|
Rep. John E. Bradley
Filed: 5/16/2013
| | 09800SB1470ham001 | | LRB098 03832 JDS 46059 a |
|
|
1 | | AMENDMENT TO SENATE BILL 1470
|
2 | | AMENDMENT NO. ______. Amend Senate Bill 1470 by replacing |
3 | | everything after the enacting clause with the following:
|
4 | | "Section 5. The Project Labor Agreements Act is amended by |
5 | | changing Section 10 as follows: |
6 | | (30 ILCS 571/10)
|
7 | | Sec. 10. Public works projects. On a project-by-project |
8 | | basis, a State department, agency, authority, board, or |
9 | | instrumentality that is under the control of the Governor shall |
10 | | include a project labor agreement on a public works project |
11 | | when that department, agency, authority, board, or |
12 | | instrumentality has determined that the agreement advances the |
13 | | State's interests of cost, efficiency, quality, safety, |
14 | | timeliness, skilled labor force, labor stability, or the |
15 | | State's policy to advance minority-owned and women-owned |
16 | | businesses and minority and female employment. For purposes of |
|
| | 09800SB1470ham001 | - 2 - | LRB098 03832 JDS 46059 a |
|
|
1 | | this Act, any corrective action performed pursuant to Title XVI |
2 | | of the Environmental Protection Act for which payment from the |
3 | | Underground Storage Tank Fund is requested shall be considered |
4 | | a public works project.
|
5 | | (Source: P.A. 97-199, eff. 7-27-11.) |
6 | | Section 10. The Environmental Protection Act is amended by |
7 | | changing Sections 57.7 and 57.8 as follows: |
8 | | (415 ILCS 5/57.7) |
9 | | Sec. 57.7. Leaking underground storage tanks; site |
10 | | investigation and
corrective action. |
11 | | (a) Site investigation. |
12 | | (1) For any site investigation activities required by |
13 | | statute or rule,
the owner or operator shall submit to the |
14 | | Agency for approval a site
investigation plan designed to |
15 | | determine the nature, concentration, direction
of |
16 | | movement, rate of movement, and extent of the contamination |
17 | | as well as the
significant physical features of the site |
18 | | and surrounding area that may affect
contaminant transport |
19 | | and risk to human health and safety and the environment. |
20 | | (2) Any owner or operator intending to seek payment |
21 | | from the Fund shall
submit to the Agency for approval a |
22 | | site investigation budget that includes,
but is not limited |
23 | | to, an accounting of all costs associated with the
|
24 | | implementation and completion of the site investigation |
|
| | 09800SB1470ham001 | - 3 - | LRB098 03832 JDS 46059 a |
|
|
1 | | plan. |
2 | | (3) Remediation objectives for the applicable |
3 | | indicator contaminants
shall be determined using the |
4 | | tiered approach to corrective action objectives
rules |
5 | | adopted by the Board pursuant to this Title and Title XVII |
6 | | of this Act.
For the purposes of this Title, "Contaminant |
7 | | of Concern" or "Regulated
Substance of Concern" in the |
8 | | rules means the applicable indicator contaminants
set |
9 | | forth in subsection (d) of this Section and the rules |
10 | | adopted thereunder. |
11 | | (4) Upon the Agency's approval of a site investigation |
12 | | plan, or as
otherwise directed by the Agency, the owner or |
13 | | operator shall conduct a site
investigation in accordance |
14 | | with the plan. |
15 | | (5) Within 30 days after completing the site |
16 | | investigation, the owner
or operator shall submit to the |
17 | | Agency for approval a site investigation
completion |
18 | | report. At a minimum the report shall include all of the |
19 | | following: |
20 | | (A) Executive summary. |
21 | | (B) Site history. |
22 | | (C) Site-specific sampling methods and results. |
23 | | (D) Documentation of all field activities, |
24 | | including quality assurance. |
25 | | (E) Documentation regarding the development of |
26 | | proposed remediation
objectives. |
|
| | 09800SB1470ham001 | - 4 - | LRB098 03832 JDS 46059 a |
|
|
1 | | (F) Interpretation of results. |
2 | | (G) Conclusions. |
3 | | (b) Corrective action. |
4 | | (1) If the site investigation confirms none of the |
5 | | applicable indicator
contaminants exceed the proposed |
6 | | remediation objectives, within 30 days after
completing |
7 | | the site investigation the owner or operator shall submit |
8 | | to the
Agency for approval a corrective action completion |
9 | | report in accordance with
this Section. |
10 | | (2) If any of the applicable indicator contaminants |
11 | | exceed the
remediation objectives approved for the site, |
12 | | within 30 days after the Agency
approves the site |
13 | | investigation completion report the owner or operator |
14 | | shall
submit to the Agency for approval a corrective action |
15 | | plan designed to mitigate
any threat to human health, human |
16 | | safety, or the environment resulting from the
underground |
17 | | storage tank release. The plan shall describe the selected |
18 | | remedy
and evaluate its ability and effectiveness to |
19 | | achieve the remediation
objectives approved for the site. |
20 | | At a minimum, the report shall include all
of the |
21 | | following: |
22 | | (A) Executive summary. |
23 | | (B) Statement of remediation objectives. |
24 | | (C) Remedial technologies selected. |
25 | | (D) Confirmation sampling plan. |
