5    "Section 5. The Environmental Protection Act is amended by
6changing Section 39.5 as follows:
 
7    (415 ILCS 5/39.5)  (from Ch. 111 1/2, par. 1039.5)
8    Sec. 39.5. Clean Air Act Permit Program.
9    1. Definitions.
10    For purposes of this Section:
11    "Administrative permit amendment" means a permit revision
12subject to subsection 13 of this Section.
13    "Affected source for acid deposition" means a source that
14includes one or more affected units under Title IV of the Clean
15Air Act.
16    "Affected States" for purposes of formal distribution of a

 

 

09900HB3341ham003- 2 -LRB099 10047 MGM 34300 a

1draft CAAPP permit to other States for comments prior to
2issuance, means all States:
3        (1) Whose air quality may be affected by the source
4    covered by the draft permit and that are contiguous to
5    Illinois; or
6        (2) That are within 50 miles of the source.
7    "Affected unit for acid deposition" shall have the meaning
8given to the term "affected unit" in the regulations
9promulgated under Title IV of the Clean Air Act.
10    "Applicable Clean Air Act requirement" means all of the
11following as they apply to emissions units in a source
12(including regulations that have been promulgated or approved
13by USEPA pursuant to the Clean Air Act which directly impose
14requirements upon a source and other such federal requirements
15which have been adopted by the Board. These may include
16requirements and regulations which have future effective
17compliance dates. Requirements and regulations will be exempt
18if USEPA determines that such requirements need not be
19contained in a Title V permit):
20        (1) Any standard or other requirement provided for in
21    the applicable state implementation plan approved or
22    promulgated by USEPA under Title I of the Clean Air Act
23    that implements the relevant requirements of the Clean Air
24    Act, including any revisions to the state Implementation
25    Plan promulgated in 40 CFR Part 52, Subparts A and O and
26    other subparts applicable to Illinois. For purposes of this

 

 

09900HB3341ham003- 3 -LRB099 10047 MGM 34300 a

1    paragraph (1) of this definition, "any standard or other
2    requirement" means only such standards or requirements
3    directly enforceable against an individual source under
4    the Clean Air Act.
5        (2)(i) Any term or condition of any preconstruction
6        permits issued pursuant to regulations approved or
7        promulgated by USEPA under Title I of the Clean Air
8        Act, including Part C or D of the Clean Air Act.
9            (ii) Any term or condition as required pursuant to
10        Section 39.5 of any federally enforceable State
11        operating permit issued pursuant to regulations
12        approved or promulgated by USEPA under Title I of the
13        Clean Air Act, including Part C or D of the Clean Air
14        Act.
15        (3) Any standard or other requirement under Section 111
16    of the Clean Air Act, including Section 111(d).
17        (4) Any standard or other requirement under Section 112
18    of the Clean Air Act, including any requirement concerning
19    accident prevention under Section 112(r)(7) of the Clean
20    Air Act.
21        (5) Any standard or other requirement of the acid rain
22    program under Title IV of the Clean Air Act or the
23    regulations promulgated thereunder.
24        (6) Any requirements established pursuant to Section
25    504(b) or Section 114(a)(3) of the Clean Air Act.
26        (7) Any standard or other requirement governing solid

 

 

09900HB3341ham003- 4 -LRB099 10047 MGM 34300 a

1    waste incineration, under Section 129 of the Clean Air Act.
2        (8) Any standard or other requirement for consumer and
3    commercial products, under Section 183(e) of the Clean Air
4    Act.
5        (9) Any standard or other requirement for tank vessels,
6    under Section 183(f) of the Clean Air Act.
7        (10) Any standard or other requirement of the program
8    to control air pollution from Outer Continental Shelf
9    sources, under Section 328 of the Clean Air Act.
10        (11) Any standard or other requirement of the
11    regulations promulgated to protect stratospheric ozone
12    under Title VI of the Clean Air Act, unless USEPA has
13    determined that such requirements need not be contained in
14    a Title V permit.
15        (12) Any national ambient air quality standard or
16    increment or visibility requirement under Part C of Title I
17    of the Clean Air Act, but only as it would apply to
18    temporary sources permitted pursuant to Section 504(e) of
19    the Clean Air Act.
20    "Applicable requirement" means all applicable Clean Air
21Act requirements and any other standard, limitation, or other
22requirement contained in this Act or regulations promulgated
23under this Act as applicable to sources of air contaminants
24(including requirements that have future effective compliance
25dates).
26    "CAAPP" means the Clean Air Act Permit Program, developed

 

 

09900HB3341ham003- 5 -LRB099 10047 MGM 34300 a

1pursuant to Title V of the Clean Air Act.
2    "CAAPP application" means an application for a CAAPP
3permit.
4    "CAAPP Permit" or "permit" (unless the context suggests
5otherwise) means any permit issued, renewed, amended, modified
6or revised pursuant to Title V of the Clean Air Act.
7    "CAAPP source" means any source for which the owner or
8operator is required to obtain a CAAPP permit pursuant to
9subsection 2 of this Section.
10    "Clean Air Act" means the Clean Air Act, as now and
11hereafter amended, 42 U.S.C. 7401, et seq.
12    "Designated representative" has the meaning given to it in
13Section 402(26) of the Clean Air Act and the regulations
14promulgated thereunder, which state that the term "designated
15representative" means a responsible person or official
16authorized by the owner or operator of a unit to represent the
17owner or operator in all matters pertaining to the holding,
18transfer, or disposition of allowances allocated to a unit, and
19the submission of and compliance with permits, permit
20applications, and compliance plans for the unit.
21    "Draft CAAPP permit" means the version of a CAAPP permit
22for which public notice and an opportunity for public comment
23and hearing is offered by the Agency.
24    "Effective date of the CAAPP" means the date that USEPA
25approves Illinois' CAAPP.
26    "Emission unit" means any part or activity of a stationary

 

 

09900HB3341ham003- 6 -LRB099 10047 MGM 34300 a

1source that emits or has the potential to emit any air
2pollutant. This term is not meant to alter or affect the
3definition of the term "unit" for purposes of Title IV of the
4Clean Air Act.
5    "Federally enforceable" means enforceable by USEPA.
6    "Final permit action" means the Agency's granting with
7conditions, refusal to grant, renewal of, or revision of a
8CAAPP permit, the Agency's determination of incompleteness of a
9submitted CAAPP application, or the Agency's failure to act on
10an application for a permit, permit renewal, or permit revision
11within the time specified in subsection 13, subsection 14, or
12paragraph (j) of subsection 5 of this Section.
13    "General permit" means a permit issued to cover numerous
14similar sources in accordance with subsection 11 of this
15Section.
16    "Major source" means a source for which emissions of one or
17more air pollutants meet the criteria for major status pursuant
18to paragraph(c) of subsection 2 of this Section.
19    "Maximum achievable control technology" or "MACT" means
20the maximum degree of reductions in emissions deemed achievable
21under Section 112 of the Clean Air Act.
22    "Owner or operator" means any person who owns, leases,
23operates, controls, or supervises a stationary source.
24    "Permit modification" means a revision to a CAAPP permit
25that cannot be accomplished under the provisions for
26administrative permit amendments under subsection 13 of this

 

 

09900HB3341ham003- 7 -LRB099 10047 MGM 34300 a

1Section.
2    "Permit revision" means a permit modification or
3administrative permit amendment.
4    "Phase II" means the period of the national acid rain
5program, established under Title IV of the Clean Air Act,
6beginning January 1, 2000, and continuing thereafter.
7    "Phase II acid rain permit" means the portion of a CAAPP
8permit issued, renewed, modified, or revised by the Agency
9during Phase II for an affected source for acid deposition.
10    "Potential to emit" means the maximum capacity of a
11stationary source to emit any air pollutant under its physical
12and operational design. Any physical or operational limitation
13on the capacity of a source to emit an air pollutant, including
14air pollution control equipment and restrictions on hours of
15operation or on the type or amount of material combusted,
16stored, or processed, shall be treated as part of its design if
17the limitation is enforceable by USEPA. This definition does
18not alter or affect the use of this term for any other purposes
19under the Clean Air Act, or the term "capacity factor" as used
20in Title IV of the Clean Air Act or the regulations promulgated
21thereunder.
22    "Preconstruction Permit" or "Construction Permit" means a
23permit which is to be obtained prior to commencing or beginning
24actual construction or modification of a source or emissions
25unit.
26    "Proposed CAAPP permit" means the version of a CAAPP permit

 

 

09900HB3341ham003- 8 -LRB099 10047 MGM 34300 a

1that the Agency proposes to issue and forwards to USEPA for
2review in compliance with applicable requirements of the Act
3and regulations promulgated thereunder.
4    "Regulated air pollutant" means the following:
5        (1) Nitrogen oxides (NOx) or any volatile organic
6    compound.
7        (2) Any pollutant for which a national ambient air
8    quality standard has been promulgated.
9        (3) Any pollutant that is subject to any standard
10    promulgated under Section 111 of the Clean Air Act.
11        (4) Any Class I or II substance subject to a standard
12    promulgated under or established by Title VI of the Clean
13    Air Act.
14        (5) Any pollutant subject to a standard promulgated
15    under Section 112 or other requirements established under
16    Section 112 of the Clean Air Act, including Sections
17    112(g), (j) and (r).
18            (i) Any pollutant subject to requirements under
19        Section 112(j) of the Clean Air Act. Any pollutant
20        listed under Section 112(b) for which the subject
21        source would be major shall be considered to be
22        regulated 18 months after the date on which USEPA was
23        required to promulgate an applicable standard pursuant
24        to Section 112(e) of the Clean Air Act, if USEPA fails
25        to promulgate such standard.
26            (ii) Any pollutant for which the requirements of

 

 

09900HB3341ham003- 9 -LRB099 10047 MGM 34300 a

1        Section 112(g)(2) of the Clean Air Act have been met,
2        but only with respect to the individual source subject
3        to Section 112(g)(2) requirement.
4        (6) Greenhouse gases.
5    "Renewal" means the process by which a permit is reissued
6at the end of its term.
7    "Responsible official" means one of the following:
8        (1) For a corporation: a president, secretary,
9    treasurer, or vice-president of the corporation in charge
10    of a principal business function, or any other person who
11    performs similar policy or decision-making functions for
12    the corporation, or a duly authorized representative of
13    such person if the representative is responsible for the
14    overall operation of one or more manufacturing,
15    production, or operating facilities applying for or
16    subject to a permit and either (i) the facilities employ
17    more than 250 persons or have gross annual sales or
18    expenditures exceeding $25 million (in second quarter 1980
19    dollars), or (ii) the delegation of authority to such
20    representative is approved in advance by the Agency.
21        (2) For a partnership or sole proprietorship: a general
22    partner or the proprietor, respectively, or in the case of
23    a partnership in which all of the partners are
24    corporations, a duly authorized representative of the
25    partnership if the representative is responsible for the
26    overall operation of one or more manufacturing,

 

 

