104TH GENERAL ASSEMBLY
State of Illinois
2025 and 2026
SB2727

 

Introduced 10/28/2025, by Sen. Bill Cunningham

 

SYNOPSIS AS INTRODUCED:
 
415 ILCS 5/9.15

    Amends the Environmental Protection Act. Defines "battery storage resource" and "total State-installed generation capacity". Provides that no variance, adjusted standard, or other regulatory relief otherwise available in the Act may be granted to the emissions reduction and elimination obligations in the amendatory provisions if battery storage resources constitute at least 10% of the total State-installed generation capacity in the State. Provides that, if battery storage resources constitute less than 10% of the total State-installed generation capacity at any time after the effective date of the amendatory Act, the Environmental Protection Agency shall delay enforcement of certain timelines and relieve generators of their obligation not to exceed their existing emission levels. Provides that, for a large GHG-emitting unit that uses gas as a fuel and is subject to certain restrictions within the provisions concerning greenhouse gases, the unit may exceed its existing emissions during run hours dispatched by a regional transmission organization during emergency, pre-emergency, or conservative operations or run hours that are required to maintain system reliability. Makes other changes. Effective immediately.


LRB104 15876 AAS 29097 b

 

 

A BILL FOR

 

SB2727LRB104 15876 AAS 29097 b

1    AN ACT concerning regulation.
 
2    Be it enacted by the People of the State of Illinois,
3represented in the General Assembly:
 
4    Section 5. The Environmental Protection Act is amended by
5changing Section 9.15 as follows:
 
6    (415 ILCS 5/9.15)
7    Sec. 9.15. Greenhouse gases.
8    (a) An air pollution construction permit shall not be
9required due to emissions of greenhouse gases if the
10equipment, site, or source is not subject to regulation, as
11defined by 40 CFR 52.21, as now or hereafter amended, for
12greenhouse gases or is otherwise not addressed in this Section
13or by the Board in regulations for greenhouse gases. These
14exemptions do not relieve an owner or operator from the
15obligation to comply with other applicable rules or
16regulations.
17    (b) An air pollution operating permit shall not be
18required due to emissions of greenhouse gases if the
19equipment, site, or source is not subject to regulation, as
20defined by Section 39.5 of this Act, for greenhouse gases or is
21otherwise not addressed in this Section or by the Board in
22regulations for greenhouse gases. These exemptions do not
23relieve an owner or operator from the obligation to comply

 

 

SB2727- 2 -LRB104 15876 AAS 29097 b

1with other applicable rules or regulations.
2    (c) (Blank).
3    (d) (Blank).
4    (e) (Blank).
5    (f) As used in this Section:
6    "Battery storage resource" means any device or assembly of
7devices that is (i) either installed as a stand-alone system
8or tied to a power generation system, (ii) used for the primary
9purpose of storing energy for wholesale or retail sale and not
10primarily for storage to later consume on the property on
11which the device resides, and (iii) an energy storage system,
12as defined in Section 16-135 of the Public Utilities Act.
13    "Carbon dioxide emission" means the plant annual CO2 total
14output emission as measured by the United States Environmental
15Protection Agency in its Emissions & Generation Resource
16Integrated Database (eGrid), or its successor.
17    "Carbon dioxide equivalent emissions" or "CO2e" means the
18sum total of the mass amount of emissions in tons per year,
19calculated by multiplying the mass amount of each of the 6
20greenhouse gases specified in Section 3.207, in tons per year,
21by its associated global warming potential as set forth in 40
22CFR 98, subpart A, table A-1 or its successor, and then adding
23them all together.
24    "Cogeneration" or "combined heat and power" refers to any
25system that, either simultaneously or sequentially, produces
26electricity and useful thermal energy from a single fuel

 

 

SB2727- 3 -LRB104 15876 AAS 29097 b

1source.
2    "Copollutants" refers to the 6 criteria pollutants that
3have been identified by the United States Environmental
4Protection Agency pursuant to the Clean Air Act.
5    "Electric generating unit" or "EGU" means a fossil
6fuel-fired stationary boiler, combustion turbine, or combined
7cycle system that serves a generator that has a nameplate
8capacity greater than 25 MWe and produces electricity for
9sale.
10    "Environmental justice community" means the definition of
11that term based on existing methodologies and findings, used
12and as may be updated by the Illinois Power Agency and its
13program administrator in the Illinois Solar for All Program.
14    "Equity investment eligible community" or "eligible
15community" means the geographic areas throughout Illinois that
16would most benefit from equitable investments by the State
17designed to combat discrimination and foster sustainable
18economic growth. Specifically, eligible community means the
19following areas:
20        (1) areas where residents have been historically
21    excluded from economic opportunities, including
22    opportunities in the energy sector, as defined as R3 areas
23    pursuant to Section 10-40 of the Cannabis Regulation and
24    Tax Act; and
25        (2) areas where residents have been historically
26    subject to disproportionate burdens of pollution,