26 | | (E) Current and projected future use of the |
|
| | 09800SB1470ham001 | - 5 - | LRB098 03832 JDS 46059 a |
|
|
1 | | property. |
2 | | (F) Applicable preventive, engineering, and |
3 | | institutional controls
including long-term |
4 | | reliability, operating, and maintenance plans, and
|
5 | | monitoring procedures. |
6 | | (G) A schedule for implementation and completion |
7 | | of the plan. |
8 | | (3) Any owner or operator intending to seek payment |
9 | | from the Fund shall
submit to the Agency for approval a |
10 | | corrective action budget that includes,
but is not limited |
11 | | to, an accounting of all costs associated with the
|
12 | | implementation and completion of the corrective action |
13 | | plan. |
14 | | (4) Upon the Agency's approval of a corrective action |
15 | | plan, or as
otherwise directed by the Agency, the owner or |
16 | | operator shall proceed with
corrective action in |
17 | | accordance with the plan. |
18 | | (5) Within 30 days after the completion of a corrective |
19 | | action plan that
achieves applicable remediation |
20 | | objectives the owner or operator shall submit
to the Agency |
21 | | for approval a corrective action completion report. The |
22 | | report
shall demonstrate whether corrective action was |
23 | | completed in accordance with
the approved corrective |
24 | | action plan and whether the remediation objectives
|
25 | | approved for the site, as well as any other requirements of |
26 | | the plan, have
been achieved. |
|
| | 09800SB1470ham001 | - 6 - | LRB098 03832 JDS 46059 a |
|
|
1 | | (6) If within 4 years after the approval of any |
2 | | corrective action plan
the applicable remediation |
3 | | objectives have not been achieved and the owner or
operator |
4 | | has not submitted a corrective action completion report, |
5 | | the owner or
operator must submit a status report for |
6 | | Agency review. The status report must
include, but is not |
7 | | limited to, a description of the remediation activities
|
8 | | taken to date, the effectiveness of the method of |
9 | | remediation being used, the
likelihood of meeting the |
10 | | applicable remediation objectives using the current
method |
11 | | of remediation, and the date the applicable remediation |
12 | | objectives are
expected to be achieved. |
13 | | (7) If the Agency determines any approved corrective |
14 | | action plan will
not achieve applicable remediation |
15 | | objectives within a reasonable time, based
upon the method |
16 | | of remediation and site specific circumstances, the Agency |
17 | | may
require the owner or operator to submit to the Agency |
18 | | for approval a revised
corrective action plan. If the owner |
19 | | or operator intends to seek payment from
the Fund, the |
20 | | owner or operator must also submit a revised budget. |
21 | | (c) Agency review and approval. |
22 | | (1) Agency approval of any plan and associated budget, |
23 | | as described in
this subsection (c), shall be considered |
24 | | final approval for purposes of
seeking and obtaining |
25 | | payment from the Underground Storage Tank Fund if the
costs |
26 | | associated with the completion of any such plan are less |
|
| | 09800SB1470ham001 | - 7 - | LRB098 03832 JDS 46059 a |
|
|
1 | | than or equal
to the amounts approved in such budget. |
2 | | (2) In the event the Agency fails to approve, |
3 | | disapprove, or modify any
plan or report submitted pursuant |
4 | | to this Title in writing within 120 days
of the receipt by |
5 | | the Agency, the plan or report shall be considered to be
|
6 | | rejected by operation of law for purposes of this Title and |
7 | | rejected for
purposes of payment from the Underground |
8 | | Storage Tank Fund. |
9 | | (A) For purposes of those plans as identified in |
10 | | paragraph (5) of this
subsection (c), the Agency's |
11 | | review may be an audit procedure. Such review or
audit |
12 | | shall be consistent with the procedure for such review |
13 | | or audit as
promulgated by the Board under Section |
14 | | 57.14. The Agency has the authority to
establish an |
15 | | auditing program to verify compliance of such plans |
16 | | with the
provisions of this Title. |
17 | | (B) For purposes of corrective action plans |
18 | | submitted pursuant to
subsection (b) of this Section |
19 | | for which payment from the Fund is not being
sought, |
20 | | the Agency need not take action on such plan until 120 |
21 | | days after it
receives the corrective action |
22 | | completion report required under subsection (b)
of |
23 | | this Section. In the event the Agency approved the |
24 | | plan, it shall proceed
under the provisions of this |
25 | | subsection (c). |
26 | | (3) In approving any plan submitted pursuant to |
|
| | 09800SB1470ham001 | - 8 - | LRB098 03832 JDS 46059 a |
|
|
1 | | subsection (a) or (b)
of this Section, the Agency shall |
2 | | determine, by a procedure promulgated by
the Board under |
3 | | Section 57.14, that the costs associated with the plan are
|
4 | | reasonable, will be incurred in the performance of site |
5 | | investigation or
corrective action, and will not be used |
6 | | for site investigation or corrective
action activities in |
7 | | excess of those required to meet the minimum requirements
|
8 | | of this Title. The Agency shall also determine, pursuant to |
9 | | the Project Labor Agreements Act, whether the corrective |
