|
Environment & Energy Committee
Filed: 11/29/2010
| | 09600SB3388ham001 | | LRB096 20594 ASK 44192 a |
|
|
1 | | AMENDMENT TO SENATE BILL 3388
|
2 | | AMENDMENT NO. ______. Amend Senate Bill 3388 by replacing |
3 | | everything after the enacting clause with the following:
|
4 | | "Section 5. The Illinois Power Agency Act is amended by |
5 | | changing Sections 1-10 and 1-20 and by adding Sections 1-77 and |
6 | | 1-78 as follows:
|
7 | | (20 ILCS 3855/1-10)
|
8 | | Sec. 1-10. Definitions. |
9 | | "Agency" means the Illinois Power Agency. |
10 | | "Agency loan agreement" means any agreement pursuant to |
11 | | which the Illinois Finance Authority agrees to loan the |
12 | | proceeds of revenue bonds issued with respect to a project to |
13 | | the Agency upon terms providing for loan repayment installments |
14 | | at least sufficient to pay when due all principal of, interest |
15 | | and premium, if any, on those revenue bonds, and providing for |
16 | | maintenance, insurance, and other matters in respect of the |
|
| | 09600SB3388ham001 | - 2 - | LRB096 20594 ASK 44192 a |
|
|
1 | | project. |
2 | | "Authority" means the Illinois Finance Authority. |
3 | | "Clean coal facility" means an electric generating |
4 | | facility that uses primarily coal as a feedstock and that |
5 | | captures and sequesters carbon dioxide emissions at the |
6 | | following levels: at least 50% of the total carbon dioxide |
7 | | emissions that the facility would otherwise emit if, at the |
8 | | time construction commences, the facility is scheduled to |
9 | | commence operation before 2016, at least 70% of the total |
10 | | carbon dioxide emissions that the facility would otherwise emit |
11 | | if, at the time construction commences, the facility is |
12 | | scheduled to commence operation during 2016 or 2017, and at |
13 | | least 90% of the total carbon dioxide emissions that the |
14 | | facility would otherwise emit if, at the time construction |
15 | | commences, the facility is scheduled to commence operation |
16 | | after 2017. The power block of the clean coal facility shall |
17 | | not exceed allowable emission rates for sulfur dioxide, |
18 | | nitrogen oxides, carbon monoxide, particulates and mercury for |
19 | | a natural gas-fired combined-cycle facility the same size as |
20 | | and in the same location as the clean coal facility at the time |
21 | | the clean coal facility obtains an approved air permit. All |
22 | | coal used by a clean coal facility shall have high volatile |
23 | | bituminous rank and greater than 1.7 pounds of sulfur per |
24 | | million btu content, unless the clean coal facility does not |
25 | | use gasification technology and was operating as a conventional |
26 | | coal-fired electric generating facility on June 1, 2009 (the |
|
| | 09600SB3388ham001 | - 3 - | LRB096 20594 ASK 44192 a |
|
|
1 | | effective date of Public Act 95-1027). |
2 | | "Clean coal SNG brownfield facility" means a facility that |
3 | | (1) has commenced construction by July 1, 2014 on an urban |
4 | | brownfield site in a municipality with at least 1,000,000 |
5 | | residents; (2) uses a gasification process to produce |
6 | | substitute natural gas; (3) uses coal as at least 50% of the |
7 | | total feedstock over the term of any sourcing agreement with a |
8 | | utility and the remainder of the feedstock may be either |
9 | | petroleum coke or coal, with all such coal having a high |
10 | | bituminous rank and greater than 1.7 pounds of sulfur per |
11 | | million Btu content; and (4) captures and sequesters at least |
12 | | 85% of the total carbon dioxide emissions that the facility |
13 | | would otherwise emit. |
14 | | "Clean coal SNG facility" means a facility that uses a |
15 | | gasification process to produce substitute natural gas, that |
16 | | sequesters at least 90% of the total carbon dioxide emissions |
17 | | that the facility would otherwise emit and that uses petroleum |
18 | | coke or coal as a feedstock, with all such coal having a high |
19 | | bituminous rank and greater than 1.7 pounds of sulfur per |
20 | | million btu content ; provided, however, a clean coal SNG |
21 | | brownfield facility shall not be a clean coal SNG facility . |
22 | | "Commission" means the Illinois Commerce Commission. |
23 | | "Costs incurred in connection with the development and |
24 | | construction of a facility" means: |
25 | | (1) the cost of acquisition of all real property , |
26 | | fixtures, and improvements in connection therewith and |
|
| | 09600SB3388ham001 | - 4 - | LRB096 20594 ASK 44192 a |
|
|
1 | | equipment , personal property, and other property, rights, |
2 | | and easements acquired that are deemed necessary for the |
3 | | operation and maintenance of the facility; |
4 | | (2) financing costs with respect to bonds, notes, and |
5 | | other evidences of indebtedness of the Agency; |
6 | | (3) all origination, commitment, utilization, |
7 | | facility, placement, underwriting, syndication, credit |
8 | | enhancement, and rating agency fees; |
9 | | (4) engineering, design, procurement, consulting, |
10 | | legal, accounting, title insurance, survey, appraisal, |
11 | | escrow, trustee, collateral agency, interest rate hedging, |
12 | | interest rate swap, capitalized interest , contingency, as |
13 | | required by lenders, and other financing costs, and other |
14 | | expenses for professional services; and |
15 | | (5) the costs of plans, specifications, site study and |
16 | | investigation, installation, surveys, other Agency costs |
17 | | and estimates of costs, and other expenses necessary or |
18 | | incidental to determining the feasibility of any project, |
19 | | together with such other expenses as may be necessary or |
20 | | incidental to the financing, insuring, acquisition, and |
21 | | construction of a specific project and starting up, |
22 | | commissioning, and placing that project in operation. |
23 | | "Department" means the Department of Commerce and Economic |
24 | | Opportunity. |
25 | | "Director" means the Director of the Illinois Power Agency. |
26 | | "Demand-response" means measures that decrease peak |
|
| | 09600SB3388ham001 | - 5 - | LRB096 20594 ASK 44192 a |
|
|
1 | | electricity demand or shift demand from peak to off-peak |
2 | | periods. |
3 | | "Energy efficiency" means measures that reduce the amount |
4 | | of electricity or natural gas required to achieve a given end |
5 | | use. |
6 | | "Electric utility" has the same definition as found in |
7 | | Section 16-102 of the Public Utilities Act. |
8 | | "Facility" means an electric generating unit or a |
9 | | co-generating unit that produces electricity along with |
10 | | related equipment necessary to connect the facility to an |
11 | | electric transmission or distribution system. |
12 | | "Governmental aggregator" means one or more units of local |
13 | | government that individually or collectively procure |
14 | | electricity to serve residential retail electrical loads |
15 | | located within its or their jurisdiction. |
16 | | "Local government" means a unit of local government as |
17 | | defined in Article VII of Section 1 of the Illinois |
18 | | Constitution. |
19 | | "Municipality" means a city, village, or incorporated |
20 | | town. |
21 | | "Person" means any natural person, firm, partnership, |
22 | | corporation, either domestic or foreign, company, association, |
23 | | limited liability company, joint stock company, or association |
24 | | and includes any trustee, receiver, assignee, or personal |
25 | | representative thereof. |
26 | | "Project" means the planning, bidding, and construction of |
|
| | 09600SB3388ham001 | - 6 - | LRB096 20594 ASK 44192 a |
|
|
1 | | a facility. |
2 | | "Public utility" has the same definition as found in |
3 | | Section 3-105 of the Public Utilities Act. |
4 | | "Real property" means any interest in land together with |
5 | | all structures, fixtures, and improvements thereon, including |
6 | | lands under water and riparian rights, any easements, |
7 | | covenants, licenses, leases, rights-of-way, uses, and other |
8 | | interests, together with any liens, judgments, mortgages, or |
9 | | other claims or security interests related to real property. |
10 | | "Renewable energy credit" means a tradable credit that |
11 | | represents the environmental attributes of a certain amount of |
12 | | energy produced from a renewable energy resource. |
13 | | "Renewable energy resources" includes energy and its |
14 | | associated renewable energy credit or renewable energy credits |
15 | | from wind, solar thermal energy, photovoltaic cells and panels, |
16 | | biodiesel, crops and untreated and unadulterated organic waste |
17 | | biomass, tree waste, hydropower that does not involve new |
18 | | construction or significant expansion of hydropower dams, and |
19 | | other alternative sources of environmentally preferable |
20 | | energy. For purposes of this Act, landfill gas produced in the |
21 | | State is considered a renewable energy resource. "Renewable |
22 | | energy resources" does not include the incineration or burning |
23 | | of tires, garbage, general household, institutional, and |
24 | | commercial waste, industrial lunchroom or office waste, |
25 | | landscape waste other than tree waste, railroad crossties, |
26 | | utility poles, or construction or demolition debris, other than |
|
| | 09600SB3388ham001 | - 7 - | LRB096 20594 ASK 44192 a |
|
|
1 | | untreated and unadulterated waste wood. |
2 | | "Revenue bond" means any bond, note, or other evidence of |
3 | | indebtedness issued by the Authority, the principal and |
4 | | interest of which is payable solely from revenues or income |
5 | | derived from any project or activity of the Agency. |
6 | | "Sequester" means permanent storage of carbon dioxide only |
7 | | as approved by the Commission pursuant to subsection (h-7) of |
8 | | Section 9-220 of the Public Utilities Act by injecting it into |
9 | | a saline aquifer, a depleted gas reservoir, or an oil |
10 | | reservoir, directly or through an enhanced oil recovery process |
11 | | that may involve intermediate storage , regardless of whether |
12 | | these activities are conducted by a clean coal facility, clean |
13 | | coal SNG facility, clean coal SNG brownfield facility, or a |
14 | | party with which a clean coal facility, clean coal SNG |
15 | | facility, or clean coal SNG brownfield facility has contracted |
16 | | for such purposes in a salt dome . |
17 | | " Sourcing Servicing agreement" means (i) in the case of an |
18 | | electric utility, an agreement between the owner of a clean |
19 | | coal facility and such electric utility, which agreement shall |
20 | | have terms and conditions meeting the requirements of paragraph |
21 | | (3) of subsection (d) of Section 1-75, and (ii) in the case of |
22 | | an alternative retail electric supplier, an agreement between |
23 | | the owner of a clean coal facility and such alternative retail |
24 | | electric supplier, which agreement shall have terms and |
25 | | conditions meeting the requirements of Section 16-115(d)(5) of |
26 | | the Public Utilities Act , and (iii) in case of a gas utility, |
|
| | 09600SB3388ham001 | - 8 - | LRB096 20594 ASK 44192 a |
|
|
1 | | an agreement between the owner of a clean coal SNG brownfield |
2 | | facility and the gas utility, which agreement shall have the |
3 | | terms and conditions meeting the requirements of subsection |
4 | | (h-1) of Section 9-220 of the Public Utilities Act . |
5 | | "Substitute natural gas" or "SNG" means a gas manufactured |
6 | | by gasification of hydrocarbon feedstock, which is |
7 | | substantially interchangeable in use and distribution with |
8 | | conventional natural gas. |
9 | | "Total resource cost test" or "TRC test" means a standard |
10 | | that is met if, for an investment in energy efficiency or |
11 | | demand-response measures, the benefit-cost ratio is greater |
12 | | than one. The benefit-cost ratio is the ratio of the net |
13 | | present value of the total benefits of the program to the net |
14 | | present value of the total costs as calculated over the |
15 | | lifetime of the measures. A total resource cost test compares |
16 | | the sum of avoided electric utility costs, representing the |
17 | | benefits that accrue to the system and the participant in the |
18 | | delivery of those efficiency measures, as well as other |
19 | | quantifiable societal benefits, including avoided natural gas |
20 | | utility costs, to the sum of all incremental costs of end-use |
21 | | measures that are implemented due to the program (including |
22 | | both utility and participant contributions), plus costs to |
23 | | administer, deliver, and evaluate each demand-side program, to |
24 | | quantify the net savings obtained by substituting the |
25 | | demand-side program for supply resources. In calculating |
26 | | avoided costs of power and energy that an electric utility |
|
| | 09600SB3388ham001 | - 9 - | LRB096 20594 ASK 44192 a |
|
|
1 | | would otherwise have had to acquire, reasonable estimates shall |
2 | | be included of financial costs likely to be imposed by future |
3 | | regulations and legislation on emissions of greenhouse gases.
|
4 | | (Source: P.A. 95-481, eff. 8-28-07; 95-913, eff. 1-1-09; |
5 | | 95-1027, eff. 6-1-09; 96-33, eff. 7-10-09; 96-159, eff. |
6 | | 8-10-09; 96-784, eff. 8-28-09; 96-1000, eff. 7-2-10.)
|
7 | | (20 ILCS 3855/1-20)
|
8 | | Sec. 1-20. General powers of the Agency. |
9 | | (a) The Agency is authorized to do each of the following: |
10 | | (1) Develop electricity procurement plans to ensure |
11 | | adequate, reliable, affordable, efficient, and |
12 | | environmentally sustainable electric service at the lowest |
13 | | total cost over time, taking into account any benefits of |
14 | | price stability, for electric utilities that on December |
15 | | 31, 2005 provided electric service to at least 100,000 |
16 | | customers in Illinois. The procurement plans shall be |
17 | | updated on an annual basis and shall include electricity |
18 | | generated from renewable resources sufficient to achieve |
19 | | the standards specified in this Act. |
20 | | (2) Conduct competitive procurement processes to |
21 | | procure the supply resources identified in the procurement |
22 | | plan, pursuant to Section 16-111.5 of the Public Utilities |
23 | | Act. |
24 | | (3) Develop electric generation and co-generation |
25 | | facilities that use indigenous coal or renewable |
|
| | 09600SB3388ham001 | - 10 - | LRB096 20594 ASK 44192 a |
|
|
1 | | resources, or both, financed with bonds issued by the |
2 | | Illinois Finance Authority. |
3 | | (4) Supply electricity from the Agency's facilities at |
4 | | cost to one or more of the following: municipal electric |
5 | | systems, governmental aggregators, or rural electric |
6 | | cooperatives in Illinois. |
7 | | (b) Except as otherwise limited by this Act, the Agency has |
8 | | all of the powers necessary or convenient to carry out the |
9 | | purposes and provisions of this Act, including without |
10 | | limitation, each of the following: |
11 | | (1) To have a corporate seal, and to alter that seal at |
12 | | pleasure, and to use it by causing it or a facsimile to be |
13 | | affixed or impressed or reproduced in any other manner. |
14 | | (2) To use the services of the Illinois Finance |
15 | | Authority necessary to carry out the Agency's purposes. |
16 | | (3) To negotiate and enter into loan agreements and |
17 | | other agreements with the Illinois Finance Authority. |
18 | | (4) To obtain and employ personnel and hire consultants |
19 | | that are necessary to fulfill the Agency's purposes, and to |
20 | | make expenditures for that purpose within the |
21 | | appropriations for that purpose. |
22 | | (5) To purchase, receive, take by grant, gift, devise, |
23 | | bequest, or otherwise, lease, or otherwise acquire, own, |
24 | | hold, improve, employ, use, and otherwise deal in and with, |
25 | | real or personal property whether tangible or intangible, |
26 | | or any interest therein, within the State. |
|
| | 09600SB3388ham001 | - 11 - | LRB096 20594 ASK 44192 a |
|
|
1 | | (6) To acquire real or personal property, whether |
2 | | tangible or intangible, including without limitation |
3 | | property rights, interests in property, franchises, |
4 | | obligations, contracts, and debt and equity securities, |
5 | | and to do so by the exercise of the power of eminent domain |
6 | | in accordance with Section 1-21; except that any real |
7 | | property acquired by the exercise of the power of eminent |
8 | | domain must be located within the State. |
9 | | (7) To sell, convey, lease, exchange, transfer, |
10 | | abandon, or otherwise dispose of, or mortgage, pledge, or |
11 | | create a security interest in, any of its assets, |
12 | | properties, or any interest therein, wherever situated. |
13 | | (8) To purchase, take, receive, subscribe for, or |
14 | | otherwise acquire, hold, make a tender offer for, vote, |
15 | | employ, sell, lend, lease, exchange, transfer, or |
16 | | otherwise dispose of, mortgage, pledge, or grant a security |
17 | | interest in, use, and otherwise deal in and with, bonds and |
18 | | other obligations, shares, or other securities (or |
19 | | interests therein) issued by others, whether engaged in a |
20 | | similar or different business or activity. |
21 | | (9) To make and execute agreements, contracts, and |
22 | | other instruments necessary or convenient in the exercise |
23 | | of the powers and functions of the Agency under this Act, |
24 | | including contracts with any person, local government, |
25 | | State agency, or other entity; and all State agencies and |
26 | | all local governments are authorized to enter into and do |
|
| | 09600SB3388ham001 | - 12 - | LRB096 20594 ASK 44192 a |
|
|
1 | | all things necessary to perform any such agreement, |
2 | | contract, or other instrument with the Agency. No such |
3 | | agreement, contract, or other instrument shall exceed 40 |
4 | | years. |
5 | | (10) To lend money, invest and reinvest its funds in |
6 | | accordance with the Public Funds Investment Act, and take |
7 | | and hold real and personal property as security for the |
8 | | payment of funds loaned or invested. |
9 | | (11) To borrow money at such rate or rates of interest |
10 | | as the Agency may determine, issue its notes, bonds, or |
11 | | other obligations to evidence that indebtedness, and |
12 | | secure any of its obligations by mortgage or pledge of its |
13 | | real or personal property, machinery, equipment, |
14 | | structures, fixtures, inventories, revenues, grants, and |
15 | | other funds as provided or any interest therein, wherever |
16 | | situated. |
17 | | (12) To enter into agreements with the Illinois Finance |
18 | | Authority to issue bonds whether or not the income |
19 | | therefrom is exempt from federal taxation. |
20 | | (13) To procure insurance against any loss in |
21 | | connection with its properties or operations in such amount |
22 | | or amounts and from such insurers, including the federal |
23 | | government, as it may deem necessary or desirable, and to |
24 | | pay any premiums therefor. |
25 | | (14) To negotiate and enter into agreements with |
26 | | trustees or receivers appointed by United States |
|
| | 09600SB3388ham001 | - 13 - | LRB096 20594 ASK 44192 a |
|
|
1 | | bankruptcy courts or federal district courts or in other |
2 | | proceedings involving adjustment of debts and authorize |
3 | | proceedings involving adjustment of debts and authorize |
4 | | legal counsel for the Agency to appear in any such |
5 | | proceedings. |
6 | | (15) To file a petition under Chapter 9 of Title 11 of |
7 | | the United States Bankruptcy Code or take other similar |
8 | | action for the adjustment of its debts. |
9 | | (16) To enter into management agreements for the |
10 | | operation of any of the property or facilities owned by the |
11 | | Agency. |
12 | | (17) To enter into an agreement to transfer and to |
13 | | transfer any land, facilities, fixtures, or equipment of |
14 | | the Agency to one or more municipal electric systems, |
15 | | governmental aggregators, or rural electric agencies or |
16 | | cooperatives, for such consideration and upon such terms as |
17 | | the Agency may determine to be in the best interest of the |
18 | | citizens of Illinois. |
19 | | (18) To enter upon any lands and within any building |
20 | | whenever in its judgment it may be necessary for the |
21 | | purpose of making surveys and examinations to accomplish |
22 | | any purpose authorized by this Act. |
23 | | (19) To maintain an office or offices at such place or |
24 | | places in the State as it may determine. |
25 | | (20) To request information, and to make any inquiry, |
26 | | investigation, survey, or study that the Agency may deem |
|
| | 09600SB3388ham001 | - 14 - | LRB096 20594 ASK 44192 a |
|
|
1 | | necessary to enable it effectively to carry out the |
2 | | provisions of this Act. |
3 | | (21) To accept and expend appropriations. |
4 | | (22) To engage in any activity or operation that is |
5 | | incidental to and in furtherance of efficient operation to |
6 | | accomplish the Agency's purposes. |
7 | | (23) To adopt, revise, amend, and repeal rules with |
8 | | respect to its operations, properties, and facilities as |
9 | | may be necessary or convenient to carry out the purposes of |
10 | | this Act, subject to the provisions of the Illinois |
11 | | Administrative Procedure Act and Sections 1-22 and 1-35 of |
12 | | this Act. |
13 | | (24) To establish and collect charges and fees as |
14 | | described in this Act.
