95TH GENERAL ASSEMBLY
State of Illinois
2007 and 2008 HB5571
Introduced , by Rep. Kathleen A. Ryg SYNOPSIS AS INTRODUCED: |
|
|
|
Amends the Illinois Procurement Code. Requires that each Department of Transportation construction contract specify a construction completion date and a monetary penalty against the contractor for each day completion is delayed for a cause attributable to the contractor or a subcontractor. Grants a business that suffers economic losses due to the delay the right to recover those losses from the contractor in the circuit court, up to the contract's penalty amount.
|
| |
|
|
|
|
A BILL FOR
|
|
|
|
|
HB5571 |
|
LRB095 18152 JAM 44235 b |
|
|
| 1 |
| AN ACT concerning finance.
|
| 2 |
| Be it enacted by the People of the State of Illinois,
|
| 3 |
| represented in the General Assembly:
|
| 4 |
| Section 5. The Illinois Procurement Code is amended by |
| 5 |
| adding Section 30-36 as follows: |
| 6 |
| (30 ILCS 500/30-36 new) |
| 7 |
| Sec. 30-36. Construction delays. Each contract subject to |
| 8 |
| this Article awarded after the effective date of this |
| 9 |
| amendatory Act of the 95th General Assembly for which the |
| 10 |
| Department of Transportation is the construction agency shall |
| 11 |
| specify a construction completion date and shall include as a |
| 12 |
| condition of the contract a monetary penalty for each day after |
| 13 |
| that date that the construction is not completed for a cause |
| 14 |
| attributable to the contractor or any of its subcontractors. |
| 15 |
| The amount of the monetary penalty shall be determined from |
| 16 |
| criteria established by rule of the Department. |
| 17 |
| A business that suffers economic losses because |
| 18 |
| construction pursuant to a contract subject to this Section is |
| 19 |
| not completed by the contract's specified construction |
| 20 |
| completion date due to a cause attributable to the contractor |
| 21 |
| or any of the contractor's subcontractors may recover those |
| 22 |
| economic losses in the circuit court from that contractor in an |
| 23 |
| amount not to exceed the monetary penalty specified in the |