 

 

SB2727- 4 -LRB104 15876 AAS 29097 b

1    including pollution from the energy sector, as established
2    by environmental justice communities as defined by the
3    Illinois Power Agency pursuant to the Illinois Power
4    Agency Act, excluding any racial or ethnic indicators.
5    "Equity investment eligible person" or "eligible person"
6means the persons who would most benefit from equitable
7investments by the State designed to combat discrimination and
8foster sustainable economic growth. Specifically, eligible
9person means the following people:
10        (1) persons whose primary residence is in an equity
11    investment eligible community;
12        (2) persons whose primary residence is in a
13    municipality, or a county with a population under 100,000,
14    where the closure of an electric generating unit or mine
15    has been publicly announced or the electric generating
16    unit or mine is in the process of closing or closed within
17    the last 5 years;
18        (3) persons who are graduates of or currently enrolled
19    in the foster care system; or
20        (4) persons who were formerly incarcerated.
21    "Existing emissions" means:
22        (1) for CO2e, the total average tons-per-year of CO2e
23    emitted by the EGU or large GHG-emitting unit either in
24    the years 2018 through 2020 or, if the unit was not yet in
25    operation by January 1, 2018, in the first 3 full years of
26    that unit's operation; and

 

 

SB2727- 5 -LRB104 15876 AAS 29097 b

1        (2) for any copollutant, the total average
2    tons-per-year of that copollutant emitted by the EGU or
3    large GHG-emitting unit either in the years 2018 through
4    2020 or, if the unit was not yet in operation by January 1,
5    2018, in the first 3 full years of that unit's operation.
6    "Green hydrogen" means a power plant technology in which
7an EGU creates electric power exclusively from electrolytic
8hydrogen, in a manner that produces zero carbon and
9copollutant emissions, using hydrogen fuel that is
10electrolyzed using a 100% renewable zero carbon emission
11energy source.
12    "Large greenhouse gas-emitting unit" or "large
13GHG-emitting unit" means a unit that is an electric generating
14unit or other fossil fuel-fired unit that itself has a
15nameplate capacity or serves a generator that has a nameplate
16capacity greater than 25 MWe and that produces electricity,
17including, but not limited to, coal-fired, coal-derived,
18oil-fired, natural gas-fired, and cogeneration units.
19    "NOx emission rate" means the plant annual NOx total output
20emission rate as measured by the United States Environmental
21Protection Agency in its Emissions & Generation Resource
22Integrated Database (eGrid), or its successor, in the most
23recent year for which data is available.
24    "Public greenhouse gas-emitting units" or "public
25GHG-emitting unit" means large greenhouse gas-emitting units,
26including EGUs, that are wholly owned, directly or indirectly,

 

 

SB2727- 6 -LRB104 15876 AAS 29097 b

1by one or more municipalities, municipal corporations, joint
2municipal electric power agencies, electric cooperatives, or
3other governmental or nonprofit entities, whether organized
4and created under the laws of Illinois or another state.
5    "SO2 emission rate" means the "plant annual SO2 total
6output emission rate" as measured by the United States
7Environmental Protection Agency in its Emissions & Generation
8Resource Integrated Database (eGrid), or its successor, in the
9most recent year for which data is available.
10    "Total State-installed generation capacity" means the
11electric power industry capacity in Illinois by primary energy
12source as of September 15, 2021, as published by the United
13States Energy Information Administration.
14    (g) All EGUs and large greenhouse gas-emitting units that
15use coal or oil as a fuel and are not public GHG-emitting units
16shall permanently reduce all CO2e and copollutant emissions to
17zero no later than January 1, 2030.
18    (h) All EGUs and large greenhouse gas-emitting units that
19use coal as a fuel and are public GHG-emitting units shall
20permanently reduce CO2e emissions to zero no later than
21December 31, 2045. Any source or plant with such units must
22also reduce their CO2e emissions by 45% from existing
23emissions by no later than January 1, 2035. If the emissions
24reduction requirement is not achieved by December 31, 2035,
25the plant shall retire one or more units or otherwise reduce
26its CO2e emissions by 45% from existing emissions by June 30,