|
15 | | (25) To conduct competitive gasification feedstock |
16 | | procurement processes to procure the feedstocks for the |
17 | | clean coal SNG brownfield facility in accordance with the |
18 | | requirements of Section 1-78 of this Act To manage |
19 | | procurement of substitute natural gas from a facility that |
20 | | meets the criteria specified in subsection (a) of Section |
21 | | 1-58 of this Act, on terms and conditions that may be |
22 | | approved by the Agency pursuant to subsection (d) of |
23 | | Section 1-58 of this Act, to support the operations of |
24 | | State agencies and local governments that agree to such |
25 | | terms and conditions. This procurement process is not |
26 | | subject to the Procurement Code . |
|
| | 09600SB3388ham001 | - 15 - | LRB096 20594 ASK 44192 a |
|
|
1 | | (26) To review, revise, and approve sourcing |
2 | | agreements and mediate and resolve disputes between gas |
3 | | utilities and the clean coal SNG brownfield facility |
4 | | pursuant to subsection (h-1) of Section 9-220 of the Public |
5 | | Utilities Act. |
6 | | (Source: P.A. 95-481, eff. 8-28-07; 96-784, eff. 8-28-09; |
7 | | 96-1000, eff. 7-2-10.) |
8 | | (20 ILCS 3855/1-77 new) |
9 | | Sec. 1-77. The Planning and Procurement Bureau; feedstock |
10 | | procurement administrator; qualified expert or expert |
11 | | consulting firm. |
12 | | (a) The Planning and Procurement Bureau shall at least |
13 | | every 5
years beginning in 2015 develop feedstock procurement |
14 | | plans and conduct competitive feedstock procurement processes |
15 | | in accordance with the requirements of Section 1-78 of this |
16 | | Act. |
17 | | (1) The Agency shall at least every 5 years beginning |
18 | | in
2015 issue a request for qualifications for experts or |
19 | | expert consulting firms to develop the feedstock |
20 | | procurement plans in accordance with Section 1-78 of this |
21 | | Act. In order to qualify, an expert or expert consulting |
22 | | firm must have: |
23 | | (A) direct previous experience assembling
large |
24 | | scale feedstock supply plans or portfolios for |
25 | | industrial customers; |
|
| | 09600SB3388ham001 | - 16 - | LRB096 20594 ASK 44192 a |
|
|
1 | | (B) an advanced degree in economics,
mathematics, |
2 | | engineering, risk management, or a related area of |
3 | | study; |
4 | | (C) ten years of experience in the energy
sector, |
5 | | including managing supply risk; |
6 | | (D) expertise in wholesale feedstock markets, |
7 | | which may be particularized to the specific type of |
8 | | feedstock to be purchased in that procurement event; |
9 | | (E) expertise in credit protocols and
familiarity |
10 | | with contract protocols; |
11 | | (F) adequate resources to perform and fulfill
the |
12 | | required functions and responsibilities; and |
13 | | (G) the absence of a conflict of interest and
|
14 | | inappropriate bias for or against potential bidders or |
15 | | the affected clean coal SNG brownfield facility. |
16 | | (2) The Agency shall at least every 5 years beginning |
17 | | in 2015 issue
a request for qualifications for a feedstock |
18 | | procurement administrator to conduct the competitive |
19 | | feedstock procurement processes in accordance with Section |
20 | | 1-78 of this Act. In order to qualify, an expert or expert |
21 | | consulting firm must have: |
22 | | (A) direct previous experience administering
a |
23 | | large scale competitive feedstock procurement process; |
24 | | (B) an advanced degree in economics,
mathematics, |
25 | | engineering, or a related area of study; |
26 | | (C) ten years of experience in the energy
sector, |
|
| | 09600SB3388ham001 | - 17 - | LRB096 20594 ASK 44192 a |
|
|
1 | | including risk management experience; |
2 | | (D) expertise in wholesale feedstock market
rules, |
3 | | which may be particularized to the specific type of |
4 | | feedstock to be purchased in that procurement event; |
5 | | (E) expertise in credit and contract
protocols; |
6 | | (F) adequate resources to perform and fulfill
the |
7 | | required functions and responsibilities; and |
8 | | (G) the absence of a conflict of interest and
|
9 | | inappropriate bias for or against potential bidders or |
10 | | the affected clean coal SNG brownfield facility. |
11 | | (3) The Agency shall provide the clean coal SNG |
12 | | brownfield facility
and other interested parties with the |
13 | | lists of qualified experts or expert consulting firms |
14 | | identified through the request for qualifications |
15 | | processes that are under consideration to develop the |
16 | | feedstock procurement plans and to serve as the feedstock |
17 | | procurement administrator. The Agency shall also provide |
18 | | the clean coal SNG brownfield facility
and other interested |
19 | | parties with each qualified expert's or expert consulting |
20 | | firm's response to the request for qualifications. All |
21 | | information provided under this subparagraph (3) shall |
22 | | also be provided to the Commission. The Agency may provide |
23 | | by rule for fees associated with supplying the information |
24 | | to the clean coal SNG brownfield facility and other |
25 | | interested parties. The clean coal SNG brownfield facility
|
26 | | and other interested parties must, within 5 business days |
|
| | 09600SB3388ham001 | - 18 - | LRB096 20594 ASK 44192 a |
|
|
1 | | after receiving the lists and information, notify the |
2 | | Agency in writing if they object to any experts or expert |
3 | | consulting firms on the lists. Objections shall be based |
4 | | on: |
5 | | (A) failure to satisfy qualification
criteria; |
6 | | (B) identification of a conflict of interest;
or |
7 | | (C) evidence of inappropriate bias for or
against |
8 | | potential bidders or the clean coal SNG brownfield |
9 | | facility. |
10 | | The Agency shall remove an expert or expert
consulting |
11 | | firm from the list within 10 days if there is a reasonable |
12 | | basis for an objection and provide the updated list to the |
13 | | clean coal SNG brownfield facility and other interested |
14 | | parties. If the Agency fails to remove an expert or expert |
15 | | consulting firm from a list, then an objecting party may |
16 | | seek review by the Commission within 5 days thereafter by |
17 | | filing a petition, and the Commission shall render a ruling |
18 | | on the petition within 10 days after the filing. There is |
19 | | no right of appeal of the Commission's ruling. |
20 | | (4) The Agency shall, as needed, issue requests for |
21 | | proposals
to the qualified experts or expert consulting |
22 | | firms to develop a feedstock procurement plan for the clean |
23 | | coal SNG brownfield facility and to serve as feedstock |
24 | | procurement administrator. |
25 | | (5) The Agency shall select an expert or expert
|
26 | | consulting firm to develop feedstock procurement plans |
|
| | 09600SB3388ham001 | - 19 - | LRB096 20594 ASK 44192 a |
|
|
1 | | based on the proposals submitted and shall award one-year |
2 | | contracts to those selected with an option for the Agency |
3 | | for a one-year renewal. |
4 | | (6) The Agency shall select, with the approval of the |
5 | | Commission, an expert or expert
consulting firm to serve as |
6 | | feedstock procurement administrator based on the proposals |
7 | | submitted. If the Commission rejects the Agency's |
8 | | selection within 5 days after being notified of the |
9 | | Agency's selection, then the Agency shall submit another |
10 | | recommendation within 3 days after the Commission's |
11 | | rejection based on the proposals submitted. The Agency |
12 | | shall award at least a one-year contract to the expert or |
13 | | expert consulting firm selected with the Commission's |
14 | | approval with an option for the Agency for renewal for a |
15 | | term equal to the term of the contract. |
16 | | (b) The experts or expert consulting firms retained
by the |
17 | | Agency shall, as appropriate, prepare feedstock procurement |
18 | | plans and conduct a competitive feedstock procurement process |
19 | | as prescribed in Section 1-78 of this Act to ensure adequate, |
20 | | reliable, affordable feedstocks, taking into account any |
21 | | benefits of price stability, for the clean coal SNG brownfield |
22 | | facility. |
23 | | (c) The draft procurement plans are subject to public |
24 | | comment pursuant to Section 1-78 of this Act. |
25 | | (d) The Agency shall assess fees to each bidder to recover |
26 | | the costs incurred in connection with the competitive |
|
| | 09600SB3388ham001 | - 20 - | LRB096 20594 ASK 44192 a |
|
|
1 | | procurement process. |
2 | | (20 ILCS 3855/1-78 new) |
3 | | Sec. 1-78. Feedstock procurement plan; feedstock |
4 | | procurement process. |
5 | | (a) A feedstock procurement plan shall at least every 5 |
6 | | years beginning in 2015 be prepared for the clean coal SNG |
7 | | brownfield facility based on the clean coal SNG brownfield |
8 | | facility's projection of feedstock usage and ratios, and |
9 | | consistent with the applicable requirements of the Public |
10 | | Utilities Act and this Act. The plan shall specifically |
11 | | identify the wholesale feedstock products to be procured |
12 | | following plan approval and shall follow all the requirements |
13 | | set forth in this Act, the Public Utilities Act, and all |
14 | | applicable State and federal laws, statutes, rules, or |
15 | | regulations, as well as Commission orders. Nothing in this |
16 | | Section precludes consideration of contracts longer than 5 |
17 | | years and related forecast data. Any feedstock procurement |
18 | | occurring in accordance with this plan shall be competitively |
19 | | bid through a request for proposals process. Approval and |
20 | | implementation of the feedstock procurement plan shall be |
21 | | subject to review and approval by the Commission according to |
22 | | the provisions set forth in this Section. A feedstock |
23 | | procurement plan shall include each of the following |
24 | | components: |
25 | | (1) Daily load analysis. This analysis shall
include: |
|
| | 09600SB3388ham001 | - 21 - | LRB096 20594 ASK 44192 a |
|
|
1 | | (A) multi-year historical analysis of hourly
|
2 | | loads; and |
3 | | (B) known or projected changes to future loads. |
4 | | (2) Determination of the fuel specifications required |
5 | | for the clean coal SNG brownfield facility, including: |
6 | | (A) coal and petroleum coke mix, as set by the |
7 | | clean coal SNG brownfield facility with coal |
8 | | comprising at least 50% of the total feedstock over the |
9 | | term of any sourcing agreement; |
10 | | (B) volume of each feedstock required; |
11 | | (C) quality standards of each feedstock; |
12 | | (D) delivery requirements, including cost |
13 | | implications; and |
14 | | (E) technical specifications of the clean coal SNG |
15 | | brownfield facility for its feedstocks. |
16 | | (b) The feedstock procurement process shall be |
17 | | administered by a feedstock procurement administrator and |
18 | | monitored by a feedstock procurement monitor. |
19 | | (1) The feedstock procurement administrator shall: |
20 | | (A) design the final feedstock procurement process |
21 | | in
accordance with subsection (d) of this Section |
22 | | following Commission approval of the feedstock |
23 | | procurement plan; |
24 | | (B) develop feedstock benchmarks in accordance |
25 | | with
subsection (d)(3) to be used to evaluate bids; |
26 | | these benchmarks shall be submitted to the Commission |
|
| | 09600SB3388ham001 | - 22 - | LRB096 20594 ASK 44192 a |
|
|
1 | | for review and approval on a confidential basis prior |
2 | | to the feedstock procurement event; |
3 | | (C) serve as the interface between the clean coal |
4 | | SNG brownfield facility
and coal and petroleum coke |
5 | | suppliers; |
6 | | (D) manage the bidder pre-qualification and
|
7 | | registration process; |
8 | | (E) obtain the facility's agreement to
the final |
9 | | form of all supply contracts and credit collateral |
10 | | agreements; |
11 | | (F) administer the request for feedstock proposals |
12 | | process; |
13 | | (G) have the discretion to negotiate to
determine |
14 | | whether bidders are willing to lower the price of bids |
15 | | that meet the benchmarks approved by the Commission; |
16 | | any post-bid negotiations with bidders shall be |
17 | | limited to price only and shall be completed within 24 |
18 | | hours after opening the sealed bids and shall be |
19 | | conducted in a fair and unbiased manner; in conducting |
20 | | the negotiations, there shall be no disclosure of any |
21 | | information derived from proposals submitted by |
22 | | competing bidders; if information is disclosed to any |
23 | | bidder, it shall be provided to all competing bidders; |
24 | | (H) maintain confidentiality of supplier and
|
25 | | bidding information in a manner consistent with all |
26 | | applicable laws, rules, regulations, and tariffs; |
|
| | 09600SB3388ham001 | - 23 - | LRB096 20594 ASK 44192 a |
|
|
1 | | (I) submit a confidential report to the
Commission |
2 | | recommending acceptance or rejection of bids; |
3 | | (J) notify the facility of contract counterparties
|
4 | | and contract specifics; and |
5 | | (K) administer related contingency feedstock |
6 | | procurement
events. |
7 | | (2) The feedstock procurement monitor, who shall be |
8 | | retained by
the Commission, shall: |
9 | | (A) monitor interactions among the feedstock |
10 | | procurement
administrator, suppliers, and the |
11 | | facility; |
12 | | (B) monitor and report to the Commission on the
|
13 | | progress of the feedstock procurement process; |
14 | | (C) provide an independent, confidential report
to |
15 | | the Commission regarding the results of the feedstock |
16 | | procurement event; |
17 | | (D) preserve the confidentiality of supplier and
|
18 | | bidding information in a manner consistent with all |
19 | | applicable laws, rules, regulations, and tariffs; |
20 | | (E) provide expert advice to the Commission and
|
21 | | consult with the feedstock procurement administrator |
22 | | regarding issues related to feedstock procurement |
23 | | process design, rules, protocols, and policy-related |
24 | | matters; |
25 | | (F) consult with the feedstock procurement |
26 | | administrator
regarding the development and use of |
|
| | 09600SB3388ham001 | - 24 - | LRB096 20594 ASK 44192 a |
|
|
1 | | benchmark criteria, standard form contracts, credit |
2 | | policies, and bid documents; and |
3 | | (G) assess compliance with the procurement plans |
4 | | approved by the Commission. |
5 | | (c) The feedstock planning process shall be conducted as |
6 | | follows: |
7 | | (1) Beginning in 2015, the clean coal SNG brownfield |
8 | | facility
shall annually provide a range of feedstock |
9 | | requirement forecasts to the Agency by May 15 of each year, |
10 | | or such other date as may be required by the Commission or |
11 | | Agency. The feedstock requirement forecasts shall cover |
12 | | the 5-year feedstock procurement planning period for the |
13 | | next feedstock procurement plan, or such other longer |
14 | | period that the Agency or the Commission may require and |
15 | | shall include daily data representing a high-load, |
16 | | low-load, and expected-load scenario for the load of the |
17 | | utilities required to enter into sourcing agreements with |
18 | | the clean coal SNG brownfield facility. The utility shall |
19 | | provide supporting data and assumptions for each of the |
20 | | scenarios. |
21 | | (2) Beginning in 2015, the Agency
shall at least every |
22 | | 5 years prepare a feedstock procurement plan by June 15, or |
23 | | such other date as may be required by the Commission. The |
24 | | feedstock procurement plan shall identify the portfolio of |
25 | | feedstocks to be procured. Copies of the feedstock |
26 | | procurement plan shall be posted and made publicly |
|
| | 09600SB3388ham001 | - 25 - | LRB096 20594 ASK 44192 a |
|
|
1 | | available on the Agency's and Commission's websites, and |
2 | | copies shall also be provided to the clean coal SNG |
3 | | brownfield facility. The clean coal SNG brownfield |
4 | | facility shall have 30 days following the date of posting |
5 | | to provide comment to the Agency on the feedstock |
6 | | procurement plan. Other interested entities also may |
7 | | comment on the feedstock procurement plan. All comments |
8 | | submitted to the Agency shall be specific, supported by |
9 | | data or other detailed analyses, and, if objecting to all |
10 | | or a portion of the feedstock procurement plan, accompanied |
11 | | by specific alternative wording or proposals. All comments |
12 | | shall be posted on the Agency's and Commission's websites. |
13 | | During this 30-day comment period, the Agency shall hold at |
14 | | least one public hearing for the purpose of receiving |
15 | | public comment on the procurement plan. Within 14 days |
16 | | following the end of the 30-day comment period, the Agency |
17 | | shall revise the feedstock procurement plan as necessary |
18 | | based on the comments received, file the feedstock |
19 | | procurement plan with the Commission, and post the |
20 | | feedstock procurement plan on the websites. |
21 | | (3) Within 5 days after the filing of the feedstock |
22 | | procurement
plan, any person objecting to the feedstock |
23 | | procurement plan shall file an objection with the |
24 | | Commission. Within 10 days after the filing, the Commission |
25 | | shall determine whether a hearing is necessary. The |
26 | | Commission shall enter its order confirming or modifying |
|
| | 09600SB3388ham001 | - 26 - | LRB096 20594 ASK 44192 a |
|
|
1 | | the feedstock procurement plan within 90 days after the |
2 | | filing of the feedstock procurement plan by the Agency. |
3 | | (4) The Commission shall approve the feedstock |
4 | | procurement
plan, including expressly the forecast used in |
5 | | the feedstock procurement plan, if the Commission |
6 | | determines that it will ensure adequate, reliable, and |
7 | | affordable feedstocks to the clean coal SNG brownfield |
8 | | facility at the lowest total cost over time, taking into |
9 | | account any benefits of price stability. |
10 | | (d) The feedstock procurement process shall include each of |
11 | | the following components: |
12 | | (1) Solicitation, pre qualification, and registration
|
13 | | of bidders. The feedstock procurement administrator shall |
14 | | disseminate information to potential bidders to promote a |
15 | | feedstock procurement event, notify potential bidders that |
16 | | the feedstock procurement administrator may enter into a |
17 | | post-bid price negotiation with bidders that meet the |
18 | | applicable benchmarks, provide supply requirements, and |
19 | | otherwise explain the competitive feedstock procurement |
20 | | process. In addition to such other publication as the |
21 | | feedstock procurement administrator determines is |
22 | | appropriate, this information shall be posted on the |
23 | | Agency's and the Commission's websites. The feedstock |
24 | | procurement administrator shall also administer the |
25 | | prequalification process, including evaluation of credit |
26 | | worthiness, compliance with feedstock procurement rules, |
|
| | 09600SB3388ham001 | - 27 - | LRB096 20594 ASK 44192 a |
|
|
1 | | and agreement to the standard form contract developed |
2 | | pursuant to paragraph (2) of this subsection (d). The |
3 | | feedstock procurement administrator shall then identify |
4 | | and register bidders to participate in the feedstock |
5 | | procurement event. |
6 | | (2) Standard contract forms and credit terms and
|
7 | | instruments. The feedstock procurement administrator, in |
8 | | consultation with the clean coal SNG brownfield facility, |
9 | | gas utilities, the Commission, and other interested |
10 | | parties and subject to Commission oversight, shall develop |
11 | | and provide standard contract forms for the supplier |
12 | | contracts that meet generally accepted industry practices. |
13 | | Standard credit terms and instruments that meet generally |
14 | | accepted industry practices shall be similarly developed. |
15 | | The feedstock procurement administrator shall make |
16 | | available to the Commission all written comments it |
17 | | receives on the contract forms, credit terms, or |
18 | | instruments. If the feedstock procurement administrator |
19 | | cannot reach agreement with the applicable clean coal SNG |
20 | | brownfield facility as to the contract terms and |
21 | | conditions, then the feedstock procurement administrator |
22 | | must notify the Commission of any disputed terms and the |
23 | | Commission shall resolve the dispute. The terms of the |
24 | | contracts shall not be subject to negotiation by winning |
25 | | bidders and the bidders must agree to the terms of the |
26 | | contract in advance so that winning bids are selected |
|
| | 09600SB3388ham001 | - 28 - | LRB096 20594 ASK 44192 a |
|
|
1 | | solely on the basis of price. |
2 | | (3) Establishment of a market-based price benchmark.
