104TH GENERAL ASSEMBLY
State of Illinois
2025 and 2026
HB5374

 

Introduced 2/10/2026, by Rep. Robyn Gabel

 

SYNOPSIS AS INTRODUCED:
 
415 ILCS 5/39.16 new
415 ILCS 155/18 new

    Amends the Environmental Protection Act. Makes findings about the imposition of disproportionate and adverse effects on communities in areas of environmental justice concern. Defines terms. Applies to the following permits for which an owner or operator applies on or after January 1, 2026: (1) a construction permit for a new source that is to be located in an area of environmental justice concern and that is required to obtain from the Agency a CAAPP permit or a Federally Enforceable State Operating Permit; (2) a construction permit for any existing source that is located in an area of environmental justice concern, that possesses a CAAPP permit or a Federally Enforceable State Operating Permit issued by the Agency, and that seeks an increase in annual permitted emissions; or (3) a construction permit for any existing source that is located in an area of environmental justice concern, that seeks an increase in annual permitted emissions, and that will for the first time require a new CAAPP permit or a Federally Enforceable State Operating Permit issued by the Agency. Requires the Environmental Protection Agency to evaluate the application for affects on environmental justice and may suggest additional testing or changes in the application. Requires that the Agency to conduct an evaluation of the prospective owner's or operator's prior experience in owning and operating sources of air pollution before it may issue a construction permit. Makes other changes. Creates the Office of Environmental Justice within the Environmental Protection Agency. Effective immediately.


LRB104 13646 RTM 26289 b

 

 

A BILL FOR

 

HB5374LRB104 13646 RTM 26289 b

1    AN ACT concerning safety.
 
2    Be it enacted by the People of the State of Illinois,
3represented in the General Assembly:
 
4    Section 5. The Environmental Protection Act is amended by
5adding Section 39.16 as follows:
 
6    (415 ILCS 5/39.16 new)
7    Sec. 39.16. Air Pollution Control Construction Permitting
8in Areas of Environmental Justice Concern.
9    (a) Legislative Findings. The General Assembly finds that:
10        (1) all residents of this State have a right to a
11    healthful environment under Article XI of the Illinois
12    Constitution of 1970;
13        (2) no community should bear disproportionate and
14    adverse effects from pollution;
15        (3) in 2024, the Agency entered in an Informal
16    Resolution Agreement with the United States Environmental
17    Protection Agency requiring, among other things,
18    enhancements to its permit review process for certain
19    permit transactions in areas of environmental justice
20    concern; and
21        (4) such enhancements to the Agency's permit review
22    process are necessary to avoid the imposition of
23    disproportionate and adverse effects to communities in

 

 

HB5374- 2 -LRB104 13646 RTM 26289 b

1    areas of environmental justice concern, as such areas are
2    identified herein.
3    The provisions of this Section shall be liberally
4construed to carry out the purposes of this Section.
5    (b) Definitions. For purposes of this Section:
6    "Area of environmental justice concern" or "area of EJ
7concern" means a geographical area, the population of which
8potentially experiences disproportionate environmental harms
9and risks as a result of both environmental and socioeconomic
10conditions that may act cumulatively to affect health and the
11environment and contribute to persistent environmental health
12disparities. "Area of EJ concern" shall include all census
13block groups, and all areas within one mile of such census
14block groups, identified and updated by the Agency on a
15triennial basis as being within the top 25% of census blocks
16statewide, scored by multiplying each census block group's
17average statewide percentile for each of the following
18environmental indicators, by the census block group's average
19statewide percentile for each of the following socioeconomic
20indicators:
21    Environmental indicators:
22        (1) annual average concentration of particulate matter
23    less than 2.5 microns or smaller in diameter;
24        (2) annual average concentration of ozone;
25        (3) annual average concentration of nitrogen dioxide;
26        (4) annual average concentration of diesel particulate

 

 

HB5374- 3 -LRB104 13646 RTM 26289 b

1    matter;
2        (5) annual average toxicity-weighted concentrations of
3    Toxic Release Inventory-listed chemicals;
4        (6) vehicle traffic;
5        (7) drinking water violations that have not been
6    returned to compliance;
7        (8) percentage of housing units built pre-1960;
8        (9) number of proposed or listed National Priorities
9    List sites;
10        (10) number of facilities with Risk Management Plans;
11        (11) number of treatment, storage, and disposal and
12    large-quantity generator hazardous waste facilities;
13        (12) number of leaking underground storage tanks and
14    underground storage tanks; and
15        (13) toxics concentrations at stream segments.
16    Socioeconomic indicators - percentage of population:
17        (1) with household income less than or equal to twice
18    the federal poverty level;
19        (2) unemployed;
20        (3) living in limited English proficiency households;
21        (4) aged 25 or older whose education is short of a high
22    school diploma;
23        (5) under the age of 5; and
24        (6) over the age of 64.
25    Environmental indicators (7) through (13) are given half
26the weight of environmental indicators (1) through (6) in