10 | | action shall include a project labor agreement if payment |
11 | | from the Underground Storage Tank Fund is to be requested. |
12 | | (A) For purposes of payment from the Fund, |
13 | | corrective action activities required to meet the |
14 | | minimum requirements of this Title shall include, but |
15 | | not be limited to, the following use of the Board's |
16 | | Tiered Approach to Corrective Action Objectives rules |
17 | | adopted under Title XVII of this Act: |
18 | | (i) For the site where the release occurred, |
19 | | the use of Tier 2 remediation objectives that are |
20 | | no more stringent than Tier 1 remediation |
21 | | objectives. |
22 | | (ii) The use of industrial/commercial property |
23 | | remediation objectives, unless the owner or |
24 | | operator demonstrates that the property being |
25 | | remediated is residential property or being |
26 | | developed into residential property. |
|
| | 09800SB1470ham001 | - 9 - | LRB098 03832 JDS 46059 a |
|
|
1 | | (iii) The use of groundwater ordinances as |
2 | | institutional controls in accordance with Board |
3 | | rules. |
4 | | (iv) The use of on-site groundwater use |
5 | | restrictions as institutional controls in |
6 | | accordance with Board rules. |
7 | | (B) Any bidding process adopted under Board rules |
8 | | to determine the reasonableness of costs of corrective |
9 | | action must provide for a publicly-noticed, |
10 | | competitive, and sealed bidding process that includes, |
11 | | at a minimum, the following: |
12 | | (i) The owner or operator must issue |
13 | | invitations for bids that include, at a minimum, a |
14 | | description of the work being bid and applicable |
15 | | contractual terms and conditions. The criteria on |
16 | | which the bids will be evaluated must be set forth |
17 | | in the invitation for bids. The criteria may |
18 | | include, but shall not be limited to, criteria for |
19 | | determining acceptability, such as inspection, |
20 | | testing, quality, workmanship, delivery, and |
21 | | suitability for a particular purpose. Criteria |
22 | | that will affect the bid price and be considered in |
23 | | the evaluation of a bid, such as discounts, shall |
24 | | be objectively measurable. |
25 | | (ii) At least 14 days prior to the date set in |
26 | | the invitation for the opening of bids, public |
|
| | 09800SB1470ham001 | - 10 - | LRB098 03832 JDS 46059 a |
|
|
1 | | notice of the invitation for bids must be published |
2 | | in a local paper of general circulation for the |
3 | | area in which the site is located. |
4 | | (iii) Bids must be opened publicly in the |
5 | | presence of one or more witnesses at the time and |
6 | | place designated in the invitation for bids. The |
7 | | name of each bidder, the amount of each bid, and |
8 | | other relevant information as specified in Board |
9 | | rules must be recorded and submitted to the Agency |
10 | | in the applicable budget. After selection of the |
11 | | winning bid, the winning bid and the record of each |
12 | | unsuccessful bid shall be open to public |
13 | | inspection. |
14 | | (iv) Bids must be unconditionally accepted |
15 | | without alteration or correction. Bids must be |
16 | | evaluated based on the requirements set forth in |
17 | | the invitation for bids, which may include |
18 | | criteria for determining acceptability, such as |
19 | | inspection, testing, quality, workmanship, |
20 | | delivery, and suitability for a particular |
21 | | purpose. Criteria that will affect the bid price |
22 | | and be considered in the evaluation of a bid, such |
23 | | as discounts, shall be objectively measurable. The |
24 | | invitation for bids shall set forth the evaluation |
25 | | criteria to be used. |
26 | | (v) Correction or withdrawal of inadvertently |
|
| | 09800SB1470ham001 | - 11 - | LRB098 03832 JDS 46059 a |
|
|
1 | | erroneous bids before or after selection of the |
2 | | winning bid, or cancellation of winning bids based |
3 | | on bid mistakes, shall be allowed in accordance |
4 | | with Board rules. After bid opening, no changes in |
5 | | bid prices or other provisions of bids prejudicial |
6 | | to the owner or operator or fair competition shall |
7 | | be allowed. All decisions to allow the correction |
8 | | or withdrawal of bids based on bid mistakes shall |
9 | | be supported by a written determination made by the |
10 | | owner or operator. |
11 | | (vi) The owner or operator shall select the |
12 | | winning bid with reasonable promptness by written |
13 | | notice to the lowest responsible and responsive |
14 | | bidder whose bid meets the requirements and |
15 | | criteria set forth in the invitation for bids. The |
16 | | winning bid and other relevant information as |
17 | | specified in Board rules must be recorded and |
18 | | submitted to the Agency in the applicable budget. |
19 | | (vii) All bidding documentation must be |
20 | | retained by the owner or operator for a minimum of |
21 | | 3 years after the costs bid are submitted in an |
22 | | application for payment, except that documentation |
23 | | relating to an appeal, litigation, or other |
24 | | disputed claim must be maintained until at least 3 |
25 | | years after the date of the final disposition of |
26 | | the appeal, litigation, or other disputed claim. |
|
| | 09800SB1470ham001 | - 12 - | LRB098 03832 JDS 46059 a |
