104TH GENERAL ASSEMBLY
State of Illinois
2025 and 2026
SB2686

 

Introduced 10/14/2025, by Sen. Sue Rezin

 

SYNOPSIS AS INTRODUCED:
 
New Act

    Creates the Energy Production Zones Act. Defines terms. Provides that a project owner is not required to obtain a permit or any other land use or zoning approval from a local authority for the construction of an electric generation facility if: (1) the Illinois Commerce Commission grants the project owner a certificate under the Public Utilities Act for the construction, the Commission declines jurisdiction over the construction under the Public Utilities Act, or the electric generation facility files notice with the Commission to not use a certificate under the Public Utilities Act; (2) the electric generating facility will be located on a premise of land that is an energy production zone; and (3) the project owner complies with other provisions of the Act. Provides that no later than 270 days before beginning construction, a project owner shall provide notice of the construction to the local authority with planning authority for the premise of land on which the construction will occur. Sets forth requirements for the content of the notice. Provides that, no later than 60 days after a project owner's provision of notice, the project owner shall hold a public hearing in the unit of local government in which the electric generation facility will be located, during which the project owner shall provide information to the public and receive public comment regarding the electric generation facility and the construction of the electric generation facility. Makes other changes. Effective immediately.


LRB104 14637 AAS 27779 b

 

 

A BILL FOR

 

SB2686LRB104 14637 AAS 27779 b

1    AN ACT concerning regulation.
 
2    Be it enacted by the People of the State of Illinois,
3represented in the General Assembly:
 
4    Section 1. Short title. This Act may be cited as the Energy
5Production Zones Act.
 
6    Section 5. Definitions. As used in this Act:
7    "Commercial solar energy system" means any device or
8assembly of devices that (i) is ground installed and (ii) uses
9solar energy from the sun for generating electricity for the
10primary purpose of wholesale or retail sale and not primarily
11for consumption on the property on which the device or devices
12reside.
13    "Electric generation facility" means a facility or
14infrastructure associated with a facility for the generation
15of electricity. "Electric generation facility" does not
16include a wind power device or a commercial solar energy
17system.
18    "Energy production zone" means a premise of land on which
19either of the following was located as of January 1, 2026:
20        (1) an electric generation facility with a generating
21    capacity of at least 80 megawatts, regardless of whether
22    the electric generation facility is operational; or
23        (2) a surface or underground mine at which mining

 

 

SB2686- 2 -LRB104 14637 AAS 27779 b

1    operations are no longer occurring.
2"Energy production zone" does not include a premise of land on
3which one or more wind power devices that are integrated into
4an electric generation facility or one or more commercial
5solar energy systems were located as of January 1, 2026.
6    "Local authority" means any agency, officer, board, or
7commission of a unit of local government that may issue a
8permit or an approval of a land use for the construction of a
9development, a building, or another structure.
10    "Permit" means any of the following:
11        (1) an improvement location permit;
12        (2) a building permit;
13        (3) a certificate of occupancy;
14        (4) an approval of a site-specific development plan;
15        (5) an approval of a primary or secondary plat;
16        (6) an approval of a variance, contingent use,
17    conditional use, special exception, or special use; or
18        (7) an approval of a planned unit of local government
19    development.
20    "Premise of land" means property comprising a tract of
21land on which a project owner proposes to construct an
22electric generation facility, including land within the
23perimeter of the tract of land that was not owned by the
24project owner as of January 1, 2026.
25    "Project owner" means a person that proposes to construct
26an electric generation facility.

 

 

SB2686- 3 -LRB104 14637 AAS 27779 b

1    "Retail electric service" means electric service furnished
2to a customer, including a residential, commercial, or
3industrial customer, for consumption by the customer. "Retail
4electric service" does not include wholesale electric service.
5    "Wholesale electric service" means the provision of
6electricity to another person for resale, including in
7wholesale markets.
8    "Wind power device" means a device, including a windmill
9or a wind turbine, that is designed to use the kinetic energy
10of moving air to provide mechanical energy or to produce
11electricity.
 