09900HB3341ham003- 10 -LRB099 10047 MGM 34300 a

1    production, or operating facilities applying for or
2    subject to a permit and either (i) the facilities employ
3    more than 250 persons or have gross annual sales or
4    expenditures exceeding $25 million (in second quarter 1980
5    dollars), or (ii) the delegation of authority to such
6    representative is approved in advance by the Agency.
7        (3) For a municipality, State, Federal, or other public
8    agency: either a principal executive officer or ranking
9    elected official. For the purposes of this part, a
10    principal executive officer of a Federal agency includes
11    the chief executive officer having responsibility for the
12    overall operations of a principal geographic unit of the
13    agency (e.g., a Regional Administrator of USEPA).
14        (4) For affected sources for acid deposition:
15            (i) The designated representative shall be the
16        "responsible official" in so far as actions,
17        standards, requirements, or prohibitions under Title
18        IV of the Clean Air Act or the regulations promulgated
19        thereunder are concerned.
20            (ii) The designated representative may also be the
21        "responsible official" for any other purposes with
22        respect to air pollution control.
23    "Section 502(b)(10) changes" means changes that contravene
24express permit terms. "Section 502(b)(10) changes" do not
25include changes that would violate applicable requirements or
26contravene federally enforceable permit terms or conditions

 

 

09900HB3341ham003- 11 -LRB099 10047 MGM 34300 a

1that are monitoring (including test methods), recordkeeping,
2reporting, or compliance certification requirements.
3    "Solid waste incineration unit" means a distinct operating
4unit of any facility which combusts any solid waste material
5from commercial or industrial establishments or the general
6public (including single and multiple residences, hotels, and
7motels). The term does not include incinerators or other units
8required to have a permit under Section 3005 of the Solid Waste
9Disposal Act. The term also does not include (A) materials
10recovery facilities (including primary or secondary smelters)
11which combust waste for the primary purpose of recovering
12metals, (B) qualifying small power production facilities, as
13defined in Section 3(17)(C) of the Federal Power Act (16 U.S.C.
14769(17)(C)), or qualifying cogeneration facilities, as defined
15in Section 3(18)(B) of the Federal Power Act (16 U.S.C.
16796(18)(B)), which burn homogeneous waste (such as units which
17burn tires or used oil, but not including refuse-derived fuel)
18for the production of electric energy or in the case of
19qualifying cogeneration facilities which burn homogeneous
20waste for the production of electric energy and steam or forms
21of useful energy (such as heat) which are used for industrial,
22commercial, heating or cooling purposes, or (C) air curtain
23incinerators provided that such incinerators only burn wood
24wastes, yard waste and clean lumber and that such air curtain
25incinerators comply with opacity limitations to be established
26by the USEPA by rule.

 

 

09900HB3341ham003- 12 -LRB099 10047 MGM 34300 a

1    "Source" means any stationary source (or any group of
2stationary sources) that is located on one or more contiguous
3or adjacent properties that are under common control of the
4same person (or persons under common control) and that belongs
5to a single major industrial grouping. For the purposes of
6defining "source," a stationary source or group of stationary
7sources shall be considered part of a single major industrial
8grouping if all of the pollutant emitting activities at such
9source or group of sources located on contiguous or adjacent
10properties and under common control belong to the same Major
11Group (i.e., all have the same two-digit code) as described in
12the Standard Industrial Classification Manual, 1987, or such
13pollutant emitting activities at a stationary source (or group
14of stationary sources) located on contiguous or adjacent
15properties and under common control constitute a support
16facility. The determination as to whether any group of
17stationary sources is located on contiguous or adjacent
18properties, and/or is under common control, and/or whether the
19pollutant emitting activities at such group of stationary
20sources constitute a support facility shall be made on a case
21by case basis.
22    "Stationary source" means any building, structure,
23facility, or installation that emits or may emit any regulated
24air pollutant or any pollutant listed under Section 112(b) of
25the Clean Air Act, except those emissions resulting directly
26from an internal combustion engine for transportation purposes

 

 

09900HB3341ham003- 13 -LRB099 10047 MGM 34300 a

1or from a nonroad engine or nonroad vehicle as defined in
2Section 216 of the Clean Air Act.
3    "Subject to regulation" has the meaning given to it in 40
4CFR 70.2, as now or hereafter amended.
5    "Support facility" means any stationary source (or group of
6stationary sources) that conveys, stores, or otherwise assists
7to a significant extent in the production of a principal
8product at another stationary source (or group of stationary
9sources). A support facility shall be considered to be part of
10the same source as the stationary source (or group of
11stationary sources) that it supports regardless of the 2-digit
12Standard Industrial Classification code for the support
13facility.
14    "USEPA" means the Administrator of the United States
15Environmental Protection Agency (USEPA) or a person designated
16by the Administrator.
 
17    1.1. Exclusion From the CAAPP.
18        a. An owner or operator of a source which determines
19    that the source could be excluded from the CAAPP may seek
20    such exclusion prior to the date that the CAAPP application
21    for the source is due but in no case later than 9 months
22    after the effective date of the CAAPP through the
23    imposition of federally enforceable conditions limiting
24    the "potential to emit" of the source to a level below the
25    major source threshold for that source as described in

 

 

09900HB3341ham003- 14 -LRB099 10047 MGM 34300 a

1    paragraph(c) of subsection 2 of this Section, within a
2    State operating permit issued pursuant to subsection (a) of
3    Section 39 of this Act. After such date, an exclusion from
4    the CAAPP may be sought under paragraph(c) of subsection 3
5    of this Section.
6        b. An owner or operator of a source seeking exclusion
7    from the CAAPP pursuant to paragraph (a) of this subsection
8    must submit a permit application consistent with the
9    existing State permit program which specifically requests
10    such exclusion through the imposition of such federally
11    enforceable conditions.
12        c. Upon such request, if the Agency determines that the
13    owner or operator of a source has met the requirements for
14    exclusion pursuant to paragraph (a) of this subsection and
15    other applicable requirements for permit issuance under
16    subsection (a) of Section 39 of this Act, the Agency shall
17    issue a State operating permit for such source under
18    subsection (a) of Section 39 of this Act, as amended, and
19    regulations promulgated thereunder with federally
20    enforceable conditions limiting the "potential to emit" of
21    the source to a level below the major source threshold for
22    that source as described in paragraph(c) of subsection 2 of
23    this Section.
24        d. The Agency shall provide an owner or operator of a
25    source which may be excluded from the CAAPP pursuant to
26    this subsection with reasonable notice that the owner or

 

 

09900HB3341ham003- 15 -LRB099 10047 MGM 34300 a

1    operator may seek such exclusion.
2        e. The Agency shall provide such sources with the
3    necessary permit application forms.
 
4    2. Applicability.
5        a. Sources subject to this Section shall include:
6            i. Any major source as defined in paragraph (c) of
7        this subsection.
8            ii. Any source subject to a standard or other
9        requirements promulgated under Section 111 (New Source
10        Performance Standards) or Section 112 (Hazardous Air
11        Pollutants) of the Clean Air Act, except that a source
12        is not required to obtain a permit solely because it is
13        subject to regulations or requirements under Section
14        112(r) of the Clean Air Act.
15            iii. Any affected source for acid deposition, as
16        defined in subsection 1 of this Section.
17            iv. Any other source subject to this Section under
18        the Clean Air Act or regulations promulgated
19        thereunder, or applicable Board regulations.
20        b. Sources exempted from this Section shall include:
21            i. All sources listed in paragraph (a) of this
22        subsection that are not major sources, affected
23        sources for acid deposition or solid waste
24        incineration units required to obtain a permit
25        pursuant to Section 129(e) of the Clean Air Act, until

 

 

09900HB3341ham003- 16 -LRB099 10047 MGM 34300 a

1        the source is required to obtain a CAAPP permit
2        pursuant to the Clean Air Act or regulations
3        promulgated thereunder.
4            ii. Nonmajor sources subject to a standard or other
5        requirements subsequently promulgated by USEPA under
6        Section 111 or 112 of the Clean Air Act that are
7        determined by USEPA to be exempt at the time a new
8        standard is promulgated.
9            iii. All sources and source categories that would
10        be required to obtain a permit solely because they are
11        subject to Part 60, Subpart AAA - Standards of
12        Performance for New Residential Wood Heaters (40 CFR
13        Part 60).
14            iv. All sources and source categories that would be
15        required to obtain a permit solely because they are
16        subject to Part 61, Subpart M - National Emission
17        Standard for Hazardous Air Pollutants for Asbestos,
18        Section 61.145 (40 CFR Part 61).
19            v. Any other source categories exempted by USEPA
20        regulations pursuant to Section 502(a) of the Clean Air
21        Act.
22            vi. Major sources of greenhouse gas emissions
23        required to obtain a CAAPP permit under this Section if
24        any of the following occurs:
25                (A) enactment of federal legislation depriving
26            the Administrator of the USEPA of authority to

 

 

09900HB3341ham003- 17 -LRB099 10047 MGM 34300 a

1            regulate greenhouse gases under the Clean Air Act;
2                (B) the issuance of any opinion, ruling,
3            judgment, order, or decree by a federal court
4            depriving the Administrator of the USEPA of
5            authority to regulate greenhouse gases under the
6            Clean Air Act; or
7                (C) action by the President of the United
8            States or the President's authorized agent,
9            including the Administrator of the USEPA, to
10            repeal or withdraw the Greenhouse Gas Tailoring
11            Rule (75 Fed. Reg. 31514, June 3, 2010).
12            If any event listed in this subparagraph (vi)
13        occurs, CAAPP permits issued after such event shall not
14        impose permit terms or conditions addressing
15        greenhouse gases during the effectiveness of any event
16        listed in subparagraph (vi). If any event listed in
17        this subparagraph (vi) occurs, any owner or operator
18        with a CAAPP permit that includes terms or conditions
19        addressing greenhouse gases may elect to submit an
20        application to the Agency to address a revision or
21        repeal of such terms or conditions. If any owner or
22        operator submits such an application, the Agency shall
23        expeditiously process the permit application in
24        accordance with applicable laws and regulations.
25        Nothing in this subparagraph (vi) shall relieve an
26        owner or operator of a source from the requirement to

 

 

09900HB3341ham003- 18 -LRB099 10047 MGM 34300 a

1        obtain a CAAPP permit for its emissions of regulated
2        air pollutants other than greenhouse gases, as
3        required by this Section.
4        c. For purposes of this Section the term "major source"
5    means any source that is:
6            i. A major source under Section 112 of the Clean
7        Air Act, which is defined as:
8                A. For pollutants other than radionuclides,
9            any stationary source or group of stationary
10            sources located within a contiguous area and under
11            common control that emits or has the potential to
12            emit, in the aggregate, 10 tons per year (tpy) or
13            more of any hazardous air pollutant which has been
14            listed pursuant to Section 112(b) of the Clean Air
15            Act, 25 tpy or more of any combination of such
16            hazardous air pollutants, or such lesser quantity
17            as USEPA may establish by rule. Notwithstanding
18            the preceding sentence, emissions from any oil or
19            gas exploration or production well (with its
20            associated equipment) and emissions from any
21            pipeline compressor or pump station shall not be
22            aggregated with emissions from other similar
23            units, whether or not such units are in a
24            contiguous area or under common control, to
25            determine whether such stations are major sources.
26                B. For radionuclides, "major source" shall

 

 

