| requirements of design-build entities that the agency has set
|
2 |
| forth. Each request for proposal shall establish the relative |
3 |
| importance
assigned to each evaluation factor and subfactor, |
4 |
| including any weighting of
criteria to be employed by the State |
5 |
| construction agency. The State
construction agency must |
6 |
| maintain a
record of the evaluation scoring to be disclosed in |
7 |
| event of a protest
regarding the solicitation.
|
8 |
| The State construction agency shall include the following |
9 |
| criteria in every
Phase I
evaluation of design-build entities: |
10 |
| (1) experience of personnel; (2)
successful
experience with |
11 |
| similar project types; (3) financial capability; (4) |
12 |
| timeliness
of past performance; (5) experience with similarly |
13 |
| sized projects; (6)
successful reference checks of the firm; |
14 |
| (7) commitment to assign personnel
for the duration of the |
15 |
| project and qualifications of the entity's consultants; and (8) |
16 |
| ability or past performance in meeting or exhausting good faith |
17 |
| efforts to meet the utilization goals for business enterprises |
18 |
| established in the Business Enterprise for Minorities, |
19 |
| Females, and Persons with Disabilities Act and with Section |
20 |
| 2-105 of the Illinois Human Rights Act.
The State construction |
21 |
| agency may include any additional relevant criteria in
Phase I |
22 |
| that
it deems necessary for a proper qualification review.
|
23 |
| The State construction agency may not consider any |
24 |
| design-build entity for
evaluation or
award if the entity has |
25 |
| any pecuniary interest in the project or has other
|
26 |
| relationships or circumstances, including but not limited to, |
|
|
|
09600HB0372sam001 |
- 3 - |
LRB096 04520 JAM 25442 a |
|
|
1 |
| long-term
leasehold, mutual performance, or development |
2 |
| contracts with the State
construction agency,
that may give the |
3 |
| design-build entity a financial or tangible advantage over
|
4 |
| other design-build entities in the preparation, evaluation, or |
5 |
| performance of
the
design-build contract or that create the |
6 |
| appearance of impropriety.
No proposal shall be considered that |
7 |
| does not include an entity's plan to comply with the |
8 |
| requirements established in the Business Enterprise for |
9 |
| Minorities, Females, and Persons with Disabilities Act , for |
10 |
| both the design and construction areas of performance, and with |
11 |
| Section 2-105 of the Illinois Human Rights Act.
|
12 |
| Upon completion of the qualifications evaluation, the |
13 |
| State construction
agency shall
create a shortlist of the most |
14 |
| highly qualified design-build entities. The
State
construction |
15 |
| agency, in its discretion, is not required to shortlist the
|
16 |
| maximum number of
entities as identified for Phase II |
17 |
| evaluation, provided however, no less than
2
design-build |
18 |
| entities nor more than 6 are selected to submit Phase II
|
19 |
| proposals.
|
20 |
| The State construction agency shall notify the entities |
21 |
| selected for the
shortlist in
writing. This notification shall |
22 |
| commence the period for the preparation of the
Phase II |
23 |
| technical and cost evaluations. The State construction agency |
24 |
| must
allow sufficient
time for the shortlist entities to |
25 |
| prepare their Phase II submittals
considering
the scope and |
26 |
| detail requested by the State agency.
|
|
|
|
09600HB0372sam001 |
- 4 - |
LRB096 04520 JAM 25442 a |
|
|
1 |
| (c) The State construction agency shall include in the |
2 |
| request for proposal
the
evaluating factors to be used in the |
3 |
| technical and cost submission components
of Phase II. Each |
4 |
| request for proposal shall establish, for both the technical
|
5 |
| and cost submission components of Phase II, the relative |
6 |
| importance assigned to
each evaluation factor and subfactor, |
7 |
| including any weighting of criteria to be
employed by the State |
8 |
| construction agency. The State construction agency must
|
9 |
| maintain a record of the
evaluation scoring to be disclosed in |
10 |
| event of a protest regarding the
solicitation.
|
11 |
| The State construction agency shall include the following |
12 |
| criteria in every
Phase II
technical evaluation of design-build |
13 |
| entities: (1) compliance with objectives
of
the
project; (2) |
14 |
| compliance of proposed services to the request for proposal
|
15 |
| requirements; (3) quality of products or materials proposed; |
16 |
| (4) quality of
design parameters; (5) design concepts; (6) |
17 |
| innovation in meeting the scope and
performance criteria; and |
18 |
| (7) constructability of the
proposed project. The State |
19 |
| construction agency may include any additional
relevant
|
20 |
| technical evaluation factors it deems necessary for proper |
21 |
| selection.
|
22 |
| The State construction agency shall include the following |
23 |
| criteria in every
Phase II cost
evaluation: the total project |
24 |
| cost, the construction costs, and the time of
completion. The |
25 |
| State construction agency may include any additional relevant
|
26 |
| technical
evaluation factors it deems necessary for proper |
|
|
|
09600HB0372sam001 |
- 5 - |
LRB096 04520 JAM 25442 a |
|
|
1 |
| selection. The total project cost criteria weighing factor |
2 |
| shall be 25%.
|
3 |
| The State construction agency shall directly employ or |
4 |
| retain a licensed
design
professional to evaluate the technical |
5 |
| and cost submissions to determine if the
technical submissions |
6 |
| are in accordance with generally
accepted industry standards.
|
7 |
| Upon completion of the technical submissions and cost |
8 |
| submissions evaluation,
the State construction agency may |
9 |
| award the design-build contract to the
highest
overall ranked |
10 |
| entity.
|
11 |
| (Source: P.A. 94-716, eff. 12-13-05.)".
|