|
3 | | As part of the development of the feedstock procurement |
4 | | process, the feedstock procurement administrator, in |
5 | | consultation with the Commission staff, Agency staff, and |
6 | | the feedstock procurement monitor, shall establish |
7 | | benchmarks for evaluating the final prices in the contracts |
8 | | for each of the feedstocks that will be procured through |
9 | | the feedstock procurement process. The benchmarks shall be |
10 | | based on price data for similar feedstocks for the same |
11 | | delivery period and same delivery hub or other delivery |
12 | | hubs after adjusting for that difference. The price |
13 | | benchmarks may also be adjusted to take into account |
14 | | differences between the information reflected in the |
15 | | underlying data sources and the specific feedstocks and |
16 | | gasification feedstock procurement process being used to |
17 | | procure for the clean coal SNG brownfield facility. The |
18 | | benchmarks shall be confidential but shall be provided to, |
19 | | and shall be subject to, the Commission's review and |
20 | | approval prior to a feedstock procurement event. |
21 | | (4) Request for proposals. The feedstock procurement |
22 | | administrator shall design and issue a request for |
23 | | proposals to supply coal or petroleum coke in accordance |
24 | | with the clean coal SNG brownfield facility's usage plan, |
25 | | as approved by the Commission. The request for proposals |
26 | | shall set forth a procedure for sealed, binding commitment |
|
| | 09600SB3388ham001 | - 29 - | LRB096 20594 ASK 44192 a |
|
|
1 | | bidding with pay-as-bid settlement, and provision for |
2 | | selection of bids on the basis of price. |
3 | | (5) A plan for implementing contingencies in the
event |
4 | | of supplier default or failure of the feedstock procurement |
5 | | process to fully meet the expected feedstock requirement |
6 | | due to insufficient supplier participation, Commission |
7 | | rejection of results, or any other cause. The plan must be |
8 | | specific to the clean coal SNG brownfield facility's |
9 | | feedstock specifications and requirements. |
10 | | The feedstock procurement process described in this
|
11 | | subsection (d) is exempt from the requirements of the Illinois |
12 | | Procurement Code, pursuant to Section 20-10 of that Code. |
13 | | (e) Within 2 business days after opening the sealed bids, |
14 | | the feedstock procurement administrator shall submit a |
15 | | confidential report to the Commission. The report shall contain |
16 | | the results of the bidding for each of the feedstock types |
17 | | along with the feedstock procurement administrator's |
18 | | recommendation for the acceptance and rejection of bids based |
19 | | on the price benchmark criteria and other factors observed in |
20 | | the process. The feedstock procurement monitor also shall |
21 | | submit a confidential report to the Commission within 2 |
22 | | business days after opening the sealed bids. The report shall |
23 | | contain the feedstock procurement monitor's assessment of |
24 | | bidder behavior in the process, as well as an assessment of the |
25 | | feedstock procurement administrator's compliance with the |
26 | | feedstock procurement process and rules. The Commission shall |
|
| | 09600SB3388ham001 | - 30 - | LRB096 20594 ASK 44192 a |
|
|
1 | | review the confidential reports submitted by the feedstock |
2 | | procurement administrator and feedstock procurement monitor |
3 | | and shall accept or reject the recommendations of the feedstock |
4 | | procurement administrator within 2 business days after receipt |
5 | | of the reports. |
6 | | (f) Within 3 business days after the Commission decision |
7 | | approving the results of a feedstock procurement event, the |
8 | | clean coal SNG brownfield facility shall enter into binding |
9 | | contractual arrangements with the winning suppliers using |
10 | | standard form contracts. |
11 | | (g) The names of the successful bidders and the amount of |
12 | | feedstock to be delivered for each contract type and for each |
13 | | contract term shall be made available to the public at the time |
14 | | of Commission approval of a feedstock procurement event. The |
15 | | Commission, the procurement monitor, the feedstock procurement |
16 | | administrator, the Agency, and all participants in the |
17 | | feedstock procurement process shall maintain the |
18 | | confidentiality of all other supplier and bidding information |
19 | | in a manner consistent with all applicable laws, rules, |
20 | | regulations, and tariffs. Confidential information, including |
21 | | the confidential reports submitted by the feedstock |
22 | | procurement administrator and feedstock procurement monitor |
23 | | pursuant to subsection (e) of this Section, shall not be |
24 | | publicly available or discoverable by any party in any |
25 | | proceeding absent a compelling demonstration of need. The |
26 | | reports shall not be admissible in any proceeding other than |
|
| | 09600SB3388ham001 | - 31 - | LRB096 20594 ASK 44192 a |
|
|
1 | | one for law enforcement purposes. |
2 | | (h) Within 2 business days after a Commission decision |
3 | | approving the results of a feedstock procurement event or such |
4 | | other date as may be required by the Commission from time to |
5 | | time, the clean coal SNG brownfield facility shall file for |
6 | | informational purposes with the Commission its actual or |
7 | | estimated feedstock costs by utility customer reflecting the |
8 | | costs associated with the feedstock procurement. |
9 | | (i) The clean coal SNG brownfield facility shall pay for |
10 | | reasonable costs incurred by the Agency in administering the |
11 | | feedstock procurement events, which costs shall be included in |
12 | | the actual delivered fuel costs of the clean coal SNG |
13 | | brownfield facility. The Agency shall determine the amount owed |
14 | | for each feedstock procurement event, and the clean coal SNG |
15 | | brownfield facility shall pay that amount to the Agency within |
16 | | 30 days after being informed by the Agency of the amount owed. |
17 | | Those funds shall be deposited into the Illinois Power Agency |
18 | | Operations Fund, pursuant to Section 1-55 of this Act, to be |
19 | | used to reimburse expenses related to the feedstock |
20 | | procurement. |
21 | | (j) The Commission has the authority to adopt rules to |
22 | | carry out the provisions of this Section. For the public |
23 | | interest, safety, and welfare, the Commission also has the |
24 | | authority to adopt rules to carry out the provisions of this |
25 | | Section on an emergency basis. |
26 | | (k) On or before April 1 of each year, the Commission may |
|
| | 09600SB3388ham001 | - 32 - | LRB096 20594 ASK 44192 a |
|
|
1 | | hold an informal hearing for the purpose of receiving comments |
2 | | on the prior year's feedstock procurement process and any |
3 | | recommendations for change. |
4 | | Section 7. The Illinois Procurement Code is amended by |
5 | | changing Sections 1-10 and 20-10 as follows:
|
6 | | (30 ILCS 500/1-10)
|
7 | | Sec. 1-10. Application.
|
8 | | (a) This Code applies only to procurements for which |
9 | | contractors were first
solicited on or after July 1, 1998. This |
10 | | Code shall not be construed to affect
or impair any contract, |
11 | | or any provision of a contract, entered into based on a
|
12 | | solicitation prior to the implementation date of this Code as |
13 | | described in
Article 99, including but not limited to any |
14 | | covenant entered into with respect
to any revenue bonds or |
15 | | similar instruments.
All procurements for which contracts are |
16 | | solicited between the effective date
of Articles 50 and 99 and |
17 | | July 1, 1998 shall be substantially in accordance
with this |
18 | | Code and its intent.
|
19 | | (b) This Code shall apply regardless of the source of the |
20 | | funds with which
the contracts are paid, including federal |
21 | | assistance moneys.
This Code shall
not apply to:
|
22 | | (1) Contracts between the State and its political |
23 | | subdivisions or other
governments, or between State |
24 | | governmental bodies except as specifically
provided in |
|
| | 09600SB3388ham001 | - 33 - | LRB096 20594 ASK 44192 a |
|
|
1 | | this Code.
|
2 | | (2) Grants, except for the filing requirements of |
3 | | Section 20-80.
|
4 | | (3) Purchase of care.
|
5 | | (4) Hiring of an individual as employee and not as an |
6 | | independent
contractor, whether pursuant to an employment |
7 | | code or policy or by contract
directly with that |
8 | | individual.
|
9 | | (5) Collective bargaining contracts.
|
10 | | (6) Purchase of real estate, except that notice of this |
11 | | type of contract with a value of more than $25,000 must be |
12 | | published in the Procurement Bulletin within 7 days after |
13 | | the deed is recorded in the county of jurisdiction. The |
14 | | notice shall identify the real estate purchased, the names |
15 | | of all parties to the contract, the value of the contract, |
16 | | and the effective date of the contract.
|
17 | | (7) Contracts necessary to prepare for anticipated |
18 | | litigation, enforcement
actions, or investigations, |
19 | | provided
that the chief legal counsel to the Governor shall |
20 | | give his or her prior
approval when the procuring agency is |
21 | | one subject to the jurisdiction of the
Governor, and |
22 | | provided that the chief legal counsel of any other |
23 | | procuring
entity
subject to this Code shall give his or her |
24 | | prior approval when the procuring
entity is not one subject |
25 | | to the jurisdiction of the Governor.
|
26 | | (8) Contracts for
services to Northern Illinois |
|
| | 09600SB3388ham001 | - 34 - | LRB096 20594 ASK 44192 a |
|
|
1 | | University by a person, acting as
an independent |
2 | | contractor, who is qualified by education, experience, and
|
3 | | technical ability and is selected by negotiation for the |
4 | | purpose of providing
non-credit educational service |
5 | | activities or products by means of specialized
programs |
6 | | offered by the university.
|
7 | | (9) Procurement expenditures by the Illinois |
8 | | Conservation Foundation
when only private funds are used.
|
9 | | (10) Procurement expenditures by the Illinois Health |
10 | | Information Exchange Authority involving private funds |
11 | | from the Health Information Exchange Fund. "Private funds" |
12 | | means gifts, donations, and private grants. |
13 | | (c) This Code does not apply to the electric power |
14 | | procurement process provided for under Section 1-75 of the |
15 | | Illinois Power Agency Act and Section 16-111.5 of the Public |
16 | | Utilities Act. |
17 | | (d) Except for Section 20-160 and Article 50 of this Code, |
18 | | and as expressly required by Section 9.1 of the Illinois |
19 | | Lottery Law, the provisions of this Code do not apply to the |
20 | | procurement process provided for under Section 9.1 of the |
21 | | Illinois Lottery Law. |
22 | | (e) This Code does not apply to the process used by the |
23 | | Capital Development Board to retain a person or entity to |
24 | | assist the Capital Development Board with its duties related to |
25 | | the determination of costs of a clean coal SNG brownfield |
26 | | facility, as defined by Section 1-10 of the Illinois Power |
|
| | 09600SB3388ham001 | - 35 - | LRB096 20594 ASK 44192 a |
|
|
1 | | Agency Act, as required in subsection (h-3) of Section 9-220 of |
2 | | the Public Utilities Act, including calculating the range of |
3 | | capital costs, the range of operating and maintenance costs, or |
4 | | the sequestration costs or monitoring the construction of clean |
5 | | coal SNG brownfield facility for the full duration of |
6 | | construction. |
7 | | (f) This Code does not apply to the process used by the |
8 | | Illinois Power Agency to retain a mediator to mediate sourcing |
9 | | agreement disputes between gas utilities and the clean coal SNG |
10 | | brownfield facility, as defined in Section 1-10 of the Illinois |
11 | | Power Agency Act, as required under subsection (h-1) of Section |
12 | | 9-220 of the Public Utilities Act. |
13 | | (Source: P.A. 95-481, eff. 8-28-07; 95-615, eff. 9-11-07; |
14 | | 95-876, eff. 8-21-08; 96-840, eff. 12-23-09; 96-1331, eff. |
15 | | 7-27-10.)
|
16 | | (30 ILCS 500/20-10)
|
17 | | (Text of Section from P.A. 96-159 and 96-588) |
18 | | Sec. 20-10. Competitive sealed bidding; reverse auction.
|
19 | | (a) Conditions for use. All contracts shall be awarded by
|
20 | | competitive sealed bidding
except as otherwise provided in |
21 | | Section 20-5.
|
22 | | (b) Invitation for bids. An invitation for bids shall be
|
23 | | issued and shall include a
purchase description and the |
24 | | material contractual terms and
conditions applicable to the
|
25 | | procurement.
|
|
| | 09600SB3388ham001 | - 36 - | LRB096 20594 ASK 44192 a |
|
|
1 | | (c) Public notice. Public notice of the invitation for bids |
2 | | shall be
published in the Illinois Procurement Bulletin at |
3 | | least 14 days before the date
set in the invitation for the |
4 | | opening of bids.
|
5 | | (d) Bid opening. Bids shall be opened publicly in the
|
6 | | presence of one or more witnesses
at the time and place |
7 | | designated in the invitation for bids. The
name of each bidder, |
8 | | the amount
of each bid, and other relevant information as may |
9 | | be specified by
rule shall be
recorded. After the award of the |
10 | | contract, the winning bid and the
record of each unsuccessful |
11 | | bid shall be open to
public inspection.
|
12 | | (e) Bid acceptance and bid evaluation. Bids shall be
|
13 | | unconditionally accepted without
alteration or correction, |
14 | | except as authorized in this Code. Bids
shall be evaluated |
15 | | based on the
requirements set forth in the invitation for bids, |
16 | | which may
include criteria to determine
acceptability such as |
17 | | inspection, testing, quality, workmanship,
delivery, and |
18 | | suitability for a
particular purpose. Those criteria that will |
19 | | affect the bid price
and be considered in evaluation
for award, |
20 | | such as discounts, transportation costs, and total or
life |
21 | | cycle costs, shall be
objectively measurable. The invitation |
22 | | for bids shall set forth
the evaluation criteria to be used.
|
23 | | (f) Correction or withdrawal of bids. Correction or
|
24 | | withdrawal of inadvertently
erroneous bids before or after |
25 | | award, or cancellation of awards of
contracts based on bid
|
26 | | mistakes, shall be permitted in accordance with rules.
After |
|
| | 09600SB3388ham001 | - 37 - | LRB096 20594 ASK 44192 a |
|
|
1 | | bid opening, no
changes in bid prices or other provisions of |
2 | | bids prejudicial to
the interest of the State or fair
|
3 | | competition shall be permitted. All decisions to permit the
|
4 | | correction or withdrawal of bids
based on bid mistakes shall be |
5 | | supported by written determination
made by a State purchasing |
6 | | officer.
|
7 | | (g) Award. The contract shall be awarded with reasonable
|
8 | | promptness by written notice
to the lowest responsible and |
9 | | responsive bidder whose bid meets
the requirements and criteria
|
10 | | set forth in the invitation for bids, except when a State |
11 | | purchasing officer
determines it is not in the best interest of |
12 | | the State and by written
explanation determines another bidder |
13 | | shall receive the award. The explanation
shall appear in the |
14 | | appropriate volume of the Illinois Procurement Bulletin.
|
15 | | (h) Multi-step sealed bidding. When it is considered
|
16 | | impracticable to initially prepare
a purchase description to |
17 | | support an award based on price, an
invitation for bids may be |
18 | | issued
requesting the submission of unpriced offers to be |
19 | | followed by an
invitation for bids limited to
those bidders |
20 | | whose offers have been qualified under the criteria
set forth |
21 | | in the first solicitation.
|
22 | | (i) Alternative procedures. Notwithstanding any other |
23 | | provision of this Act to the contrary, the Director of the |
24 | | Illinois Power Agency may create alternative bidding |
25 | | procedures to be used in procuring professional services under |
26 | | subsection (a) of Section 1-75 and subsection (d) of Section |
|
| | 09600SB3388ham001 | - 38 - | LRB096 20594 ASK 44192 a |
|
|
1 | | 1-78 1-75(a) of the Illinois Power Agency Act and Section |
2 | | 16-111.5(c) of the Public Utilities Act and to procure |
3 | | renewable energy resources under Section 1-56 of the Illinois |
4 | | Power Agency Act. These alternative procedures shall be set |
5 | | forth together with the other criteria contained in the |
6 | | invitation for bids, and shall appear in the appropriate volume |
7 | | of the Illinois Procurement Bulletin.
|
8 | | (j) Reverse auction. Notwithstanding any other provision |
9 | | of this Section and in accordance with rules adopted by the |
10 | | Director of Central Management Services as chief procurement |
11 | | officer, a State purchasing officer under that chief |
12 | | procurement officer's jurisdiction may procure supplies or |
13 | | services through a competitive electronic auction bidding |
14 | | process after the purchasing officer explains in writing to the |
15 | | chief procurement officer his or her determination that the use |
16 | | of such a process will be in the best interest of the State. |
17 | | The chief procurement officer shall publish that determination |
18 | | in his or her next volume of the Illinois Procurement Bulletin. |
19 | | An invitation for bids shall be issued and shall include |
20 | | (i) a procurement description, (ii) all contractual terms, |
21 | | whenever practical, and (iii) conditions applicable to the |
22 | | procurement, including a notice that bids will be received in |
23 | | an electronic auction manner. |
24 | | Public notice of the invitation for bids shall be given in |
25 | | the same manner as provided in subsection (c). |
26 | | Bids shall be accepted electronically at the time and in |
|
| | 09600SB3388ham001 | - 39 - | LRB096 20594 ASK 44192 a |
|
|
1 | | the manner designated in the invitation for bids. During the |
2 | | auction, a bidder's price shall be disclosed to other bidders. |
3 | | Bidders shall have the opportunity to reduce their bid prices |
4 | | during the auction. At the conclusion of the auction, the |
5 | | record of the bid prices received and the name of each bidder |
6 | | shall be open to public inspection. |
7 | | After the auction period has terminated, withdrawal of bids |
8 | | shall be permitted as provided in subsection (f). |
9 | | The contract shall be awarded within 60 days after the |
10 | | auction by written notice to the lowest responsible bidder, or |
11 | | all bids shall be rejected except as otherwise provided in this |
12 | | Code. Extensions of the date for the award may be made by |
13 | | mutual written consent of the State purchasing officer and the |
14 | | lowest responsible bidder. |
15 | | This subsection does not apply to (i) procurements of |
16 | | professional and artistic services, including but not limited |
17 | | to telecommunications services, communications services, |
18 | | Internet services, and information services, and (ii) |
19 | | contracts for construction projects. |
20 | | (Source: P.A. 95-481, eff. 8-28-07; 96-159, eff. 8-10-09; |
21 | | 96-588, eff. 8-18-09; revised 10-5-10 .)
|
22 | | (Text of Section from P.A. 96-159 and 96-795)
|
23 | | Sec. 20-10. Competitive sealed bidding; reverse auction.
|
24 | | (a) Conditions for use. All contracts shall be awarded by
|
25 | | competitive sealed bidding
except as otherwise provided in |
|
| | 09600SB3388ham001 | - 40 - | LRB096 20594 ASK 44192 a |
|
|
1 | | Section 20-5.
|
2 | | (b) Invitation for bids. An invitation for bids shall be
|
3 | | issued and shall include a
purchase description and the |
4 | | material contractual terms and
conditions applicable to the
|
5 | | procurement.
|
6 | | (c) Public notice. Public notice of the invitation for bids |
7 | | shall be
published in the Illinois Procurement Bulletin at |
8 | | least 14 days before the date
set in the invitation for the |
9 | | opening of bids.
|
10 | | (d) Bid opening. Bids shall be opened publicly in the
|
11 | | presence of one or more witnesses
at the time and place |
12 | | designated in the invitation for bids. The
name of each bidder, |
13 | | the amount
of each bid, and other relevant information as may |
14 | | be specified by
rule shall be
recorded. After the award of the |
15 | | contract, the winning bid and the
record of each unsuccessful |
16 | | bid shall be open to
public inspection.
|
17 | | (e) Bid acceptance and bid evaluation. Bids shall be
|
18 | | unconditionally accepted without
alteration or correction, |
19 | | except as authorized in this Code. Bids
shall be evaluated |
20 | | based on the
requirements set forth in the invitation for bids, |
21 | | which may
include criteria to determine
acceptability such as |
22 | | inspection, testing, quality, workmanship,
delivery, and |
23 | | suitability for a
particular purpose. Those criteria that will |
24 | | affect the bid price
and be considered in evaluation
for award, |
25 | | such as discounts, transportation costs, and total or
life |
26 | | cycle costs, shall be
objectively measurable. The invitation |
|
| | 09600SB3388ham001 | - 41 - | LRB096 20594 ASK 44192 a |
|
|
1 | | for bids shall set forth
the evaluation criteria to be used.
|
2 | | (f) Correction or withdrawal of bids. Correction or
|
3 | | withdrawal of inadvertently
erroneous bids before or after |
4 | | award, or cancellation of awards of
contracts based on bid
|
5 | | mistakes, shall be permitted in accordance with rules.
