|
|
|
95TH GENERAL ASSEMBLY
State of Illinois
2007 and 2008 SB0945
Introduced 2/8/2007, by Sen. James F. Clayborne, Jr. - Emil Jones, Jr. SYNOPSIS AS INTRODUCED: |
|
|
Amends the Environmental Protection Act. Makes a technical change in a Section concerning NPDES discharge fees.
|
| |
|
|
A BILL FOR
|
|
|
|
|
SB0945 |
|
LRB095 05760 CMK 25850 b |
|
|
1 |
| AN ACT concerning safety.
|
2 |
| Be it enacted by the People of the State of Illinois,
|
3 |
| represented in the General Assembly:
|
4 |
| Section 5. The Environmental Protection Act is amended by |
5 |
| changing Section 12.5 as follows:
|
6 |
| (415 ILCS 5/12.5)
|
7 |
| Sec. 12.5. NPDES discharge fees; sludge permit fees.
|
8 |
| (a) Beginning July 1, 2003, the
the Agency shall assess and |
9 |
| collect annual fees
(i) in the amounts set forth in subsection |
10 |
| (e) for all discharges that require
an NPDES permit under |
11 |
| subsection (f) of Section 12, from each person holding an
NPDES |
12 |
| permit authorizing those discharges (including a person who |
13 |
| continues to
discharge under an expired permit pending |
14 |
| renewal), and (ii) in the amounts
set forth in subsection (f) |
15 |
| of this Section for all activities that require a
permit under |
16 |
| subsection (b) of Section 12, from each person holding a |
17 |
| domestic
sewage sludge generator or user permit. |
18 |
| Each person subject to this Section must remit the |
19 |
| applicable annual fee to
the Agency in accordance with the |
20 |
| requirements set forth in this Section and
any rules adopted |
21 |
| pursuant to this Section.
|
22 |
| (b) Within 30 days after the effective date of this |
23 |
| Section, and each year thereafter, the Agency shall send a fee |
|
|
|
SB0945 |
- 2 - |
LRB095 05760 CMK 25850 b |
|
|
1 |
| notice by mail
to each existing permittee subject to a fee |
2 |
| under this Section at his or her
address of record. The notice |
3 |
| shall state the amount of the applicable annual
fee and the |
4 |
| date by which payment is required.
|
5 |
| Except as provided in subsection (c) with respect to |
6 |
| initial fees under
new permits and certain modifications of |
7 |
| existing permits, fees payable under
this Section are due by |
8 |
| the date
specified in the fee notice, which shall be no less |
9 |
| than 30 days after the date
the fee notice is mailed by the |
10 |
| Agency.
|
11 |
| (c) The initial annual fee for discharges under a new |
12 |
| individual NPDES
permit or for activity under a new individual |
13 |
| sludge generator or sludge user
permit must be remitted to the |
14 |
| Agency prior to the issuance of the permit.
The Agency shall |
15 |
| provide notice of the amount of the fee to the applicant
during |
16 |
| its review of the application. In the case of a new individual |
17 |
| NPDES
or sludge permit issued during the months of January |
18 |
| through June, the Agency
may prorate the initial annual fee |
19 |
| payable under this Section.
|
20 |
| The initial annual fee for discharges or other activity |
21 |
| under a general
NPDES permit must be remitted to the Agency as |
22 |
| part of the application
for coverage under that general permit.
|
23 |
| If a requested modification to an existing NPDES permit |
24 |
| causes a change in
the applicable fee categories under |
25 |
| subsection (e) that results in an increase
in the required fee, |
26 |
| the permittee must pay to the Agency the amount of the
|
|
|
|
SB0945 |
- 3 - |
LRB095 05760 CMK 25850 b |
|
|
1 |
| increase, prorated for the number of months remaining before |
2 |
| the next July 1,
before the modification is granted.
