitled to be heard or to otherwise |
| 3 | | appear or participate in any proceeding initiated under this |
| 4 | | Section for authorization of power plant construction and as |
| 5 | | to matters as to which a remedy is available under the Electric |
| 6 | | Supplier Act. |
| 7 | | (f) Such certificates may be altered or modified by the |
| 8 | | Commission, upon its own motion or upon application by the |
| 9 | | person or corporation affected. Unless exercised within a |
| 10 | | period of 2 years from the grant thereof, authority conferred |
| 11 | | by a certificate of convenience and necessity issued by the |
| 12 | | Commission shall be null and void. |
| 13 | | No certificate of public convenience and necessity shall |
| 14 | | be construed as granting a monopoly or an exclusive privilege, |
| 15 | | immunity or franchise. |
| 16 | | (g) A public utility that undertakes any of the actions |
| 17 | | described in items (1) through (3) of this subsection (g) or |
| 18 | | that has obtained approval pursuant to Section 8-406.1 of this |
| 19 | | Act shall not be required to comply with the requirements of |
| 20 | | this Section to the extent such requirements otherwise would |
| 21 | | apply. For purposes of this Section and Section 8-406.1 of |
| 22 | | this Act, "high voltage electric service line" means an |
| 23 | | electric line having a design voltage of 100,000 or more. For |
| 24 | | purposes of this subsection (g), a public utility may do any of |
| 25 | | the following: |
| 26 | | (1) replace or upgrade any existing high voltage |
|
| | 10400HB4803ham002 | - 15 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | electric service line and related facilities, |
| 2 | | notwithstanding its length; |
| 3 | | (2) relocate any existing high voltage electric |
| 4 | | service line and related facilities, notwithstanding its |
| 5 | | length, to accommodate construction or expansion of a |
| 6 | | roadway or other transportation infrastructure; or |
| 7 | | (3) construct a high voltage electric service line and |
| 8 | | related facilities that is constructed solely to serve a |
| 9 | | single customer's premises or to provide a generator |
| 10 | | interconnection to the public utility's transmission |
| 11 | | system and that will pass under or over the premises owned |
| 12 | | by the customer or generator to be served or under or over |
| 13 | | premises for which the customer or generator has secured |
| 14 | | the necessary right of way. |
| 15 | | (h) A public utility seeking to construct a high-voltage |
| 16 | | electric service line and related facilities (Project) must |
| 17 | | show that the utility has held a minimum of 2 pre-filing public |
| 18 | | meetings to receive public comment concerning the Project in |
| 19 | | each county where the Project is to be located, no earlier than |
| 20 | | 6 months prior to filing an application for a certificate of |
| 21 | | public convenience and necessity from the Commission. Notice |
| 22 | | of the public meeting shall be published in a newspaper of |
| 23 | | general circulation within the affected county once a week for |
| 24 | | 3 consecutive weeks, beginning no earlier than one month prior |
| 25 | | to the first public meeting. If the Project traverses 2 |
| 26 | | contiguous counties and where in one county the transmission |
|
| | 10400HB4803ham002 | - 16 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | line mileage and number of landowners over whose property the |
| 2 | | proposed route traverses is one-fifth or less of the |
| 3 | | transmission line mileage and number of such landowners of the |
| 4 | | other county, then the utility may combine the 2 pre-filing |
| 5 | | meetings in the county with the greater transmission line |
| 6 | | mileage and affected landowners. All other requirements |
| 7 | | regarding pre-filing meetings shall apply in both counties. |
| 8 | | Notice of the public meeting, including a description of the |
| 9 | | Project, must be provided in writing to the clerk of each |
| 10 | | county where the Project is to be located. A representative of |
| 11 | | the Commission shall be invited to each pre-filing public |
| 12 | | meeting. |
| 13 | | (h-5) A public utility seeking to construct a high-voltage |
| 14 | | electric service line and related facilities must also show |
| 15 | | that the Project has complied with training and competence |
| 16 | | requirements under subsection (b) of Section 15 of the |
| 17 | | Electric Transmission Systems Construction Standards Act. |
| 18 | | (h-10) A public utility may be permitted to use highway |
| 19 | | corridors for the purposes of constructing a high-voltage |
| 20 | | electric service line and related facilities. |
| 21 | | (h-15) A public utility seeking to construct a |
| 22 | | high-voltage electric service line and related facilities must |
| 23 | | consider corridors of development in the following order of |
| 24 | | priority: |
| 25 | | (1) existing utility corridors, where adding new lines |
| 26 | | or making improvements to existing lines can achieve |
|