|
|
1 | | All bidding documentation must be made available |
2 | | to the Agency for inspection and copying during |
3 | | normal business hours. |
4 | | (C) Any bidding process adopted under Board rules |
5 | | to determine the reasonableness of costs of corrective |
6 | | action shall (i) be optional and (ii) allow bidding |
7 | | only if the owner or operator demonstrates that |
8 | | corrective action cannot be performed for amounts less |
9 | | than or equal to maximum payment amounts adopted by the |
10 | | Board. |
11 | | (4) For any plan or report received after June 24,
|
12 | | 2002, any action by the Agency to disapprove or modify a |
13 | | plan submitted
pursuant to this Title shall be provided to |
14 | | the owner or operator in writing
within 120 days of the |
15 | | receipt by the Agency or, in the case of a site
|
16 | | investigation plan or corrective action plan for which |
17 | | payment is not being
sought, within 120 days of receipt of |
18 | | the site investigation completion report
or corrective |
19 | | action completion report, respectively, and shall be |
20 | | accompanied
by: |
21 | | (A) an explanation of the Sections of this Act |
22 | | which may be violated
if the plans were approved; |
23 | | (B) an explanation of the provisions of the |
24 | | regulations, promulgated
under this Act, which may be |
25 | | violated if the plan were approved; |
26 | | (C) an explanation of the specific type of |
|
| | 09800SB1470ham001 | - 13 - | LRB098 03832 JDS 46059 a |
|
|
1 | | information, if any,
which the Agency deems the |
2 | | applicant did not provide the Agency; and |
3 | | (D) a statement of specific reasons why the Act and |
4 | | the regulations
might not be met if the plan were |
5 | | approved. |
6 | | Any action by the Agency to disapprove or modify a plan |
7 | | or report or
the rejection of any plan or report by |
8 | | operation of law shall be subject
to appeal to the Board in |
9 | | accordance with the procedures of Section 40. If
the owner |
10 | | or operator elects to incorporate modifications required |
11 | | by the
Agency rather than appeal, an amended plan shall be |
12 | | submitted to the Agency
within 35 days of receipt of the |
13 | | Agency's written notification. |
14 | | (5) For purposes of this Title, the term "plan" shall |
15 | | include: |
16 | | (A) Any site investigation plan submitted pursuant |
17 | | to subsection (a)
of this Section; |
18 | | (B) Any site investigation budget submitted |
19 | | pursuant to subsection (a)
of this Section; |
20 | | (C) Any corrective action plan submitted pursuant |
21 | | to
subsection (b) of this Section; or |
22 | | (D) Any corrective action plan budget submitted |
23 | | pursuant to
subsection (b) of this Section. |
24 | | (d) For purposes of this Title, the term "indicator |
25 | | contaminant" shall
mean, unless and until the Board promulgates |
26 | | regulations to the contrary, the
following: (i) if an |
|
| | 09800SB1470ham001 | - 14 - | LRB098 03832 JDS 46059 a |
|
|
1 | | underground storage tank contains gasoline, the indicator
|
2 | | parameter shall be BTEX and Benzene; (ii) if the tank contained |
3 | | petroleum
products consisting of middle distillate or heavy |
4 | | ends, then the indicator
parameter shall be determined by a |
5 | | scan of PNA's taken from the location where
contamination is |
6 | | most likely to be present; and (iii) if the tank contained
used |
7 | | oil, then the indicator contaminant shall be those chemical |
8 | | constituents
which indicate the type of petroleum stored in an |
9 | | underground storage tank.
All references in this Title to |
10 | | groundwater objectives shall mean Class I
groundwater |
11 | | standards or objectives as applicable. |
12 | | (e) (1) Notwithstanding the provisions of this Section, an |
13 | | owner or
operator may proceed to conduct site investigation |
14 | | or corrective action prior
to the submittal or approval of |
15 | | an otherwise required plan. If the owner or
operator elects |
16 | | to so proceed, an applicable plan shall be filed with the
|
17 | | Agency at any time. Such plan shall detail the steps taken |
18 | | to determine the
type of site investigation or corrective |
19 | | action which was necessary at the site
along with the site |
20 | | investigation or corrective action taken or to be taken, in
|
21 | | addition to costs associated with activities to date and |
22 | | anticipated costs. |
23 | | (2) Upon receipt of a plan submitted after activities |
24 | | have commenced at a
site, the Agency shall proceed to |
25 | | review in the same manner as required under
this Title. In |
26 | | the event the Agency disapproves all or part of the costs, |
|
| | 09800SB1470ham001 | - 15 - | LRB098 03832 JDS 46059 a |
|
|
1 | | the
owner or operator may appeal such decision to the |
2 | | Board. The owner or operator
shall not be eligible to be |
3 | | reimbursed for such disapproved costs unless and
until the |
4 | | Board determines that such costs were eligible for
payment. |
5 | | (f) All investigations, plans, and reports conducted or |
6 | | prepared under
this Section shall be conducted or prepared |
7 | | under the supervision of a
licensed professional engineer and |
8 | | in accordance with the requirements
of this Title. |
9 | | (Source: P.A. 95-331, eff. 8-21-07; 96-908, eff. 6-8-10.)