09900HB3341ham003- 19 -LRB099 10047 MGM 34300 a

1            have the meaning specified by the USEPA by rule.
2            ii. A major stationary source of air pollutants, as
3        defined in Section 302 of the Clean Air Act, that
4        directly emits or has the potential to emit, 100 tpy or
5        more of any air pollutant subject to regulation
6        (including any major source of fugitive emissions of
7        any such pollutant, as determined by rule by USEPA).
8        For purposes of this subsection, "fugitive emissions"
9        means those emissions which could not reasonably pass
10        through a stack, chimney, vent, or other
11        functionally-equivalent opening. The fugitive
12        emissions of a stationary source shall not be
13        considered in determining whether it is a major
14        stationary source for the purposes of Section 302(j) of
15        the Clean Air Act, unless the source belongs to one of
16        the following categories of stationary source:
17                A. Coal cleaning plants (with thermal dryers).
18                B. Kraft pulp mills.
19                C. Portland cement plants.
20                D. Primary zinc smelters.
21                E. Iron and steel mills.
22                F. Primary aluminum ore reduction plants.
23                G. Primary copper smelters.
24                H. Municipal incinerators capable of charging
25            more than 250 tons of refuse per day.
26                I. Hydrofluoric, sulfuric, or nitric acid

 

 

09900HB3341ham003- 20 -LRB099 10047 MGM 34300 a

1            plants.
2                J. Petroleum refineries.
3                K. Lime plants.
4                L. Phosphate rock processing plants.
5                M. Coke oven batteries.
6                N. Sulfur recovery plants.
7                O. Carbon black plants (furnace process).
8                P. Primary lead smelters.
9                Q. Fuel conversion plants.
10                R. Sintering plants.
11                S. Secondary metal production plants.
12                T. Chemical process plants.
13                U. Fossil-fuel boilers (or combination
14            thereof) totaling more than 250 million British
15            thermal units per hour heat input.
16                V. Petroleum storage and transfer units with a
17            total storage capacity exceeding 300,000 barrels.
18                W. Taconite ore processing plants.
19                X. Glass fiber processing plants.
20                Y. Charcoal production plants.
21                Z. Fossil fuel-fired steam electric plants of
22            more than 250 million British thermal units per
23            hour heat input.
24                AA. All other stationary source categories,
25            which as of August 7, 1980 are being regulated by a
26            standard promulgated under Section 111 or 112 of

 

 

09900HB3341ham003- 21 -LRB099 10047 MGM 34300 a

1            the Clean Air Act.
2                BB. Any other stationary source category
3            designated by USEPA by rule.
4            iii. A major stationary source as defined in part D
5        of Title I of the Clean Air Act including:
6                A. For ozone nonattainment areas, sources with
7            the potential to emit 100 tons or more per year of
8            volatile organic compounds or oxides of nitrogen
9            in areas classified as "marginal" or "moderate",
10            50 tons or more per year in areas classified as
11            "serious", 25 tons or more per year in areas
12            classified as "severe", and 10 tons or more per
13            year in areas classified as "extreme"; except that
14            the references in this clause to 100, 50, 25, and
15            10 tons per year of nitrogen oxides shall not apply
16            with respect to any source for which USEPA has made
17            a finding, under Section 182(f)(1) or (2) of the
18            Clean Air Act, that requirements otherwise
19            applicable to such source under Section 182(f) of
20            the Clean Air Act do not apply. Such sources shall
21            remain subject to the major source criteria of
22            subparagraph (ii) of paragraph(c) of this
23            subsection.
24                B. For ozone transport regions established
25            pursuant to Section 184 of the Clean Air Act,
26            sources with the potential to emit 50 tons or more

 

 

09900HB3341ham003- 22 -LRB099 10047 MGM 34300 a

1            per year of volatile organic compounds (VOCs).
2                C. For carbon monoxide nonattainment areas (1)
3            that are classified as "serious", and (2) in which
4            stationary sources contribute significantly to
5            carbon monoxide levels as determined under rules
6            issued by USEPA, sources with the potential to emit
7            50 tons or more per year of carbon monoxide.
8                D. For particulate matter (PM-10)
9            nonattainment areas classified as "serious",
10            sources with the potential to emit 70 tons or more
11            per year of PM-10.
 
12    3. Agency Authority To Issue CAAPP Permits and Federally
13Enforceable State Operating Permits.
14        a. The Agency shall issue CAAPP permits under this
15    Section consistent with the Clean Air Act and regulations
16    promulgated thereunder and this Act and regulations
17    promulgated thereunder.
18        b. The Agency shall issue CAAPP permits for fixed terms
19    of 5 years, except CAAPP permits issued for solid waste
20    incineration units combusting municipal waste which shall
21    be issued for fixed terms of 12 years and except CAAPP
22    permits for affected sources for acid deposition which
23    shall be issued for initial terms to expire on December 31,
24    1999, and for fixed terms of 5 years thereafter.
25        c. The Agency shall have the authority to issue a State

 

 

09900HB3341ham003- 23 -LRB099 10047 MGM 34300 a

1    operating permit for a source under subsection (a) of
2    Section 39 of this Act, as amended, and regulations
3    promulgated thereunder, which includes federally
4    enforceable conditions limiting the "potential to emit" of
5    the source to a level below the major source threshold for
6    that source as described in paragraph(c) of subsection 2 of
7    this Section, thereby excluding the source from the CAAPP,
8    when requested by the applicant pursuant to paragraph(u) of
9    subsection 5 of this Section. The public notice
10    requirements of this Section applicable to CAAPP permits
11    shall also apply to the initial issuance of permits under
12    this paragraph.
13        d. For purposes of this Act, a permit issued by USEPA
14    under Section 505 of the Clean Air Act, as now and
15    hereafter amended, shall be deemed to be a permit issued by
16    the Agency pursuant to Section 39.5 of this Act.
 
17    4. Transition.
18        a. An owner or operator of a CAAPP source shall not be
19    required to renew an existing State operating permit for
20    any emission unit at such CAAPP source once a CAAPP
21    application timely submitted prior to expiration of the
22    State operating permit has been deemed complete. For
23    purposes other than permit renewal, the obligation upon the
24    owner or operator of a CAAPP source to obtain a State
25    operating permit is not removed upon submittal of the

 

 

09900HB3341ham003- 24 -LRB099 10047 MGM 34300 a

1    complete CAAPP permit application. An owner or operator of
2    a CAAPP source seeking to make a modification to a source
3    prior to the issuance of its CAAPP permit shall be required
4    to obtain a construction permit, operating permit, or both
5    as required for such modification in accordance with the
6    State permit program under subsection (a) of Section 39 of
7    this Act, as amended, and regulations promulgated
8    thereunder. The application for such construction permit,
9    operating permit, or both shall be considered an amendment
10    to the CAAPP application submitted for such source.
11        b. An owner or operator of a CAAPP source shall
12    continue to operate in accordance with the terms and
13    conditions of its applicable State operating permit
14    notwithstanding the expiration of the State operating
15    permit until the source's CAAPP permit has been issued.
16        c. An owner or operator of a CAAPP source shall submit
17    its initial CAAPP application to the Agency no later than
18    12 months after the effective date of the CAAPP. The Agency
19    may request submittal of initial CAAPP applications during
20    this 12-month period according to a schedule set forth
21    within Agency procedures, however, in no event shall the
22    Agency require such submittal earlier than 3 months after
23    such effective date of the CAAPP. An owner or operator may
24    voluntarily submit its initial CAAPP application prior to
25    the date required within this paragraph or applicable
26    procedures, if any, subsequent to the date the Agency

 

 

09900HB3341ham003- 25 -LRB099 10047 MGM 34300 a

1    submits the CAAPP to USEPA for approval.
2        d. The Agency shall act on initial CAAPP applications
3    in accordance with paragraph (j) of subsection 5 of this
4    Section.
5        e. For purposes of this Section, the term "initial
6    CAAPP application" shall mean the first CAAPP application
7    submitted for a source existing as of the effective date of
8    the CAAPP.
9        f. The Agency shall provide owners or operators of
10    CAAPP sources with at least 3 months advance notice of the
11    date on which their applications are required to be
12    submitted. In determining which sources shall be subject to
13    early submittal, the Agency shall include among its
14    considerations the complexity of the permit application,
15    and the burden that such early submittal will have on the
16    source.
17        g. The CAAPP permit shall upon becoming effective
18    supersede the State operating permit.
19        h. The Agency shall have the authority to adopt
20    procedural rules, in accordance with the Illinois
21    Administrative Procedure Act, as the Agency deems
22    necessary, to implement this subsection.
 
23    5. Applications and Completeness.
24        a. An owner or operator of a CAAPP source shall submit
25    its complete CAAPP application consistent with the Act and

 

 

09900HB3341ham003- 26 -LRB099 10047 MGM 34300 a

1    applicable regulations.
2        b. An owner or operator of a CAAPP source shall submit
3    a single complete CAAPP application covering all emission
4    units at that source.
5        c. To be deemed complete, a CAAPP application must
6    provide all information, as requested in Agency
7    application forms, sufficient to evaluate the subject
8    source and its application and to determine all applicable
9    requirements, pursuant to the Clean Air Act, and
10    regulations thereunder, this Act and regulations
11    thereunder. Such Agency application forms shall be
12    finalized and made available prior to the date on which any
13    CAAPP application is required.
14        d. An owner or operator of a CAAPP source shall submit,
15    as part of its complete CAAPP application, a compliance
16    plan, including a schedule of compliance, describing how
17    each emission unit will comply with all applicable
18    requirements. Any such schedule of compliance shall be
19    supplemental to, and shall not sanction noncompliance
20    with, the applicable requirements on which it is based.
21        e. Each submitted CAAPP application shall be certified
22    for truth, accuracy, and completeness by a responsible
23    official in accordance with applicable regulations.
24        f. The Agency shall provide notice to a CAAPP applicant
25    as to whether a submitted CAAPP application is complete.
26    Unless the Agency notifies the applicant of

 

 

09900HB3341ham003- 27 -LRB099 10047 MGM 34300 a

1    incompleteness, within 60 days after receipt of the CAAPP
2    application, the application shall be deemed complete. The
3    Agency may request additional information as needed to make
4    the completeness determination. The Agency may to the
5    extent practicable provide the applicant with a reasonable
6    opportunity to correct deficiencies prior to a final
7    determination of completeness.
8        g. If after the determination of completeness the
9    Agency finds that additional information is necessary to
10    evaluate or take final action on the CAAPP application, the
11    Agency may request in writing such information from the
12    source with a reasonable deadline for response.
13        h. If the owner or operator of a CAAPP source submits a
14    timely and complete CAAPP application, the source's
15    failure to have a CAAPP permit shall not be a violation of
16    this Section until the Agency takes final action on the
17    submitted CAAPP application, provided, however, where the
18    applicant fails to submit the requested information under
19    paragraph(g) of this subsection 5 within the time frame
20    specified by the Agency, this protection shall cease to
21    apply.
22        i. Any applicant who fails to submit any relevant facts
23    necessary to evaluate the subject source and its CAAPP
24    application or who has submitted incorrect information in a
25    CAAPP application shall, upon becoming aware of such
26    failure or incorrect submittal, submit supplementary facts

 

 