|
3 |
| (d) Failure to submit the fee required under this Section |
4 |
| by the due
date constitutes a violation of this Section. Late |
5 |
| payments shall incur an
interest penalty, calculated at the |
6 |
| rate in effect from time to time for tax
delinquencies under |
7 |
| subsection (a) of Section 1003 of the Illinois Income Tax
Act, |
8 |
| from the date the fee is due until the date the fee payment is |
9 |
| received
by the Agency.
|
10 |
| (e) The annual fees applicable to discharges under NPDES |
11 |
| permits are as
follows:
|
12 |
| (1) For NPDES permits for publicly owned treatment |
13 |
| works, other
facilities for which the wastewater being |
14 |
| treated and discharged is primarily
domestic sewage, and |
15 |
| wastewater discharges from the operation of public water
|
16 |
| supply treatment facilities, the fee is:
|
17 |
| (i) $1,500 for the 12 months beginning July 1, 2003 |
18 |
| and $500 for each subsequent year, for facilities with |
19 |
| a Design Average Flow rate of less than
100,000 gallons |
20 |
| per day;
|
21 |
| (ii) $5,000 for the 12 months beginning July 1, |
22 |
| 2003 and $2,500 for each subsequent year, for |
23 |
| facilities with a Design Average Flow rate of at least
|
24 |
| 100,000 gallons per day but less than 500,000 gallons |
25 |
| per day;
|
26 |
| (iii) $7,500 for facilities with a Design Average |
|
|
|
SB0945 |
- 4 - |
LRB095 05760 CMK 25850 b |
|
|
1 |
| Flow rate of at least
500,000 gallons per day but less |
2 |
| than 1,000,000 gallons per day;
|
3 |
| (iv) $15,000 for facilities with a Design Average |
4 |
| Flow rate of at least
1,000,000 gallons per day but |
5 |
| less than 5,000,000 gallons per day;
|
6 |
| (v) $30,000 for facilities with a Design Average |
7 |
| Flow rate of at least
5,000,000 gallons per day but |
8 |
| less than 10,000,000 gallons per day; and
|
9 |
| (vi) $50,000 for facilities with a Design Average |
10 |
| Flow rate of
10,000,000 gallons per day or more.
|
11 |
| (2) For NPDES permits for treatment works or sewer |
12 |
| collection systems
that include combined sewer overflow |
13 |
| outfalls, the fee is:
|
14 |
| (i) $1,000 for systems serving a tributary |
15 |
| population of 10,000 or less;
|
16 |
| (ii) $5,000 for systems serving a tributary |
17 |
| population that is greater
than 10,000 but not more |
18 |
| than 25,000; and
|
19 |
| (iii) $20,000 for systems serving a tributary |
20 |
| population that is greater
than 25,000.
|
21 |
| The fee amounts in this subdivision (e)(2) are in |
22 |
| addition to the fees
stated in subdivision (e)(1) when the |
23 |
| combined sewer overflow outfall is
contained within a |
24 |
| permit subject to subsection (e)(1) fees.
|
25 |
| (3) For NPDES permits for mines producing coal, the fee |
26 |
| is $5,000.
|
|
|
|
SB0945 |
- 5 - |
LRB095 05760 CMK 25850 b |
|
|
1 |
| (4) For NPDES permits for mines other than mines |
2 |
| producing coal, the fee
is $5,000.
|
3 |
| (5) For NPDES permits for industrial activity where |
4 |
| toxic substances are
not regulated, other than permits |
5 |
| covered under subdivision (e)(3) or (e)(4),
the fee is:
|
6 |
| (i) $1,000 for a facility with a Design Average |
7 |
| Flow rate that is not
more than 10,000 gallons per day;
|
8 |
| (ii) $2,500 for a facility with a Design Average |
9 |
| Flow rate that is more
than 10,000 gallons per day but |
10 |
| not more than 100,000 gallons per day; and
|
11 |
| (iii) $10,000 for a facility with a Design Average |
12 |
| Flow rate that is
more than 100,000 gallons per day.