|
10 | | (415 ILCS 5/57.8)
|
11 | | Sec. 57.8. Underground Storage Tank Fund; payment; options |
12 | | for State payment;
deferred correction election to commence |
13 | | corrective action upon availability of
funds. If an owner or |
14 | | operator is eligible to access the Underground Storage
Tank |
15 | | Fund pursuant to an Office of State Fire Marshal |
16 | | eligibility/deductible
final determination letter issued in |
17 | | accordance with Section 57.9, the owner or
operator may submit |
18 | | a complete application for final or partial payment to the
|
19 | | Agency for activities taken in response to a confirmed release. |
20 | | An owner or
operator may submit a request for partial or final |
21 | | payment regarding a site no
more frequently than once every 90 |
22 | | days.
|
23 | | (a) Payment after completion of corrective action |
24 | | measures.
The owner or operator may submit an application for |
25 | | payment for
activities performed at a site after completion of |
|
| | 09800SB1470ham001 | - 16 - | LRB098 03832 JDS 46059 a |
|
|
1 | | the requirements of Sections
57.6 and 57.7, or after completion |
2 | | of any other required activities at the
underground storage |
3 | | tank site.
|
4 | | (1) In the case of any approved plan and budget for |
5 | | which payment is
being sought, the Agency shall make a |
6 | | payment determination within 120 days of
receipt of the |
7 | | application. Such determination shall be considered a |
8 | | final
decision. The Agency's review shall be limited to |
9 | | generally accepted auditing
and accounting practices. In |
10 | | no case shall the Agency conduct additional
review of any |
11 | | plan which was completed within the budget, beyond auditing |
12 | | for
adherence to the corrective action measures in the |
13 | | proposal. If the Agency
fails to approve the payment |
14 | | application within 120 days, such application
shall be |
15 | | deemed approved by operation of law and the Agency shall |
16 | | proceed to
reimburse the owner or operator the amount |
17 | | requested in the payment
application. However, in no event |
18 | | shall the Agency reimburse the owner or
operator an amount |
19 | | greater than the amount approved in the plan.
|
20 | | (2) If sufficient funds are available in the |
21 | | Underground Storage Tank
Fund, the Agency shall, within 60 |
22 | | days, forward to the Office of the State
Comptroller a |
23 | | voucher in the amount approved under the payment |
24 | | application.
|
25 | | (3) In the case of insufficient funds, the Agency shall |
26 | | form a priority
list for payment and shall notify
persons |
|
| | 09800SB1470ham001 | - 17 - | LRB098 03832 JDS 46059 a |
|
|
1 | | in such
priority list monthly of the availability of funds |
2 | | and when payment shall be
made. Payment shall be made to |
3 | | the owner or operator at such time as
sufficient funds |
4 | | become available for the costs associated with site
|
5 | | investigation and corrective
action and costs expended for |
6 | | activities performed where no proposal is
required, if |
7 | | applicable. Such priority list shall be available to any |
8 | | owner or
operator upon request. Priority for payment shall |
9 | | be determined by the date the
Agency receives a complete |
10 | | request for partial or final payment. Upon receipt
of |
11 | | notification from the Agency that the requirements of this |
12 | | Title have been
met, the Comptroller shall make payment to |
13 | | the owner or operator of the amount
approved by the Agency, |
14 | | if sufficient money exists in the Fund. If there is
|
15 | | insufficient money in the Fund, then payment shall not be |
16 | | made. If the owner
or operator appeals a final Agency |
17 | | payment determination and it is determined
that the owner |
18 | | or operator is eligible for payment or additional payment, |
19 | | the
priority date for the payment or additional payment |
20 | | shall be the same as the
priority date assigned to the |
21 | | original request for partial or final payment.
|
22 | | (4) Any deductible, as determined pursuant to the |
23 | | Office of the State Fire
Marshal's eligibility and |
24 | | deductibility final determination in accordance with
|
25 | | Section 57.9, shall be subtracted from any payment invoice |
26 | | paid to an eligible
owner or operator. Only one deductible |
|
| | 09800SB1470ham001 | - 18 - | LRB098 03832 JDS 46059 a |
|
|
1 | | shall apply per underground storage
tank site.