After |
6 | | bid opening, no
changes in bid prices or other provisions of |
7 | | bids prejudicial to
the interest of the State or fair
|
8 | | competition shall be permitted. All decisions to permit the
|
9 | | correction or withdrawal of bids
based on bid mistakes shall be |
10 | | supported by written determination
made by a State purchasing |
11 | | officer.
|
12 | | (g) Award. The contract shall be awarded with reasonable
|
13 | | promptness by written notice
to the lowest responsible and |
14 | | responsive bidder whose bid meets
the requirements and criteria
|
15 | | set forth in the invitation for bids, except when a State |
16 | | purchasing officer
determines it is not in the best interest of |
17 | | the State and by written
explanation determines another bidder |
18 | | shall receive the award. The explanation
shall appear in the |
19 | | appropriate volume of the Illinois Procurement Bulletin. The |
20 | | written explanation must include:
|
21 | | (1) a description of the agency's needs; |
22 | | (2) a determination that the anticipated cost will be |
23 | | fair and reasonable; |
24 | | (3) a listing of all responsible and responsive |
25 | | bidders; and |
26 | | (4) the name of the bidder selected, pricing, and the |
|
| | 09600SB3388ham001 | - 42 - | LRB096 20594 ASK 44192 a |
|
|
1 | | reasons for selecting that bidder. |
2 | | Each chief procurement officer may adopt guidelines to |
3 | | implement the requirements of this subsection (g). |
4 | | The written explanation shall be filed with the Legislative |
5 | | Audit Commission and the Procurement Policy Board and be made |
6 | | available for inspection by the public within 30 days after the |
7 | | agency's decision to award the contract. |
8 | | (h) Multi-step sealed bidding. When it is considered
|
9 | | impracticable to initially prepare
a purchase description to |
10 | | support an award based on price, an
invitation for bids may be |
11 | | issued
requesting the submission of unpriced offers to be |
12 | | followed by an
invitation for bids limited to
those bidders |
13 | | whose offers have been qualified under the criteria
set forth |
14 | | in the first solicitation.
|
15 | | (i) Alternative procedures. Notwithstanding any other |
16 | | provision of this Act to the contrary, the Director of the |
17 | | Illinois Power Agency may create alternative bidding |
18 | | procedures to be used in procuring professional services under |
19 | | subsection (a) of Section 1-75 and subsection (d) of Section |
20 | | 1-78 1-75(a) of the Illinois Power Agency Act and Section |
21 | | 16-111.5(c) of the Public Utilities Act and to procure |
22 | | renewable energy resources under Section 1-56 of the Illinois |
23 | | Power Agency Act. These alternative procedures shall be set |
24 | | forth together with the other criteria contained in the |
25 | | invitation for bids, and shall appear in the appropriate volume |
26 | | of the Illinois Procurement Bulletin.
|
|
| | 09600SB3388ham001 | - 43 - | LRB096 20594 ASK 44192 a |
|
|
1 | | (j) Reverse auction. Notwithstanding any other provision |
2 | | of this Section and in accordance with rules adopted by the |
3 | | chief procurement officer, that chief procurement officer may |
4 | | procure supplies or services through a competitive electronic |
5 | | auction bidding process after the chief procurement officer |
6 | | determines that the use of such a process will be in the best |
7 | | interest of the State. The chief procurement officer shall |
8 | | publish that determination in his or her next volume of the |
9 | | Illinois Procurement Bulletin. |
10 | | An invitation for bids shall be issued and shall include |
11 | | (i) a procurement description, (ii) all contractual terms, |
12 | | whenever practical, and (iii) conditions applicable to the |
13 | | procurement, including a notice that bids will be received in |
14 | | an electronic auction manner. |
15 | | Public notice of the invitation for bids shall be given in |
16 | | the same manner as provided in subsection (c). |
17 | | Bids shall be accepted electronically at the time and in |
18 | | the manner designated in the invitation for bids. During the |
19 | | auction, a bidder's price shall be disclosed to other bidders. |
20 | | Bidders shall have the opportunity to reduce their bid prices |
21 | | during the auction. At the conclusion of the auction, the |
22 | | record of the bid prices received and the name of each bidder |
23 | | shall be open to public inspection. |
24 | | After the auction period has terminated, withdrawal of bids |
25 | | shall be permitted as provided in subsection (f). |
26 | | The contract shall be awarded within 60 days after the |
|
| | 09600SB3388ham001 | - 44 - | LRB096 20594 ASK 44192 a |
|
|
1 | | auction by written notice to the lowest responsible bidder, or |
2 | | all bids shall be rejected except as otherwise provided in this |
3 | | Code. Extensions of the date for the award may be made by |
4 | | mutual written consent of the State purchasing officer and the |
5 | | lowest responsible bidder. |
6 | | This subsection does not apply to (i) procurements of |
7 | | professional and artistic services, (ii) telecommunications |
8 | | services, communication services, and information services,
|
9 | | and (iii) contracts for construction projects. |
10 | | (Source: P.A. 95-481, eff. 8-28-07; 96-159, eff. 8-10-09; |
11 | | 96-795, eff. 7-1-10 (see Section 5 of P.A. 96-793 for the |
12 | | effective date of changes made by P.A. 96-795); revised |
13 | | 10-5-10 .) |
14 | | Section 10. The Public Utilities Act is amended by changing |
15 | | Sections 3-101 and 9-220 and by adding Section 3-123 as |
16 | | follows:
|
17 | | (220 ILCS 5/3-101) (from Ch. 111 2/3, par. 3-101)
|
18 | | Sec. 3-101. Definitions. Unless otherwise specified, the |
19 | | terms set forth
in Sections 3-102 through 3-123 3-121 are used |
20 | | in this Act as therein defined.
|
21 | | (Source: P.A. 84-617; 84-1118.)
|
22 | | (220 ILCS 5/3-123 new) |
23 | | Sec. 3-123. Clean coal SNG brownfield facility; sequester; |
|
| | 09600SB3388ham001 | - 45 - | LRB096 20594 ASK 44192 a |
|
|
1 | | SNG facility; sourcing agreement; substitute natural gas or |
2 | | SNG. As used in this Act: |
3 | | "Clean coal SNG brownfield facility" shall have the same |
4 | | meaning as provided in Section 1-10 of the Illinois Power |
5 | | Agency Act. |
6 | | "Sequester" shall have the same meaning as provided in |
7 | | Section 1-10 of the Illinois Power Agency Act. |
8 | | "SNG facility" means a facility that produces substitute |
9 | | natural gas from feedstock that includes coal through a |
10 | | gasification process, including a clean coal facility, the |
11 | | clean coal SNG brownfield facility, and the facility described |
12 | | in subsection (h) of Section 9-220 of this Act. |
13 | | "Sourcing agreement" means an agreement between the owner |
14 | | of a clean coal SNG brownfield facility and the gas utility |
15 | | that has the terms and conditions meeting the requirements of |
16 | | subsection (h-1) of Section 9-220 of this Act. |
17 | | "Substitute natural gas" or "SNG" shall have the same |
18 | | meaning as provided in Section 1-10 of the Illinois Power |
19 | | Agency Act. |
20 | | (220 ILCS 5/9-220) (from Ch. 111 2/3, par. 9-220) |
21 | | Sec. 9-220. Rate changes based on changes in fuel costs. |
22 | | (a) Notwithstanding the provisions of Section 9-201, the
|
23 | | Commission may authorize the increase or decrease of rates and |
24 | | charges
based upon changes in the cost of fuel used in the |
25 | | generation or production
of electric power, changes in the cost |
|
| | 09600SB3388ham001 | - 46 - | LRB096 20594 ASK 44192 a |
|
|
1 | | of purchased power, or changes in
the cost of purchased gas |
2 | | through the application of fuel adjustment
clauses or purchased |
3 | | gas adjustment clauses. The Commission may also
authorize the |
4 | | increase or decrease of rates and charges based upon |
5 | | expenditures
or revenues resulting from the purchase or sale of |
6 | | emission allowances created
under the federal Clean Air Act |
7 | | Amendments of 1990,
through such fuel adjustment clauses, as a |
8 | | cost of fuel. For the purposes of
this paragraph, cost of fuel |
9 | | used in the generation or production of electric
power shall |
10 | | include the amount of any fees paid by the utility for the
|
11 | | implementation and operation of a process for the |
12 | | desulfurization of the
flue gas when burning high sulfur coal |
13 | | at any location within the State of
Illinois irrespective of |
14 | | the attainment status designation of such
location; but shall |
15 | | not include transportation costs
of coal
(i) except to the |
16 | | extent that for contracts entered into on
and after the |
17 | | effective date of this amendatory Act of 1997,
the cost of the |
18 | | coal, including transportation costs,
constitutes the lowest |
19 | | cost for adequate and reliable fuel
supply reasonably available |
20 | | to the public utility in
comparison to the cost, including |
21 | | transportation costs, of
other adequate and reliable sources of |
22 | | fuel supply reasonably
available to the public utility, or (ii)
|
23 | | except as otherwise provided in the next 3 sentences of this |
24 | | paragraph.
Such costs of fuel
shall, when requested by a |
25 | | utility or at the conclusion of the utility's
next general |
26 | | electric rate proceeding, whichever shall first occur, include
|
|
| | 09600SB3388ham001 | - 47 - | LRB096 20594 ASK 44192 a |
|
|
1 | | transportation costs of coal purchased under existing coal |
2 | | purchase
contracts. For purposes of this paragraph "existing |
3 | | coal purchase
contracts" means contracts for the purchase of |
4 | | coal in effect on the
effective date of this amendatory Act of |
5 | | 1991, as such contracts may
thereafter be amended, but only to |
6 | | the extent that any such amendment does
not increase the |
7 | | aggregate quantity of coal to be purchased under such
contract.
|
8 | | Nothing herein shall authorize an electric utility
to recover |
9 | | through its fuel adjustment clause any amounts of
|
10 | | transportation costs of coal that were included in the revenue
|
11 | | requirement used to set base rates in its most recent general
|
12 | | rate proceeding.
Cost shall be based upon uniformly applied |
13 | | accounting
principles. Annually, the Commission shall initiate |
14 | | public hearings to
determine whether the clauses reflect actual |
15 | | costs of fuel, gas, power, or
coal transportation purchased to |
16 | | determine whether such purchases were
prudent, and to reconcile |
17 | | any amounts collected with the actual costs of
fuel, power, |
18 | | gas, or coal transportation prudently purchased. In each such
|
19 | | proceeding, the burden of proof shall be upon the utility to |
20 | | establish the
prudence of its cost of fuel, power, gas, or coal
|
21 | | transportation purchases
and costs.
The Commission shall
issue |
22 | | its final order in each such annual proceeding for an
electric |
23 | | utility by December 31 of the year immediately
following the |
24 | | year to which the proceeding pertains, provided,
that the |
25 | | Commission shall issue its final order with respect
to such |
26 | | annual proceeding for the years 1996 and earlier by December |
|
| | 09600SB3388ham001 | - 48 - | LRB096 20594 ASK 44192 a |
|
|
1 | | 31, 1998. |
2 | | (b) A public utility providing electric service, other than |
3 | | a public utility
described in subsections (e) or (f) of this |
4 | | Section, may at
any time during the mandatory transition period |
5 | | file with the
Commission proposed tariff sheets that eliminate |
6 | | the public
utility's fuel adjustment clause and adjust the |
7 | | public
utility's base rate tariffs by the amount necessary for |
8 | | the
base fuel component of the base rates to recover the public
|
9 | | utility's average fuel and power supply costs per kilowatt-hour |
10 | | for the 2
most recent years for which the Commission
has issued |
11 | | final orders in annual proceedings pursuant to
subsection (a), |
12 | | where the average fuel and power supply costs
per kilowatt-hour |
13 | | shall be calculated as the sum of the public
utility's prudent |
14 | | and allowable fuel and power supply costs as
found by the |
15 | | Commission in the 2 proceedings divided by the
public utility's |
16 | | actual jurisdictional kilowatt-hour sales for
those 2 years. |
17 | | Notwithstanding any contrary or inconsistent
provisions in |
18 | | Section 9-201 of this Act, in subsection (a) of
this Section or |
19 | | in any rules or regulations promulgated by the
Commission |
20 | | pursuant to subsection (g) of this Section, the
Commission |
21 | | shall review and shall by order approve, or approve
as |
22 | | modified, the proposed tariff sheets within 60 days after
the |
23 | | date of the public utility's filing. The Commission may
modify |
24 | | the public utility's proposed tariff sheets only to the
extent |
25 | | the Commission finds necessary to achieve conformance
to the |
26 | | requirements of this subsection (b). During the 5
years |
|
| | 09600SB3388ham001 | - 49 - | LRB096 20594 ASK 44192 a |
|
|
1 | | following the date of the Commission's order, but in any
event |
2 | | no earlier than January 1, 2007, a public utility whose
fuel |
3 | | adjustment clause has been eliminated pursuant to this
|
4 | | subsection shall not file proposed tariff sheets seeking, or
|
5 | | otherwise petition the Commission for, reinstatement of a fuel
|
6 | | adjustment clause. |
7 | | (c) Notwithstanding any contrary or inconsistent
|
8 | | provisions in Section 9-201 of this Act, in subsection (a) of
|
9 | | this Section or in any rules or regulations promulgated by the
|
10 | | Commission pursuant to subsection (g) of this Section, a
public |
11 | | utility providing electric service, other than a public utility
|
12 | | described
in subsection (e) or (f) of this Section, may at any |
13 | | time
during the mandatory transition period file with the
|
14 | | Commission proposed tariff sheets that establish the rate per
|
15 | | kilowatt-hour to be applied pursuant to the public utility's
|
16 | | fuel adjustment clause at the average value for such rate
|
17 | | during the preceding 24 months, provided that such average
rate |
18 | | results in a credit to customers' bills, without making
any |
19 | | revisions to the public utility's base rate tariffs. The
|
20 | | proposed tariff sheets shall establish the fuel adjustment
rate |
21 | | for a specific time period of at least 3 years but not
more |
22 | | than 5 years, provided that the terms and conditions for
any |
23 | | reinstatement earlier than 5 years shall be set forth in
the |
24 | | proposed tariff sheets and subject to modification or
approval |
25 | | by the Commission. The Commission shall review and
shall by |
26 | | order approve the proposed tariff sheets if it finds
that the |
|
| | 09600SB3388ham001 | - 50 - | LRB096 20594 ASK 44192 a |
|
|
1 | | requirements of this subsection are met. The
Commission shall |
2 | | not conduct the annual hearings specified in the
last 3 |
3 | | sentences of subsection (a) of this Section for the
utility for |
4 | | the period that the factor established pursuant to
this |
5 | | subsection is in effect. |
6 | | (d) A public utility providing electric service, or a |
7 | | public utility
providing gas service
may file with the |
8 | | Commission proposed tariff sheets that
eliminate the public |
9 | | utility's fuel or purchased gas
adjustment clause and adjust |
10 | | the public utility's base rate
tariffs to provide for recovery |
11 | | of power supply costs or gas
supply costs that would have been |
12 | | recovered through such
clause; provided, that the provisions of |
13 | | this subsection (d) shall not be
available to a public utility |
14 | | described in subsections (e) or (f) of this
Section to |
15 | | eliminate its fuel adjustment clause. Notwithstanding any |
16 | | contrary
or inconsistent
provisions in Section 9-201 of this |
17 | | Act, in subsection (a) of
this Section, or in any rules or |
18 | | regulations promulgated by
the Commission pursuant to |
19 | | subsection (g) of this Section, the
Commission shall review and |
20 | | shall by order approve, or approve
as modified in the |
21 | | Commission's order, the proposed tariff
sheets within 240 days |
22 | | after the date of the public utility's
filing. The Commission's |
23 | | order shall approve rates and
charges that the Commission, |
24 | | based on information in the
public utility's filing or on the |
25 | | record if a hearing is held
by the Commission, finds will |
26 | | recover the reasonable, prudent
and necessary jurisdictional |
|
| | 09600SB3388ham001 | - 51 - | LRB096 20594 ASK 44192 a |
|
|
1 | | power supply costs or gas supply
costs incurred or to be |
2 | | incurred by the public utility during
a 12 month period found |
3 | | by the Commission to be appropriate
for these purposes, |
4 | | provided, that such period shall be either
(i) a 12 month |
5 | | historical period occurring during the 15
months ending on the |
6 | | date of the public utility's filing, or
(ii) a 12 month future |
7 | | period ending no later than 15 months
following the date of the |
8 | | public utility's filing. The public
utility shall include with |
9 | | its tariff filing information
showing both (1) its actual |
10 | | jurisdictional power supply costs
or gas supply costs for a 12 |
11 | | month historical period
conforming to (i) above and (2) its |
12 | | projected jurisdictional
power supply costs or gas supply costs |
13 | | for a future 12 month
period conforming to (ii) above. If the |
14 | | Commission's order
requires modifications in the tariff sheets |
15 | | filed by the
public utility, the public utility shall have 7 |
16 | | days following
the date of the order to notify the Commission |
17 | | whether the
public utility will implement the modified tariffs |
18 | | or elect to
continue its fuel or purchased gas adjustment |
19 | | clause in force
as though no order had been entered. The |
20 | | Commission's order
shall provide for any reconciliation of |
21 | | power supply costs or
gas supply costs, as the case may be, and |
22 | | associated revenues
through the date that the public utility's |
23 | | fuel or purchased
gas adjustment clause is eliminated. During |
24 | | the 5 years
following the date of the Commission's order, a |
25 | | public utility
whose fuel or purchased gas adjustment clause |
26 | | has been
eliminated pursuant to this subsection shall not file |
|
| | 09600SB3388ham001 | - 52 - | LRB096 20594 ASK 44192 a |
|
|
1 | | proposed
tariff sheets seeking, or otherwise petition the |
2 | | Commission
for, reinstatement or adoption of a fuel or |
3 | | purchased gas
adjustment clause. Nothing in this subsection (d) |
4 | | shall be
construed as limiting the Commission's authority to |
5 | | eliminate
a public utility's fuel adjustment clause or |
6 | | purchased gas
adjustment clause in accordance with any other |
7 | | applicable
provisions of this Act. |
8 | | (e) Notwithstanding any contrary or inconsistent |
9 | | provisions in
Section 9-201 of this Act, in subsection (a) of |
10 | | this Section, or in
any rules promulgated by the Commission |
11 | | pursuant
to subsection (g) of this Section, a public utility |
12 | | providing
electric service to more than 1,000,000 customers in |
13 | | this State may, within the
first 6 months after the
effective |
14 | | date of this amendatory Act of 1997, file with the
Commission |
15 | | proposed tariff sheets that eliminate, effective
January 1, |
16 | | 1997, the public utility's fuel adjustment clause
without |
17 | | adjusting its base rates, and such tariff sheets shall be
|
18 | | effective upon filing. To the extent the application of the |
19 | | fuel
adjustment clause had resulted in net charges to customers |
20 | | after
January 1, 1997, the utility shall also file a tariff |
21 | | sheet that
provides for a refund stated on a per kilowatt-hour |
22 | | basis of such
charges over a period not to exceed 6 months; |
23 | | provided
however, that such refund shall not include the |
24 | | proportional
amounts of taxes paid under the Use Tax Act, |
25 | | Service Use Tax Act,
Service Occupation Tax Act, and Retailers' |
26 | | Occupation Tax Act on
fuel used in generation. The Commission |
|
| | 09600SB3388ham001 | - 53 - | LRB096 20594 ASK 44192 a |
|
|
1 | | shall issue an order
within 45 days after the date of the |
2 | | public utility's filing
approving or approving as modified such |
3 | | tariff sheet. If the fuel
adjustment clause is eliminated |
4 | | pursuant to this subsection, the
Commission shall not conduct |
5 | | the annual hearings specified in the
last 3 sentences of |
6 | | subsection (a) of this Section for the
utility for any period |
7 | | after December 31, 1996 and prior to any
reinstatement of such |
8 | | clause. A public utility whose fuel
adjustment clause has been |
9 | | eliminated pursuant to this subsection
shall not file a |
10 | | proposed tariff sheet seeking, or otherwise
petition the |
11 | | Commission for, reinstatement of the fuel adjustment
clause |
12 | | prior to January 1, 2007. |
13 | | (f) Notwithstanding any contrary or inconsistent |
14 | | provisions in Section
9-201 of this Act, in subsection (a) of |
15 | | this Section, or in any rules or
regulations promulgated by the |
16 | | Commission pursuant to subsection (g) of this
Section, a public |
17 | | utility providing electric service to more than 500,000
|
18 | | customers but fewer than 1,000,000 customers in this State may, |
19 | | within the
first
6 months after the effective date of this |
20 | | amendatory Act of 1997, file with the
Commission proposed |
21 | | tariff sheets that eliminate, effective January 1, 1997,
the |
22 | | public utility's fuel adjustment clause and adjust its base |
23 | | rates by the
amount necessary for the base fuel component of |
24 | | the base rates to recover
91% of the public utility's average |
25 | | fuel and power supply costs for the 2 most
recent years for |
26 | | which the Commission, as of January 1, 1997, has issued final
|
|
| | 09600SB3388ham001 | - 54 - | LRB096 20594 ASK 44192 a |
|
|
1 | | orders in annual proceedings pursuant to subsection (a), where |
2 | | the average fuel
and power supply costs per kilowatt-hour shall |
3 | | be calculated as the sum of the
public utility's prudent and |
4 | | allowable fuel and power supply costs as found by
the |
5 | | Commission in the 2 proceedings divided by the public utility's |
6 | | actual
jurisdictional kilowatt-hour sales for those 2 years, |
7 | | provided, that such
tariff sheets shall be effective upon |
8 | | filing. To the extent the application of
the fuel adjustment |
9 | | clause had resulted in net charges to customers after
January |
10 | | 1, 1997, the utility shall also file a tariff sheet that |
11 | | provides for a
refund stated on a per kilowatt-hour basis of |
12 | | such charges over a period not to
exceed 6 months. Provided |
13 | | however, that such refund shall not include the
proportional |
14 | | amounts of taxes paid under the Use Tax Act, Service Use Tax |
15 | | Act,
Service Occupation Tax Act, and Retailers' Occupation Tax |
16 | | Act on fuel used in
generation. The Commission shall issue an |
17 | | order within 45 days after the date
of the public utility's |
18 | | filing approving or approving as modified such tariff
sheet. If |
19 | | the fuel adjustment clause is eliminated pursuant to this
|
20 | | subsection, the Commission shall not conduct the annual |
21 | | hearings specified in
the last 3 sentences of subsection (a) of |
22 | | this Section for the utility for any
period after December 31, |
23 | | 1996 and prior to any reinstatement of such clause.
