Sen. Christine Radogno
Filed: 3/20/2007
|
|
09500SB1305sam002 |
|
LRB095 10735 JAM 34207 a |
|
|
| 1 |
| AMENDMENT TO SENATE BILL 1305
|
| 2 |
| AMENDMENT NO. ______. Amend Senate Bill 1305, AS AMENDED, |
| 3 |
| with reference to page and line numbers of Senate Amendment No. |
| 4 |
| 1, on page 48, in line 2 by inserting "20-25," after "20-10,"; |
| 5 |
| and
|
| 6 |
| on page 56, by inserting after line 8 the following:
|
| 7 |
| "(30 ILCS 500/20-25)
|
| 8 |
| Sec. 20-25. Sole source procurements. In accordance with
|
| 9 |
| standards set by rule,
contracts may be awarded without use of |
| 10 |
| the specified
method of source selection when
there is only one |
| 11 |
| economically feasible source for the item. This Section may not |
| 12 |
| be used as a basis for amending a contract if the amendment |
| 13 |
| would result in an increase in the amount paid under the |
| 14 |
| contract of more than 5% of the initial award, or would extend |
| 15 |
| the contract term beyond the time reasonably needed for a |
| 16 |
| competitive procurement, not to exceed 2 months. At
least 2 |