1 | AMENDMENT TO HOUSE BILL 639
| ||||||
2 | AMENDMENT NO. ______. Amend House Bill 639 by replacing | ||||||
3 | everything after the enacting clause with the following:
| ||||||
4 | "Section 5. The Public Utilities Act is amended by changing | ||||||
5 | Section 9-201 as follows:
| ||||||
6 | (220 ILCS 5/9-201) (from Ch. 111 2/3, par. 9-201)
| ||||||
7 | Sec. 9-201.
(a) Unless the Commission otherwise orders, and | ||||||
8 | except as
otherwise provided in this Section, no change shall | ||||||
9 | be made by any
public utility in any rate or other charge or | ||||||
10 | classification, or in any
rule, regulation, practice or | ||||||
11 | contract relating to or affecting any rate
or other charge, | ||||||
12 | classification or service, or in any privilege or
facility, | ||||||
13 | except after 45 days' notice to the Commission and to the
| ||||||
14 | public as herein provided. Such notice shall be given by filing | ||||||
15 | with
the Commission and keeping open for public inspection new | ||||||
16 | schedules or
supplements stating plainly the change or changes |
| |||||||
| |||||||
1 | to be made in the
schedule or schedules then in force, and the | ||||||
2 | time when the change or
changes will go into effect, and by | ||||||
3 | publication in a newspaper of
general circulation or such other | ||||||
4 | notice to persons affected by such
change as may be prescribed | ||||||
5 | by rule of the Commission. The Commission,
for good cause | ||||||
6 | shown, may allow changes without requiring the 45 days'
notice | ||||||
7 | herein provided for, by an order specifying the changes so to | ||||||
8 | be
made and the time when they shall take effect and the manner | ||||||
9 | in which
they shall be filed and published.
| ||||||
10 | When any change is proposed in any rate or other charge, or
| ||||||
11 | classification, or in any rule, regulation, practice, or | ||||||
12 | contract
relating to or affecting any rate or other charge, | ||||||
13 | classification or
service, or in any privilege or facility, | ||||||
14 | such proposed change shall be
plainly indicated on the new | ||||||
15 | schedule filed with the Commission, by some
character to be | ||||||
16 | designated by the Commission, immediately preceding or
| ||||||
17 | following the item.
| ||||||
18 | When any public utility providing water or sewer service | ||||||
19 | proposes any
change in any rate or other charge, or | ||||||
20 | classification, or in any rule,
regulation, practice, or | ||||||
21 | contract relating to or affecting any rate or
other charge, | ||||||
22 | classification or service, or in any privilege or facility,
| ||||||
23 | such utility shall, in addition to the other notice | ||||||
24 | requirements of this
Act, provide notice of such change to all | ||||||
25 | customers potentially affected by
including a notice and | ||||||
26 | description of such change, and of Commission
procedures for |
| |||||||
| |||||||
1 | intervention, in the first bill sent to each such customer
| ||||||
2 | after the filing of the proposed change. | ||||||
3 | (a-5) No member of the Commission may discuss with any | ||||||
4 | representative of a public utility any matter that the public | ||||||
5 | utility is considering filing with the Commission pursuant to | ||||||
6 | this Section. If a public utility makes a filing under this | ||||||
7 | Section, then no communication concerning the filing is | ||||||
8 | permitted until a notice of hearing of a formal hearing has | ||||||
9 | been issued. After the notice of hearing has been issued, only | ||||||
10 | communications concerning the filing that are permitted under | ||||||
11 | Section 10-103 of this Act are permitted.
| ||||||
12 | (b) Whenever there shall be filed with the Commission any | ||||||
13 | schedule
stating an individual or joint rate or other charge, | ||||||
14 | classification,
contract, practice, rule or regulation, the | ||||||
15 | Commission shall have power,
and it is hereby given authority, | ||||||
16 | either upon complaint or upon its own
initiative without | ||||||
17 | complaint, at once, and if it so orders, without
answer or | ||||||
18 | other formal pleadings by the interested public utility or
| ||||||
19 | utilities, but upon reasonable notice, to enter upon a hearing
| ||||||
20 | concerning the propriety of such rate or other charge, | ||||||
21 | classification,
contract, practice, rule or regulation, and | ||||||
22 | pending the hearing and
decision thereon, such rate or other | ||||||
23 | charge, classification, contract,
practice, rule or regulation | ||||||
24 | shall not go into effect. The period of
suspension of such rate | ||||||
25 | or other charge, classification, contract,
practice, rule or | ||||||
26 | regulation shall not extend more than 105 days beyond
the time |
| |||||||
| |||||||
1 | when such rate or other charge, classification, contract,
| ||||||
2 | practice, rule or regulation would otherwise go into effect | ||||||
3 | unless the
Commission, in its discretion, extends the period of | ||||||
4 | suspension for a
further period not exceeding 6 months.
| ||||||
5 | All rates or other charges, classifications, contracts, | ||||||
6 | practices, rules or
regulations not so suspended shall, on the | ||||||
7 | expiration of 45 days from
the time of filing the same with the | ||||||
8 | Commission, or of such lesser time
as the Commission may grant, | ||||||
9 | go into effect and be the established and
effective rates or | ||||||
10 | other charges, classifications, contracts, practices,
rules | ||||||
11 | and regulations, subject to the power of the Commission, after | ||||||
12 | a
hearing had on its own motion or upon complaint, as herein | ||||||
13 | provided, to
alter or modify the same.
| ||||||
14 | Within 30 days after such changes have been
authorized by | ||||||
15 | the Commission, copies of the new or revised schedules
shall be | ||||||
16 | posted or filed in accordance with the terms of Section 9-103 | ||||||
17 | of
this Act, in such a manner that all changes shall be plainly | ||||||
18 | indicated.
| ||||||
19 | (c) If the Commission enters upon a hearing concerning the | ||||||
20 | propriety of
any proposed rate or other charge, classification, | ||||||
21 | contract, practice, rule
or regulation, the Commission shall | ||||||
22 | establish the rates or other charges,
classifications, | ||||||
23 | contracts, practices, rules or regulations proposed, in
whole | ||||||
24 | or in part, or others in lieu thereof, which it shall find to | ||||||
25 | be just
and reasonable. In such hearing, the burden of proof to | ||||||
26 | establish the justness
and reasonableness of the proposed rates |
| |||||||
| |||||||
1 | or other charges, classifications,
contracts, practices, rules | ||||||
2 | or regulations, in whole and in part, shall be
upon the | ||||||
3 | utility. The staff of the Commission and any party to a | ||||||
4 | proceeding regarding the propriety of any proposed rate or | ||||||
5 | other charge, classification, contract, practice, rule, or | ||||||
6 | regulation must, upon request, be given the opportunity to | ||||||
7 | present oral arguments in front of the Commission after the | ||||||
8 | conclusion of the hearings. No rate or other charge, | ||||||
9 | classification, contract,
practice, rule or regulation shall | ||||||
10 | be found just and reasonable unless it
is consistent with | ||||||
11 | Sections of this Article.
| ||||||
12 | (Source: P.A. 84-617.)".
|