| | 10400HB4803ham002 | - 17 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | expanded electric capacity at the lowest possible cost; |
| 2 | | (2) highway corridors; and |
| 3 | | (3) new utility corridors. |
| 4 | | Consideration of corridors shall be done, to the greatest |
| 5 | | extent possible, in a manner that accounts for economic and |
| 6 | | engineering considerations, the reliability of the electric |
| 7 | | system, and the protection of the environment. |
| 8 | | (i) For applications filed after August 18, 2015 (the |
| 9 | | effective date of Public Act 99-399), the Commission shall, by |
| 10 | | certified mail, notify each owner of record of land, as |
| 11 | | identified in the records of the relevant county tax assessor, |
| 12 | | included in the right-of-way over which the utility seeks in |
| 13 | | its application to construct a high-voltage electric line of |
| 14 | | the time and place scheduled for the initial hearing on the |
| 15 | | public utility's application. The utility shall reimburse the |
| 16 | | Commission for the cost of the postage and supplies incurred |
| 17 | | for mailing the notice. |
| 18 | | (Source: P.A. 102-609, eff. 8-27-21; 102-662, eff. 9-15-21; |
| 19 | | 102-813, eff. 5-13-22; 102-931, eff. 5-27-22; 103-569, eff. |
| 20 | | 6-1-24; 103-1066, eff. 2-20-25.) |
| 21 | | (Text of Section after amendment by P.A. 104-458) |
| 22 | | Sec. 8-406. Certificate of public convenience and |
| 23 | | necessity. |
| 24 | | (a) No public utility not owning any city or village |
| 25 | | franchise nor engaged in performing any public service or in |
|
| | 10400HB4803ham002 | - 18 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | furnishing any product or commodity within this State as of |
| 2 | | July 1, 1921 and not possessing a certificate of public |
| 3 | | convenience and necessity from the Illinois Commerce |
| 4 | | Commission, the State Public Utilities Commission, or the |
| 5 | | Public Utilities Commission, at the time Public Act 84-617 |
| 6 | | goes into effect (January 1, 1986), shall transact any |
| 7 | | business in this State until it shall have obtained a |
| 8 | | certificate from the Commission that public convenience and |
| 9 | | necessity require the transaction of such business. A |
| 10 | | certificate of public convenience and necessity requiring the |
| 11 | | transaction of public utility business in any area of this |
| 12 | | State shall include authorization to the public utility |
| 13 | | receiving the certificate of public convenience and necessity |
| 14 | | to construct such plant, equipment, property, or facility as |
| 15 | | is provided for under the terms and conditions of its tariff |
| 16 | | and as is necessary to provide utility service and carry out |
| 17 | | the transaction of public utility business by the public |
| 18 | | utility in the designated area. |
| 19 | | (b) No public utility shall begin the construction of any |
| 20 | | new plant, equipment, property, or facility which is not in |
| 21 | | substitution of any existing plant, equipment, property, or |
| 22 | | facility, or any extension or alteration thereof or in |
| 23 | | addition thereto, unless and until it shall have obtained from |
| 24 | | the Commission a certificate that public convenience and |
| 25 | | necessity require such construction. Whenever after a hearing |
| 26 | | the Commission determines that any new construction or the |
|
| | 10400HB4803ham002 | - 19 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | transaction of any business by a public utility will promote |
| 2 | | the public convenience and is necessary thereto, it shall have |
| 3 | | the power to issue certificates of public convenience and |
| 4 | | necessity. The Commission shall determine that proposed |
| 5 | | construction will promote the public convenience and necessity |
| 6 | | only if the utility demonstrates: (1) that the proposed |
| 7 | | construction is necessary to provide adequate, reliable, and |
| 8 | | efficient service to its customers and is the least-cost means |
| 9 | | of satisfying the service needs of its customers or that the |
| 10 | | proposed construction will promote the development of an |
| 11 | | effectively competitive electricity market that operates |
| 12 | | efficiently, is equitable to all customers, and is the |
| 13 | | least-cost means of satisfying those objectives; (2) that the |
| 14 | | utility is capable of efficiently managing and supervising the |
| 15 | | construction process and has taken sufficient action to ensure |
| 16 | | adequate and efficient construction and supervision thereof; |
| 17 | | and (3) that the utility is capable of financing the proposed |
| 18 | | construction without significant adverse financial |
| 19 | | consequences for the utility or its customers. |
| 20 | | (b-5) As used in this subsection (b-5): |
| 21 | | "Qualifying direct current applicant" means an entity that |
| 22 | | seeks to provide direct current bulk transmission service for |
| 23 | | the purpose of transporting electric energy in interstate |