12    Section 10. Electric generation facility permit.
13    (a) Notwithstanding any other provision of law to the
14contrary, a project owner is not required to obtain a permit or
15any other land use or zoning approval from a local authority
16for the construction of an electric generation facility if:
17        (1) the Illinois Commerce Commission grants the
18    project owner a certificate under Section 8-406 of the
19    Public Utilities Act for the construction, the Commission
20    declines jurisdiction over the construction under Section
21    8-406 of the Public Utilities Act, or the electric
22    generation facility files notice with the Commission to
23    not use a certificate under Section 8-406 of the Public
24    Utilities Act;
25        (2) the electric generating facility will be located

 

 

SB2686- 4 -LRB104 14637 AAS 27779 b

1    on a premise of land that is an energy production zone; and
2        (3) the project owner complies with subsections (b)
3    and (c) of this Section.
4    (b) No later than 270 days before beginning any
5construction to which subsection (a) of this Section applies,
6a project owner shall provide notice of the construction to
7the local authority with planning authority for the premise of
8land on which the construction will occur. The notice must
9include all of the following information with regard to the
10construction and the electric generation facility to be
11constructed:
12        (1) A comprehensive description of the electric
13    generation facility, including the following:
14            (A) the planned generation capacity of the
15        electric generation facility, expressed in megawatts;
16            (B) the energy source or technology that will be
17        used by the electric generation facility to generate
18        electricity; and
19            (C) the expected operational lifespan of the
20        electric generation facility.
21        (2) The expected date on which the construction will
22    begin.
23        (3) The expected date on which the electric generation
24    facility will begin operation.
25        (4) Whether the electric generation facility will
26    provide retail electric service, wholesale electric

 

 

SB2686- 5 -LRB104 14637 AAS 27779 b

1    service, or both.
2        (5) The project owner's plan for the eventual
3    decommissioning of the electric generation facility.
4        (6) If construction of the electric generation
5    facility will entail decommissioning an existing electric
6    generation facility that is located on the premise of land
7    on which the electric generation facility will be located,
8    the project owner's plan for decommissioning the existing
9    electric generation facility, including financial
10    assurances for the decommissioning.
11        (7) A detailed site plan that includes the location of
12    the following within or adjacent to the premise of land on
13    which the electric generation facility will be
14    constructed:
15            (A) The structures associated with the electric
16        generation facility.
17            (B) Any of the following that are located on the
18        premise of land on which the electric generation
19        facility will be constructed:
20                (i) any existing electric generation facility
21            and any structures associated with the existing
22            electric generation facility; or
23                (ii) any surface or underground mine and any
24            structures associated with the surface or
25            underground mine.
26            (C) Existing and proposed access roads.

 

 

SB2686- 6 -LRB104 14637 AAS 27779 b

1            (D) Regulated drains or ditches.
2            (E) Flood plains.
3            (F) Wetlands.
4            (G) Historic sites or other areas of cultural or
5        environmental significance.
6        (8) An economic development plan detailing the
7    expected economic effect of the electric generation
8    facility on the unit of local government within which the
9    electric generation facility will be located, including
10    all of the following:
11            (A) The anticipated number and types of jobs to be
12        created during the construction of the electric
13        generation facility and in the operation of the
14        electric generation facility.
15            (B) The estimated property tax revenue the
16        electric generation facility will produce for the unit
17        of local government.
18            (C) An estimate of the overall cost to the unit of
19        local government and the overall effect on the unit of
20        local government's revenue associated with the
21        electric generation facility.
22        (9) A safety, security, and emergency response plan
23    describing measures to ensure the following with regard to
24    the construction and operation of the electric generation
25    facility:
26            (A) site security and safety;

 

 

SB2686- 7 -LRB104 14637 AAS 27779 b

1            (B) coordination with the unit of local
2        government's services; and
3            (C) the safeguarding of the public.
4    (c) No later than 60 days after a project owner's
5provision of notice under subsection (b) of this Section, the
6project owner shall hold a public hearing in the unit of local
7government in which the electric generation facility will be
8located, during which the project owner shall provide
9information to the public and receive public comment regarding
10the electric generation facility and the construction of the
11electric generation facility. The project owner shall publish
12notice of the date, time, location, and subject of the public
13hearing.
14    (d) After providing notice to a local authority under
15subsection (b) of this Section, a project owner shall notify
16the local authority regarding any substantive changes in the
17information provided by the project owner under subsection (b)
18of this Section that occur before construction begins on the
19electric generation facility to which the notice pertains.
 
20    Section 15. Local authority. This Act may not be construed
21to increase or modify the authority of a local authority or a
22unit of local government to regulate the siting, construction,
23or deployment of an electric generation facility that is not
24located in an energy production zone.
 
25    Section 99. Effective date. This Act takes effect upon

 

 

SB2686- 8 -LRB104 14637 AAS 27779 b

1becoming law.