|
13 |
| (6) For NPDES permits for industrial activity where |
14 |
| toxic substances are
regulated, other than permits covered |
15 |
| under subdivision (e)(3) or (e)(4), the
fee is:
|
16 |
| (i) $15,000 for a facility with a Design Average |
17 |
| Flow rate that is not
more than 250,000 gallons per |
18 |
| day; and
|
19 |
| (ii) $20,000 for a facility with a Design Average |
20 |
| Flow rate that is
more than 250,000 gallons per day.
|
21 |
| (7) For NPDES permits for industrial activity |
22 |
| classified by USEPA as a
major discharge, other than |
23 |
| permits covered under subdivision (e)(3) or (e)(4),
the fee |
24 |
| is:
|
25 |
| (i) $30,000 for a facility where toxic substances |
26 |
| are not regulated; and
|
|
|
|
SB0945 |
- 6 - |
LRB095 05760 CMK 25850 b |
|
|
1 |
| (ii) $50,000 for a facility where toxic substances |
2 |
| are regulated.
|
3 |
| (8) For NPDES permits for municipal separate storm |
4 |
| sewer systems, the fee
is $1,000.
|
5 |
| (9) For NPDES permits for construction site or |
6 |
| industrial storm water,
the fee is $500.
|
7 |
| (f) The annual fee for activities under a permit that |
8 |
| authorizes applying
sludge on land is $2,500 for a sludge |
9 |
| generator permit and $5,000 for a sludge
user permit.
|
10 |
| (g) More than one of the annual fees specified in |
11 |
| subsections (e) and (f)
may be applicable to a permit holder. |
12 |
| These fees are in addition to any other
fees required under |
13 |
| this Act.
|
14 |
| (h) The fees imposed under this Section do not apply to the |
15 |
| State or any
department or agency of the State, nor to any |
16 |
| school district, or to any private sewage disposal system as |
17 |
| defined in the Private Sewage Disposal Licensing Act (225 ILCS |
18 |
| 225/).
|
19 |
| (i) The Agency may adopt rules to administer the fee |
20 |
| program established
in this Section. The Agency may include |
21 |
| provisions pertaining to invoices,
notice of late payment, and |
22 |
| disputes concerning the amount or timeliness of
payment. The |
23 |
| Agency may set forth procedures and criteria for the acceptance
|
24 |
| of payments. The absence of such rules does not affect the duty |
25 |
| of the Agency
to immediately begin the assessment and |
26 |
| collection of fees under this Section.
|
|
|
|
SB0945 |
- 7 - |
LRB095 05760 CMK 25850 b |
|
|
1 |
| (j) All fees and interest penalties collected by the Agency |
2 |
| under this
Section shall be deposited into the Illinois Clean |
3 |
| Water Fund, which is
hereby created as a special fund in the |
4 |
| State treasury. Gifts,
supplemental environmental project |
5 |
| funds, and grants may be deposited into
the Fund. Investment |
6 |
| earnings on moneys held in the Fund shall be credited
to the |
7 |
| Fund.
|
8 |
| Subject to appropriation, the moneys in the Fund shall be |
9 |
| used by the
Agency to carry out the Agency's clean water |
10 |
| activities.
|
11 |
| (k) Except as provided in subsection (l), fees paid to the |
12 |
| Agency under this Section are not refundable.
|
13 |
| (l) The Agency may refund the difference between (a) the |
14 |
| amount paid by any person under subsection (e)(1)(i) or |
15 |
| (e)(1)(ii) of this Section for the 12 months beginning July 1, |
16 |
| 2004 and (b) the amount due under subsection (e)(1)(i) or |
17 |
| (e)(1)(ii) as established by this amendatory Act of the 93rd |
18 |
| General Assembly.
|
19 |
| (Source: P.A. 93-32, eff. 7-1-03; 93-840, eff. 7-30-04.)
|