A public |
24 | | utility whose fuel adjustment clause has been eliminated |
25 | | pursuant to
this subsection shall not file a proposed tariff |
26 | | sheet seeking, or otherwise
petition the Commission for, |
|
| | 09600SB3388ham001 | - 55 - | LRB096 20594 ASK 44192 a |
|
|
1 | | reinstatement of the fuel adjustment clause prior
to January 1, |
2 | | 2007. |
3 | | (g) The Commission shall have authority to promulgate rules |
4 | | and
regulations to
carry out the provisions of this Section. |
5 | | (h) Any Illinois gas utility may enter into a contract on |
6 | | or before March 31, 2011 for up to 10 years of supply with any |
7 | | company for the purchase of substitute natural gas (SNG) |
8 | | produced from coal through the gasification process if the |
9 | | company has commenced construction of a coal gasification |
10 | | facility by July 1, 2012 in Jefferson County and commencement |
11 | | of construction shall mean that material physical site work has |
12 | | occurred, such as site clearing and excavation, water runoff |
13 | | prevention, water retention reservoir preparation, or |
14 | | foundation development. The contract shall contain the |
15 | | following provisions: (i) the only coal to be used in the |
16 | | gasification process has high volatile bituminous rank and |
17 | | greater than 1.7 pounds of sulfur per million Btu content; (ii) |
18 | | at the time the contract term commences, the price per million |
19 | | Btu may not exceed $7.95 in 2008 dollars, adjusted annually |
20 | | based on the change in the Annual Consumer Price Index for All |
21 | | Urban Consumers for the Midwest Region as published in April by |
22 | | the United States Department of Labor, Bureau of Labor |
23 | | Statistics (or a suitable Consumer Price Index calculation if |
24 | | this Consumer Price Index is not available) for the previous |
25 | | calendar year; provided that the price per million Btu shall |
26 | | not exceed $9.95 at any time during the contract; (iii) the |
|
| | 09600SB3388ham001 | - 56 - | LRB096 20594 ASK 44192 a |
|
|
1 | | utility's aggregate long-term supply contracts for the |
2 | | purchase of SNG does not exceed 25% of the annual system supply |
3 | | requirements of the utility as of 2008 and the quantity of SNG |
4 | | supplied to a utility may not exceed 16 million MMBtus; and |
5 | | (iv) contract costs pursuant to subsection (h-10) of this |
6 | | Section shall not include any lobbying expenses, charitable |
7 | | contributions, advertising, organizational memberships, or |
8 | | marketing expenses per year. |
9 | | (h-1) Any Illinois gas utility may enter into a sourcing |
10 | | agreement for up to 30 years of supply with the clean coal SNG |
11 | | brownfield facility if the clean coal SNG brownfield facility |
12 | | has commenced construction. Any gas utility that is providing |
13 | | service to more than 150,000 customers on the effective date of |
14 | | this amendatory Act of the 96th General Assembly shall either |
15 | | elect to file biennial rate proceedings before the Commission |
16 | | in the years 2011, 2013, and 2015 or enter into a sourcing |
17 | | agreement or sourcing agreements with a clean coal SNG |
18 | | brownfield facility for 30 years for either (i) 43,500,000,000 |
19 | | cubic feet per year times a percentage calculated by dividing |
20 | | 100 by the number of utilities entering into sourcing |
21 | | agreements with the clean coal SNG brownfield facility or (ii) |
22 | | such lesser amount as may be available from the clean coal SNG |
23 | | brownfield facility. |
24 | | Provided, however, that the Illinois Power Agency may |
25 | | allocate the purchase obligations more proportionately based |
26 | | upon total therms sold to ultimate customers, if it is |
|
| | 09600SB3388ham001 | - 57 - | LRB096 20594 ASK 44192 a |
|
|
1 | | demonstrated with certainty that such alternative allocation |
2 | | will not result in adverse consolidation, derivative, or lease |
3 | | impacts to the balance sheet or income statement of any |
4 | | purchasing utility. In any event, no utility shall be required |
5 | | to purchase more than 42% of the projected annual output of the |
6 | | clean coal SNG brownfield facility, with the remainder of such |
7 | | utility's obligation to be divided proportionately between the |
8 | | other utilities. |
9 | | A gas utility electing to file biennial rate proceedings |
10 | | before the Commission must file a notice of its election with |
11 | | the Commission within 60 days after the effective date of this |
12 | | amendatory Act of the 96th General Assembly or its right to |
13 | | make the election is irrevocably waived. A gas utility electing |
14 | | to file biennial rate proceedings shall make such filings no |
15 | | later than August 1 of the years 2011, 2013, and 2015, |
16 | | consistent with all requirements of 83 Ill. Adm. Code 255 and |
17 | | 285 as though the gas utility were filing for an increase in |
18 | | its rates, without regard to whether such filing would produce |
19 | | an increase, a decrease, or no change in the gas utility's |
20 | | rates, and the Commission shall review the gas utility's filing |
21 | | and shall issue its order in accordance with the provisions of |
22 | | Section 9-201 of this Act. |
23 | | Within 15 days after the effective date of this amendatory |
24 | | Act of the 96th General Assembly, the owner of the clean coal |
25 | | SNG brownfield facility shall submit to the Illinois Power |
26 | | Agency and each gas utility that is providing service to more |
|
| | 09600SB3388ham001 | - 58 - | LRB096 20594 ASK 44192 a |
|
|
1 | | than 150,000 customers on the effective date of this amendatory |
2 | | Act of the 96th General Assembly a copy of a draft sourcing |
3 | | agreement. Within 45 days after receipt of the draft sourcing |
4 | | agreement, each such gas utility shall provide the Illinois |
5 | | Power Agency and the owner of a clean coal SNG brownfield |
6 | | facility with its comments and recommended revisions to the |
7 | | draft sourcing agreement. Within 15 days after the receipt of |
8 | | the gas utility's comments and recommended revisions, the owner |
9 | | of the clean coal SNG brownfield facility shall submit its |
10 | | responsive comments and a further revised draft of the sourcing |
11 | | agreement to the Illinois Power Agency. The Illinois Power |
12 | | Agency shall review the draft sourcing agreement and comments. |
13 | | If the parties to the sourcing agreement do not agree on |
14 | | the terms therein, then the Illinois Power Agency shall retain |
15 | | an independent mediator to mediate the dispute between the |
16 | | parties. If the parties are in agreement on the terms of the |
17 | | sourcing agreement, the Illinois Power Agency shall approve the |
18 | | final draft sourcing agreement. If after mediation the parties |
19 | | have failed to come to agreement, then the Illinois Power |
20 | | Agency shall revise the draft sourcing agreement as necessary |
21 | | to confirm that the final draft sourcing agreement contains |
22 | | only terms that are reasonable and equitable. The Illinois |
23 | | Power Agency shall adopt and make public a policy detailing the |
24 | | process for retaining a mediator under this subsection (h-1). |
25 | | Any mediator retained to assist with calculating the range of |
26 | | capital costs or operations and maintenance costs shall be |
|
| | 09600SB3388ham001 | - 59 - | LRB096 20594 ASK 44192 a |
|
|
1 | | retained no later than 90 days after the effective date of this |
2 | | amendatory Act of the 96th General Assembly. |
3 | | Upon approval of a final draft agreement, the Illinois |
4 | | Power Agency shall submit the final draft agreement to the |
5 | | Capital Development Board and the Commission no later than 90 |
6 | | days after the effective date of this amendatory Act of the |
7 | | 96th General Assembly. The gas utility and the clean coal SNG |
8 | | brownfield facility shall pay a reasonable fee as required by |
9 | | the Illinois Power Agency for its services under this |
10 | | subsection (h-1) and shall pay the mediator's reasonable fees, |
11 | | if any. The Illinois Power Agency shall adopt and make public a |
12 | | policy detailing the process for retaining a mediator under |
13 | | this Section. |
14 | | The sourcing agreement between a gas utility and the clean |
15 | | coal SNG brownfield facility shall contain the following |
16 | | provisions: |
17 | | (1) Any and all coal used in the gasification process |
18 | | must be coal that has high volatile bituminous rank and |
19 | | greater than 1.7 pounds of sulfur per million Btu content. |
20 | | (2) Coal and petroleum coke are feedstocks for the |
21 | | gasification process, with coal comprising at least 50% of |
22 | | the total feedstock over the term of the sourcing agreement |
23 | | and with the feedstocks to be procured in accordance with |
24 | | requirements of Section 1-78 of the Illinois Power Agency |
25 | | Act. |
26 | | (3) The sourcing agreement once entered into |
|
| | 09600SB3388ham001 | - 60 - | LRB096 20594 ASK 44192 a |
|
|
1 | | terminates no more than 30 years after the commencement of |
2 | | the commercial production of SNG at the clean coal SNG |
3 | | brownfield facility. |
4 | | (4) The clean coal SNG brownfield facility guarantees a |
5 | | minimum of $100,000,000 in consumer savings, calculated in |
6 | | real 2010 dollars at the conclusion of the term of the |
7 | | sourcing agreement by comparing the delivered SNG price to |
8 | | the Chicago City-gate price on a weighted daily basis for |
9 | | each day over the entire term of the sourcing agreement, to |
10 | | be provided in accordance with subsection (h-2) of this |
11 | | Section. |
12 | | (5) Prior to the clean coal SNG brownfield facility |
13 | | issuing a notice to proceed to construction, the clean coal |
14 | | SNG brownfield facility shall establish a consumer |
15 | | protection reserve account for the benefit of the customers |
16 | | of the utilities that have entered into sourcing agreements |
17 | | with the clean coal SNG brownfield facility pursuant to |
18 | | this subsection (h-1), with cash principal in the amount of |
19 | | $150,000,000. This cash principal shall only be |
20 | | recoverable through the consumer protection reserve |
21 | | account and not as a cost to be recovered in the delivered |
22 | | SNG price pursuant to subsection (h-3) of this Section. The |
23 | | consumer protection reserve account shall be maintained |
24 | | and administered by an independent trustee that is mutually |
25 | | agreed upon by the clean coal SNG brownfield facility, the |
26 | | utilities, and the Commission in an interest-bearing |
|
| | 09600SB3388ham001 | - 61 - | LRB096 20594 ASK 44192 a |
|
|
1 | | account in accordance with subsection (h-2) of this |
2 | | Section. |
3 | | (6) The clean coal SNG brownfield facility shall |
4 | | identify and sell economically viable by-products produced |
5 | | by the facility. |
6 | | (7) 50% of all additional net revenue, defined as |
7 | | miscellaneous net revenue after cost allowance for costs |
8 | | associated with additional net revenue that are not |
9 | | otherwise recoverable pursuant to subsection (h-3) of this |
10 | | Section, including net revenue from sales of substitute |
11 | | natural gas derived from the facility above the nameplate |
12 | | capacity of the facility and other by-products produced by |
13 | | the facility, shall be credited to the consumer protection |
14 | | reserve account pursuant to subsection (h-2) of this |
15 | | Section. |
16 | | (8) The delivered SNG price per million btu to be paid |
17 | | monthly by the utility to the clean coal SNG brownfield |
18 | | facility, which shall be based only upon the following: (A) |
19 | | a capital recovery charge, operations and maintenance |
20 | | costs, and sequestration costs, only to the extent approved |
21 | | by the Commission pursuant to paragraphs (1), (2), and (3) |
22 | | of subsection (h-3) of this Section; (B) the actual |
23 | | delivered and processed fuel costs pursuant to paragraph |
24 | | (4) of subsection (h-3) of this Section; (C) actual costs |
25 | | of SNG transportation pursuant to paragraph (6) of |
26 | | subsection (h-3) of this Section; (D) certain taxes and |
|
| | 09600SB3388ham001 | - 62 - | LRB096 20594 ASK 44192 a |
|
|
1 | | fees imposed by the federal government, the State, or any |
2 | | unit of local government as provided in paragraph (6) of |
3 | | subsection (h-3) of this Section; and (E) the credit, if |
4 | | any, from the consumer protection reserve account pursuant |
5 | | to subsection (h-2) of this Section. The delivered SNG |
6 | | price per million Btu shall proportionately reflect these |
7 | | elements over the term of the sourcing agreement. |
8 | | (9) A formula to translate the recoverable costs and |
9 | | charges under subsection (h-3) of this Section into the |
10 | | delivered SNG price per million btu. |
11 | | (10) Title to the SNG shall pass at a |
12 | | mutually-agreeable point in Illinois, and may provide |
13 | | that, rather than the utility taking title to the SNG, a |
14 | | mutually-agreed upon third-party gas marketer pursuant to |
15 | | a contract approved by the Illinois Power Agency or its |
16 | | designee, may take title to the SNG pursuant to an |
17 | | agreement between the utility, the owner of the clean coal |
18 | | SNG brownfield facility, and the third-party gas marketer. |
19 | | (11) A utility may exit the sourcing agreement without |
20 | | penalty if the clean coal SNG brownfield facility does not |
21 | | commence construction by July 1, 2014. |
22 | | (12) A utility is responsible to pay only the |
23 | | Commission determined unit price cost of SNG that is |
24 | | purchased by the utility. Nothing in the sourcing agreement |
25 | | will obligate a utility to invest capital in a clean coal |
26 | | SNG brownfield facility. |
|
| | 09600SB3388ham001 | - 63 - | LRB096 20594 ASK 44192 a |
|
|
1 | | (13) The quality of SNG must, at a minimum, be |
2 | | equivalent to the equality required for an interstate |
3 | | pipeline gas before a utility is required to accept and pay |
4 | | for SNG gas. |
5 | | (14) Nothing in the sourcing agreement will require a |
6 | | utility to construct any facilities to accept delivery of |
7 | | SNG. Provided, however, if a utility is required by law or |
8 | | otherwise elects to connect the clean coal SNG brownfield |
9 | | facility to an interstate pipeline, then the utility shall |
10 | | be entitled to recover pursuant to its tariffs all just and |
11 | | reasonable costs that are prudently incurred. Any costs |
12 | | incurred by the utility to receive, deliver, manage, or |
13 | | otherwise accommodate purchases under the SNG sourcing |
14 | | agreement will be fully recoverable through a utility's |
15 | | purchased gas adjustment clause rider mechanism. |
16 | | (15) Remedies for the clean coal SNG brownfield |
17 | | facility's failure to deliver a designated amount for a |
18 | | designated period. |
19 | | For the purposes of this subsection (h-1), in any given |
20 | | year, the net increase in the prices paid in connection with |
21 | | gas service by residential customers due to the costs of the |
22 | | SNG purchased pursuant to a sourcing agreement under this |
23 | | subsection (h-1) shall be limited to: |
24 | | (A) in 2010, no more than 0.5% of the amount paid per |
25 | | million Btu by those customers during the year ending May |
26 | | 31, 2009; |
|
| | 09600SB3388ham001 | - 64 - | LRB096 20594 ASK 44192 a |
|
|
1 | | (B) in 2011, the greater of an additional 0.5% of the |
2 | | amount paid per million btu by those customers during the |
3 | | year ending May 31, 2010 or 1% of the amount paid per |
4 | | million btu by those customers during the year ending May |
5 | | 31, 2009; |
6 | | (C) in 2012, the greater of an additional 0.5% of the |
7 | | amount paid per million btu by those customers during the |
8 | | year ending May 31, 2011 or 1.5% of the amount paid per |
9 | | million btu during the year ending May 31, 2009; |
10 | | (D) in 2013, the greater of an additional 0.5% of the |
11 | | amount paid per million btu by those customers during the |
12 | | year ending May 2012 or 2% of the amount paid per million |
13 | | btu by those customers during the year ending May 31, 2009; |
14 | | and |
15 | | (E) thereafter, the estimated average net increase due |
16 | | to the cost of these resources included in the amounts paid |
17 | | by residential customers in connection with gas service |
18 | | shall be no more than the greater of (i) 2.015% of the |
19 | | amount paid per million btu by those customers during the |
20 | | year ending May 31, 2009 or (ii) the incremental amount per |
21 | | million btu paid for these resources in 2013. Any increase |
22 | | over these limits in prices in connection with gas service |
23 | | shall be spread evenly among commercial and industrial |
24 | | customers who purchase gas directly from the utility or |
25 | | have gas delivered by the utility. These requirements may |
26 | | be altered only as provided by statute. No later than June |
|
| | 09600SB3388ham001 | - 65 - | LRB096 20594 ASK 44192 a |
|
|
1 | | 30, 2016, the Commission shall review the limitation on the |
2 | | total amount paid under sourcing agreements, if any, with |
3 | | the clean coal SNG brownfield facility pursuant to this |
4 | | subsection (h-1) and report to the General Assembly its |
5 | | findings as to the effect of the limitation on the clean |
6 | | coal SNG brownfield facility, gas utilities, and |
7 | | customers. |
8 | | (h-2) Consumer protection reserve account. The clean coal |
9 | | SNG brownfield facility shall guarantee a minimum of |
10 | | $100,000,000 in consumer savings, calculated in real 2010 |
11 | | dollars at the conclusion of the term of the sourcing agreement |
12 | | by comparing the delivered SNG price to the Chicago City-gate |
13 | | price on a weighted daily basis for each day over the entire |
14 | | term of the sourcing agreement. Prior to the clean coal SNG |
15 | | brownfield facility issuing a notice to proceed to |
16 | | construction, the clean coal SNG brownfield facility shall |
17 | | establish a consumer protection reserve account for the benefit |
18 | | of the retail customers of the utilities that have entered into |
19 | | sourcing agreements with the clean coal SNG brownfield facility |
20 | | pursuant to subsection (h-1), with cash principal in the amount |
21 | | of $150,000,000. Such cash principal shall only be recovered |
22 | | through the consumer protection reserve account and not as a |
23 | | cost to be recovered in the delivered SNG price pursuant to |
24 | | subsection (h-3) of this Section. The consumer protection |
25 | | reserve account shall be maintained and administered by an |
26 | | independent trustee that is mutually agreed upon by the clean |
|
| | 09600SB3388ham001 | - 66 - | LRB096 20594 ASK 44192 a |
|
|
1 | | coal SNG brownfield facility, the utilities, and the Commission |
2 | | in an interest-bearing account in accordance with the |
3 | | following: |
4 | | (1) The clean coal SNG brownfield facility monthly |
5 | | shall calculate the difference between the monthly |
6 | | delivered SNG price and the Chicago City-gate price, by |
7 | | comparing the delivered SNG price, which shall include the |
8 | | cost of transportation to the delivery point, if any, to |
9 | | the Chicago City-gate price on a weighted daily basis for |
10 | | each day of the prior month based upon a mutually-agreed |
11 | | upon published index. |
12 | | (2) During the first 2 years of operation of the |
13 | | facility: |
14 | | (A) to the extent the monthly delivered SNG price, |
15 | | is greater than the Chicago City-gate price, the |
16 | | consumer protection reserve account shall be used to |
17 | | provide a credit to reduce the SNG price by an amount |
18 | | equal to the difference between the monthly delivered |
19 | | SNG price and the Chicago City-gate price; and |
20 | | (B) to the extent the monthly delivered SNG price |
21 | | is less than or equal to the Chicago City-gate price, |
22 | | the utility shall credit the difference between the |
23 | | monthly delivered SNG price and the monthly Chicago |
24 | | City-gate price, if any, to the consumer protection |
25 | | reserve account. Such credit issued pursuant to this |
26 | | paragraph (B) shall be deemed prudent and reasonable |
|
| | 09600SB3388ham001 | - 67 - | LRB096 20594 ASK 44192 a |
|
|
1 | | and not subject to a Commission prudence review; |
2 | | (3) After 2 years of operation of the facility, and |
3 | | monthly, on an on-going basis, thereafter: |
4 | | (A) to the extent that the monthly delivered SNG |
5 | | price is less than or equal to the Chicago City-gate |
6 | | price, calculated using the weighted average of the |
7 | | daily Chicago City-gate price on a daily basis over the |
8 | | entire month, the utility shall credit the difference, |
9 | | if any, to the consumer protection reserve account. |
10 | | Such credit issued pursuant to this subparagraph (A) |
11 | | shall be deemed prudent and reasonable and not subject |
12 | | to a Commission prudence review; |
13 | | (B) any amounts in the consumer protection reserve |
14 | | account in excess of $100,000,000 shall be distributed |