09900HB3341ham003- 28 -LRB099 10047 MGM 34300 a

1    or correct information to the Agency. In addition, an
2    applicant shall provide to the Agency additional
3    information as necessary to address any requirements which
4    become applicable to the source subsequent to the date the
5    applicant submitted its complete CAAPP application but
6    prior to release of the draft CAAPP permit.
7        j. The Agency shall issue or deny the CAAPP permit
8    within 18 months after the date of receipt of the complete
9    CAAPP application, with the following exceptions: (i)
10    permits for affected sources for acid deposition shall be
11    issued or denied within 6 months after receipt of a
12    complete application in accordance with subsection 17 of
13    this Section; (ii) the Agency shall act on initial CAAPP
14    applications within 24 months after the date of receipt of
15    the complete CAAPP application; (iii) the Agency shall act
16    on complete applications containing early reduction
17    demonstrations under Section 112(i)(5) of the Clean Air Act
18    within 9 months of receipt of the complete CAAPP
19    application.
20        Where the Agency does not take final action on the
21    permit within the required time period, the permit shall
22    not be deemed issued; rather, the failure to act shall be
23    treated as a final permit action for purposes of judicial
24    review pursuant to Sections 40.2 and 41 of this Act.
25        k. The submittal of a complete CAAPP application shall
26    not affect the requirement that any source have a

 

 

09900HB3341ham003- 29 -LRB099 10047 MGM 34300 a

1    preconstruction permit under Title I of the Clean Air Act.
2        l. Unless a timely and complete renewal application has
3    been submitted consistent with this subsection, a CAAPP
4    source operating upon the expiration of its CAAPP permit
5    shall be deemed to be operating without a CAAPP permit.
6    Such operation is prohibited under this Act.
7        m. Permits being renewed shall be subject to the same
8    procedural requirements, including those for public
9    participation and federal review and objection, that apply
10    to original permit issuance.
11        n. For purposes of permit renewal, a timely application
12    is one that is submitted no less than 9 months prior to the
13    date of permit expiration.
14        o. The terms and conditions of a CAAPP permit shall
15    remain in effect until the issuance of a CAAPP renewal
16    permit provided a timely and complete CAAPP application has
17    been submitted.
18        p. The owner or operator of a CAAPP source seeking a
19    permit shield pursuant to paragraph(j) of subsection 7 of
20    this Section shall request such permit shield in the CAAPP
21    application regarding that source.
22        q. The Agency shall make available to the public all
23    documents submitted by the applicant to the Agency,
24    including each CAAPP application, compliance plan
25    (including the schedule of compliance), and emissions or
26    compliance monitoring report, with the exception of

 

 

09900HB3341ham003- 30 -LRB099 10047 MGM 34300 a

1    information entitled to confidential treatment pursuant to
2    Section 7 of this Act.
3        r. The Agency shall use the standardized forms required
4    under Title IV of the Clean Air Act and regulations
5    promulgated thereunder for affected sources for acid
6    deposition.
7        s. An owner or operator of a CAAPP source may include
8    within its CAAPP application a request for permission to
9    operate during a startup, malfunction, or breakdown
10    consistent with applicable Board regulations.
11        t. An owner or operator of a CAAPP source, in order to
12    utilize the operational flexibility provided under
13    paragraph(l) of subsection 7 of this Section, must request
14    such use and provide the necessary information within its
15    CAAPP application.
16        u. An owner or operator of a CAAPP source which seeks
17    exclusion from the CAAPP through the imposition of
18    federally enforceable conditions, pursuant to paragraph(c)
19    of subsection 3 of this Section, must request such
20    exclusion within a CAAPP application submitted consistent
21    with this subsection on or after the date that the CAAPP
22    application for the source is due. Prior to such date, but
23    in no case later than 9 months after the effective date of
24    the CAAPP, such owner or operator may request the
25    imposition of federally enforceable conditions pursuant to
26    paragraph(b) of subsection 1.1 of this Section.

 

 

09900HB3341ham003- 31 -LRB099 10047 MGM 34300 a

1        v. CAAPP applications shall contain accurate
2    information on allowable emissions to implement the fee
3    provisions of subsection 18 of this Section.
4        w. An owner or operator of a CAAPP source shall submit
5    within its CAAPP application emissions information
6    regarding all regulated air pollutants emitted at that
7    source consistent with applicable Agency procedures.
8    Emissions information regarding insignificant activities
9    or emission levels, as determined by the Agency pursuant to
10    Board regulations, may be submitted as a list within the
11    CAAPP application. The Agency shall propose regulations to
12    the Board defining insignificant activities or emission
13    levels, consistent with federal regulations, if any, no
14    later than 18 months after the effective date of this
15    amendatory Act of 1992, consistent with Section 112(n)(1)
16    of the Clean Air Act. The Board shall adopt final
17    regulations defining insignificant activities or emission
18    levels no later than 9 months after the date of the
19    Agency's proposal.
20        x. The owner or operator of a new CAAPP source shall
21    submit its complete CAAPP application consistent with this
22    subsection within 12 months after commencing operation of
23    such source. The owner or operator of an existing source
24    that has been excluded from the provisions of this Section
25    under subsection 1.1 or paragraph (c) of subsection 3 of
26    this Section and that becomes subject to the CAAPP solely

 

 

09900HB3341ham003- 32 -LRB099 10047 MGM 34300 a

1    due to a change in operation at the source shall submit its
2    complete CAAPP application consistent with this subsection
3    at least 180 days before commencing operation in accordance
4    with the change in operation.
5        y. The Agency shall have the authority to adopt
6    procedural rules, in accordance with the Illinois
7    Administrative Procedure Act, as the Agency deems
8    necessary to implement this subsection.
 
9    6. Prohibitions.
10        a. It shall be unlawful for any person to violate any
11    terms or conditions of a permit issued under this Section,
12    to operate any CAAPP source except in compliance with a
13    permit issued by the Agency under this Section or to
14    violate any other applicable requirements. All terms and
15    conditions of a permit issued under this Section are
16    enforceable by USEPA and citizens under the Clean Air Act,
17    except those, if any, that are specifically designated as
18    not being federally enforceable in the permit pursuant to
19    paragraph(m) of subsection 7 of this Section.
20        b. After the applicable CAAPP permit or renewal
21    application submittal date, as specified in subsection 5 of
22    this Section, no person shall operate a CAAPP source
23    without a CAAPP permit unless the complete CAAPP permit or
24    renewal application for such source has been timely
25    submitted to the Agency.

 

 

09900HB3341ham003- 33 -LRB099 10047 MGM 34300 a

1        c. No owner or operator of a CAAPP source shall cause
2    or threaten or allow the continued operation of an emission
3    source during malfunction or breakdown of the emission
4    source or related air pollution control equipment if such
5    operation would cause a violation of the standards or
6    limitations applicable to the source, unless the CAAPP
7    permit granted to the source provides for such operation
8    consistent with this Act and applicable Board regulations.
 
9    7. Permit Content.
10        a. All CAAPP permits shall contain emission
11    limitations and standards and other enforceable terms and
12    conditions, including but not limited to operational
13    requirements, and schedules for achieving compliance at
14    the earliest reasonable date, which are or will be required
15    to accomplish the purposes and provisions of this Act and
16    to assure compliance with all applicable requirements.
17        b. The Agency shall include among such conditions
18    applicable monitoring, reporting, record keeping and
19    compliance certification requirements, as authorized by
20    paragraphs (d), (e), and (f) of this subsection, that the
21    Agency deems necessary to assure compliance with the Clean
22    Air Act, the regulations promulgated thereunder, this Act,
23    and applicable Board regulations. When monitoring,
24    reporting, record keeping, and compliance certification
25    requirements are specified within the Clean Air Act,

 

 

09900HB3341ham003- 34 -LRB099 10047 MGM 34300 a

1    regulations promulgated thereunder, this Act, or
2    applicable regulations, such requirements shall be
3    included within the CAAPP permit. The Board shall have
4    authority to promulgate additional regulations where
5    necessary to accomplish the purposes of the Clean Air Act,
6    this Act, and regulations promulgated thereunder.
7        c. The Agency shall assure, within such conditions, the
8    use of terms, test methods, units, averaging periods, and
9    other statistical conventions consistent with the
10    applicable emission limitations, standards, and other
11    requirements contained in the permit.
12        d. To meet the requirements of this subsection with
13    respect to monitoring, the permit shall:
14            i. Incorporate and identify all applicable
15        emissions monitoring and analysis procedures or test
16        methods required under the Clean Air Act, regulations
17        promulgated thereunder, this Act, and applicable Board
18        regulations, including any procedures and methods
19        promulgated by USEPA pursuant to Section 504(b) or
20        Section 114 (a)(3) of the Clean Air Act.
21            ii. Where the applicable requirement does not
22        require periodic testing or instrumental or
23        noninstrumental monitoring (which may consist of
24        recordkeeping designed to serve as monitoring),
25        require periodic monitoring sufficient to yield
26        reliable data from the relevant time period that is

 

 

09900HB3341ham003- 35 -LRB099 10047 MGM 34300 a

1        representative of the source's compliance with the
2        permit, as reported pursuant to paragraph (f) of this
3        subsection. The Agency may determine that
4        recordkeeping requirements are sufficient to meet the
5        requirements of this subparagraph.
6            iii. As necessary, specify requirements concerning
7        the use, maintenance, and when appropriate,
8        installation of monitoring equipment or methods.
9        e. To meet the requirements of this subsection with
10    respect to record keeping, the permit shall incorporate and
11    identify all applicable recordkeeping requirements and
12    require, where applicable, the following:
13            i. Records of required monitoring information that
14        include the following:
15                A. The date, place and time of sampling or
16            measurements.
17                B. The date(s) analyses were performed.
18                C. The company or entity that performed the
19            analyses.
20                D. The analytical techniques or methods used.
21                E. The results of such analyses.
22                F. The operating conditions as existing at the
23            time of sampling or measurement.
24            ii.    Retention of records of all monitoring data
25        and support information for a period of at least 5
26        years from the date of the monitoring sample,

 

 

09900HB3341ham003- 36 -LRB099 10047 MGM 34300 a

1        measurement, report, or application. Support
2        information includes all calibration and maintenance
3        records, original strip-chart recordings for
4        continuous monitoring instrumentation, and copies of
5        all reports required by the permit.
6        f. To meet the requirements of this subsection with
7    respect to reporting, the permit shall incorporate and
8    identify all applicable reporting requirements and require
9    the following:
10            i. Submittal of reports of any required monitoring
11        every 6 months. More frequent submittals may be
12        requested by the Agency if such submittals are
13        necessary to assure compliance with this Act or
14        regulations promulgated by the Board thereunder. All
15        instances of deviations from permit requirements must
16        be clearly identified in such reports. All required
17        reports must be certified by a responsible official
18        consistent with subsection 5 of this Section.
19            ii. Prompt reporting of deviations from permit
20        requirements, including those attributable to upset
21        conditions as defined in the permit, the probable cause
22        of such deviations, and any corrective actions or
23        preventive measures taken.
24        g. Each CAAPP permit issued under subsection 10 of this
25    Section shall include a condition prohibiting emissions
26    exceeding any allowances that the source lawfully holds

 

 

09900HB3341ham003- 37 -LRB099 10047 MGM 34300 a

1    under Title IV of the Clean Air Act or the regulations
2    promulgated thereunder, consistent with subsection 17 of
3    this Section and applicable regulations, if any.
4        h. All CAAPP permits shall state that, where another
5    applicable requirement of the Clean Air Act is more
6    stringent than any applicable requirement of regulations
7    promulgated under Title IV of the Clean Air Act, both
8    provisions shall be incorporated into the permit and shall
9    be State and federally enforceable.
10        i. Each CAAPP permit issued under subsection 10 of this
11    Section shall include a severability clause to ensure the
12    continued validity of the various permit requirements in
13    the event of a challenge to any portions of the permit.
14        j. The following shall apply with respect to owners or
15    operators requesting a permit shield:
16            i. The Agency shall include in a CAAPP permit, when
17        requested by an applicant pursuant to paragraph(p) of
18        subsection 5 of this Section, a provision stating that
19        compliance with the conditions of the permit shall be
20        deemed compliance with applicable requirements which
21        are applicable as of the date of release of the
22        proposed permit, provided that:
23                A. The applicable requirement is specifically
24            identified within the permit; or
25                B. The Agency in acting on the CAAPP
26            application or revision determines in writing that