| 24 | | commerce. |
| 25 | | "Qualifying direct current project" means a high voltage |
| 26 | | direct current electric service line that crosses at least one |
|
| | 10400HB4803ham002 | - 20 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | Illinois border, the Illinois portion of which is physically |
| 2 | | located within the region of the Midcontinent Independent |
| 3 | | System Operator, Inc., or its successor organization, and runs |
| 4 | | through the counties of Pike, Scott, Greene, Macoupin, |
| 5 | | Montgomery, Christian, Shelby, Cumberland, and Clark, is |
| 6 | | capable of transmitting electricity at voltages of 345 |
| 7 | | kilovolts or above, and may also include associated |
| 8 | | interconnected alternating current interconnection facilities |
| 9 | | in this State that are part of the proposed project and |
| 10 | | reasonably necessary to connect the project with other |
| 11 | | portions of the grid. |
| 12 | | Notwithstanding any other provision of this Act, a |
| 13 | | qualifying direct current applicant that does not own, |
| 14 | | control, operate, or manage, within this State, any plant, |
| 15 | | equipment, or property used or to be used for the transmission |
| 16 | | of electricity at the time of its application or of the |
| 17 | | Commission's order may file an application on or before |
| 18 | | December 31, 2023 with the Commission pursuant to this Section |
| 19 | | or Section 8-406.1 for, and the Commission may grant, a |
| 20 | | certificate of public convenience and necessity to construct, |
| 21 | | operate, and maintain a qualifying direct current project. The |
| 22 | | qualifying direct current applicant may also include in the |
| 23 | | application requests for authority under Section 8-503. The |
| 24 | | Commission shall grant the application for a certificate of |
| 25 | | public convenience and necessity and requests for authority |
| 26 | | under Section 8-503 if it finds that the qualifying direct |
|
| | 10400HB4803ham002 | - 21 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | current applicant and the proposed qualifying direct current |
| 2 | | project satisfy the requirements of this subsection and |
| 3 | | otherwise satisfy the criteria of this Section or Section |
| 4 | | 8-406.1 and the criteria of Section 8-503, as applicable to |
| 5 | | the application and to the extent such criteria are not |
| 6 | | superseded by the provisions of this subsection. The |
| 7 | | Commission's order on the application for the certificate of |
| 8 | | public convenience and necessity shall also include the |
| 9 | | Commission's findings and determinations on the request or |
| 10 | | requests for authority pursuant to Section 8-503. Prior to |
| 11 | | filing its application under either this Section or Section |
| 12 | | 8-406.1, the qualifying direct current applicant shall conduct |
| 13 | | 3 public meetings in accordance with subsection (h) of this |
| 14 | | Section. If the qualifying direct current applicant |
| 15 | | demonstrates in its application that the proposed qualifying |
| 16 | | direct current project is designed to deliver electricity to a |
| 17 | | point or points on the electric transmission grid in either or |
| 18 | | both the PJM Interconnection, LLC or the Midcontinent |
| 19 | | Independent System Operator, Inc., or their respective |
| 20 | | successor organizations, the proposed qualifying direct |
| 21 | | current project shall be deemed to be, and the Commission |
| 22 | | shall find it to be, for public use. If the qualifying direct |
| 23 | | current applicant further demonstrates in its application that |
| 24 | | the proposed transmission project has a capacity of 1,000 |
| 25 | | megawatts or larger and a voltage level of 345 kilovolts or |
| 26 | | greater, the proposed transmission project shall be deemed to |
|
| | 10400HB4803ham002 | - 22 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | satisfy, and the Commission shall find that it satisfies, the |
| 2 | | criteria stated in item (1) of subsection (b) of this Section |
| 3 | | or in paragraph (1) of subsection (f) of Section 8-406.1, as |
| 4 | | applicable to the application, without the taking of |
| 5 | | additional evidence on these criteria. Prior to the transfer |
| 6 | | of functional control of any transmission assets to a regional |
| 7 | | transmission organization, a qualifying direct current |
| 8 | | applicant shall request Commission approval to join a regional |
| 9 | | transmission organization in an application filed pursuant to |
| 10 | | this subsection (b-5) or separately pursuant to Section 7-102 |
| 11 | | of this Act. The Commission may grant permission to a |
| 12 | | qualifying direct current applicant to join a regional |
| 13 | | transmission organization if it finds that the membership, and |
| 14 | | associated transfer of functional control of transmission |
| 15 | | assets, benefits Illinois customers in light of the attendant |
| 16 | | costs and is otherwise in the public interest. Nothing in this |