 

 

SB2727- 7 -LRB104 15876 AAS 29097 b

12038.
2    (i) All EGUs and large greenhouse gas-emitting units that
3use gas as a fuel and are not public GHG-emitting units shall
4permanently reduce all CO2e and copollutant emissions to zero,
5including through unit retirement or the use of 100% green
6hydrogen or other similar technology that is commercially
7proven to achieve zero carbon emissions, according to the
8following:
9        (1) No later than January 1, 2030: all EGUs and large
10    greenhouse gas-emitting units that have a NOx emissions
11    rate of greater than 0.12 lbs/MWh or a SO2 emission rate of
12    greater than 0.006 lb/MWh, and are located in or within 3
13    miles of an environmental justice community designated as
14    of January 1, 2021 or an equity investment eligible
15    community.
16        (2) No later than January 1, 2040: all EGUs and large
17    greenhouse gas-emitting units that have a NOx emission
18    rate of greater than 0.12 lbs/MWh or a SO2 emission rate
19    greater than 0.006 lb/MWh, and are not located in or
20    within 3 miles of an environmental justice community
21    designated as of January 1, 2021 or an equity investment
22    eligible community. After January 1, 2035, each such EGU
23    and large greenhouse gas-emitting unit shall reduce its
24    CO2e emissions by at least 50% from its existing emissions
25    for CO2e, and shall be limited in operation to, on average,
26    6 hours or less per day, measured over a calendar year, and

 

 

SB2727- 8 -LRB104 15876 AAS 29097 b

1    shall not run for more than 24 consecutive hours except in
2    emergency conditions, as designated by a Regional
3    Transmission Organization or Independent System Operator.
4        (3) No later than January 1, 2035: all EGUs and large
5    greenhouse gas-emitting units that began operation prior
6    to the effective date of this amendatory Act of the 102nd
7    General Assembly and have a NOx emission rate of less than
8    or equal to 0.12 lb/MWh and a SO2 emission rate less than
9    or equal to 0.006 lb/MWh, and are located in or within 3
10    miles of an environmental justice community designated as
11    of January 1, 2021 or an equity investment eligible
12    community. Each such EGU and large greenhouse gas-emitting
13    unit shall reduce its CO2e emissions by at least 50% from
14    its existing emissions for CO2e no later than January 1,
15    2030.
16        (4) No later than January 1, 2040: All remaining EGUs
17    and large greenhouse gas-emitting units that have a heat
18    rate greater than or equal to 7000 BTU/kWh. Each such EGU
19    and Large greenhouse gas-emitting unit shall reduce its
20    CO2e emissions by at least 50% from its existing emissions
21    for CO2e no later than January 1, 2035.
22        (5) No later than January 1, 2045: all remaining EGUs
23    and large greenhouse gas-emitting units.
24    (j) All EGUs and large greenhouse gas-emitting units that
25use gas as a fuel and are public GHG-emitting units shall
26permanently reduce all CO2e and copollutant emissions to zero,

 

 

SB2727- 9 -LRB104 15876 AAS 29097 b

1including through unit retirement or the use of 100% green
2hydrogen or other similar technology that is commercially
3proven to achieve zero carbon emissions by January 1, 2045.
4    (k) All EGUs and large greenhouse gas-emitting units that
5utilize combined heat and power or cogeneration technology
6shall permanently reduce all CO2e and copollutant emissions to
7zero, including through unit retirement or the use of 100%
8green hydrogen or other similar technology that is
9commercially proven to achieve zero carbon emissions by
10January 1, 2045.
11    (k-5) Except as provided in subsection (m) of this
12Section, no No EGU or large greenhouse gas-emitting unit that
13uses gas as a fuel and is not a public GHG-emitting unit may
14emit, in any 12-month period, CO2e or copollutants in excess of
15that unit's existing emissions for those pollutants.
16    (l) Notwithstanding subsections (g) through (k-5), large
17GHG-emitting units including EGUs may temporarily continue
18emitting CO2e and copollutants after any applicable deadline
19specified in any of subsections (g) through (k-5) if it has
20been determined, as described in paragraphs (1) and (2) of
21this subsection, that ongoing operation of the EGU is
22necessary to maintain power grid supply and reliability or
23ongoing operation of large GHG-emitting unit that is not an
24EGU is necessary to serve as an emergency backup to
25operations. Up to and including the occurrence of an emission
26reduction deadline under subsection (i), all EGUs and large

