State Government Administration Committee
Filed: 2/19/2009
|
|
09600HB0639ham001 |
|
LRB096 03045 MJR 21477 a |
|
|
1 |
| AMENDMENT TO HOUSE BILL 639
|
2 |
| AMENDMENT NO. ______. Amend House Bill 639 by replacing |
3 |
| everything after the enacting clause with the following:
|
4 |
| "Section 5. The Public Utilities Act is amended by changing |
5 |
| Section 9-201 as follows:
|
6 |
| (220 ILCS 5/9-201) (from Ch. 111 2/3, par. 9-201)
|
7 |
| Sec. 9-201.
(a) Unless the Commission otherwise orders, and |
8 |
| except as
otherwise provided in this Section, no change shall |
9 |
| be made by any
public utility in any rate or other charge or |
10 |
| classification, or in any
rule, regulation, practice or |
11 |
| contract relating to or affecting any rate
or other charge, |
12 |
| classification or service, or in any privilege or
facility, |
13 |
| except after 45 days' notice to the Commission and to the
|
14 |
| public as herein provided. Such notice shall be given by filing |
15 |
| with
the Commission and keeping open for public inspection new |
16 |
| schedules or
supplements stating plainly the change or changes |
|
|
|
09600HB0639ham001 |
- 2 - |
LRB096 03045 MJR 21477 a |
|
|
1 |
| to be made in the
schedule or schedules then in force, and the |
2 |
| time when the change or
changes will go into effect, and by |
3 |
| publication in a newspaper of
general circulation or such other |
4 |
| notice to persons affected by such
change as may be prescribed |
5 |
| by rule of the Commission. The Commission,
for good cause |
6 |
| shown, may allow changes without requiring the 45 days'
notice |
7 |
| herein provided for, by an order specifying the changes so to |
8 |
| be
made and the time when they shall take effect and the manner |
9 |
| in which
they shall be filed and published.
|
10 |
| When any change is proposed in any rate or other charge, or
|
11 |
| classification, or in any rule, regulation, practice, or |
12 |
| contract
relating to or affecting any rate or other charge, |
13 |
| classification or
service, or in any privilege or facility, |
14 |
| such proposed change shall be
plainly indicated on the new |
15 |
| schedule filed with the Commission, by some
character to be |
16 |
| designated by the Commission, immediately preceding or
|
17 |
| following the item.
|
18 |
| When any public utility providing water or sewer service |
19 |
| proposes any
change in any rate or other charge, or |
20 |
| classification, or in any rule,
regulation, practice, or |
21 |
| contract relating to or affecting any rate or
other charge, |
22 |
| classification or service, or in any privilege or facility,
|
23 |
| such utility shall, in addition to the other notice |
24 |
| requirements of this
Act, provide notice of such change to all |
25 |
| customers potentially affected by
including a notice and |
26 |
| description of such change, and of Commission
procedures for |
|
|
|
09600HB0639ham001 |
- 3 - |
LRB096 03045 MJR 21477 a |
|
|
1 |
| intervention, in the first bill sent to each such customer
|
2 |
| after the filing of the proposed change. |
3 |
| (a-5) No member of the Commission may discuss with any |
4 |
| representative of a public utility any matter that the public |
5 |
| utility is considering filing with the Commission pursuant to |
6 |
| this Section. If a public utility makes a filing under this |
7 |
| Section, then no communication concerning the filing is |
8 |
| permitted until a notice of hearing of a formal hearing has |
9 |
| been issued. After the notice of hearing has been issued, only |
10 |
| communications concerning the filing that are permitted under |
11 |
| Section 10-103 of this Act are permitted.
|
12 |
| (b) Whenever there shall be filed with the Commission any |
13 |
| schedule
stating an individual or joint rate or other charge, |
14 |
| classification,
contract, practice, rule or regulation, the |
15 |
| Commission shall have power,
and it is hereby given authority, |
16 |
| either upon complaint or upon its own
initiative without |
17 |
| complaint, at once, and if it so orders, without
answer or |
18 |
| other formal pleadings by the interested public utility or
|
19 |
| utilities, but upon reasonable notice, to enter upon a hearing
|
20 |
| concerning the propriety of such rate or other charge, |
21 |
| classification,
contract, practice, rule or regulation, and |
22 |
| pending the hearing and
decision thereon, such rate or other |
23 |
| charge, classification, contract,
practice, rule or regulation |
24 |
| shall not go into effect. The period of
suspension of such rate |
25 |
| or other charge, classification, contract,
practice, rule or |
26 |
| regulation shall not extend more than 105 days beyond
the time |
|
|
|
09600HB0639ham001 |
- 4 - |
LRB096 03045 MJR 21477 a |
|
|
1 |
| when such rate or other charge, classification, contract,
|
2 |
| practice, rule or regulation would otherwise go into effect |
3 |
| unless the
Commission, in its discretion, extends the period of |
4 |
| suspension for a
further period not exceeding 6 months.
|
5 |
| All rates or other charges, classifications, contracts, |
6 |
| practices, rules or
regulations not so suspended shall, on the |
7 |
| expiration of 45 days from
the time of filing the same with the |
8 |
| Commission, or of such lesser time
as the Commission may grant, |
9 |
| go into effect and be the established and
effective rates or |
10 |
| other charges, classifications, contracts, practices,
rules |
11 |
| and regulations, subject to the power of the Commission, after |
12 |
| a
hearing had on its own motion or upon complaint, as herein |
13 |
| provided, to
alter or modify the same.
|
14 |
| Within 30 days after such changes have been
authorized by |
15 |
| the Commission, copies of the new or revised schedules
shall be |
16 |
| posted or filed in accordance with the terms of Section 9-103 |
17 |
| of
this Act, in such a manner that all changes shall be plainly |
18 |
| indicated.
|
19 |
| (c) If the Commission enters upon a hearing concerning the |
20 |
| propriety of
any proposed rate or other charge, classification, |
21 |
| contract, practice, rule
or regulation, the Commission shall |
22 |
| establish the rates or other charges,
classifications, |
23 |
| contracts, practices, rules or regulations proposed, in
whole |
24 |
| or in part, or others in lieu thereof, which it shall find to |
25 |
| be just
and reasonable. In such hearing, the burden of proof to |
26 |
| establish the justness
and reasonableness of the proposed rates |
|
|
|
09600HB0639ham001 |
- 5 - |
LRB096 03045 MJR 21477 a |
|
|
1 |
| or other charges, classifications,
contracts, practices, rules |
2 |
| or regulations, in whole and in part, shall be
upon the |
3 |
| utility. The staff of the Commission and any party to a |
4 |
| proceeding regarding the propriety of any proposed rate or |
5 |
| other charge, classification, contract, practice, rule, or |
6 |
| regulation must, upon request, be given the opportunity to |
7 |
| present oral arguments in front of the Commission after the |
8 |
| conclusion of the hearings. No rate or other charge, |
9 |
| classification, contract,
practice, rule or regulation shall |
10 |
| be found just and reasonable unless it
is consistent with |
11 |
| Sections of this Article.
|
12 |
| (Source: P.A. 84-617.)".
|