 

 

HB5374- 4 -LRB104 13646 RTM 26289 b

1calculating the averaged percentile.
2    (c) Applicability. This Section applies to the following
3permits for which an owner or operator applies on or after
4January 1, 2026:
5        (1) a construction permit for a new source that is to
6    be located in an area of EJ concern and that will require a
7    Clean Air Act Permit Program permit, or a Federally
8    Enforceable State Operating Permit issued by the Agency
9    under Section 39.5 of this Act;
10        (2) a construction permit for any existing source that
11    is located in an area of EJ concern, that possesses a Clean
12    Air Act Permit Program permit, or a Federally Enforceable
13    State Operating Permit issued by the Agency under Section
14    39.5 of this Act and that seeks an increase in annual
15    permitted emissions; or
16        (3) a construction permit for any existing source that
17    is located in an area of EJ concern, that seeks an increase
18    in annual permitted emissions and that will require a new
19    Clean Air Act Permit Program permit, or a Federally
20    Enforceable State Operating Permit issued by the Agency
21    under Section 39.5 of this Act for the first time.
22    (d) Review of permit applications; notifications. Upon
23receipt of an air pollution control construction permit
24application, the Agency shall evaluate the application to:
25        (1) determine whether the source falls within an area
26    of EJ concern. Based on this review, the Agency shall send

 

 

HB5374- 5 -LRB104 13646 RTM 26289 b

1    an EJ notification letter to elected officials, community
2    groups, and individuals who have requested to be notified,
3    to provide information about the proposed project and how
4    an individual can request a public hearing on a permit
5    application;
6        (2) determine whether emissions increases from the
7    proposed project can be reduced or voluntarily limited by
8    the applicant to avoid or minimize potential impacts to
9    any affected area(s) of EJ concern. This includes, but is
10    not limited to, establishment of lower thresholds for
11    potential-to-emit, installation of alternative pollution
12    controls, and decreased utilization of other units at the
13    facility; and
14        (3) determine the need for the applicant to conduct
15    additional air quality modeling to confirm that the
16    project will not threaten or compromise existing National
17    Ambient Air Quality Standards or other applicable
18    standards appropriate for comparison with other pollutants
19    of concern.
20    (e) Permit enhancements.
21        (1) The Agency shall evaluate and, if necessary to
22    comply with this Act, include appropriate permit
23    enhancements to address potential impacts to an area of EJ
24    concern. These enhancements may include, but are not
25    limited to:
26            (A) improved air monitoring systems, including

 

 

HB5374- 6 -LRB104 13646 RTM 26289 b

1        parametric and continuous monitoring systems;
2            (B) development of a fugitive dust operating
3        program/plan or enhancements to an existing
4        program/plan;
5            (C) operational requirements to establish limits
6        on potential-to-emit or to demonstrate source
7        compliance with an emission rate;
8            (D) increased use or frequency of emissions
9        testing;
10            (E) development of enforceable requirements to go
11        into the construction permit to assure that the source
12        meets modeling assumptions used in the air quality
13        modeling (including hours of operation, operating
14        requirements, operating schedule, meteorological
15        assumptions, property boundaries, etc.);
16            (F) development of an odor control plant to
17        identify and mitigate potential off-site odor impacts
18        from the project;
19            (G) development of odor monitoring of third-party
20        complaints, including a process for tracking
21        complaints and inspecting affected process operations
22        known to be capable of causing air pollution;
23            (H) discretionary use of prior adjudications of
24        violations of this Act and regulations adopted
25        thereunder by the applicant that involve a release of
26        a contaminant into the environment in evaluating the

 

 

HB5374- 7 -LRB104 13646 RTM 26289 b

1        permit application;
2            (I) discretionary use of reasonable conditions
3        specifically related to an applicant's past compliance
4        history with this Act and regulations adopted
5        thereunder as necessary to correct, detect, or prevent
6        noncompliance;
7            (J) use of pollution prevention techniques; or
8            (K) applicant outreach, independent of the permit
9        review process, with the affected community.
10        (2) The Agency may also conduct further analysis, as
11    needed, to inform its permit decision, including:
12            (A) consideration of information relating to other
13        sources permitted by the Agency or the United States
14        Environmental Protection Agency;
15            (B) information relating to regulated sources
16        under State or federal environmental laws;
17            (C) data bearing upon the classification of an
18        area of EJ concern;
19            (D) location of sensitive populations or places
20        near the proposed facility, including schools,
21        hospitals, day care centers, and culturally
22        significant resources;
23            (E) factors that may increase community exposure
24        or vulnerability as compared to other populations; or
25            (F) consultation with the United States
26        Environmental Protection Agency or other state and