|
2 | | (5) In the event that costs are or will be incurred in |
3 | | addition to those
approved by the Agency, or after payment, |
4 | | the owner or operator may submit
successive plans |
5 | | containing amended budgets. The requirements of Section |
6 | | 57.7
shall apply to any amended plans.
|
7 | | (6) For purposes of this Section, a complete |
8 | | application shall consist of:
|
9 | | (A) A certification from a Licensed Professional |
10 | | Engineer or Licensed
Professional Geologist as |
11 | | required
under this Title and acknowledged by the owner |
12 | | or operator.
|
13 | | (B) A statement of the amounts approved in the |
14 | | budget and the amounts
actually sought for payment |
15 | | along with a certified statement by the owner or
|
16 | | operator that the amounts so
sought were expended in |
17 | | conformance with the approved budget.
|
18 | | (C) A copy of the Office of the State Fire |
19 | | Marshal's eligibility and
deductibility determination.
|
20 | | (D) Proof that approval of the payment requested |
21 | | will not result in the
limitations set forth in |
22 | | subsection (g) of this Section being exceeded.
|
23 | | (E) A federal taxpayer identification number and |
24 | | legal status disclosure
certification on a form |
25 | | prescribed and provided by the Agency.
|
26 | | (F) If the Agency determined under subsection |
|
| | 09800SB1470ham001 | - 19 - | LRB098 03832 JDS 46059 a |
|
|
1 | | (c)(3) of Section 57.7 of this Act that corrective |
2 | | action must include a project labor agreement, a |
3 | | certification from the owner or operator that the |
4 | | corrective action was (i) performed under a project |
5 | | labor agreement that meets the requirements of Section |
6 | | 25 of the Project Labor Agreements Act and (ii) |
7 | | implemented in a manner consistent with the terms and |
8 | | conditions of the Project Labor Agreements Act and in |
9 | | full compliance with all statutes, regulations, and |
10 | | Executive Orders as required under that Act and the |
11 | | Prevailing Wage Act. |
12 | | (b) Commencement of site investigation or corrective |
13 | | action upon
availability of funds.
The Board shall adopt |
14 | | regulations setting forth procedures based on risk to
human |
15 | | health or the environment under which the owner or operator who |
16 | | has
received approval for any budget plan submitted pursuant to |
17 | | Section
57.7, and who is eligible for payment from the |
18 | | Underground Storage Tank Fund
pursuant to an Office of the |
19 | | State Fire Marshal eligibility and deductibility
|
20 | | determination, may elect to defer site investigation or |
21 | | corrective action activities until funds are available
in
an |
22 | | amount equal to the amount approved in the budget. The |
23 | | regulations
shall establish criteria based on risk to human |
24 | | health or the environment to be
used for determining on a |
25 | | site-by-site basis whether deferral is appropriate.
The |
26 | | regulations also shall establish the minimum investigatory |
|
| | 09800SB1470ham001 | - 20 - | LRB098 03832 JDS 46059 a |
|
|
1 | | requirements for
determining whether the risk based criteria |
2 | | are present at a site considering
deferral and procedures for |
3 | | the notification of owners or operators of
insufficient funds, |
4 | | Agency review of request for deferral, notification of
Agency |
5 | | final decisions, returning deferred sites to active status, and
|
6 | | earmarking of funds for payment.
|
7 | | (c) When the owner or operator requests indemnification for |
8 | | payment of costs
incurred as a result of a release of petroleum |
9 | | from an underground storage
tank, if the owner or operator has |
10 | | satisfied the requirements of subsection (a)
of this Section, |
11 | | the Agency shall forward a copy of the request to the Attorney
|
12 | | General. The Attorney General shall review and approve the |
13 | | request for
indemnification if:
|
14 | | (1) there is a legally enforceable judgment entered |
15 | | against the owner or
operator and such judgment was entered |
16 | | due to harm caused by a release of
petroleum from an |
17 | | underground storage tank and such judgment was not entered |
18 | | as
a result of fraud; or
|
19 | | (2) a settlement with a third party due to a release of |
20 | | petroleum from an
underground storage tank is reasonable.
|
21 | | (d) Notwithstanding any other provision of this Title, the |
22 | | Agency shall not
approve payment to an owner or operator from |
23 | | the Fund for costs of corrective
action or indemnification |
24 | | incurred during a calendar year in excess of the
following |
25 | | aggregate amounts based on the number of petroleum underground
|
26 | | storage tanks owned or operated by such owner or operator in |
|
| | 09800SB1470ham001 | - 21 - | LRB098 03832 JDS 46059 a |
|
|
1 | | Illinois.
|
2 | | Amount Number of Tanks
|
3 | | $2,000,000 ........................fewer than 101
|
4 | | $3,000,000 ................................101 or more
|
5 | | (1) Costs incurred in excess of the aggregate amounts |
6 | | set forth in
paragraph (1) of this subsection shall not be |
7 | | eligible for payment in
subsequent years.
|
8 | | (2) For purposes of this subsection, requests |
9 | | submitted by any of the
agencies, departments, boards, |
10 | | committees or commissions of the State of
Illinois shall be |
11 | | acted upon as claims from a single owner or operator.