| 17 | | subsection (b-5) requires a qualifying direct current |
| 18 | | applicant to join a regional transmission organization. |
| 19 | | Nothing in this subsection (b-5) requires the owner or |
| 20 | | operator of a high voltage direct current transmission line |
| 21 | | that is not a qualifying direct current project to obtain a |
| 22 | | certificate of public convenience and necessity to the extent |
| 23 | | it is not otherwise required by this Section 8-406 or any other |
| 24 | | provision of this Act. |
| 25 | | (c) As used in this subsection (c): |
| 26 | | "Decommissioning" has the meaning given to that term in |
|
| | 10400HB4803ham002 | - 23 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | subsection (a) of Section 8-508.1. |
| 2 | | "Nuclear power reactor" has the meaning given to that term |
| 3 | | in Section 8 of the Nuclear Safety Law of 2004. |
| 4 | | Beginning January 1, 2026, construction may commence on a |
| 5 | | new nuclear power reactor within this State if the entity |
| 6 | | constructing the new nuclear power reactor has obtained all |
| 7 | | permits, licenses, permissions, or approvals governing the |
| 8 | | construction, operation, and funding of decommissioning of |
| 9 | | such nuclear power reactors required by: (1) this Act; (2) any |
| 10 | | rules adopted by the Illinois Emergency Management Agency and |
| 11 | | Office of Homeland Security under the authority of this Act; |
| 12 | | (3) any applicable federal statutes, including, but not |
| 13 | | limited to, the Atomic Energy Act of 1954, the Energy |
| 14 | | Reorganization Act of 1974, the Low-Level Radioactive Waste |
| 15 | | Policy Amendments Act of 1985, and the Energy Policy Act of |
| 16 | | 1992; (4) any regulations promulgated or enforced by the U.S. |
| 17 | | Nuclear Regulatory Commission, including, but not limited to, |
| 18 | | those codified at Title X, Parts 20, 30, 40, 50, 70, and 72 of |
| 19 | | the Code of Federal Regulations, as from time to time amended; |
| 20 | | and (5) any other federal or State statute, rule, or |
| 21 | | regulation governing the permitting, licensing, operation, or |
| 22 | | decommissioning of such nuclear power reactors. None of the |
| 23 | | rules developed by the Illinois Emergency Management Agency |
| 24 | | and Office of Homeland Security or any other State agency, |
| 25 | | board, or commission pursuant to this Act shall be construed |
| 26 | | to supersede the authority of the U.S. Nuclear Regulatory |
|
| | 10400HB4803ham002 | - 24 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | Commission. The changes made by this amendatory Act of the |
| 2 | | 103rd General Assembly shall not apply to the uprate, renewal, |
| 3 | | or subsequent renewal of any license for an existing nuclear |
| 4 | | power reactor that began operation prior to the effective date |
| 5 | | of this amendatory Act of the 103rd General Assembly. |
| 6 | | None of the changes made in this amendatory Act of the |
| 7 | | 104th General Assembly are intended to authorize the |
| 8 | | construction of nuclear power plants powered by nuclear power |
| 9 | | reactors that are not nuclear power reactors licensed by the |
| 10 | | U.S. Nuclear Regulatory Commission to operate in this State. |
| 11 | | (d) In making its determination under subsection (b) of |
| 12 | | this Section, the Commission shall attach primary weight to |
| 13 | | the cost or cost savings to the customers of the utility. The |
| 14 | | Commission may consider any or all factors which will or may |
| 15 | | affect such cost or cost savings, including the public |
| 16 | | utility's engineering judgment regarding the materials used |
| 17 | | for construction. |
| 18 | | (e) The Commission may issue a temporary certificate which |
| 19 | | shall remain in force not to exceed one year in cases of |
| 20 | | emergency, to assure maintenance of adequate service or to |
| 21 | | serve particular customers, without notice or hearing, pending |
| 22 | | the determination of an application for a certificate, and may |
| 23 | | by regulation exempt from the requirements of this Section |
| 24 | | temporary acts or operations for which the issuance of a |
| 25 | | certificate will not be required in the public interest. |
| 26 | | A public utility shall not be required to obtain but may |
|
| | 10400HB4803ham002 | - 25 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | apply for and obtain a certificate of public convenience and |
| 2 | | necessity pursuant to this Section with respect to any matter |
| 3 | | as to which it has received the authorization or order of the |
| 4 | | Commission under the Electric Supplier Act, and any such |
| 5 | | authorization or order granted a public utility by the |
| 6 | | Commission under that Act shall as between public utilities be |
| 7 | | deemed to be, and shall have except as provided in that Act the |
| 8 | | same force and effect as, a certificate of public convenience |
| 9 | | and necessity issued pursuant to this Section. |
| 10 | | No electric cooperative shall be made or shall become a |