 

 

09900HB3341ham003- 38 -LRB099 10047 MGM 34300 a

1            other requirements specifically identified are not
2            applicable to the source, and the permit includes
3            that determination or a concise summary thereof.
4            ii. The permit shall identify the requirements for
5        which the source is shielded. The shield shall not
6        extend to applicable requirements which are
7        promulgated after the date of release of the proposed
8        permit unless the permit has been modified to reflect
9        such new requirements.
10            iii. A CAAPP permit which does not expressly
11        indicate the existence of a permit shield shall not
12        provide such a shield.
13            iv. Nothing in this paragraph or in a CAAPP permit
14        shall alter or affect the following:
15                A. The provisions of Section 303 (emergency
16            powers) of the Clean Air Act, including USEPA's
17            authority under that section.
18                B. The liability of an owner or operator of a
19            source for any violation of applicable
20            requirements prior to or at the time of permit
21            issuance.
22                C. The applicable requirements of the acid
23            rain program consistent with Section 408(a) of the
24            Clean Air Act.
25                D. The ability of USEPA to obtain information
26            from a source pursuant to Section 114

 

 

09900HB3341ham003- 39 -LRB099 10047 MGM 34300 a

1            (inspections, monitoring, and entry) of the Clean
2            Air Act.
3        k. Each CAAPP permit shall include an emergency
4    provision providing an affirmative defense of emergency to
5    an action brought for noncompliance with technology-based
6    emission limitations under a CAAPP permit if the following
7    conditions are met through properly signed,
8    contemporaneous operating logs, or other relevant
9    evidence:
10            i. An emergency occurred and the permittee can
11        identify the cause(s) of the emergency.
12            ii. The permitted facility was at the time being
13        properly operated.
14            iii. The permittee submitted notice of the
15        emergency to the Agency within 2 working days after the
16        time when emission limitations were exceeded due to the
17        emergency. This notice must contain a detailed
18        description of the emergency, any steps taken to
19        mitigate emissions, and corrective actions taken.
20            iv. During the period of the emergency the
21        permittee took all reasonable steps to minimize levels
22        of emissions that exceeded the emission limitations,
23        standards, or requirements in the permit.
24        For purposes of this subsection, "emergency" means any
25    situation arising from sudden and reasonably unforeseeable
26    events beyond the control of the source, such as an act of

 

 

09900HB3341ham003- 40 -LRB099 10047 MGM 34300 a

1    God, that requires immediate corrective action to restore
2    normal operation, and that causes the source to exceed a
3    technology-based emission limitation under the permit, due
4    to unavoidable increases in emissions attributable to the
5    emergency. An emergency shall not include noncompliance to
6    the extent caused by improperly designed equipment, lack of
7    preventative maintenance, careless or improper operation,
8    or operation error.
9        In any enforcement proceeding, the permittee seeking
10    to establish the occurrence of an emergency has the burden
11    of proof. This provision is in addition to any emergency or
12    upset provision contained in any applicable requirement.
13    This provision does not relieve a permittee of any
14    reporting obligations under existing federal or state laws
15    or regulations.
16        l. The Agency shall include in each permit issued under
17    subsection 10 of this Section:
18            i. Terms and conditions for reasonably anticipated
19        operating scenarios identified by the source in its
20        application. The permit terms and conditions for each
21        such operating scenario shall meet all applicable
22        requirements and the requirements of this Section.
23                A. Under this subparagraph, the source must
24            record in a log at the permitted facility a record
25            of the scenario under which it is operating
26            contemporaneously with making a change from one

 

 

09900HB3341ham003- 41 -LRB099 10047 MGM 34300 a

1            operating scenario to another.
2                B. The permit shield described in paragraph(j)
3            of subsection 7 of this Section shall extend to all
4            terms and conditions under each such operating
5            scenario.
6            ii. Where requested by an applicant, all terms and
7        conditions allowing for trading of emissions increases
8        and decreases between different emission units at the
9        CAAPP source, to the extent that the applicable
10        requirements provide for trading of such emissions
11        increases and decreases without a case-by-case
12        approval of each emissions trade. Such terms and
13        conditions:
14                A. Shall include all terms required under this
15            subsection to determine compliance;
16                B. Must meet all applicable requirements;
17                C. Shall extend the permit shield described in
18            paragraph(j) of subsection 7 of this Section to all
19            terms and conditions that allow such increases and
20            decreases in emissions.
21        m. The Agency shall specifically designate as not being
22    federally enforceable under the Clean Air Act any terms and
23    conditions included in the permit that are not specifically
24    required under the Clean Air Act or federal regulations
25    promulgated thereunder. Terms or conditions so designated
26    shall be subject to all applicable state requirements,

 

 

09900HB3341ham003- 42 -LRB099 10047 MGM 34300 a

1    except the requirements of subsection 7 (other than this
2    paragraph, paragraph q of subsection 7, subsections 8
3    through 11, and subsections 13 through 16 of this Section.
4    The Agency shall, however, include such terms and
5    conditions in the CAAPP permit issued to the source.
6        n. Each CAAPP permit issued under subsection 10 of this
7    Section shall specify and reference the origin of and
8    authority for each term or condition, and identify any
9    difference in form as compared to the applicable
10    requirement upon which the term or condition is based.
11        o. Each CAAPP permit issued under subsection 10 of this
12    Section shall include provisions stating the following:
13            i. Duty to comply. The permittee must comply with
14        all terms and conditions of the CAAPP permit. Any
15        permit noncompliance constitutes a violation of the
16        Clean Air Act and the Act, and is grounds for any or
17        all of the following: enforcement action; permit
18        termination, revocation and reissuance, or
19        modification; or denial of a permit renewal
20        application.
21            ii. Need to halt or reduce activity not a defense.
22        It shall not be a defense for a permittee in an
23        enforcement action that it would have been necessary to
24        halt or reduce the permitted activity in order to
25        maintain compliance with the conditions of this
26        permit.

 

 

09900HB3341ham003- 43 -LRB099 10047 MGM 34300 a

1            iii. Permit actions. The permit may be modified,
2        revoked, reopened, and reissued, or terminated for
3        cause in accordance with the applicable subsections of
4        Section 39.5 of this Act. The filing of a request by
5        the permittee for a permit modification, revocation
6        and reissuance, or termination, or of a notification of
7        planned changes or anticipated noncompliance does not
8        stay any permit condition.
9            iv. Property rights. The permit does not convey any
10        property rights of any sort, or any exclusive
11        privilege.
12            v. Duty to provide information. The permittee
13        shall furnish to the Agency within a reasonable time
14        specified by the Agency any information that the Agency
15        may request in writing to determine whether cause
16        exists for modifying, revoking and reissuing, or
17        terminating the permit or to determine compliance with
18        the permit. Upon request, the permittee shall also
19        furnish to the Agency copies of records required to be
20        kept by the permit or, for information claimed to be
21        confidential, the permittee may furnish such records
22        directly to USEPA along with a claim of
23        confidentiality.
24            vi. Duty to pay fees. The permittee must pay fees
25        to the Agency consistent with the fee schedule approved
26        pursuant to subsection 18 of this Section, and submit

 

 

09900HB3341ham003- 44 -LRB099 10047 MGM 34300 a

1        any information relevant thereto.
2            vii. Emissions trading. No permit revision shall
3        be required for increases in emissions allowed under
4        any approved economic incentives, marketable permits,
5        emissions trading, and other similar programs or
6        processes for changes that are provided for in the
7        permit and that are authorized by the applicable
8        requirement.
9        p. Each CAAPP permit issued under subsection 10 of this
10    Section shall contain the following elements with respect
11    to compliance:
12            i. Compliance certification, testing, monitoring,
13        reporting, and record keeping requirements sufficient
14        to assure compliance with the terms and conditions of
15        the permit. Any document (including reports) required
16        by a CAAPP permit shall contain a certification by a
17        responsible official that meets the requirements of
18        subsection 5 of this Section and applicable
19        regulations.
20            ii. Inspection and entry requirements that
21        necessitate that, upon presentation of credentials and
22        other documents as may be required by law and in
23        accordance with constitutional limitations, the
24        permittee shall allow the Agency, or an authorized
25        representative to perform the following:
26                A. Enter upon the permittee's premises where a

 

 

09900HB3341ham003- 45 -LRB099 10047 MGM 34300 a

1            CAAPP source is located or emissions-related
2            activity is conducted, or where records must be
3            kept under the conditions of the permit.
4                B. Have access to and copy, at reasonable
5            times, any records that must be kept under the
6            conditions of the permit.
7                C. Inspect at reasonable times any facilities,
8            equipment (including monitoring and air pollution
9            control equipment), practices, or operations
10            regulated or required under the permit.
11                D. Sample or monitor any substances or
12            parameters at any location:
13                    1. As authorized by the Clean Air Act, at
14                reasonable times, for the purposes of assuring
15                compliance with the CAAPP permit or applicable
16                requirements; or
17                    2. As otherwise authorized by this Act.
18            iii. A schedule of compliance consistent with
19        subsection 5 of this Section and applicable
20        regulations.
21            iv. Progress reports consistent with an applicable
22        schedule of compliance pursuant to paragraph(d) of
23        subsection 5 of this Section and applicable
24        regulations to be submitted semiannually, or more
25        frequently if the Agency determines that such more
26        frequent submittals are necessary for compliance with

 

 

09900HB3341ham003- 46 -LRB099 10047 MGM 34300 a

1        the Act or regulations promulgated by the Board
2        thereunder. Such progress reports shall contain the
3        following:
4                A. Required dates for achieving the
5            activities, milestones, or compliance required by
6            the schedule of compliance and dates when such
7            activities, milestones or compliance were
8            achieved.
9                B. An explanation of why any dates in the
10            schedule of compliance were not or will not be met,
11            and any preventive or corrective measures adopted.
12            v. Requirements for compliance certification with
13        terms and conditions contained in the permit,
14        including emission limitations, standards, or work
15        practices. Permits shall include each of the
16        following:
17                A. The frequency (annually or more frequently
18            as specified in any applicable requirement or by
19            the Agency pursuant to written procedures) of
20            submissions of compliance certifications.
21                B. A means for assessing or monitoring the
22            compliance of the source with its emissions
23            limitations, standards, and work practices.
24                C. A requirement that the compliance
25            certification include the following:
26                    1. The identification of each term or

 

 

