| capacity of not more than 40 kilowatts that is located on the |
2 |
| customer's premises and is intended to offset part or all of |
3 |
| the customer's own electrical requirements and (ii) "net energy |
4 |
| metering" means the use of a secondary energy meter to measure |
5 |
| the amount of electricity provided to the electric utility by |
6 |
| the customer.
|
7 |
| (c) An eligible customer shall pay for all costs associated |
8 |
| with the electric utility providing the required |
9 |
| interconnection and secondary meter needed, and if necessary |
10 |
| the real time pricing equipment needed, to participate in net |
11 |
| energy metering.
|
12 |
| (d) Eligible customers participating in net energy |
13 |
| metering with electric utilities serving 200,000 or more |
14 |
| customers shall be reimbursed for the electricity supplied to |
15 |
| the utility based upon real-time pricing. |
16 |
| (e) Eligible customers participating in net energy |
17 |
| metering with electric utilities serving less than 200,000 |
18 |
| customers shall be reimbursed for the electricity supplied to |
19 |
| the utility based upon the utility's avoided cost. |
20 |
| (f) The electric utility shall make all payments to |
21 |
| eligible customers promptly. |
22 |
| (g) Within 3 months after the effective date of this |
23 |
| amendatory Act of the 95th General Assembly, the Illinois |
24 |
| Commerce Commission shall establish standards for net energy |
25 |
| metering and the interconnection of solar and wind electric |
26 |
| generating equipment to the utility system if the Commission |
|
|
|
09500HB1011ham001 |
- 3 - |
LRB095 08711 MJR 32919 a |
|
|
1 |
| determines that such standards are necessary for safe and |
2 |
| adequate service and further the public policy set forth in |
3 |
| this Section. The standards may include, but shall not be |
4 |
| limited to, standards designating: |
5 |
| (1) equipment necessary to automatically isolate the |
6 |
| residential solar and wind generating system from the |
7 |
| utility system for voltage and frequency deviations; and |
8 |
| (2) a manual lockable disconnect switch provided by the |
9 |
| customer which shall be located on the outside of the |
10 |
| residence and externally accessible for the purpose of |
11 |
| isolating the solar and wind electric generating |
12 |
| equipment.
|
13 |
| (h) An electric utility shall offer net metering to |
14 |
| eligible customers until the load of its net energy metering |
15 |
| customers equals 0.1% of the total peak demand supplied by the |
16 |
| electric utility during the previous year. Electric utilities |
17 |
| are authorized to offer net energy metering beyond 0.1% of peak |
18 |
| load if they so choose.
|
19 |
| Section 99. Effective date. This Act takes effect upon |
20 |
| becoming law.".
|