| 11 | | party to or shall be entitled to be heard or to otherwise |
| 12 | | appear or participate in any proceeding initiated under this |
| 13 | | Section for authorization of power plant construction and as |
| 14 | | to matters as to which a remedy is available under the Electric |
| 15 | | Supplier Act. |
| 16 | | (f) Such certificates may be altered or modified by the |
| 17 | | Commission, upon its own motion or upon application by the |
| 18 | | person or corporation affected. Unless exercised within a |
| 19 | | period of 2 years from the grant thereof, authority conferred |
| 20 | | by a certificate of convenience and necessity issued by the |
| 21 | | Commission shall be null and void. |
| 22 | | No certificate of public convenience and necessity shall |
| 23 | | be construed as granting a monopoly or an exclusive privilege, |
| 24 | | immunity or franchise. |
| 25 | | (g) A public utility that undertakes any of the actions |
| 26 | | described in items (1) through (3) of this subsection (g) or |
|
| | 10400HB4803ham002 | - 26 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | that has obtained approval pursuant to Section 8-406.1 of this |
| 2 | | Act shall not be required to comply with the requirements of |
| 3 | | this Section to the extent such requirements otherwise would |
| 4 | | apply. For purposes of this Section and Section 8-406.1 of |
| 5 | | this Act, "high voltage electric service line" means an |
| 6 | | electric line having a design voltage of 69,000 or more. For |
| 7 | | purposes of this subsection (g), a public utility may do any of |
| 8 | | the following: |
| 9 | | (1) replace or upgrade any existing high voltage |
| 10 | | electric service line and related facilities, |
| 11 | | notwithstanding its length or, subject to applicable |
| 12 | | Article VII requirements, ownership; |
| 13 | | (2) relocate any existing high voltage electric |
| 14 | | service line and related facilities, notwithstanding its |
| 15 | | length, to accommodate construction or expansion of a |
| 16 | | roadway or other transportation infrastructure; or |
| 17 | | (3) construct a high voltage electric service line and |
| 18 | | related facilities that is constructed solely to serve a |
| 19 | | single customer's premises or to provide a generator |
| 20 | | interconnection to the public utility's transmission |
| 21 | | system and that will (i) pass under or over the premises |
| 22 | | owned by the customer or generator to be served; (ii) pass |
| 23 | | under or over premises for which the customer or generator |
| 24 | | has secured the necessary right-of-way; or (iii) be |
| 25 | | multi-circuited with the facilities of the public utility. |
| 26 | | (h) A public utility seeking to construct a high-voltage |
|
| | 10400HB4803ham002 | - 27 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | electric service line and related facilities (Project) must |
| 2 | | show that the utility has held a minimum of 2 pre-filing public |
| 3 | | meetings to receive public comment concerning the Project in |
| 4 | | each county where the Project is to be located, no earlier than |
| 5 | | 6 months prior to filing an application for a certificate of |
| 6 | | public convenience and necessity from the Commission. Notice |
| 7 | | of the public meeting shall be published in a newspaper of |
| 8 | | general circulation within the affected county once a week for |
| 9 | | 3 consecutive weeks, beginning no earlier than one month prior |
| 10 | | to the first public meeting. If the Project traverses 2 |
| 11 | | contiguous counties and where in one county the transmission |
| 12 | | line mileage and number of landowners over whose property the |
| 13 | | proposed route traverses is one-fifth or less of the |
| 14 | | transmission line mileage and number of such landowners of the |
| 15 | | other county, then the utility may combine the 2 pre-filing |
| 16 | | meetings in the county with the greater transmission line |
| 17 | | mileage and affected landowners. All other requirements |
| 18 | | regarding pre-filing meetings shall apply in both counties. |
| 19 | | Notice of the public meeting, including a description of the |
| 20 | | Project, must be provided in writing to the clerk of each |
| 21 | | county where the Project is to be located. A representative of |
| 22 | | the Commission shall be invited to each pre-filing public |
| 23 | | meeting. |
| 24 | | (h-5) A public utility seeking to construct a high-voltage |
| 25 | | electric service line and related facilities must also show |
| 26 | | that the Project has complied with training and competence |
|
| | 10400HB4803ham002 | - 28 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | requirements under subsection (b) of Section 15 of the |
| 2 | | Electric Transmission Systems Construction Standards Act. |
| 3 | | (h-10) A public utility may be permitted to use highway |
| 4 | | corridors for the purposes of constructing a high-voltage |
| 5 | | electric service line and related facilities. |
| 6 | | (h-15) A public utility seeking to construct a |
| 7 | | high-voltage electric service line and related facilities must |