09900HB3341ham003- 47 -LRB099 10047 MGM 34300 a

1                condition contained in the permit that is the
2                basis of the certification.
3                    2. The compliance status.
4                    3. Whether compliance was continuous or
5                intermittent.
6                    4. The method(s) used for determining the
7                compliance status of the source, both
8                currently and over the reporting period
9                consistent with subsection 7 of this Section.
10                D. A requirement that all compliance
11            certifications be submitted to USEPA as well as to
12            the Agency.
13                E. Additional requirements as may be specified
14            pursuant to Sections 114(a)(3) and 504(b) of the
15            Clean Air Act.
16                F. Other provisions as the Agency may require.
17        q. If the owner or operator of CAAPP source can
18    demonstrate in its CAAPP application, including an
19    application for a significant modification, that an
20    alternative emission limit would be equivalent to that
21    contained in the applicable Board regulations, the Agency
22    shall include the alternative emission limit in the CAAPP
23    permit, which shall supersede the emission limit set forth
24    in the applicable Board regulations, and shall include
25    conditions that insure that the resulting emission limit is
26    quantifiable, accountable, enforceable, and based on

 

 

09900HB3341ham003- 48 -LRB099 10047 MGM 34300 a

1    replicable procedures.
2    8. Public Notice; Affected State Review.
3        a. The Agency shall provide notice to the public,
4    including an opportunity for public comment and a hearing,
5    on each draft CAAPP permit for issuance, renewal or
6    significant modification, subject to Section 7.1 and
7    subsection (a) of Section 7 of this Act.
8        b. The Agency shall prepare a draft CAAPP permit and a
9    statement that sets forth the legal and factual basis for
10    the draft CAAPP permit conditions, including references to
11    the applicable statutory or regulatory provisions. The
12    Agency shall provide this statement to any person who
13    requests it.
14        c. The Agency shall give notice of each draft CAAPP
15    permit to the applicant and to any affected State on or
16    before the time that the Agency has provided notice to the
17    public, except as otherwise provided in this Act.
18        d. The Agency, as part of its submittal of a proposed
19    permit to USEPA (or as soon as possible after the submittal
20    for minor permit modification procedures allowed under
21    subsection 14 of this Section), shall notify USEPA and any
22    affected State in writing of any refusal of the Agency to
23    accept all of the recommendations for the proposed permit
24    that an affected State submitted during the public or
25    affected State review period. The notice shall include the
26    Agency's reasons for not accepting the recommendations.

 

 

09900HB3341ham003- 49 -LRB099 10047 MGM 34300 a

1    The Agency is not required to accept recommendations that
2    are not based on applicable requirements or the
3    requirements of this Section.
4        e. The Agency shall make available to the public any
5    CAAPP permit application, compliance plan (including the
6    schedule of compliance), CAAPP permit, and emissions or
7    compliance monitoring report. If an owner or operator of a
8    CAAPP source is required to submit information entitled to
9    protection from disclosure under Section 7.1 and
10    subsection (a) of Section 7 of this Act, the owner or
11    operator shall submit such information separately. The
12    requirements of Section 7.1 and subsection (a) of Section 7
13    of this Act shall apply to such information, which shall
14    not be included in a CAAPP permit unless required by law.
15    The contents of a CAAPP permit shall not be entitled to
16    protection under Section 7.1 and subsection (a) of Section
17    7 of this Act.
18        f. The Agency shall have the authority to adopt
19    procedural rules, in accordance with the Illinois
20    Administrative Procedure Act, as the Agency deems
21    necessary, to implement this subsection.
22        g. If requested by the permit applicant, the Agency
23    shall provide the permit applicant with a copy of the draft
24    CAAPP permit prior to any public review period. If
25    requested by the permit applicant, the Agency shall provide
26    the permit applicant with a copy of the final CAAPP permit

 

 

09900HB3341ham003- 50 -LRB099 10047 MGM 34300 a

1    prior to issuance of the CAAPP permit.
 
2    9. USEPA Notice and Objection.
3        a. The Agency shall provide to USEPA for its review a
4    copy of each CAAPP application (including any application
5    for permit modification), statement of basis as provided in
6    paragraph(b) of subsection 8 of this Section, proposed
7    CAAPP permit, CAAPP permit, and, if the Agency does not
8    incorporate any affected State's recommendations on a
9    proposed CAAPP permit, a written statement of this decision
10    and its reasons for not accepting the recommendations,
11    except as otherwise provided in this Act or by agreement
12    with USEPA. To the extent practicable, the preceding
13    information shall be provided in computer readable format
14    compatible with USEPA's national database management
15    system.
16        b. The Agency shall not issue the proposed CAAPP permit
17    if USEPA objects in writing within 45 days after receipt of
18    the proposed CAAPP permit and all necessary supporting
19    information.
20        c. If USEPA objects in writing to the issuance of the
21    proposed CAAPP permit within the 45-day period, the Agency
22    shall respond in writing and may revise and resubmit the
23    proposed CAAPP permit in response to the stated objection,
24    to the extent supported by the record, within 90 days after
25    the date of the objection. Prior to submitting a revised

 

 

09900HB3341ham003- 51 -LRB099 10047 MGM 34300 a

1    permit to USEPA, the Agency shall provide the applicant and
2    any person who participated in the public comment process,
3    pursuant to subsection 8 of this Section, with a 10-day
4    period to comment on any revision which the Agency is
5    proposing to make to the permit in response to USEPA's
6    objection in accordance with Agency procedures.
7        d. Any USEPA objection under this subsection,
8    according to the Clean Air Act, will include a statement of
9    reasons for the objection and a description of the terms
10    and conditions that must be in the permit, in order to
11    adequately respond to the objections. Grounds for a USEPA
12    objection include the failure of the Agency to: (1) submit
13    the items and notices required under this subsection; (2)
14    submit any other information necessary to adequately
15    review the proposed CAAPP permit; or (3) process the permit
16    under subsection 8 of this Section except for minor permit
17    modifications.
18        e. If USEPA does not object in writing to issuance of a
19    permit under this subsection, any person may petition USEPA
20    within 60 days after expiration of the 45-day review period
21    to make such objection.
22        f. If the permit has not yet been issued and USEPA
23    objects to the permit as a result of a petition, the Agency
24    shall not issue the permit until USEPA's objection has been
25    resolved. The Agency shall provide a 10-day comment period
26    in accordance with paragraph c of this subsection. A

 

 

09900HB3341ham003- 52 -LRB099 10047 MGM 34300 a

1    petition does not, however, stay the effectiveness of a
2    permit or its requirements if the permit was issued after
3    expiration of the 45-day review period and prior to a USEPA
4    objection.
5        g. If the Agency has issued a permit after expiration
6    of the 45-day review period and prior to receipt of a USEPA
7    objection under this subsection in response to a petition
8    submitted pursuant to paragraph e of this subsection, the
9    Agency may, upon receipt of an objection from USEPA, revise
10    and resubmit the permit to USEPA pursuant to this
11    subsection after providing a 10-day comment period in
12    accordance with paragraph c of this subsection. If the
13    Agency fails to submit a revised permit in response to the
14    objection, USEPA shall modify, terminate or revoke the
15    permit. In any case, the source will not be in violation of
16    the requirement to have submitted a timely and complete
17    application.
18        h. The Agency shall have the authority to adopt
19    procedural rules, in accordance with the Illinois
20    Administrative Procedure Act, as the Agency deems
21    necessary, to implement this subsection.
 
22    10. Final Agency Action.
23        a. The Agency shall issue a CAAPP permit, permit
24    modification, or permit renewal if all of the following
25    conditions are met:

 

 

09900HB3341ham003- 53 -LRB099 10047 MGM 34300 a

1            i. The applicant has submitted a complete and
2        certified application for a permit, permit
3        modification, or permit renewal consistent with
4        subsections 5 and 14 of this Section, as applicable,
5        and applicable regulations.
6            ii. The applicant has submitted with its complete
7        application an approvable compliance plan, including a
8        schedule for achieving compliance, consistent with
9        subsection 5 of this Section and applicable
10        regulations.
11            iii. The applicant has timely paid the fees
12        required pursuant to subsection 18 of this Section and
13        applicable regulations.
14            iv. The Agency has received a complete CAAPP
15        application and, if necessary, has requested and
16        received additional information from the applicant
17        consistent with subsection 5 of this Section and
18        applicable regulations.
19            v. The Agency has complied with all applicable
20        provisions regarding public notice and affected State
21        review consistent with subsection 8 of this Section and
22        applicable regulations.
23            vi. The Agency has provided a copy of each CAAPP
24        application, or summary thereof, pursuant to agreement
25        with USEPA and proposed CAAPP permit required under
26        subsection 9 of this Section to USEPA, and USEPA has

 

 

09900HB3341ham003- 54 -LRB099 10047 MGM 34300 a

1        not objected to the issuance of the permit in
2        accordance with the Clean Air Act and 40 CFR Part 70.
3        b. The Agency shall have the authority to deny a CAAPP
4    permit, permit modification, or permit renewal if the
5    applicant has not complied with the requirements of
6    subparagraphs (i) through (iv) of paragraph (a) of this
7    subsection or if USEPA objects to its issuance.
8        c. i. Prior to denial of a CAAPP permit, permit
9        modification, or permit renewal under this Section,
10        the Agency shall notify the applicant of the possible
11        denial and the reasons for the denial.
12            ii. Within such notice, the Agency shall specify an
13        appropriate date by which the applicant shall
14        adequately respond to the Agency's notice. Such date
15        shall not exceed 15 days from the date the notification
16        is received by the applicant. The Agency may grant a
17        reasonable extension for good cause shown.
18            iii. Failure by the applicant to adequately
19        respond by the date specified in the notification or by
20        any granted extension date shall be grounds for denial
21        of the permit.
22            For purposes of obtaining judicial review under
23        Sections 40.2 and 41 of this Act, the Agency shall
24        provide to USEPA and each applicant, and, upon request,
25        to affected States, any person who participated in the
26        public comment process, and any other person who could

 

 

09900HB3341ham003- 55 -LRB099 10047 MGM 34300 a

1        obtain judicial review under Sections 40.2 and 41 of
2        this Act, a copy of each CAAPP permit or notification
3        of denial pertaining to that party.
4        d. The Agency shall have the authority to adopt
5    procedural rules, in accordance with the Illinois
6    Administrative Procedure Act, as the Agency deems
7    necessary, to implement this subsection.
 
8    11. General Permits.
9        a. The Agency may issue a general permit covering
10    numerous similar sources, except for affected sources for
11    acid deposition unless otherwise provided in regulations
12    promulgated under Title IV of the Clean Air Act.
13        b. The Agency shall identify, in any general permit,
14    criteria by which sources may qualify for the general
15    permit.
16        c. CAAPP sources that would qualify for a general
17    permit must apply for coverage under the terms of the
18    general permit or must apply for a CAAPP permit consistent
19    with subsection 5 of this Section and applicable
20    regulations.
21        d. The Agency shall comply with the public comment and
22    hearing provisions of this Section as well as the USEPA and
23    affected State review procedures prior to issuance of a
24    general permit.
25        e. When granting a subsequent request by a qualifying

 

 

09900HB3341ham003- 56 -LRB099 10047 MGM 34300 a

1    CAAPP source for coverage under the terms of a general
2    permit, the Agency shall not be required to repeat the
3    public notice and comment procedures. The granting of such
4    request shall not be considered a final permit action for
5    purposes of judicial review.
6        f. The Agency may not issue a general permit to cover
7    any discrete emission unit at a CAAPP source if another
8    CAAPP permit covers emission units at the source.
9        g. The Agency shall have the authority to adopt
10    procedural rules, in accordance with the Illinois
11    Administrative Procedure Act, as the Agency deems
12    necessary, to implement this subsection.
 