15 | | to the clean coal SNG brownfield facility; provided, |
16 | | however, that under no circumstances shall the total |
17 | | cumulative amount distributed to the clean coal SNG |
18 | | brownfield facility under this subparagraph (B) exceed |
19 | | $150,000,000; |
20 | | (C) to the extent the monthly delivered SNG price |
21 | | is greater than the Chicago City-gate price, after |
22 | | distributing the amounts pursuant to subparagraph (B) |
23 | | of this paragraph (3), if any, the consumer protection |
24 | | reserve account shall be used to provide a credit to |
25 | | reduce the SNG price by an amount equal to the |
26 | | difference between the monthly delivered SNG price and |
|
| | 09600SB3388ham001 | - 68 - | LRB096 20594 ASK 44192 a |
|
|
1 | | the Chicago City-gate price; |
2 | | (D) if retail customers have realized net consumer |
3 | | savings, calculated by comparing the delivered SNG |
4 | | price to the weighted average of the daily Chicago |
5 | | City-gate price on a daily basis over the entire term |
6 | | of the sourcing agreement to date, then after |
7 | | distributing the amounts pursuant to subparagraphs (B) |
8 | | and (C) of this paragraph (3), 50% of any additional |
9 | | amounts in the consumer protection reserve account in |
10 | | excess of $100,000,000 shall be distributed to the |
11 | | clean coal SNG brownfield facility, with the remaining |
12 | | 50% of any such additional amounts being credited to |
13 | | retail customers; provided, however, that if retail |
14 | | customers have not realized such net consumer savings, |
15 | | no such distribution shall be made to the clean coal |
16 | | SNG brownfield facility, and 100% of such additional |
17 | | amounts shall be credited to the retail customers to |
18 | | the extent the consumer protection reserve account |
19 | | exceeds $100,000,000. |
20 | | (4) 50% of all additional net revenue, defined as |
21 | | miscellaneous net revenue after cost allowance for costs |
22 | | associated with additional net revenue that are not |
23 | | otherwise recoverable pursuant to subsection (h-3) of this |
24 | | Section, including net revenue from sales of substitute |
25 | | natural gas derived from the facility above the nameplate |
26 | | capacity of the facility and other by-products produced by |
|
| | 09600SB3388ham001 | - 69 - | LRB096 20594 ASK 44192 a |
|
|
1 | | the facility, shall be credited to the consumer protection |
2 | | reserve account. |
3 | | (5) At the conclusion of the term of the sourcing |
4 | | agreement, to the extent retail customers have not saved |
5 | | the minimum of $100,000,000 in consumer savings as |
6 | | guaranteed in this subsection (h-2), amounts in the |
7 | | consumer protection reserve account shall be credited to |
8 | | retail customers to the extent the retail customers have |
9 | | saved the minimum of $100,000,000; 50% of any additional |
10 | | amounts in the consumer protection reserve account shall be |
11 | | distributed to the company, and the remaining 50% shall be |
12 | | distributed to retail customers. |
13 | | (6) If, at the conclusion of the term of the sourcing |
14 | | agreement, the customers have not saved the minimum |
15 | | $100,000,000 in savings as guaranteed in this subsection |
16 | | (h-2) and the consumer protection reserve account has been |
17 | | depleted, then the clean coal SNG brownfield facility shall |
18 | | be liable for any remaining amount owed to the retail |
19 | | customers to the extent that the customers are provided |
20 | | with the $100,000,000 in savings as guaranteed in this |
21 | | subsection (h-2). The retail customers shall have first |
22 | | priority in recovering that debt above any creditors, |
23 | | except the original senior secured lender to the extent |
24 | | that the original senior secured lender has any senior |
25 | | secured debt outstanding, including any clean coal SNG |
26 | | brownfield facility parent companies or affiliates. |
|
| | 09600SB3388ham001 | - 70 - | LRB096 20594 ASK 44192 a |
|
|
1 | | (7) The clean coal SNG brownfield facility, the |
2 | | utilities, and the trustee shall work together to take |
3 | | commercially reasonable steps to minimize the tax impact of |
4 | | these transactions, while preserving the consumer |
5 | | benefits. |
6 | | (8) The clean coal SNG brownfield facility shall each |
7 | | month, starting in the facility's first year of commercial |
8 | | operation, file with the Commission, in such form as the |
9 | | Commission shall require, a report as to the consumer |
10 | | protection reserve account. The monthly report must |
11 | | contain the following information: |
12 | | (A) the extent the monthly delivered SNG price is |
13 | | greater than, less than, or equal to the Chicago |
14 | | City-gate price; |
15 | | (B) the amount credited or debited to the consumer |
16 | | protection reserve account during the month; |
17 | | (C) the amounts credited to consumers and |
18 | | distributed to the clean coal SNG brownfield facility |
19 | | during the month; |
20 | | (D) the total amount of the consumer protection |
21 | | reserve account at the beginning and end of the month; |
22 | | (E) the total amount of consumer savings to date; |
23 | | and |
24 | | (F) any other additional information the |
25 | | Commission shall require. |
26 | | When any report is erroneous or defective or appears to |
|
| | 09600SB3388ham001 | - 71 - | LRB096 20594 ASK 44192 a |
|
|
1 | | the Commission to be erroneous or defective, the Commission |
2 | | may notify the clean coal SNG brownfield facility to amend |
3 | | the report within 30 days, and, before or after the |
4 | | termination of the 30-day period, the Commission may |
5 | | examine the trustee of the consumer protection reserve |
6 | | account or the officers, agents, employees, books, |
7 | | records, or accounts of the clean coal SNG brownfield |
8 | | facility and correct such items in the report as upon such |
9 | | examination the Commission may find defective or |
10 | | erroneous. All reports shall be under oath. |
11 | | All reports made to the Commission by the clean coal |
12 | | SNG brownfield and the contents of the reports shall be |
13 | | open to public inspection and shall be deemed a public |
14 | | record under the Freedom of Information Act. Such reports |
15 | | shall be preserved in the office of the Commission. The |
16 | | Commission shall publish an annual summary of the reports |
17 | | prior to February 1 of the following year. The annual |
18 | | summary shall be made available to the public on the |
19 | | Commission's website and shall be submitted to the General |
20 | | Assembly. |
21 | | Any facility that fails to file a report required under |
22 | | this paragraph (8) to the Commission within the time |
23 | | specified or to make specific answer to any question |
24 | | propounded by the Commission within 30 days from the time |
25 | | it is lawfully required to do so, or within such further |
26 | | time not to exceed 90 days as may in its discretion be |
|
| | 09600SB3388ham001 | - 72 - | LRB096 20594 ASK 44192 a |
|
|
1 | | allowed by the Commission, shall pay a penalty of $500 to |
2 | | the Commission for each day it is in default. |
3 | | Any person who willfully makes any false report to the |
4 | | Commission or to any member, officer, or employee thereof, |
5 | | any person who willfully in a report withholds or fails to |
6 | | provide material information to which the Commission is |
7 | | entitled under this paragraph (8) and which information is |
8 | | either required to be filed by statute, rule, regulation, |
9 | | order, or decision of the Commission or has been requested |
10 | | by the Commission, and any person who willfully aids or |
11 | | abets such person shall be guilty of a Class A misdemeanor. |
12 | | (h-3) Recoverable costs and revenue by the clean coal SNG |
13 | | brownfield facility. |
14 | | (1) A capital recovery charge approved by the |
15 | | Commission shall be recoverable by the clean coal SNG |
16 | | brownfield facility under a sourcing agreement. The |
17 | | capital recovery charge shall be comprised of capital costs |
18 | | and a reasonable rate of return. "Capital costs" means |
19 | | costs to be incurred in connection with the construction |
20 | | and development of a facility, as defined Section 1-10 of |
21 | | the Illinois Power Agency Act, and such other costs as the |
22 | | Capital Development Board deems appropriate to be |
23 | | recovered in the capital recovery charge. |
24 | | (A) Capital costs. The Capital Development Board |
25 | | shall calculate a range of capital costs that it |
26 | | believes would be reasonable for the clean coal SNG |
|
| | 09600SB3388ham001 | - 73 - | LRB096 20594 ASK 44192 a |
|
|
1 | | brownfield facility to recover under the sourcing |
2 | | agreement. In making this determination, the Capital |
3 | | Development Board shall review the final draft of the |
4 | | sourcing agreement and the rate of return approved by |
5 | | the Commission. In addition, the Capital development |
6 | | Board may: (i) review the facility cost report, if any, |
7 | | of the clean coal SNG brownfield facility; (ii) consult |
8 | | as much as it deems necessary with the clean coal SNG |
9 | | brownfield facility; and (iii) conduct whatever |
10 | | research and investigation it deems necessary. |
11 | | The Capital Development Board shall retain an engineering |
12 | | expert to assist in determining both the range of |
13 | | capital costs and the range of operations and |
14 | | maintenance costs that it believes would be reasonable |
15 | | for the clean coal SNG brownfield facility to recover |
16 | | under the sourcing agreement. Provided, however, that |
17 | | such expert shall: (i) not have been involved in the |
18 | | clean coal SNG brownfield facility's facility cost |
19 | | report, if any, (ii) not own or control any direct or |
20 | | indirect interest in the initial clean coal facility; |
21 | | and (iii) have no contractual relationship with the |
22 | | clean coal SNG brownfield facility. In order to qualify |
23 | | as an independent expert, a person or company must |
24 | | have: |
25 | | (i) direct previous experience conducting |
26 | | front-end engineering and design studies for |
|
| | 09600SB3388ham001 | - 74 - | LRB096 20594 ASK 44192 a |
|
|
1 | | large-scale energy facilities and administering |
2 | | large-scale energy operations and maintenance |
3 | | contracts, which may be particularized to the |
4 | | specific type of financing associated with the |
5 | | clean coal SNG brownfield facility; |
6 | | (ii) an advanced degree in economics, |
7 | | mathematics, engineering, or a related area of |
8 | | study; |
9 | | (iii) ten years of experience in the energy |
10 | | sector, including construction and risk management |
11 | | experience; |
12 | | (iv) expertise in assisting companies with |
13 | | obtaining financing for large-scale energy |
14 | | projects, which may be particularized to the |
15 | | specific type of financing associated with the |
16 | | clean coal SNG brownfield facility; |
17 | | (v) expertise in operations and maintenance |
18 | | which may be particularized to the specific type of |
19 | | operations and maintenance associated with the |
20 | | clean coal SNG brownfield facility; |
21 | | (vi) expertise in credit and contract |
22 | | protocols; |
23 | | (vii) adequate resources to perform and |
24 | | fulfill the required functions and |
25 | | responsibilities; and |
26 | | (viii) the absence of a conflict of interest |
|
| | 09600SB3388ham001 | - 75 - | LRB096 20594 ASK 44192 a |
|
|
1 | | and inappropriate bias for or against an affected |
2 | | gas utility or the clean coal SNG brownfield |
3 | | facility. |
4 | | The clean coal SNG brownfield facility and the |
5 | | Illinois Power Agency shall cooperate with the Capital |
6 | | Development Board in any investigation it deems |
7 | | necessary. The Capital Development Board shall make |
8 | | its final determination of the range of capital costs |
9 | | confidentially and shall submit that range to the |
10 | | Commission in a confidential filing within 120 days |
11 | | after the effective date of this amendatory Act of the |
12 | | 96th General Assembly. The clean coal SNG brownfield |
13 | | facility shall submit to the Commission its estimate of |
14 | | the capital costs to be recovered under the sourcing |
15 | | agreement. Only after the clean coal SNG brownfield |
16 | | facility has submitted this estimate shall the |
17 | | Commission publicly announce the range of capital |
18 | | costs submitted by the Capital Development Board. |
19 | | In the event that the estimate submitted by the |
20 | | clean coal SNG brownfield facility is within or below |
21 | | the range submitted by the Capital Development Board, |
22 | | the clean coal SNG brownfield facility's estimate |
23 | | shall be approved by the Commission as the amount of |
24 | | capital costs to be recovered under the sourcing |
25 | | agreement. In the event that the estimate submitted by |
26 | | the clean coal SNG brownfield facility is above the |
|
| | 09600SB3388ham001 | - 76 - | LRB096 20594 ASK 44192 a |
|
|
1 | | range submitted by the Capital Development Board, the |
2 | | amount of capital costs at the lowest end of the range |
3 | | submitted by the Capital Development Board shall be |
4 | | approved by the Commission as the amount of capital |
5 | | costs to be recovered under the sourcing agreement. |
6 | | Within 15 days after the Capital Development Board has |
7 | | submitted its range and the clean coal SNG brownfield |
8 | | facility has submitted its estimate, the Commission |
9 | | shall approve the capital costs for the clean coal SNG |
10 | | brownfield facility. |
11 | | The Capital Development Board shall monitor the |
12 | | construction of the clean coal SNG brownfield facility |
13 | | for the full duration of construction to assess |
14 | | potential cost overruns. The Capital Development |
15 | | Board, in its discretion, may retain an expert to |
16 | | facilitate such monitoring. The clean coal SNG |
17 | | brownfield facility shall pay a reasonable fee as |
18 | | required by the Capital Development Board for the |
19 | | Capital Development Board's services under this |
20 | | subsection (h-3) to be deposited into the Capital |
21 | | Development Board Revolving Fund, and such fee shall |
22 | | not be passed through to a utility or its customers. If |
23 | | an expert is retained by the Capital Development Board |
24 | | for monitoring of construction, then the clean coal SNG |
25 | | brownfield facility must pay for the expert's |
26 | | reasonable fees and such costs shall not be passed |
|
| | 09600SB3388ham001 | - 77 - | LRB096 20594 ASK 44192 a |
|
|
1 | | through to a utility or its customers. |
2 | | (B) Rate of Return. No later than 30 days after the |
3 | | date on which the Illinois Power Agency submits a final |
4 | | draft sourcing agreement, the Commission shall hold a |
5 | | public hearing to determine the rate of return to be |
6 | | recovered under the sourcing agreement. Rate of return |
7 | | shall be comprised of the clean coal SNG brownfield |
8 | | facility's actual cost of debt, including |
9 | | mortgage-style amortization, and a reasonable return |
10 | | on equity. The Commission shall post notice of the |
11 | | hearing on its website no later than 10 days prior to |
12 | | the date of the hearing. The Commission shall provide |
13 | | the public and all interested parties, including the |
14 | | gas utilities, the Attorney General, and the Illinois |
15 | | Power Agency, an opportunity to be heard. |
16 | | In determining the return on equity, the |
17 | | Commission shall select a commercially reasonable |
18 | | return on equity taking into account the return on |
19 | | equity being received by developers of similar |
20 | | facilities in or outside of Illinois, the need to |
21 | | balance an incentive for clean-coal technology with |
22 | | the need to protect ratepayers from high gas prices, |
23 | | the risks being borne by the clean coal SNG brownfield |
24 | | facility in the final draft sourcing agreement, and any |
25 | | other information that the Commission may deem |
26 | | relevant. The Commission may establish a return on |
|
| | 09600SB3388ham001 | - 78 - | LRB096 20594 ASK 44192 a |
|
|
1 | | equity that varies with the amount of savings, if any, |
2 | | to customers during the term of the sourcing agreement, |
3 | | comparing the delivered SNG price to a daily weighted |
4 | | average price of natural gas, based upon an index. The |
5 | | Illinois Power Agency shall recommend a return on |
6 | | equity to the Commission using the same criteria. |
7 | | Within 60 days after receiving the final draft sourcing |
8 | | agreement from the Illinois Power Agency, the |
9 | | Commission shall approve the rate of return for the |
10 | | clean coal brownfield facility. Within 30 days after |
11 | | obtaining debt financing for the clean coal SNG |
12 | | brownfield facility, the clean coal SNG brownfield |
13 | | facility shall file a notice with the Commission |
14 | | identifying the actual cost of debt. |
15 | | (2) Operations and maintenance costs approved by the |
16 | | Commission shall be recoverable by the clean coal SNG |
17 | | brownfield facility under the sourcing agreement. The |
18 | | operations and maintenance costs mean costs that have been |
19 | | incurred for the administration, supervision, operation, |
20 | | maintenance, preservation, and protection of the clean |
21 | | coal SNG brownfield facility's physical plant. |
22 | | The Capital Development Board shall calculate a range |
23 | | of operations and maintenance costs that it believes would |
24 | | be reasonable for the clean coal SNG brownfield facility to |
25 | | recover under the sourcing agreement. In making this |
26 | | determination, the Capital Development Board shall review |
|
| | 09600SB3388ham001 | - 79 - | LRB096 20594 ASK 44192 a |
|
|
1 | | the final draft of the sourcing agreement and the rate of |
2 | | return approved by the Commission. In addition, the Capital |
3 | | Development Board may: (i) review the facility cost report, |
4 | | if any, of the clean coal SNG brownfield facility; (ii) |
5 | | consult as much as it deems necessary with the clean coal |
6 | | SNG brownfield facility; and (iii) conduct whatever |
7 | | research and investigation it deems necessary. As set forth |
8 | | in subparagraph (A) of paragraph (1) of this subsection |
9 | | (h-3), the Capital Development Board shall retain an |
10 | | independent engineering expert to assist in determining |
11 | | both the range of operations and maintenance costs that it |
12 | | believes would be reasonable for the clean coal SNG |
13 | | brownfield to recover under the sourcing agreement. The |
14 | | clean coal SNG brownfield facility and the Illinois Power |
15 | | Agency shall cooperate with the Capital Development Board |
16 | | in any investigation it deems necessary. The Capital |
17 | | Development Board shall make its final determination of the |
18 | | range of operations and maintenance costs confidentially |
19 | | and shall submit that range to the Commission in a |
20 | | confidential filing within 120 days after the effective |
21 | | date of this amendatory Act of the 96th General Assembly. |
22 | | The clean coal SNG brownfield facility shall submit to |
23 | | the Commission its estimate of the operations and |
24 | | maintenance costs to be recovered under the sourcing |
25 | | agreement. Only after the clean coal SNG brownfield |
26 | | facility has submitted this estimate shall the Commission |
|
| | 09600SB3388ham001 | - 80 - | LRB096 20594 ASK 44192 a |
|
|
1 | | publicly announce the range of operations and maintenance |
2 | | costs submitted by the Capital Development Board. In the |
3 | | event that the estimate submitted by the clean coal SNG |
4 | | brownfield facility is within or below the range submitted |
5 | | by the Capital Development Board, the clean coal SNG |
6 | | brownfield facility's estimate shall be approved by the |
7 | | Commission as the amount of operations and maintenance |
8 | | costs to be recovered under the sourcing agreement. In the |
9 | | event that the estimate submitted by the clean coal SNG |
10 | | brownfield facility is above the range submitted by the |
11 | | Capital Development Board, the amount of operations and |
12 | | maintenance costs at the lowest end of the range submitted |
13 | | by the Capital Development Board shall be approved by the |
14 | | Commission as the amount of operations and maintenance |
15 | | costs to be recovered under the sourcing agreement. Within |
16 | | 15 days after the Capital Development Board has submitted |
17 | | its range and the clean coal SNG brownfield facility has |
18 | | submitted its estimate, the Commission shall approve the |
19 | | operations and maintenance costs for the clean coal SNG |
20 | | brownfield facility. |
21 | | The clean coal SNG brownfield facility shall pay for |
22 | | the independent engineering expert's reasonable fees and |
23 | | such costs shall not be passed through to a utility or its |
24 | | customers. The clean coal SNG brownfield facility shall pay |
25 | | a reasonable fee as required by the Capital Development |