| 8 | | consider corridors of development in the following order of |
| 9 | | priority: |
| 10 | | (1) existing utility corridors, where adding new lines |
| 11 | | or making improvements to existing lines can achieve |
| 12 | | expanded electric capacity at the lowest possible cost; |
| 13 | | (2) highway corridors; and |
| 14 | | (3) new utility corridors. |
| 15 | | Consideration of corridors shall be done, to the greatest |
| 16 | | extent possible, in a manner that accounts for economic and |
| 17 | | engineering considerations, the reliability of the electric |
| 18 | | system, and the protection of the environment. |
| 19 | | (i) For applications filed after August 18, 2015 (the |
| 20 | | effective date of Public Act 99-399), the Commission shall, by |
| 21 | | certified mail, notify each owner of record of land, as |
| 22 | | identified in the records of the relevant county tax assessor, |
| 23 | | included in the right-of-way over which the utility seeks in |
| 24 | | its application to construct a high-voltage electric line of |
| 25 | | the time and place scheduled for the initial hearing on the |
| 26 | | public utility's application. The utility shall reimburse the |
|
| | 10400HB4803ham002 | - 29 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | Commission for the cost of the postage and supplies incurred |
| 2 | | for mailing the notice. |
| 3 | | (j) In determining whether to issue a certificate of |
| 4 | | public convenience for a new electric generation facility to a |
| 5 | | municipal power agency that is required to obtain such a |
| 6 | | certificate to exercise its power of eminent domain pursuant |
| 7 | | to Section 11-119.1-10 of the Illinois Municipal Code, the |
| 8 | | Commission shall give due consideration to whether a |
| 9 | | generation unit of similar size and type is part of the |
| 10 | | municipal power agency's preferred portfolio or least-cost |
| 11 | | plan for achieving renewable energy goals in its most recent |
| 12 | | integrated resource plan, as described in subsection (d) of |
| 13 | | Section 1-15 of the Municipal and Cooperative Electric Utility |
| 14 | | Transparent Planning Act. |
| 15 | | (Source: P.A. 103-569, eff. 6-1-24; 103-1066, eff. 2-20-25; |
| 16 | | 104-458, eff. 6-1-26.) |
| 17 | | (220 ILCS 5/8-406.1) |
| 18 | | Sec. 8-406.1. Certificate of public convenience and |
| 19 | | necessity; expedited procedure. |
| 20 | | (a) A public utility may apply for a certificate of public |
| 21 | | convenience and necessity pursuant to this Section for the |
| 22 | | construction of any new high voltage electric service line and |
| 23 | | related facilities (Project). To facilitate the expedited |
| 24 | | review process of an application filed pursuant to this |
| 25 | | Section, an application shall include all of the following: |
|
| | 10400HB4803ham002 | - 30 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | (1) Information in support of the application that |
| 2 | | shall include the following: |
| 3 | | (A) A detailed description of the Project, |
| 4 | | including location maps and plot plans to scale |
| 5 | | showing all major components. |
| 6 | | (B) The following engineering data: |
| 7 | | (i) a detailed Project description including: |
| 8 | | (I) name and destination of the Project; |
| 9 | | (II) design voltage rating (kV); |
| 10 | | (III) operating voltage rating (kV); and |
| 11 | | (IV) normal peak operating current rating; |
| 12 | | (ii) a conductor, structures, and substations |
| 13 | | description including: |
| 14 | | (I) conductor size and type; |
| 15 | | (II) type of structures; |
| 16 | | (III) height of typical structures; |
| 17 | | (IV) an explanation why these structures |
| 18 | | were selected; |
| 19 | | (V) dimensional drawings of the typical |
| 20 | | structures to be used in the Project; and |
| 21 | | (VI) a list of the names of all new (and |
| 22 | | existing if applicable) substations or |
| 23 | | switching stations that will be associated |
| 24 | | with the proposed new high voltage electric |
| 25 | | service line; |
| 26 | | (iii) the location of the site and |
|
| | 10400HB4803ham002 | - 31 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | right-of-way including: |
| 2 | | (I) miles of right-of-way; |
| 3 | | (II) miles of circuit; |
| 4 | | (III) width of the right-of-way; and |
| 5 | | (IV) a brief description of the area |
| 6 | | traversed by the proposed high voltage |
| 7 | | electric service line, including a description |
| 8 | | of the general land uses in the area and the |
| 9 | | type of terrain crossed by the proposed line; |
| 10 | | (iv) assumptions, bases, formulae, and methods |
| 11 | | used in the development and preparation of the |
| 12 | | diagrams and accompanying data, and a technical |
| 13 | | description providing the following information: |
| 14 | | (I) number of circuits, with |
| 15 | | identification as to whether the circuit is |
| 16 | | overhead or underground; |
| 17 | | (II) the operating voltage and frequency; |
| 18 | | and |