13    12. Operational Flexibility.
14        a. An owner or operator of a CAAPP source may make
15    changes at the CAAPP source without requiring a prior
16    permit revision, consistent with subparagraphs (i) through
17    (iii) of paragraph (a) of this subsection, so long as the
18    changes are not modifications under any provision of Title
19    I of the Clean Air Act and they do not exceed the emissions
20    allowable under the permit (whether expressed therein as a
21    rate of emissions or in terms of total emissions), provided
22    that the owner or operator of the CAAPP source provides
23    USEPA and the Agency with written notification as required
24    below in advance of the proposed changes, which shall be a
25    minimum of 7 days, unless otherwise provided by the Agency

 

 

09900HB3341ham003- 57 -LRB099 10047 MGM 34300 a

1    in applicable regulations regarding emergencies. The owner
2    or operator of a CAAPP source and the Agency shall each
3    attach such notice to their copy of the relevant permit.
4            i. An owner or operator of a CAAPP source may make
5        Section 502 (b) (10) changes without a permit revision,
6        if the changes are not modifications under any
7        provision of Title I of the Clean Air Act and the
8        changes do not exceed the emissions allowable under the
9        permit (whether expressed therein as a rate of
10        emissions or in terms of total emissions).
11                A. For each such change, the written
12            notification required above shall include a brief
13            description of the change within the source, the
14            date on which the change will occur, any change in
15            emissions, and any permit term or condition that is
16            no longer applicable as a result of the change.
17                B. The permit shield described in paragraph(j)
18            of subsection 7 of this Section shall not apply to
19            any change made pursuant to this subparagraph.
20            ii. An owner or operator of a CAAPP source may
21        trade increases and decreases in emissions in the CAAPP
22        source, where the applicable implementation plan
23        provides for such emission trades without requiring a
24        permit revision. This provision is available in those
25        cases where the permit does not already provide for
26        such emissions trading.

 

 

09900HB3341ham003- 58 -LRB099 10047 MGM 34300 a

1                A. Under this subparagraph(ii) of paragraph
2            (a) of this subsection, the written notification
3            required above shall include such information as
4            may be required by the provision in the applicable
5            implementation plan authorizing the emissions
6            trade, including at a minimum, when the proposed
7            changes will occur, a description of each such
8            change, any change in emissions, the permit
9            requirements with which the source will comply
10            using the emissions trading provisions of the
11            applicable implementation plan, and the pollutants
12            emitted subject to the emissions trade. The notice
13            shall also refer to the provisions in the
14            applicable implementation plan with which the
15            source will comply and provide for the emissions
16            trade.
17                B. The permit shield described in paragraph(j)
18            of subsection 7 of this Section shall not apply to
19            any change made pursuant to subparagraph (ii) of
20            paragraph (a) of this subsection. Compliance with
21            the permit requirements that the source will meet
22            using the emissions trade shall be determined
23            according to the requirements of the applicable
24            implementation plan authorizing the emissions
25            trade.
26            iii. If requested within a CAAPP application, the

 

 

09900HB3341ham003- 59 -LRB099 10047 MGM 34300 a

1        Agency shall issue a CAAPP permit which contains terms
2        and conditions, including all terms required under
3        subsection 7 of this Section to determine compliance,
4        allowing for the trading of emissions increases and
5        decreases at the CAAPP source solely for the purpose of
6        complying with a federally-enforceable emissions cap
7        that is established in the permit independent of
8        otherwise applicable requirements. The owner or
9        operator of a CAAPP source shall include in its CAAPP
10        application proposed replicable procedures and permit
11        terms that ensure the emissions trades are
12        quantifiable and enforceable. The permit shall also
13        require compliance with all applicable requirements.
14                A. Under this subparagraph(iii) of paragraph
15            (a), the written notification required above shall
16            state when the change will occur and shall describe
17            the changes in emissions that will result and how
18            these increases and decreases in emissions will
19            comply with the terms and conditions of the permit.
20                B. The permit shield described in paragraph(j)
21            of subsection 7 of this Section shall extend to
22            terms and conditions that allow such increases and
23            decreases in emissions.
24        b. An owner or operator of a CAAPP source may make
25    changes that are not addressed or prohibited by the permit,
26    other than those which are subject to any requirements

 

 

09900HB3341ham003- 60 -LRB099 10047 MGM 34300 a

1    under Title IV of the Clean Air Act or are modifications
2    under any provisions of Title I of the Clean Air Act,
3    without a permit revision, in accordance with the following
4    requirements:
5            (i) Each such change shall meet all applicable
6        requirements and shall not violate any existing permit
7        term or condition;
8            (ii) Sources must provide contemporaneous written
9        notice to the Agency and USEPA of each such change,
10        except for changes that qualify as insignificant under
11        provisions adopted by the Agency or the Board. Such
12        written notice shall describe each such change,
13        including the date, any change in emissions,
14        pollutants emitted, and any applicable requirement
15        that would apply as a result of the change;
16            (iii) The change shall not qualify for the shield
17        described in paragraph (j) of subsection 7 of this
18        Section; and
19            (iv) The permittee shall keep a record describing
20        changes made at the source that result in emissions of
21        a regulated air pollutant subject to an applicable
22        Clean Air Act requirement, but not otherwise regulated
23        under the permit, and the emissions resulting from
24        those changes.
25        c. The Agency shall have the authority to adopt
26    procedural rules, in accordance with the Illinois

 

 

09900HB3341ham003- 61 -LRB099 10047 MGM 34300 a

1    Administrative Procedure Act, as the Agency deems
2    necessary to implement this subsection.
 
3    13. Administrative Permit Amendments.
4        a. The Agency shall take final action on a request for
5    an administrative permit amendment within 60 days after
6    receipt of the request. Neither notice nor an opportunity
7    for public and affected State comment shall be required for
8    the Agency to incorporate such revisions, provided it
9    designates the permit revisions as having been made
10    pursuant to this subsection.
11        b. The Agency shall submit a copy of the revised permit
12    to USEPA.
13        c. For purposes of this Section the term
14    "administrative permit amendment" shall be defined as a
15    permit revision that can accomplish one or more of the
16    changes described below:
17            i. Corrects typographical errors;
18            ii. Identifies a change in the name, address, or
19        phone number of any person identified in the permit, or
20        provides a similar minor administrative change at the
21        source;
22            iii. Requires more frequent monitoring or
23        reporting by the permittee;
24            iv. Allows for a change in ownership or operational
25        control of a source where the Agency determines that no

 

 

09900HB3341ham003- 62 -LRB099 10047 MGM 34300 a

1        other change in the permit is necessary, provided that
2        a written agreement containing a specific date for
3        transfer of permit responsibility, coverage, and
4        liability between the current and new permittees has
5        been submitted to the Agency;
6            v. Incorporates into the CAAPP permit the
7        requirements from preconstruction review permits
8        authorized under a USEPA-approved program, provided
9        the program meets procedural and compliance
10        requirements substantially equivalent to those
11        contained in this Section;
12            vi. (Blank); or
13            vii. Any other type of change which USEPA has
14        determined as part of the approved CAAPP permit program
15        to be similar to those included in this subsection.
16        d. The Agency shall, upon taking final action granting
17    a request for an administrative permit amendment, allow
18    coverage by the permit shield in paragraph(j) of subsection
19    7 of this Section for administrative permit amendments made
20    pursuant to subparagraph(v) of paragraph (c) of this
21    subsection which meet the relevant requirements for
22    significant permit modifications.
23        e. Permit revisions and modifications, including
24    administrative amendments and automatic amendments
25    (pursuant to Sections 408(b) and 403(d) of the Clean Air
26    Act or regulations promulgated thereunder), for purposes

 

 

09900HB3341ham003- 63 -LRB099 10047 MGM 34300 a

1    of the acid rain portion of the permit shall be governed by
2    the regulations promulgated under Title IV of the Clean Air
3    Act. Owners or operators of affected sources for acid
4    deposition shall have the flexibility to amend their
5    compliance plans as provided in the regulations
6    promulgated under Title IV of the Clean Air Act.
7        f. The CAAPP source may implement the changes addressed
8    in the request for an administrative permit amendment
9    immediately upon submittal of the request.
10        g. The Agency shall have the authority to adopt
11    procedural rules, in accordance with the Illinois
12    Administrative Procedure Act, as the Agency deems
13    necessary, to implement this subsection.
 
14    14. Permit Modifications.
15        a. Minor permit modification procedures.
16            i. The Agency shall review a permit modification
17        using the "minor permit" modification procedures only
18        for those permit modifications that:
19                A. Do not violate any applicable requirement;
20                B. Do not involve significant changes to
21            existing monitoring, reporting, or recordkeeping
22            requirements in the permit;
23                C. Do not require a case-by-case determination
24            of an emission limitation or other standard, or a
25            source-specific determination of ambient impacts,

 

 

09900HB3341ham003- 64 -LRB099 10047 MGM 34300 a

1            or a visibility or increment analysis;
2                D. Do not seek to establish or change a permit
3            term or condition for which there is no
4            corresponding underlying requirement and which
5            avoids an applicable requirement to which the
6            source would otherwise be subject. Such terms and
7            conditions include:
8                    1. A federally enforceable emissions cap
9                assumed to avoid classification as a
10                modification under any provision of Title I of
11                the Clean Air Act; and
12                    2. An alternative emissions limit approved
13                pursuant to regulations promulgated under
14                Section 112(i)(5) of the Clean Air Act;
15                E. Are not modifications under any provision
16            of Title I of the Clean Air Act; and
17                F. Are not required to be processed as a
18            significant modification.
19            ii. Notwithstanding subparagraph(i) of paragraph
20        (a) and subparagraph(ii) of paragraph (b) of this
21        subsection, minor permit modification procedures may
22        be used for permit modifications involving the use of
23        economic incentives, marketable permits, emissions
24        trading, and other similar approaches, to the extent
25        that such minor permit modification procedures are
26        explicitly provided for in an applicable

 

 

09900HB3341ham003- 65 -LRB099 10047 MGM 34300 a

1        implementation plan or in applicable requirements
2        promulgated by USEPA.
3            iii. An applicant requesting the use of minor
4        permit modification procedures shall meet the
5        requirements of subsection 5 of this Section and shall
6        include the following in its application:
7                A. A description of the change, the emissions
8            resulting from the change, and any new applicable
9            requirements that will apply if the change occurs;
10                B. The source's suggested draft permit;
11                C. Certification by a responsible official,
12            consistent with paragraph(e) of subsection 5 of
13            this Section and applicable regulations, that the
14            proposed modification meets the criteria for use
15            of minor permit modification procedures and a
16            request that such procedures be used; and
17                D. Completed forms for the Agency to use to
18            notify USEPA and affected States as required under
19            subsections 8 and 9 of this Section.
20            iv. Within 5 working days after receipt of a
21        complete permit modification application, the Agency
22        shall notify USEPA and affected States of the requested
23        permit modification in accordance with subsections 8
24        and 9 of this Section. The Agency promptly shall send
25        any notice required under paragraph(d) of subsection 8
26        of this Section to USEPA.