26 | | Board for the Capital Development Board's services under |
|
| | 09600SB3388ham001 | - 81 - | LRB096 20594 ASK 44192 a |
|
|
1 | | this subsection (h-3) to be deposited into the Capital |
2 | | Development Board Revolving Fund, and such fee shall not be |
3 | | passed through to a utility or its customers. |
4 | | (3) Sequestration costs approved by the Commission |
5 | | shall be recoverable by the clean coal SNG brownfield |
6 | | facility. "Sequestration costs" means costs to be incurred |
7 | | by the clean coal SNG brownfield facility in accordance |
8 | | with its Commission-approved carbon capture and |
9 | | sequestration plan to: |
10 | | (A) capture carbon dioxide; |
11 | | (B) build, operate, and maintain a sequestration |
12 | | site in which carbon dioxide may be injected; |
13 | | (C) build, operate, and maintain a carbon dioxide |
14 | | pipeline; and |
15 | | (D) transport the carbon dioxide to the |
16 | | sequestration site or a pipeline. |
17 | | The Commission shall assess the prudency of the |
18 | | sequestration costs for the clean coal SNG brownfield |
19 | | facility before construction commences at the |
20 | | sequestration site or pipeline. Any revenues the clean coal |
21 | | SNG brownfield facility receives as a result of the |
22 | | capture, transportation, or sequestration of carbon |
23 | | dioxide shall be first credited against all sequestration |
24 | | costs, with the positive balance, if any, treated as |
25 | | additional net revenue. |
26 | | The Commission may, in its discretion, retain an expert |
|
| | 09600SB3388ham001 | - 82 - | LRB096 20594 ASK 44192 a |
|
|
1 | | to assist in its review of sequestration costs. The clean |
2 | | coal SNG brownfield facility shall pay for the expert's |
3 | | reasonable fees if an expert is retained by the Commission, |
4 | | and such costs shall not be passed through to a utility or |
5 | | its customers. Once made, the Commission's determination |
6 | | of the amount of recoverable sequestration costs shall not |
7 | | be increased unless the clean coal SNG brownfield facility |
8 | | can show by clear and convincing evidence that (i) the |
9 | | costs were not reasonably foreseeable; (ii) the costs were |
10 | | due to circumstances beyond the clean coal SNG brownfield |
11 | | facility's control; and (iii) the clean coal SNG brownfield |
12 | | facility took all reasonable steps to mitigate the costs. |
13 | | If the Commission determines that sequestration costs may |
14 | | be increased, the Commission shall provide for notice and a |
15 | | public hearing for approval of the increased sequestration |
16 | | costs. |
17 | | (4) Actual delivered and processed fuel costs shall be |
18 | | set by the Illinois Power Agency through a SNG feedstock |
19 | | procurement, pursuant to Sections 1-20, 1-77, and 1-78 of |
20 | | the Illinois Power Agency Act, to be performed at least |
21 | | every 5 years and purchased by the clean coal SNG |
22 | | brownfield facility pursuant to feedstock procurement |
23 | | contracts developed by the Illinois Power Agency, with coal |
24 | | comprising at least 50% of the total feedstock over the |
25 | | term of the sourcing agreement and petroleum coke |
26 | | comprising the remainder of the SNG feedstock. If the |
|
| | 09600SB3388ham001 | - 83 - | LRB096 20594 ASK 44192 a |
|
|
1 | | Commission fails to approve a feedstock procurement plan or |
2 | | fails to approve the results of a feedstock procurement |
3 | | event, then the fuel shall be purchased by the company |
4 | | month-by-month on the spot market and those actual |
5 | | delivered and processed fuel costs shall be recoverable |
6 | | under the sourcing agreement. If a supplier defaults under |
7 | | the terms of a procurement contract, then the Illinois |
8 | | Power Agency shall immediately initiate a feedstock |
9 | | procurement process to obtain a replacement supply, and, |
10 | | prior to the conclusion of that process, fuel shall be |
11 | | purchased by the company month-by-month on the spot market |
12 | | and those actual delivered and processed fuel costs shall |
13 | | be recoverable under the sourcing agreement. |
14 | | (5) Taxes and fees imposed by the federal government, |
15 | | the State, or any unit of local government applicable to |
16 | | the clean coal SNG brownfield facility, excluding income |
17 | | tax, shall be recoverable by the clean coal SNG brownfield |
18 | | facility under the sourcing agreement to the extent such |
19 | | taxes and fees were not applicable to the facility on the |
20 | | date of this amendatory Act of the 96th General Assembly. |
21 | | (6) The actual transportation costs, in accordance |
22 | | with the applicable utility's tariffs, and third-party |
23 | | marketer costs incurred by the company, if any, associated |
24 | | with transporting the SNG from the clean coal SNG |
25 | | brownfield facility to the Chicago City-gate to sell such |
26 | | SNG into the natural gas markets shall be recoverable under |
|
| | 09600SB3388ham001 | - 84 - | LRB096 20594 ASK 44192 a |
|
|
1 | | the sourcing agreement. |
2 | | (7) Unless otherwise provided, within 30 days after a |
3 | | decision of the Commission on recoverable costs under this |
4 | | Section, any interested party to the Commission's decision |
5 | | may apply for a rehearing with respect to the decision. The |
6 | | Commission shall receive and consider the application for |
7 | | rehearing and shall grant or deny the application in whole |
8 | | or in part within 20 days after the date of the receipt of |
9 | | the application by the Commission. If no rehearing is |
10 | | applied for within the required 30 days or an application |
11 | | for rehearing is denied, then the Commission decision shall |
12 | | be final. If an application for rehearing is granted, then |
13 | | the Commission shall hold a rehearing within 30 days after |
14 | | granting the application. The decision of the Commission |
15 | | upon rehearing shall be final. |
16 | | Any person affected by a decision of the Commission |
17 | | under this subsection (h-3) may have the decision reviewed |
18 | | only under and in accordance with the Administrative Review |
19 | | Law. Unless otherwise provided, the provisions of the |
20 | | Administrative Review Law, all amendments and |
21 | | modifications to that Law, and the rules adopted pursuant |
22 | | to that Law shall apply to and govern all proceedings for |
23 | | the judicial review of final administrative decisions of |
24 | | the Commission under this subsection (h-3). The term |
25 | | "administrative decision" is defined as in Section 3-101 of |
26 | | the Code of Civil Procedure. |
|
| | 09600SB3388ham001 | - 85 - | LRB096 20594 ASK 44192 a |
|
|
1 | | (8) The Capital Development Board shall adopt and make |
2 | | public a policy detailing the process for retaining experts |
3 | | under this Section. Any experts retained to assist with |
4 | | calculating the range of capital costs or operations and |
5 | | maintenance costs shall be retained no later than 45 days |
6 | | after the effective date of this amendatory Act of the 96th |
7 | | General Assembly. |
8 | | (h-4) No later than 60 days after the Illinois Power Agency |
9 | | submits the final draft sourcing agreement pursuant to |
10 | | subsection (h-1), the Commission shall approve a sourcing |
11 | | agreement containing the capital costs, rate of return, and |
12 | | operations and maintenance costs. Once the sourcing agreement |
13 | | is approved, then the gas utility subject to that sourcing |
14 | | agreement shall have 45 days after the date of the Commission's |
15 | | approval to enter into the sourcing agreement. |
16 | | (h-5) The Attorney General, on behalf of the people of the |
17 | | State of Illinois, may specifically enforce the requirements of |
18 | | this subsection (h-5). All contracts under subsection (h) of |
19 | | this Act and all sourcing agreements under subsection (h-1) of |
20 | | this Act , regardless of duration, shall require the owner of |
21 | | any facility supplying SNG under the contract or sourcing |
22 | | agreement to provide documentation to the Commission each year, |
23 | | starting in the facility's first year of commercial operation, |
24 | | accurately reporting the quantity of carbon dioxide emissions |
25 | | from the facility that have been captured and sequestered and |
26 | | reporting any quantities of carbon dioxide released from the |
|
| | 09600SB3388ham001 | - 86 - | LRB096 20594 ASK 44192 a |
|
|
1 | | site or sites at which carbon dioxide emissions were |
2 | | sequestered in prior years, based on continuous monitoring of |
3 | | those sites. If, in any year, the owner of the facility |
4 | | described in subsection (h) of this Act fails to demonstrate |
5 | | that the SNG facility captured and sequestered at least 90% of |
6 | | the total carbon dioxide emissions that the facility would |
7 | | otherwise emit or that sequestration of emissions from prior |
8 | | years has failed, resulting in the release of carbon dioxide |
9 | | into the atmosphere, then the owner of the facility must offset |
10 | | excess emissions. Any such carbon dioxide offsets must be |
11 | | permanent, additional, verifiable, real, located within the |
12 | | State of Illinois, and legally and practicably enforceable; |
13 | | provided that the owner of the facility described in subsection |
14 | | (h) of this Act shall not be obligated to acquire carbon |
15 | | dioxide emission offsets to the extent that the cost of |
16 | | acquiring such offsets would exceed $40 million in any given |
17 | | year. No costs of any purchases of carbon offsets may be |
18 | | recovered from a utility or its customers. All carbon offsets |
19 | | purchased for this purpose must be permanently retired. |
20 | | If, in any year, the owner of a clean coal SNG brownfield |
21 | | facility fails to demonstrate that the clean coal SNG |
22 | | brownfield facility captured and sequestered at least 85% of |
23 | | the total carbon dioxide emissions that the facility would |
24 | | otherwise emit, then the owner of the clean coal SNG brownfield |
25 | | facility must pay a penalty of $20 per ton of excess carbon |
26 | | emissions up to $20,000,000, which shall be deposited into the |
|
| | 09600SB3388ham001 | - 87 - | LRB096 20594 ASK 44192 a |
|
|
1 | | Energy Efficiency Trust Fund and distributed pursuant to |
2 | | subsection (b) of Section 6-6 of the Renewable Energy, Energy |
3 | | Efficiency, and Coal Resources Development Law of 1997. |
4 | | Provided, however, to the extent that the owner of the clean |
5 | | coal SNG brownfield facility can demonstrate that the failure |
6 | | was as a result of acts of God (including fire, flood, |
7 | | earthquake, tornado, lightning, hurricane, or other natural |
8 | | disaster); any amendment, modification, or abrogation of any |
9 | | applicable law or regulation that would prevent performance; |
10 | | war; invasion; act of foreign enemies; hostilities (regardless |
11 | | of whether war is declared); civil war; rebellion; revolution; |
12 | | insurrection; military or usurped power or confiscation; |
13 | | terrorist activities; civil disturbances; riots; |
14 | | nationalization; sabotage; blockage; or embargo, the owner of |
15 | | the clean coal SNG brownfield facility shall not be subject to |
16 | | a penalty if and only if (i) it promptly provides notice of its |
17 | | failure to the Commission; (ii) as soon as practicable and |
18 | | consistent with any order or direction from the Commission, it |
19 | | submits to the Commission proposed modifications to its carbon |
20 | | capture and sequestration plan; and (iii) it carries out its |
21 | | proposed modifications in the manner and time directed by the |
22 | | Commission. If the Commission finds that the facility has not |
23 | | satisfied each of these requirements, then the facility shall |
24 | | be subject to the penalty. If the owner of a clean coal SNG |
25 | | brownfield facility demonstrates that the clean coal SNG |
26 | | brownfield facility captured and sequestered more than 85% of |
|
| | 09600SB3388ham001 | - 88 - | LRB096 20594 ASK 44192 a |
|
|
1 | | the total carbon emissions that the facility would otherwise |
2 | | emit, the owner of the clean coal SNG brownfield facility may |
3 | | credit such additional amounts to reduce the amount of any |
4 | | future penalty to be paid. The penalty resulting from the |
5 | | failure to capture and sequester at least the minimum amount of |
6 | | carbon dioxide shall not be passed on to a utility or its |
7 | | customers. |
8 | | In addition to any penalty for the clean coal SNG |
9 | | brownfield facility's failure to capture and sequester at least |
10 | | its minimum sequestration requirement, the Attorney General, |
11 | | on behalf of the People of the State of Illinois, shall bring |
12 | | an action for specific performance of this subsection (h-5). |
13 | | Such action may be filed in any circuit court in Illinois. By |
14 | | entering into a sourcing agreement pursuant to subsection (h-1) |
15 | | of this Section, the clean coal SNG brownfield facility agrees |
16 | | to waive any objections to venue or to the jurisdiction of the |
17 | | court with regard to the Attorney General's action for specific |
18 | | performance under this subsection (h-5). |
19 | | In addition, carbon dioxide emission credits equivalent to |
20 | | 50% of the amount of credits associated with the required |
21 | | sequestration of carbon dioxide from the facility must be |
22 | | permanently retired. Compliance with the sequestration |
23 | | requirements and the offset purchase requirements specified in |
24 | | this subsection (h-5) for the facility described in subsection |
25 | | (h) of this Act shall be assessed annually by an independent |
26 | | expert retained by the owner of the SNG facility described in |
|
| | 09600SB3388ham001 | - 89 - | LRB096 20594 ASK 44192 a |
|
|
1 | | subsection (h) of this Act , with the advance written approval |
2 | | of the Attorney General. Compliance with the sequestration |
3 | | requirements and penalty requirements specified in this |
4 | | subsection (h-5) for the clean coal SNG brownfield facility |
5 | | shall be assessed annually by the Commission, which may in its |
6 | | discretion retain an expert to facilitate its assessment. If an |
7 | | expert is retained by the Commission, then the clean coal SNG |
8 | | brownfield facility shall pay for the expert's reasonable fees, |
9 | | and such costs shall not be passed through to a utility or its |
10 | | customers. A SNG facility operating pursuant to this subsection |
11 | | (h-5) shall not forfeit its designation as a clean coal SNG |
12 | | facility or a clean coal SNG brownfield facility if the |
13 | | facility fails to fully comply with the applicable carbon |
14 | | sequestration requirements in any given year, provided the |
15 | | requisite offsets are purchased or requisite penalties are |
16 | | paid . |
17 | | Responsibility for compliance with the sequestration |
18 | | requirements specified in this subsection (h-5) for the clean |
19 | | coal SNG brownfield facility shall reside solely with the clean |
20 | | coal SNG brownfield facility regardless of whether the facility |
21 | | has contracted with another party to capture, transport, or |
22 | | sequester carbon dioxide. |
23 | | (h-7) Sequestration permitting, oversight, and |
24 | | investigations. |
25 | | (1) No clean coal facility or clean coal SNG brownfield |
26 | | facility may transport or sequester carbon dioxide unless |
|
| | 09600SB3388ham001 | - 90 - | LRB096 20594 ASK 44192 a |
|
|
1 | | the Commission approves the method of carbon dioxide |
2 | | transportation or sequestration. Such approval shall be |
3 | | required regardless of whether the facility has contracted |
4 | | with another to transport or sequester the carbon dioxide. |
5 | | Nothing in this subsection (h-7) shall release the owner or |
6 | | operator of a carbon dioxide sequestration site or carbon |
7 | | dioxide pipeline from any other permitting requirements |
8 | | under applicable State and federal laws, statutes, rules, |
9 | | or regulations. |
10 | | (2) The Commission shall review carbon dioxide |
11 | | transportation and sequestration methods proposed by a |
12 | | clean coal facility or a clean coal SNG brownfield facility |
13 | | and shall approve those methods it deems reasonable and |
14 | | cost-effective. For purposes of this review, |
15 | | "cost-effective" means a commercially reasonable price for |
16 | | similar carbon dioxide transportation or sequestration |
17 | | techniques. In determining whether sequestration is |
18 | | reasonable and cost-effective, the Commission may consult |
19 | | with the Illinois State Geological Survey and retain third |
20 | | parties to assist in its determination, provided that such |
21 | | third parties shall not own or control any direct or |
22 | | indirect interest in the facility that is proposing the |
23 | | carbon dioxide transportation or the carbon dioxide |
24 | | sequestration method and shall have no contractual |
25 | | relationship with that facility. If a third party is |
26 | | retained by the Commission, then the facility proposing the |
|
| | 09600SB3388ham001 | - 91 - | LRB096 20594 ASK 44192 a |
|
|
1 | | carbon dioxide transportation or sequestration method |
2 | | shall pay for the expert's reasonable fees, and these costs |
3 | | shall not be passed through to a utility or its customers. |
4 | | No later than 6 months prior to the date upon which the |
5 | | owner intends to commence construction of a clean coal |
6 | | facility or the clean coal SNG brownfield facility, the |
7 | | owner of the facility shall file with the Commission a |
8 | | carbon dioxide transportation or sequestration plan. The |
9 | | Commission shall hold a public hearing within 30 days after |
10 | | receipt of the facility's carbon dioxide transportation or |
11 | | sequestration plan. The Commission shall post notice of the |
12 | | review on its website upon submission of a carbon dioxide |
13 | | transportation or sequestration method and shall accept |
14 | | written public comments. The Commission shall take the |
15 | | comments into account when making its decision. |
16 | | The Commission may not approve a carbon dioxide |
17 | | sequestration method if the owner or operator of the |
18 | | sequestration site has not received (i) an Underground |
19 | | Injection Control permit from the Illinois Environmental |
20 | | Protection Agency pursuant to the Environmental Protection |
21 | | Act; (ii) an Underground Injection Control permit from the |
22 | | Illinois Department of Natural Resources pursuant to the |
23 | | Illinois Oil and Gas Act; or (iii) a permit similar to |
24 | | items (i) or (ii) from the state in which the sequestration |
25 | | site is located if the sequestration will take place |
26 | | outside of Illinois. The Commission shall approve or deny |
|
| | 09600SB3388ham001 | - 92 - | LRB096 20594 ASK 44192 a |
|
|
1 | | the carbon dioxide transportation or sequestration method |
2 | | within 90 days after the receipt of all required |
3 | | information. |
4 | | (3) At least annually, the Illinois Environmental |
5 | | Protection Agency shall inspect all carbon dioxide |
6 | | sequestration sites in Illinois. The Illinois |
7 | | Environmental Protection Agency may, as often as deemed |
8 | | necessary, monitor and conduct investigations of those |
9 | | sites. The owner or operator of the sequestration site must |
10 | | cooperate with the Illinois Environmental Protection |
11 | | Agency investigations of carbon dioxide sequestration |
12 | | sites. |
13 | | If the Illinois Environmental Protection Agency |
14 | | determines at any time a site creates conditions that |
15 | | warrant the issuance of a seal order under Section 34 of |
16 | | the Environmental Protection Act, then the Illinois |
17 | | Environmental Protection Agency shall seal the site |
18 | | pursuant to the Environmental Protection Act. If the |
19 | | Illinois Environmental Protection Agency determines at any |
20 | | time a carbon dioxide sequestration site creates |
21 | | conditions that warrant the institution of a civil action |
22 | | for an injunction under Section 43 of the Environmental |
23 | | Protection Act, then the Illinois Environmental Protection |
24 | | Agency shall request the State's Attorney or the Attorney |
25 | | General institute such action. The Illinois Environmental |
26 | | Protection Agency shall provide notice of any such actions |
|
| | 09600SB3388ham001 | - 93 - | LRB096 20594 ASK 44192 a |
|
|
1 | | as soon as possible on its website. The SNG facility shall |
2 | | incur all reasonable costs associated with any such |
3 | | inspection or monitoring of the sequestration sites, and |
4 | | these costs shall not be recoverable from utilities or |
5 | | their customers. |
6 | | (4) At least annually, the Commission shall inspect all |
7 | | carbon dioxide pipelines in Illinois that transport carbon |
8 | | dioxide to ensure the safety and feasibility of those |
9 | | pipelines. The Commission may, as often as deemed |
10 | | necessary, monitor and conduct investigations of those |
11 | | pipelines. The owner or operator of the pipeline must |
12 | | cooperate with the Commission investigations of the carbon |