 

 

SB2727- 10 -LRB104 15876 AAS 29097 b

1GHG-emitting units must comply with the following terms:
2        (1) if an EGU or large GHG-emitting unit that is a
3    participant in a regional transmission organization
4    intends to retire, it must submit documentation to the
5    appropriate regional transmission organization by the
6    appropriate deadline that meets all applicable regulatory
7    requirements necessary to obtain approval to permanently
8    cease operating the large GHG-emitting unit;
9        (2) if any EGU or large GHG-emitting unit that is a
10    participant in a regional transmission organization
11    receives notice that the regional transmission
12    organization has determined that an emergency,
13    pre-emergency, or conservative operations situation exists
14    or that continued operation of the unit is required, the
15    unit may continue operating until the issue identified by
16    the regional transmission organization is resolved. The
17    owner or operator of the unit must cooperate with the
18    regional transmission organization in resolving the issue
19    and must reduce its emissions to zero, consistent with the
20    requirements under subsection (g), (h), (i), (j), (k), or
21    (k-5), as applicable, as soon as practicable when the
22    issue identified by the regional transmission organization
23    is resolved; and
24        (3) any large GHG-emitting unit that is not a
25    participant in a regional transmission organization shall
26    be allowed to continue emitting CO2e and copollutants

 

 

SB2727- 11 -LRB104 15876 AAS 29097 b

1    after the zero-emission date specified in subsection (g),
2    (h), (i), (j), (k), or (k-5), as applicable, in the
3    capacity of an emergency backup unit if approved by the
4    Illinois Commerce Commission.
5    (m) No variance, adjusted standard, or other regulatory
6relief otherwise available in this Act may be granted to the
7emissions reduction and elimination obligations in this
8Section if battery storage resources constitute at least 10%
9of the total State-installed generation capacity in the State.
10If battery storage resources constitute less than 10% of the
11total State-installed generation capacity at any time after
12the effective date of this amendatory Act of the 104th General
13Assembly, the Agency shall delay enforcement of the timelines
14in paragraphs (1) through (5) of subsection (i) and relieve
15generators of their obligation not to exceed their existing
16emission levels, as described in subsection (k-5). For a large
17GHG-emitting unit that uses gas as a fuel and is subject to the
18restrictions of subsection (k-5) of this Section, the unit may
19exceed its existing emissions during run hours dispatched by a
20regional transmission organization during emergency,
21pre-emergency, or conservative operations or run hours that
22are required to maintain system reliability.
23    (n) By June 30 of each year, beginning in 2025, the Agency
24shall prepare and publish on its website a report setting
25forth the actual greenhouse gas emissions from individual
26units and the aggregate statewide emissions from all units for

 

 

SB2727- 12 -LRB104 15876 AAS 29097 b

1the prior year.
2    (o) Every 5 years beginning in 2025, the Environmental
3Protection Agency, Illinois Power Agency, and Illinois
4Commerce Commission shall jointly prepare, and release
5publicly, a report to the General Assembly that examines the
6State's current progress toward its renewable energy resource
7development goals, the status of CO2e and copollutant
8emissions reductions, the current status and progress toward
9developing and implementing green hydrogen technologies, the
10current and projected status of electric resource adequacy and
11reliability throughout the State for the period beginning 5
12years ahead, and proposed solutions for any findings. The
13Environmental Protection Agency, Illinois Power Agency, and
14Illinois Commerce Commission shall consult PJM
15Interconnection, LLC and Midcontinent Independent System
16Operator, Inc., or their respective successor organizations
17regarding forecasted resource adequacy and reliability needs,
18anticipated new generation interconnection, new transmission
19development or upgrades, and any announced large GHG-emitting
20unit closure dates and include this information in the report.
21The report shall be released publicly by no later than
22December 15 of the year it is prepared. If the Environmental
23Protection Agency, Illinois Power Agency, and Illinois
24Commerce Commission jointly conclude in the report that the
25data from the regional grid operators, the pace of renewable
26energy development, the pace of development of energy storage