| 19 | | (III) conductor size and type and number |
| 20 | | of conductors per phase; |
| 21 | | (v) if the proposed interconnection is an |
| 22 | | overhead line, the following additional |
| 23 | | information also must be provided: |
| 24 | | (I) the wind and ice loading design |
| 25 | | parameters; |
| 26 | | (II) a full description and drawing of a |
|
| | 10400HB4803ham002 | - 32 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | typical supporting structure, including |
| 2 | | strength specifications; |
| 3 | | (III) structure spacing with typical |
| 4 | | ruling and maximum spans; |
| 5 | | (IV) conductor (phase) spacing; and |
| 6 | | (V) the designed line-to-ground and |
| 7 | | conductor-side clearances; |
| 8 | | (vi) if an underground or underwater |
| 9 | | interconnection is proposed, the following |
| 10 | | additional information also must be provided: |
| 11 | | (I) burial depth; |
| 12 | | (II) type of cable and a description of |
| 13 | | any required supporting equipment, such as |
| 14 | | insulation medium pressurizing or forced |
| 15 | | cooling; |
| 16 | | (III) cathodic protection scheme; and |
| 17 | | (IV) type of dielectric fluid and |
| 18 | | safeguards used to limit potential spills in |
| 19 | | waterways; |
| 20 | | (vii) technical diagrams that provide |
| 21 | | clarification of any item under this item (1) |
| 22 | | should be included; and |
| 23 | | (viii) applicant shall provide and identify a |
| 24 | | primary right-of-way and one or more alternate |
| 25 | | rights-of-way for the Project as part of the |
| 26 | | filing. To the extent applicable, for each |
|
| | 10400HB4803ham002 | - 33 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | right-of-way, an applicant shall provide the |
| 2 | | information described in this subsection (a). Upon |
| 3 | | a showing of good cause in its filing, an |
| 4 | | applicant may be excused from providing and |
| 5 | | identifying alternate rights-of-way. |
| 6 | | (2) An application fee of $100,000, which shall be |
| 7 | | paid into the Public Utility Fund at the time the Chief |
| 8 | | Clerk of the Commission deems it complete and accepts the |
| 9 | | filing. |
| 10 | | (3) Information showing that the utility has held a |
| 11 | | minimum of 3 pre-filing public meetings to receive public |
| 12 | | comment concerning the Project in each county where the |
| 13 | | Project is to be located, no earlier than 6 months prior to |
| 14 | | the filing of the application. Notice of the public |
| 15 | | meeting shall be published in a newspaper of general |
| 16 | | circulation within the affected county once a week for 3 |
| 17 | | consecutive weeks, beginning no earlier than one month |
| 18 | | prior to the first public meeting. If the Project |
| 19 | | traverses 2 contiguous counties and where in one county |
| 20 | | the transmission line mileage and number of landowners |
| 21 | | over whose property the proposed route traverses is 1/5 or |
| 22 | | less of the transmission line mileage and number of such |
| 23 | | landowners of the other county, then the utility may |
| 24 | | combine the 3 pre-filing meetings in the county with the |
| 25 | | greater transmission line mileage and affected landowners. |
| 26 | | All other requirements regarding pre-filing meetings shall |
|
| | 10400HB4803ham002 | - 34 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | apply in both counties. Notice of the public meeting, |
| 2 | | including a description of the Project, must be provided |
| 3 | | in writing to the clerk of each county where the Project is |
| 4 | | to be located. A representative of the Commission shall be |
| 5 | | invited to each pre-filing public meeting. |
| 6 | | For applications filed after the effective date of this |
| 7 | | amendatory Act of the 99th General Assembly, the Commission |
| 8 | | shall, by certified mail, notify each owner of record of the |
| 9 | | land, as identified in the records of the relevant county tax |
| 10 | | assessor, included in the primary or alternate rights-of-way |
| 11 | | identified in the utility's application of the time and place |
| 12 | | scheduled for the initial hearing upon the public utility's |
| 13 | | application. The utility shall reimburse the Commission for |
| 14 | | the cost of the postage and supplies incurred for mailing the |
| 15 | | notice. |
| 16 | | (b) At the first status hearing the administrative law |
| 17 | | judge shall set a schedule for discovery that shall take into |
| 18 | | consideration the expedited nature of the proceeding. |
| 19 | | (c) Nothing in this Section prohibits a utility from |
| 20 | | requesting, or the Commission from approving, protection of |
| 21 | | confidential or proprietary information under applicable law. |
| 22 | | The public utility may seek confidential protection of any of |
| 23 | | the information provided pursuant to this Section, subject to |
| 24 | | Commission approval. |
| 25 | | (d) The public utility shall publish notice of its |
| 26 | | application in the official State newspaper within 10 days |
|