13 | | dioxide pipelines. |
14 | | If the Commission determines at any time that a carbon |
15 | | dioxide pipeline creates conditions that warrant the |
16 | | issuance of a seal order under Section 34 of the |
17 | | Environmental Protection Act, then the Commission shall |
18 | | notify the Illinois Environmental Protection Agency of |
19 | | such conditions. If the Commission determines at any time a |
20 | | carbon dioxide pipeline creates conditions that warrant |
21 | | the institution of a civil action for an injunction under |
22 | | Section 43 of the Environmental Protection Act, then the |
23 | | Commission shall request the State's Attorney or the |
24 | | Attorney General institute such action. The Commission |
25 | | shall provide notice of any such actions as soon as |
26 | | possible on its website. The SNG facility shall incur all |
|
| | 09600SB3388ham001 | - 94 - | LRB096 20594 ASK 44192 a |
|
|
1 | | reasonable costs associated with any such inspection or |
2 | | monitoring of the sequestration sites, and these costs |
3 | | shall not be recoverable from a utility or its customers. |
4 | | (h-9) The clean coal SNG brownfield facility shall have the |
5 | | right to recover prudently incurred increased costs or reduced |
6 | | revenue resulting from any new or amendatory legislation or |
7 | | other action. The State of Illinois pledges that the State will |
8 | | not enact any law or take any action to: |
9 | | (1) break, or repeal the authority for, sourcing |
10 | | agreements approved by the Commission and entered into |
11 | | between public utilities and the clean coal SNG brownfield |
12 | | facility; |
13 | | (2) deny public utilities full cost recovery for their |
14 | | costs incurred under those sourcing agreements; or |
15 | | (3) deny the clean coal SNG brownfield facility full |
16 | | cost and revenue recovery as provided under those sourcing |
17 | | agreements that are recoverable pursuant to subsection |
18 | | (h-3) of this Section. |
19 | | These pledges are for the benefit of the parties to those |
20 | | sourcing agreements and the issuers and holders of bonds or |
21 | | other obligations issued or incurred to finance or refinance |
22 | | the clean coal SNG brownfield facility. The clean coal SNG |
23 | | brownfield facility is authorized to include and refer to these |
24 | | pledges in any financing agreement into which it may enter in |
25 | | regard to those sourcing agreements. |
26 | | The State of Illinois retains and reserves all other rights |
|
| | 09600SB3388ham001 | - 95 - | LRB096 20594 ASK 44192 a |
|
|
1 | | to enact new or amendatory legislation or take any other |
2 | | action, without impairment of the right of the clean coal SNG |
3 | | brownfield facility to recover prudently incurred increased |
4 | | costs or reduced revenue resulting from the new or amendatory |
5 | | legislation or other action, including, but not limited to, |
6 | | such legislation or other action that would (i) directly or |
7 | | indirectly raise the costs the clean coal SNG brownfield |
8 | | facility must incur; (ii) directly or indirectly place |
9 | | additional restrictions, regulations, or requirements on the |
10 | | clean coal SNG brownfield facility; (iii) prohibit |
11 | | sequestration in general or prohibit a specific sequestration |
12 | | method or project; or (iv) increase minimum sequestration |
13 | | requirements for the clean coal SNG brownfield facility to the |
14 | | extent technically feasible. The clean coal SNG brownfield |
15 | | facility shall have the right to recover prudently incurred |
16 | | increased costs or reduced revenue resulting from the new or |
17 | | amendatory legislation or other action as described in this |
18 | | subsection (h-9). |
19 | | (h-10) Contract costs for SNG incurred by an Illinois gas |
20 | | utility are reasonable and prudent and recoverable through the |
21 | | purchased gas adjustment clause and are not subject to review |
22 | | or disallowance by the Commission. Contract costs are costs |
23 | | incurred by the utility under the terms of a contract that |
24 | | incorporates the terms stated in subsection (h) of this Section |
25 | | as confirmed in writing by the Illinois Power Agency as set |
26 | | forth in subsection (h-20) of this Section, which confirmation |
|
| | 09600SB3388ham001 | - 96 - | LRB096 20594 ASK 44192 a |
|
|
1 | | shall be deemed conclusive, or as a consequence of or condition |
2 | | to its performance under the contract, including (i) amounts |
3 | | paid for SNG under the SNG contract and (ii) costs of |
4 | | transportation and storage services of SNG purchased from |
5 | | interstate pipelines under federally approved tariffs. Any |
6 | | contract, the terms of which have been confirmed in writing by |
7 | | the Illinois Power Agency as set forth in subsection (h-20) of |
8 | | this Section and the performance of the parties under such |
9 | | contract cannot be grounds for challenging prudence or cost |
10 | | recovery by the utility through the purchased gas adjustment |
11 | | clause, and in such cases, the Commission is directed not to |
12 | | consider, and has no authority to consider, any attempted |
13 | | challenges. |
14 | | The contracts entered into by Illinois gas utilities |
15 | | pursuant to subsection (h) of this Section shall provide that |
16 | | the utility retains the right to terminate the contract without |
17 | | further obligation or liability to any party if the contract |
18 | | has been impaired as a result of any legislative, |
19 | | administrative, judicial, or other governmental action that is |
20 | | taken that eliminates all or part of the prudence protection of |
21 | | this subsection (h-10) or denies the recoverability of all or |
22 | | part of the contract costs through the purchased gas adjustment |
23 | | clause. Should any Illinois gas utility exercise its right |
24 | | under this subsection (h-10) to terminate the contract, all |
25 | | contract costs incurred prior to termination are and will be |
26 | | deemed reasonable, prudent, and recoverable as and when |
|
| | 09600SB3388ham001 | - 97 - | LRB096 20594 ASK 44192 a |
|
|
1 | | incurred and not subject to review or disallowance by the |
2 | | Commission. Any order, issued by the State requiring or |
3 | | authorizing the discontinuation of the merchant function, |
4 | | defined as the purchase and sale of natural gas by an Illinois |
5 | | gas utility for the ultimate consumer in its service territory |
6 | | shall include provisions necessary to prevent the impairment of |
7 | | the value of any contract hereunder over its full term. |
8 | | (h-11) All costs incurred by an Illinois gas utility in |
9 | | procuring SNG, including procuring SNG from a clean coal SNG |
10 | | brownfield facility or a third-party marketer pursuant to |
11 | | subsection (h-1), are reasonable and prudent and recoverable |
12 | | through the purchased gas adjustment clause and are not subject |
13 | | to review or disallowance by the Commission. Sourcing agreement |
14 | | costs are costs incurred by the utility under the terms of a |
15 | | sourcing agreement that incorporates the terms stated in |
16 | | subsection (h-1) of this Section as approved by the Commission |
17 | | as set forth in subsection (h-4) of this Section, which |
18 | | approval shall be deemed conclusive, or as a consequence of or |
19 | | condition to its performance under the contract, including (i) |
20 | | amounts paid for SNG under the SNG contract and (ii) costs of |
21 | | transportation and storage services of SNG purchased from |
22 | | interstate pipelines under federally approved tariffs. Any |
23 | | sourcing agreement, the terms of which have been approved by |
24 | | the Commission as set forth in subsection (h-4) of this |
25 | | Section, and the performance of the parties under the sourcing |
26 | | agreement cannot be grounds for challenging prudence or cost |
|
| | 09600SB3388ham001 | - 98 - | LRB096 20594 ASK 44192 a |
|
|
1 | | recovery by the utility through the purchased gas adjustment |
2 | | clause, and in these cases, the Commission is directed not to |
3 | | consider, and has no authority to consider, any attempted |
4 | | challenges. |
5 | | (h-15) With respect to each contract entered into by the |
6 | | company with an Illinois utility in accordance with the terms |
7 | | stated in subsection (h) of this Section, within 60 days |
8 | | following the completion of purchases of SNG, the Illinois |
9 | | Power Agency shall conduct an analysis to determine (i) the |
10 | | average contract SNG cost, which shall be calculated as the |
11 | | total amount paid to a company for SNG over the contract term, |
12 | | plus the cost to the utility of the required transportation and |
13 | | storage services of SNG, divided by the total number of MMBtus |
14 | | of SNG actually purchased under the utility contract; (ii) the |
15 | | average natural gas purchase cost, which shall be calculated as |
16 | | the total annual supply costs paid for natural gas (excluding |
17 | | SNG) purchased by such utility over the contract term, plus the |
18 | | costs of transportation and storage services of such natural |
19 | | gas (excluding such costs for SNG), divided by the total number |
20 | | of MMBtus of natural gas (excluding SNG) actually purchased by |
21 | | the utility during the contract term; (iii) the cost |
22 | | differential, which shall be the difference between the average |
23 | | contract SNG cost and the average natural gas purchase cost; |
24 | | and (iv) the revenue share target, which shall be the cost |
25 | | differential multiplied by the total amount of SNG purchased |
26 | | under such utility contract. If the average contract SNG cost |
|
| | 09600SB3388ham001 | - 99 - | LRB096 20594 ASK 44192 a |
|
|
1 | | is equal to or less than the average natural gas purchase cost, |
2 | | then the company shall have no further obligation to the |
3 | | utility. If the average contract SNG cost for such SNG contract |
4 | | is greater than the average natural gas purchase cost for such |
5 | | utility, then the company shall market the daily production of |
6 | | SNG and distribute on a monthly basis 5% of amounts collected |
7 | | with respect to such future sales to the utilities in |
8 | | proportion to each utility's SNG purchases from the company |
9 | | during the term of the SNG contract to be used to reduce the |
10 | | utility's natural gas costs through the purchased gas |
11 | | adjustment clause; such payments to the utility shall continue |
12 | | until such time as the sum of such payments equals the revenue |
13 | | share target of that utility. The company or utilities shall |
14 | | have no obligation to repay the revenue share target except as |
15 | | provided for in this subsection (h-15). |
16 | | (h-20) The General Assembly authorizes the Illinois |
17 | | Finance Authority to issue bonds to the maximum extent |
18 | | permitted to finance coal gasification facilities described in |
19 | | this Section, which constitute both "industrial projects" |
20 | | under Article 801 of the Illinois Finance Authority Act and |
21 | | "clean coal and energy projects" under Sections 825-65 through |
22 | | 825-75 of the Illinois Finance Authority Act. The General |
23 | | Assembly further authorizes the Illinois Power Agency to become |
24 | | party to agreements and take such actions as necessary to |
25 | | enable the Illinois Power Agency or its designate to (i) review |
26 | | and confirm in writing that the terms stated in subsection (h) |
|
| | 09600SB3388ham001 | - 100 - | LRB096 20594 ASK 44192 a |
|
|
1 | | of this Section are incorporated in the SNG contract, and (ii) |
2 | | conduct an analysis pursuant to subsection (h-15) of this |
3 | | Section. Administrative costs incurred by the Illinois Finance |
4 | | Authority and Illinois Power Agency in performance of this |
5 | | subsection (h-20) shall be subject to reimbursement by the |
6 | | company on terms as the Illinois Finance Authority, the |
7 | | Illinois Power Agency, and the company may agree. The utility |
8 | | and its customers shall have no obligation to reimburse the |
9 | | company, the Illinois Finance Authority, or the Illinois Power |
10 | | Agency for any such costs. |
11 | | (i) If a gas utility or an affiliate of a gas utility has |
12 | | an ownership interest in any entity that produces or sells |
13 | | synthetic natural gas, Article VII of this Act shall apply.
|
14 | | (Source: P.A. 95-1027, eff. 6-1-09; 96-1364, eff. 7-28-10.) |
15 | | Section 15. The Illinois Gas Pipeline Safety Act is amended |
16 | | by changing Sections 2.02, 2.03, 2.04, and 3 as follows:
|
17 | | (220 ILCS 20/2.02) (from Ch. 111 2/3, par. 552.2)
|
18 | | Sec. 2.02.
"Gas" means natural gas, flammable gas or gas |
19 | | which is toxic or
corrosive. "Gas" also means carbon dioxide in |
20 | | any physical form, whenever transported by pipeline for the |
21 | | purpose of sequestration.
|
22 | | (Source: P.A. 76-1588.)
|
23 | | (220 ILCS 20/2.03) (from Ch. 111 2/3, par. 552.3)
|
|
| | 09600SB3388ham001 | - 101 - | LRB096 20594 ASK 44192 a |
|
|
1 | | Sec. 2.03.
"Transportation of gas" means the gathering, |
2 | | transmission, or
distribution of gas by pipeline or its |
3 | | storage, within this State and not
subject to the jurisdiction |
4 | | of the Federal Energy Regulatory
Commission under the
Natural |
5 | | Gas Act, except that it includes the transmission of gas |
6 | | through
pipeline facilities within this State that transport |
7 | | gas from an interstate
gas pipeline to a direct sales customer |
8 | | within this State purchasing gas
for its own consumption. |
9 | | "Transportation of gas" also includes
the conveyance of gas |
10 | | from a gas main through the primary fuel line to the
outside |
11 | | wall of residential
premises. If the gas meter is placed within |
12 | | 3 feet of the structure, the
utility's responsibility shall end |
13 | | at the outlet side of the meter. "Transportation of gas" also |
14 | | includes the conveyance of carbon dioxide in any physical form |
15 | | for the purpose of sequestration.
|
16 | | (Source: P.A. 87-1092; 88-314.)
|
17 | | (220 ILCS 20/2.04) (from Ch. 111 2/3, par. 552.4)
|
18 | | Sec. 2.04.
"Pipeline facilities" includes new and existing |
19 | | pipe rights-of-way and
any equipment, facility, or building |
20 | | used in the transportation of gas
or the
treatment of gas |
21 | | during the course of transportation and
includes facilities |
22 | | within this State that transport gas from an interstate
gas |
23 | | pipeline to a direct sales customer within this State |
24 | | purchasing gas
for its own consumption, but
"rights-of-way" as |
25 | | used in this Act does not authorize the Commission to
|
|
| | 09600SB3388ham001 | - 102 - | LRB096 20594 ASK 44192 a |
|
|
1 | | prescribe, under this Act, the location or
routing of any |
2 | | pipeline facility. "Pipeline facilities" also includes
new and |
3 | | existing pipes and lines and any other equipment, facility, or
|
4 | | structure, except customer-owned branch lines connected to the |
5 | | primary fuel
lines, used to convey gas from a gas main to the |
6 | | outside wall of
residential premises, and any person who |
7 | | provides gas service directly to its
residential customer |
8 | | through these facilities shall be deemed to operate
such |
9 | | pipeline facilities for purposes of this Act irrespective of |
10 | | the ownership
of the facilities or the location of the |
11 | | facilities with respect to the
meter, except that a person who |
12 | | provides gas service to a "master meter
system", as that term |
13 | | is defined at 49 C.F.R. Section 191.3, shall not be
deemed to |
14 | | operate any facilities downstream of the master meter. |
15 | | "Pipeline facilities" also includes new and existing pipe |
16 | | rights-of-way and any equipment, facility, or building used in |
17 | | the transportation of carbon dioxide in any physical form for |
18 | | the purpose of sequestration.
|
19 | | (Source: P.A. 87-1092; 88-314.)
|
20 | | (220 ILCS 20/3) (from Ch. 111 2/3, par. 553)
|
21 | | Sec. 3.
(a) As soon as practicable, but not later than 3 |
22 | | months after the
effective date of this Act, the Commission |
23 | | shall adopt rules establishing
minimum safety standards for the |
24 | | transportation of gas and for pipeline
facilities. Such rules |
25 | | shall be at least as inclusive, as stringent, and
compatible |
|
| | 09600SB3388ham001 | - 103 - | LRB096 20594 ASK 44192 a |
|
|
1 | | with, the minimum safety standards adopted by the Secretary of
|
2 | | Transportation under the Federal Act. Thereafter, the |
3 | | Commission shall
maintain such rules so that the rules are at |
4 | | least as inclusive, as
stringent, and compatible with, the |
5 | | minimum standards from time to time in
effect under the Federal |
6 | | Act. The Commission shall also adopt rules establishing minimum |
7 | | safety standards for the transportation of carbon dioxide in |
8 | | any physical form for the purpose of sequestration and for |
9 | | pipeline facilities used for that function.
|
10 | | (b) Standards established under this Act may apply to the |
11 | | design,
installation, inspection, testing, construction, |
12 | | extension, operation,
replacement, and maintenance of pipeline |
13 | | facilities. Standards affecting
the design, installation, |
14 | | construction, initial inspection and initial
testing are not |
15 | | applicable to pipeline facilities in existence on the date
such |
16 | | standards are adopted. Whenever the Commission finds a |
17 | | particular
facility to be hazardous to life or property, it may |
18 | | require the person
operating such facility to take the steps |
19 | | necessary to remove the hazard.
|
20 | | (c) Standards established by the Commission under this Act |
21 | | shall,
subject to paragraphs (a) and (b) of this Section 3, be |
22 | | practicable and
designed to meet the need for pipeline safety. |
23 | | In prescribing such
standards, the Commission shall consider: |
24 | | similar standards established in
other states; relevant |
25 | | available pipeline safety data; whether such
standards are |
26 | | appropriate for the particular type of pipeline
|
|
| | 09600SB3388ham001 | - 104 - | LRB096 20594 ASK 44192 a |
|
|
1 | | transportation; the reasonableness of any proposed standards; |
2 | | and the
extent to which such standards will contribute to |
3 | | public safety.
|
4 | | Rules adopted under this Act are subject to "The Illinois |
5 | | Administrative
Procedure Act", approved September 22, 1975, as |
6 | | amended.
|
7 | | (Source: P.A. 83-333.)
|
8 | | Section 20. The Illinois Environmental Protection Act is |
9 | | amended by adding Section 13.7 as follows: |
10 | | (415 ILCS 5/13.7 new) |
11 | | Sec. 13.7. Carbon dioxide sequestration sites. |
12 | | (a) For purposes of this Section, the term "carbon dioxide |
13 | | sequestration site" means a site or facility for which the |
14 | | Agency has issued a permit for the underground injection of |
15 | | carbon dioxide. |
16 | | (b) The Agency shall inspect carbon dioxide sequestration |
17 | | sites for compliance with this Act, rules adopted under this |
18 | | Act, and permits issued by the Agency. |
19 | | (c) If the Agency issues a seal order under Section 34 of |
20 | | this Act in relation to a carbon dioxide sequestration site, or |
21 | | if a civil action for an injunction to halt activity at a |
22 | | carbon dioxide sequestration site is initiated under Section 43 |
23 | | of this Act at the request of the Agency, then the Agency shall |
24 | | post notice of such action on its website. |
|
| | 09600SB3388ham001 | - 105 - | LRB096 20594 ASK 44192 a |
|
|
1 | | (d) Persons seeking a permit or permit modification for the |
2 | | underground injection of carbon dioxide shall be liable to the |
3 | | Agency for all reasonable and documented costs incurred by the |
4 | | Agency that are associated with review and issuance of the |
5 | | permit, including, but not limited to, costs associated with |
6 | | public hearings and the review of permit applications. Once a |
7 | | permit is issued, the permittee shall be liable to the Agency |
8 | | for all reasonable and documented costs incurred by the Agency |
9 | | that are associated with inspections and other oversight of the |
10 | | carbon dioxide sequestration site. Persons liable for costs |
11 | | under this subsection (d) must pay the costs upon invoicing, or |
12 | | other request or demand for payment, by the Agency. |
13 | | Moneys collected under this subsection (d) shall be |
14 | | deposited into the Environmental Protection Permit and |
15 | | Inspection Fund established under Section 22.8 of this Act. The |
16 | | Agency may adopt rules relating to the collection of costs due |
17 | | under this subsection (d). |
18 | | (e) The Agency shall not issue a permit or permit |
19 | | modification for the underground injection of carbon dioxide |
20 | | unless all costs for which the permitee is liable under |
21 | | subsection (d) of this Section have been paid. |
22 | | (f) No person shall fail or refuse to pay costs for which |
23 | | the person is liable under subsection (d) of this Section. |
24 | | Section 85. Rulemaking. The Illinois Environmental |
25 | | Protection Agency, the Illinois Commerce Commission, the |