 

 

HB5374- 8 -LRB104 13646 RTM 26289 b

1        federal regulatory authorities regarding additional
2        areas of study.
3        (3) If the Agency's analysis described in this Section
4    shows disproportionate and adverse effects, the Agency
5    shall consider making additional refinements to the
6    project emissions analysis, air quality modeling, or
7    permit enhancements; prioritizing compliance inspections
8    and any resulting enforcement initiatives of an
9    applicant's existing permitted source or other
10    contributing sources to the affected area, with the aim of
11    reducing existing adverse impacts; prioritizing grant
12    funding for projects in the affected community; and
13    conducting consultations with the United States
14    Environmental Protection Agency or other state and federal
15    agencies relating to potential mitigation options,
16    including fence-line monitoring, risk assessments, or
17    rulemakings.
18    (e) Issuance of permits; prohibitions.
19        (1) The Agency shall not issue a construction permit
20    identified in Section 39.16(2) of this Act unless the
21    Agency conducts an evaluation of the prospective owner's
22    or operator's prior experience in owning and operating
23    sources of air pollution. The Agency may deny the permit
24    if the prospective owner or operator or any board member
25    has a history of:
26            (A) repeated violations of federal, State, or

 

 

HB5374- 9 -LRB104 13646 RTM 26289 b

1        local laws, rules, regulations, standards, or
2        ordinances in the ownership or operation of sources of
3        air pollution;
4            (B) conviction in this State, another state, or
5        federal court of knowingly submitting false
6        information under any environmental law, rule,
7        regulation, or permit term or condition; or
8            (C) proof of gross carelessness or incompetence in
9        the ownership or operation of a source of air
10        pollution.
11        (2) In making its determination on permit applications
12    identified in Section 39.16(2) of this Act, the Agency
13    shall consider prior adjudications of noncompliance with
14    this Act and regulations adopted thereunder by the
15    applicant. In granting permits, the Agency shall consider
16    whether to impose reasonable conditions specifically
17    related to the applicant's past compliance history with
18    this Act and regulations adopted thereunder as necessary
19    to correct, detect, or prevent noncompliance. This may
20    include consideration of:
21            (A) information contained within USEPA's and the
22        Agency's environmental compliance tracking system;
23            (B) information submitted in public comments to a
24        construction permit application pending review;
25            (C) judicial or administrative consent decrees or
26        compliance orders that are entered into, or issued by,

 

 

HB5374- 10 -LRB104 13646 RTM 26289 b

1        USEPA involving requirements of the Illinois State
2        Implementation Plan; or
3            (D) information relating to State-only compliance
4        history.
5        (3) The Agency shall prepare a written analysis of its
6    evaluation of compliance enforcement history, as well as
7    any additional civil rights analysis or mitigation
8    measures undertaken. The analysis shall be prepared before
9    a notice of public comment or hearing concerning a draft
10    construction permit and must be posted among the documents
11    available on the Agency's public notice website or public
12    repository. If no public participation is provided for
13    under Agency rules, the analysis shall be posted to the
14    Agency's public notice webpage at the time of permit
15    issuance.
16    (g) Severability. If any provision of this Section or its
17application to any person or circumstance is held invalid, the
18invalidity of that provision or application does not affect
19other provisions or applications of this Section that can be
20given effect without the invalid provision or application.
 
21    Section 10. The Environmental Justice Act is amended by
22adding Section 18 as follows:
 
23    (415 ILCS 155/18 new)
24    Sec. 18. Office of Environmental Justice. An Office of

 

 

HB5374- 11 -LRB104 13646 RTM 26289 b

1Environmental Justice is established within the Illinois
2Environmental Protection Agency. The Office shall coordinate
3the integration of environmental justice into Agency programs
4and activities, oversee implementation of language access
5policies, and provide enhanced public outreach to areas of
6environmental justice concern. The Director shall appoint an
7Environmental Justice Officer within the Office of
8Environmental Justice to administer the Office.
 
9    Section 97. Severability. If any provision of this
10Amendatory Act of the 104th General Assembly or its
11application to any person or circumstance is held invalid, the
12invalidity of that provision or application does not affect
13other provisions or applications of this Amendatory Act of the
14104th General Assembly that can be given effect without the
15invalid provision or application.
 
16    Section 99. Effective date. This Act takes effect upon
17becoming law.