 

 

SB2727- 13 -LRB104 15876 AAS 29097 b

1and demand response utilization, transmission capacity, and
2the CO2e and copollutant emissions reductions required by
3subsection (i) or (k-5) reasonably demonstrate that a resource
4adequacy shortfall will occur, including whether there will be
5sufficient in-state capacity to meet the zonal requirements of
6MISO Zone 4 or the PJM ComEd Zone, per the requirements of the
7regional transmission organizations, or that the regional
8transmission operators determine that a reliability violation
9will occur during the time frame the study is evaluating, then
10the Illinois Power Agency, in conjunction with the
11Environmental Protection Agency shall develop a plan to reduce
12or delay CO2e and copollutant emissions reductions
13requirements only to the extent and for the duration necessary
14to meet the resource adequacy and reliability needs of the
15State, including allowing any plants whose emission reduction
16deadline has been identified in the plan as creating a
17reliability concern to continue operating, including operating
18with reduced emissions or as emergency backup where
19appropriate. The plan shall also consider the use of renewable
20energy, energy storage, demand response, transmission
21development, or other strategies to resolve the identified
22resource adequacy shortfall or reliability violation.
23        (1) In developing the plan, the Environmental
24    Protection Agency and the Illinois Power Agency shall hold
25    at least one workshop open to, and accessible at a time and
26    place convenient to, the public and shall consider any

 

 

SB2727- 14 -LRB104 15876 AAS 29097 b

1    comments made by stakeholders or the public. Upon
2    development of the plan, copies of the plan shall be
3    posted and made publicly available on the Environmental
4    Protection Agency's, the Illinois Power Agency's, and the
5    Illinois Commerce Commission's websites. All interested
6    parties shall have 60 days following the date of posting
7    to provide comment to the Environmental Protection Agency
8    and the Illinois Power Agency on the plan. All comments
9    submitted to the Environmental Protection Agency and the
10    Illinois Power Agency shall be encouraged to be specific,
11    supported by data or other detailed analyses, and, if
12    objecting to all or a portion of the plan, accompanied by
13    specific alternative wording or proposals. All comments
14    shall be posted on the Environmental Protection Agency's,
15    the Illinois Power Agency's, and the Illinois Commerce
16    Commission's websites. Within 30 days following the end of
17    the 60-day review period, the Environmental Protection
18    Agency and the Illinois Power Agency shall revise the plan
19    as necessary based on the comments received and file its
20    revised plan with the Illinois Commerce Commission for
21    approval.
22        (2) Within 60 days after the filing of the revised
23    plan at the Illinois Commerce Commission, any person
24    objecting to the plan shall file an objection with the
25    Illinois Commerce Commission. Within 30 days after the
26    expiration of the comment period, the Illinois Commerce

 

 

SB2727- 15 -LRB104 15876 AAS 29097 b

1    Commission shall determine whether an evidentiary hearing
2    is necessary. The Illinois Commerce Commission shall also
3    host 3 public hearings within 90 days after the plan is
4    filed. Following the evidentiary and public hearings, the
5    Illinois Commerce Commission shall enter its order
6    approving or approving with modifications the reliability
7    mitigation plan within 180 days.
8        (3) The Illinois Commerce Commission shall only
9    approve the plan if the Illinois Commerce Commission
10    determines that it will resolve the resource adequacy or
11    reliability deficiency identified in the reliability
12    mitigation plan at the least amount of CO2e and copollutant
13    emissions, taking into consideration the emissions impacts
14    on environmental justice communities, and that it will
15    ensure adequate, reliable, affordable, efficient, and
16    environmentally sustainable electric service at the lowest
17    total cost over time, taking into account the impact of
18    increases in emissions.
19        (4) If the resource adequacy or reliability deficiency
20    identified in the reliability mitigation plan is resolved
21    or reduced, the Environmental Protection Agency and the
22    Illinois Power Agency may file an amended plan adjusting
23    the reduction or delay in CO2e and copollutant emission
24    reduction requirements identified in the plan.
25    (p) The Agency shall adopt rules implementing this Section
26no later than July 1, 2026.

 

 

SB2727- 16 -LRB104 15876 AAS 29097 b

1(Source: P.A. 102-662, eff. 9-15-21; 102-1031, eff. 5-27-22.)
 
2    Section 99. Effective date. This Act takes effect upon
3becoming law.