| | 10400HB4803ham002 | - 35 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | following the date of the application's filing. |
| 2 | | (e) The public utility shall establish a dedicated website |
| 3 | | for the Project 3 weeks prior to the first public meeting and |
| 4 | | maintain the website until construction of the Project is |
| 5 | | complete. The website address shall be included in all public |
| 6 | | notices. |
| 7 | | (f) The Commission shall, after notice and hearing, grant |
| 8 | | a certificate of public convenience and necessity filed in |
| 9 | | accordance with the requirements of this Section if, based |
| 10 | | upon the application filed with the Commission and the |
| 11 | | evidentiary record, it finds the Project will promote the |
| 12 | | public convenience and necessity and that all of the following |
| 13 | | criteria are satisfied: |
| 14 | | (1) That the Project is necessary to provide adequate, |
| 15 | | reliable, and efficient service to the public utility's |
| 16 | | customers and is the least-cost means of satisfying the |
| 17 | | service needs of the public utility's customers or that |
| 18 | | the Project will promote the development of an effectively |
| 19 | | competitive electricity market that operates efficiently, |
| 20 | | is equitable to all customers, and is the least cost means |
| 21 | | of satisfying those objectives. |
| 22 | | (2) That the public utility is capable of efficiently |
| 23 | | managing and supervising the construction process and has |
| 24 | | taken sufficient action to ensure adequate and efficient |
| 25 | | construction and supervision of the construction. |
| 26 | | (3) That the public utility is capable of financing |
|
| | 10400HB4803ham002 | - 36 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | the proposed construction without significant adverse |
| 2 | | financial consequences for the utility or its customers. |
| 3 | | (4) That the Project has complied with training and |
| 4 | | competence and Diversity Plan requirements under |
| 5 | | subsections (b) and (d) of Section 15 of the Electric |
| 6 | | Transmission Systems Construction Standards Act. |
| 7 | | (g) The Commission shall issue its decision with findings |
| 8 | | of fact and conclusions of law granting or denying the |
| 9 | | application no later than 150 days after the application is |
| 10 | | filed. The Commission may extend the 150-day deadline upon |
| 11 | | notice by an additional 75 days if, on or before the 30th day |
| 12 | | after the filing of the application, the Commission finds that |
| 13 | | good cause exists to extend the 150-day period. |
| 14 | | (h) In the event the Commission grants a public utility's |
| 15 | | application for a certificate pursuant to this Section, the |
| 16 | | public utility shall pay a one-time construction fee to each |
| 17 | | county in which the Project is constructed within 30 days |
| 18 | | after the completion of construction. The construction fee |
| 19 | | shall be $20,000 per mile of high voltage electric service |
| 20 | | line constructed in that county, or a proportionate fraction |
| 21 | | of that fee. The fee shall be in lieu of any permitting fees |
| 22 | | that otherwise would be imposed by a county. Counties |
| 23 | | receiving a payment under this subsection (h) may distribute |
| 24 | | all or portions of the fee to local taxing districts in that |
| 25 | | county. |
| 26 | | (i) Notwithstanding any other provisions of this Act, a |
|
| | 10400HB4803ham002 | - 37 - | LRB104 16923 AAS 36827 a |
|
|
| 1 | | decision granting a certificate under this Section shall |
| 2 | | include an order pursuant to Section 8-503 of this Act |
| 3 | | authorizing or directing the construction of the high voltage |
| 4 | | electric service line and related facilities as approved by |
| 5 | | the Commission, in the manner and within the time specified in |
| 6 | | said order. |
| 7 | | (j) A public utility may be permitted to use highway |
| 8 | | corridors for the purposes of constructing a high-voltage |
| 9 | | electric service line and related facilities for the purposes |
| 10 | | of this Section. |
| 11 | | (j-5) A public utility seeking to construct a high-voltage |
| 12 | | electric service line and related facilities must consider |
| 13 | | corridors of development in the following order of priority: |
| 14 | | (1) existing utility corridors, where adding new lines |
| 15 | | or making improvements to existing lines can achieve |
| 16 | | expanded electric capacity at the lowest possible cost; |
| 17 | | (2) highway corridors; and |
| 18 | | (3) new utility corridors. |
| 19 | | Consideration of corridors shall be done, to the greatest |
| 20 | | extent possible, in a manner that accounts for economic and |
| 21 | | engineering considerations, the reliability of the electric |
| 22 | | system, and the protection of the environment. |
| 23 | | (Source: P.A. 102-931, eff. 5-27-22; 103-1066, eff. 2-20-25.) |
| 24 | | Section 95. No acceleration or delay. Where this Act makes |
| 25 | | changes in a statute that is represented in this Act by text |