|
12 | | (3) For purposes of this subsection, owner or operator |
13 | | includes (i) any
subsidiary, parent, or joint stock company |
14 | | of the owner or operator and (ii)
any company owned by any |
15 | | parent, subsidiary, or joint stock company of the
owner or |
16 | | operator.
|
17 | | (e) Costs of corrective action or indemnification incurred |
18 | | by an owner or
operator which have been paid to an owner or |
19 | | operator under a policy of
insurance, another written |
20 | | agreement, or a court order are not eligible for
payment under |
21 | | this Section. An owner or operator who receives payment under a
|
22 | | policy of insurance, another written agreement, or a court |
23 | | order shall
reimburse the State to the extent such payment |
24 | | covers costs for which payment
was received from the Fund. Any |
25 | | monies received by the State under this
subsection (e) shall be |
26 | | deposited into the Fund.
|
|
| | 09800SB1470ham001 | - 22 - | LRB098 03832 JDS 46059 a |
|
|
1 | | (f) (Blank.)
|
2 | | (g) The Agency shall not approve any payment from the Fund |
3 | | to pay an owner
or operator:
|
4 | | (1) for costs of corrective action incurred by such |
5 | | owner or operator
in an
amount in excess of $1,500,000 per |
6 | | occurrence; and
|
7 | | (2) for costs of indemnification of such owner or |
8 | | operator in an amount in
excess of $1,500,000 per |
9 | | occurrence.
|
10 | | (h) Payment of any amount from the Fund for corrective |
11 | | action or
indemnification shall be subject to the State |
12 | | acquiring by subrogation the
rights of any owner, operator, or |
13 | | other person to recover the costs of
corrective action or |
14 | | indemnification for which the Fund has compensated such
owner, |
15 | | operator, or person from the person responsible or liable for |
16 | | the
release.
|
17 | | (i) If the Agency refuses to pay or authorizes only
a |
18 | | partial payment, the affected owner or operator may petition |
19 | | the Board for a
hearing in the manner provided for the review |
20 | | of permit decisions in Section 40
of this Act.
|
21 | | (j) Costs of corrective action or indemnification incurred |
22 | | by an owner or
operator prior to July 28, 1989, shall not be |
23 | | eligible for payment or
reimbursement under this Section.
|
24 | | (k) The Agency shall not pay costs of corrective action or
|
25 | | indemnification incurred before providing notification of the |
26 | | release of
petroleum in accordance with the provisions of this |
|
| | 09800SB1470ham001 | - 23 - | LRB098 03832 JDS 46059 a |
|
|
1 | | Title.
|
2 | | (l) Corrective action does not include legal defense costs. |
3 | | Legal defense
costs include legal costs for seeking payment |
4 | | under this Title unless the owner
or operator prevails before |
5 | | the Board in which case the Board may authorize
payment of |
6 | | legal fees.
|
7 | | (m) The Agency may apportion payment of costs for plans |
8 | | submitted under
Section 57.7 if:
|
9 | | (1) the owner or operator was deemed eligible to access |
10 | | the Fund for
payment of corrective action costs for some, |
11 | | but not all, of the underground
storage tanks at the site; |
12 | | and
|
13 | | (2) the owner or operator failed to justify all costs |
14 | | attributable to each
underground storage tank at the site.
|
15 | | (n) The Agency shall not pay costs associated with a |
16 | | corrective action
plan incurred after the Agency provides
|
17 | | notification to the owner or operator pursuant to item (7) of |
18 | | subsection (b) of
Section 57.7 that a revised corrective action |
19 | | plan
is required. Costs associated with any subsequently |
20 | | approved corrective action
plan shall be eligible for |
21 | | reimbursement if they
meet the requirements of this Title.
|
22 | | (Source: P.A. 95-331, eff. 8-21-07.)
|
23 | | Section 15. The Prevailing Wage Act is amended by changing |
24 | | Section 2 as follows:
|
|
| | 09800SB1470ham001 | - 24 - | LRB098 03832 JDS 46059 a |
|
|
1 | | (820 ILCS 130/2) (from Ch. 48, par. 39s-2)
|
2 | | Sec. 2. This Act applies to the wages of laborers, |
3 | | mechanics and
other workers employed in any public works, as |
4 | | hereinafter defined, by
any public body and to anyone under |
5 | | contracts for public works. This includes any maintenance, |
6 | | repair, assembly, or disassembly work performed on equipment |
7 | | whether owned, leased, or rented.
|
8 | | As used in this Act, unless the context indicates |
9 | | otherwise:
|
10 | | "Public works" means all fixed works constructed or |
11 | | demolished by
any public body,
or paid for wholly or in part |
12 | | out of public funds. "Public works" as
defined herein includes |
13 | | all projects financed in whole
or in part with bonds, grants, |
14 | | loans, or other funds made available by or through the State or |
15 | | any of its political subdivisions, including but not limited |
16 | | to: bonds issued under the Industrial Project Revenue Bond
Act |
17 | | (Article 11, Division 74 of the Illinois Municipal Code), the |
18 | | Industrial
Building Revenue Bond Act, the Illinois Finance |
19 | | Authority Act,
the Illinois Sports Facilities Authority Act, or |
20 | | the Build Illinois Bond Act; loans or other funds made
|
21 | | available pursuant to the Build Illinois Act; or funds from the |
22 | | Fund for
Illinois' Future under Section 6z-47 of the State |
23 | | Finance Act, funds for school
construction under Section 5 of |
24 | | the General Obligation Bond Act, funds
authorized under Section |
25 | | 3 of the School Construction Bond Act, funds for
school |
26 | | infrastructure under Section 6z-45 of the State Finance Act, |
|
| | 09800SB1470ham001 | - 25 - | LRB098 03832 JDS 46059 a |
|
|
1 | | and funds
for transportation purposes under Section 4 of the |
2 | | General Obligation Bond
Act. "Public works" also includes (i) |
3 | | all projects financed in whole or in part
with funds from the |
4 | | Department of Commerce and Economic Opportunity under the |
5 | | Illinois Renewable Fuels Development Program
Act for which |
6 | | there is no project labor agreement; (ii) all work performed |
7 | | pursuant to a public private agreement under the Public Private |
8 | | Agreements for the Illiana Expressway Act; and (iii) all |
9 | | projects undertaken under a public-private agreement under the |
10 | | Public-Private Partnerships for Transportation Act. "Public |
11 | | works" also includes all projects at leased facility property |
12 | | used for airport purposes under Section 35 of the Local |
13 | | Government Facility Lease Act. "Public works" also includes the |
14 | | construction of a new wind power facility by a business |
15 | | designated as a High Impact Business under Section 5.5(a)(3)(E) |
16 | | of the Illinois Enterprise Zone Act.
"Public works" also |
17 | | includes any corrective action performed pursuant to Title XVI |
18 | | of the Environmental Protection Act for which payment from the |
19 | | Underground Storage Tank Fund is requested. "Public works" does |
20 | | not include work done directly by any public utility company, |
21 | | whether or not done under public supervision or direction, or |
22 | | paid for wholly or in part out of public funds. "Public works" |
23 | | does not include projects undertaken by the owner at an |
24 | | owner-occupied single-family residence or at an owner-occupied |
25 | | unit of a multi-family residence.
|
26 | | "Construction" means all work on public works involving |
|
| | 09800SB1470ham001 | - 26 - | LRB098 03832 JDS 46059 a |
|
|
1 | | laborers,
workers or mechanics. This includes any maintenance, |
2 | | repair, assembly, or disassembly work performed on equipment |
3 | | whether owned, leased, or rented.
|
4 | | "Locality" means the county where the physical work upon |
5 | | public works
is performed, except (1) that if there is not |
6 | | available in the county a
sufficient number of competent |
7 | | skilled laborers, workers and mechanics
to construct the public |
8 | | works efficiently and properly, "locality"
includes any other |
9 | | county nearest the one in which the work or
construction is to |
10 | | be performed and from which such persons may be
obtained in |
11 | | sufficient numbers to perform the work and (2) that, with
|
12 | | respect to contracts for highway work with the Department of
|
13 | | Transportation of this State, "locality" may at the discretion |
14 | | of the
Secretary of the Department of Transportation be |
15 | | construed to include
two or more adjacent counties from which |
16 | | workers may be accessible for
work on such construction.
|
17 | | "Public body" means the State or any officer, board or |
18 | | commission of
the State or any political subdivision or |
19 | | department thereof, or any
institution supported in whole or in |
20 | | part by public funds,
and includes every county, city, town,
|
21 | | village, township, school district, irrigation, utility, |
22 | | reclamation
improvement or other district and every other |
23 | | political subdivision,
district or municipality of the state |
24 | | whether such political
subdivision, municipality or district |
25 | | operates under a special charter
or not.
|
26 | | The terms "general prevailing rate of hourly wages", |
|
| | 09800SB1470ham001 | - 27 - | LRB098 03832 JDS 46059 a |
|
|
1 | | "general
prevailing rate of wages" or "prevailing rate of |
2 | | wages" when used in
this Act mean the hourly cash wages plus |
3 | | fringe benefits for training and
apprenticeship programs |
4 | | approved by the U.S. Department of Labor, Bureau of
|
5 | | Apprenticeship and Training, health and welfare, insurance, |
6 | | vacations and
pensions paid generally, in the
locality in which |
7 | | the work is being performed, to employees engaged in
work of a |
8 | | similar character on public works.
|
9 | | (Source: P.A. 96-28, eff. 7-1-09; 96-58, eff. 1-1-10; 96-186, |
10 | | eff. 1-1-10; 96-913, eff. 6-9-10; 96-1000, eff. 7-2-10; 97-502, |
11 | | eff. 8-23-11.)
|
12 | | Section 99. Effective date. This Act takes effect August 1, |
13 | | 2013.".
|