 

 

09900HB3341ham003- 66 -LRB099 10047 MGM 34300 a

1            v. The Agency may not issue a final permit
2        modification until after the 45-day review period for
3        USEPA or until USEPA has notified the Agency that USEPA
4        will not object to the issuance of the permit
5        modification, whichever comes first, although the
6        Agency can approve the permit modification prior to
7        that time. Within 90 days after the Agency's receipt of
8        an application under the minor permit modification
9        procedures or 15 days after the end of USEPA's 45-day
10        review period under subsection 9 of this Section,
11        whichever is later, the Agency shall:
12                A. Issue the permit modification as proposed;
13                B. Deny the permit modification application;
14                C. Determine that the requested modification
15            does not meet the minor permit modification
16            criteria and should be reviewed under the
17            significant modification procedures; or
18                D. Revise the draft permit modification and
19            transmit to USEPA the new proposed permit
20            modification as required by subsection 9 of this
21            Section.
22            vi. Any CAAPP source may make the change proposed
23        in its minor permit modification application
24        immediately after it files such application. After the
25        CAAPP source makes the change allowed by the preceding
26        sentence, and until the Agency takes any of the actions

 

 

09900HB3341ham003- 67 -LRB099 10047 MGM 34300 a

1        specified in items(A) through(C) of subparagraph (v)
2        of paragraph (a) of this subsection, the source must
3        comply with both the applicable requirements governing
4        the change and the proposed permit terms and
5        conditions. During this time period, the source need
6        not comply with the existing permit terms and
7        conditions it seeks to modify. If the source fails to
8        comply with its proposed permit terms and conditions
9        during this time period, the existing permit terms and
10        conditions which it seeks to modify may be enforced
11        against it.
12            vii. The permit shield under paragraph (j) of
13        subsection 7 of this Section may not extend to minor
14        permit modifications.
15            viii. If a construction permit is required,
16        pursuant to subsection (a) of Section 39 of this Act
17        and regulations thereunder, for a change for which the
18        minor permit modification procedures are applicable,
19        the source may request that the processing of the
20        construction permit application be consolidated with
21        the processing of the application for the minor permit
22        modification. In such cases, the provisions of this
23        Section, including those within subsections 5, 8, and
24        9, shall apply and the Agency shall act on such
25        applications pursuant to subparagraph(v) of paragraph
26        (a) of subsection 14 of this Section. The source may

 

 

09900HB3341ham003- 68 -LRB099 10047 MGM 34300 a

1        make the proposed change immediately after filing its
2        application for the minor permit modification. Nothing
3        in this subparagraph shall otherwise affect the
4        requirements and procedures applicable to construction
5        permits.
6        b. Group Processing of Minor Permit Modifications.
7            i. Where requested by an applicant within its
8        application, the Agency shall process groups of a
9        source's applications for certain modifications
10        eligible for minor permit modification processing in
11        accordance with the provisions of this paragraph (b).
12            ii. Permit modifications may be processed in
13        accordance with the procedures for group processing,
14        for those modifications:
15                A. Which meet the criteria for minor permit
16            modification procedures under subparagraph(i) of
17            paragraph (a) of subsection 14 of this Section; and
18                B. That collectively are below 10 percent of
19            the emissions allowed by the permit for the
20            emissions unit for which change is requested, 20
21            percent of the applicable definition of major
22            source set forth in subsection 2 of this Section,
23            or 5 tons per year, whichever is least.
24            iii. An applicant requesting the use of group
25        processing procedures shall meet the requirements of
26        subsection 5 of this Section and shall include the

 

 

09900HB3341ham003- 69 -LRB099 10047 MGM 34300 a

1        following in its application:
2                A. A description of the change, the emissions
3            resulting from the change, and any new applicable
4            requirements that will apply if the change occurs.
5                B. The source's suggested draft permit.
6                C. Certification by a responsible official
7            consistent with paragraph (e) of subsection 5 of
8            this Section, that the proposed modification meets
9            the criteria for use of group processing
10            procedures and a request that such procedures be
11            used.
12                D. A list of the source's other pending
13            applications awaiting group processing, and a
14            determination of whether the requested
15            modification, aggregated with these other
16            applications, equals or exceeds the threshold set
17            under item(B) of subparagraph (ii) of paragraph
18            (b) of this subsection.
19                E. Certification, consistent with paragraph(e)
20            of subsection 5 of this Section, that the source
21            has notified USEPA of the proposed modification.
22            Such notification need only contain a brief
23            description of the requested modification.
24                F. Completed forms for the Agency to use to
25            notify USEPA and affected states as required under
26            subsections 8 and 9 of this Section.

 

 

09900HB3341ham003- 70 -LRB099 10047 MGM 34300 a

1            iv. On a quarterly basis or within 5 business days
2        after receipt of an application demonstrating that the
3        aggregate of a source's pending applications equals or
4        exceeds the threshold level set forth within item (B)
5        of subparagraph (ii) of paragraph (b) of this
6        subsection, whichever is earlier, the Agency shall
7        promptly notify USEPA and affected States of the
8        requested permit modifications in accordance with
9        subsections 8 and 9 of this Section. The Agency shall
10        send any notice required under paragraph(d) of
11        subsection 8 of this Section to USEPA.
12            v. The provisions of subparagraph(v) of paragraph
13        (a) of this subsection shall apply to modifications
14        eligible for group processing, except that the Agency
15        shall take one of the actions specified in items(A)
16        through (D) of subparagraph (v) of paragraph (a) of
17        this subsection within 180 days after receipt of the
18        application or 15 days after the end of USEPA's 45-day
19        review period under subsection 9 of this Section,
20        whichever is later.
21            vi. The provisions of subparagraph(vi) of
22        paragraph (a) of this subsection shall apply to
23        modifications for group processing.
24            vii. The provisions of paragraph(j) of subsection
25        7 of this Section shall not apply to modifications
26        eligible for group processing.

 

 

09900HB3341ham003- 71 -LRB099 10047 MGM 34300 a

1        c. Significant Permit Modifications.
2            i. Significant modification procedures shall be
3        used for applications requesting significant permit
4        modifications and for those applications that do not
5        qualify as either minor permit modifications or as
6        administrative permit amendments.
7            ii. Every significant change in existing
8        monitoring permit terms or conditions and every
9        relaxation of reporting or recordkeeping requirements
10        shall be considered significant. A modification shall
11        also be considered significant if in the judgment of
12        the Agency action on an application for modification
13        would require decisions to be made on technically
14        complex issues. Nothing herein shall be construed to
15        preclude the permittee from making changes consistent
16        with this Section that would render existing permit
17        compliance terms and conditions irrelevant.
18            iii. Significant permit modifications must meet
19        all the requirements of this Section, including those
20        for applications (including completeness review),
21        public participation, review by affected States, and
22        review by USEPA applicable to initial permit issuance
23        and permit renewal. The Agency shall take final action
24        on significant permit modifications within 9 months
25        after receipt of a complete application.
26        d. The Agency shall have the authority to adopt

 

 

09900HB3341ham003- 72 -LRB099 10047 MGM 34300 a

1    procedural rules, in accordance with the Illinois
2    Administrative Procedure Act, as the Agency deems
3    necessary, to implement this subsection.
 
4    15. Reopenings for Cause by the Agency.
5        a. Each issued CAAPP permit shall include provisions
6    specifying the conditions under which the permit will be
7    reopened prior to the expiration of the permit. Such
8    revisions shall be made as expeditiously as practicable. A
9    CAAPP permit shall be reopened and revised under any of the
10    following circumstances, in accordance with procedures
11    adopted by the Agency:
12            i. Additional requirements under the Clean Air Act
13        become applicable to a major CAAPP source for which 3
14        or more years remain on the original term of the
15        permit. Such a reopening shall be completed not later
16        than 18 months after the promulgation of the applicable
17        requirement. No such revision is required if the
18        effective date of the requirement is later than the
19        date on which the permit is due to expire.
20            ii. Additional requirements (including excess
21        emissions requirements) become applicable to an
22        affected source for acid deposition under the acid rain
23        program. Excess emissions offset plans shall be deemed
24        to be incorporated into the permit upon approval by
25        USEPA.

 

 

09900HB3341ham003- 73 -LRB099 10047 MGM 34300 a

1            iii. The Agency or USEPA determines that the permit
2        contains a material mistake or that inaccurate
3        statements were made in establishing the emissions
4        standards, limitations, or other terms or conditions
5        of the permit.
6            iv. The Agency or USEPA determines that the permit
7        must be revised or revoked to assure compliance with
8        the applicable requirements.
9        b. In the event that the Agency determines that there
10    are grounds for revoking a CAAPP permit, for cause,
11    consistent with paragraph a of this subsection, it shall
12    file a petition before the Board setting forth the basis
13    for such revocation. In any such proceeding, the Agency
14    shall have the burden of establishing that the permit
15    should be revoked under the standards set forth in this Act
16    and the Clean Air Act. Any such proceeding shall be
17    conducted pursuant to the Board's procedures for
18    adjudicatory hearings and the Board shall render its
19    decision within 120 days of the filing of the petition. The
20    Agency shall take final action to revoke and reissue a
21    CAAPP permit consistent with the Board's order.
22        c. Proceedings regarding a reopened CAAPP permit shall
23    follow the same procedures as apply to initial permit
24    issuance and shall affect only those parts of the permit
25    for which cause to reopen exists.
26        d. Reopenings under paragraph (a) of this subsection

 

 

09900HB3341ham003- 74 -LRB099 10047 MGM 34300 a

1    shall not be initiated before a notice of such intent is
2    provided to the CAAPP source by the Agency at least 30 days
3    in advance of the date that the permit is to be reopened,
4    except that the Agency may provide a shorter time period in
5    the case of an emergency.
6        e. The Agency shall have the authority to adopt
7    procedural rules, in accordance with the Illinois
8    Administrative Procedure Act, as the Agency deems
9    necessary, to implement this subsection.
 
10    16. Reopenings for Cause by USEPA.
11        a. When USEPA finds that cause exists to terminate,
12    modify, or revoke and reissue a CAAPP permit pursuant to
13    subsection 15 of this Section, and thereafter notifies the
14    Agency and the permittee of such finding in writing, the
15    Agency shall forward to USEPA and the permittee a proposed
16    determination of termination, modification, or revocation
17    and reissuance as appropriate, in accordance with
18    paragraph (b) of this subsection. The Agency's proposed
19    determination shall be in accordance with the record, the
20    Clean Air Act, regulations promulgated thereunder, this
21    Act and regulations promulgated thereunder. Such proposed
22    determination shall not affect the permit or constitute a
23    final permit action for purposes of this Act or the
24    Administrative Review Law. The Agency shall forward to
25    USEPA such proposed determination within 90 days after

 

 

09900HB3341ham003- 75 -LRB099 10047 MGM 34300 a

1    receipt of the notification from USEPA. If additional time
2    is necessary to submit the proposed determination, the
3    Agency shall request a 90-day extension from USEPA and
4    shall submit the proposed determination within 180 days
5    after receipt of notification from USEPA.
6            b. i. Prior to the Agency's submittal to USEPA of a
7        proposed determination to terminate or revoke and
8        reissue the permit, the Agency shall file a petition
9        before the Board setting forth USEPA's objection, the
10        permit record, the Agency's proposed determination,
11        and the justification for its proposed determination.
12        The Board shall conduct a hearing pursuant to the rules
13        prescribed by Section 32 of this Act, and the burden of
14        proof shall be on the Agency.
15            ii. After due consideration of the written and oral
16        statements, the testimony and arguments that shall be
17        submitted at hearing, the Board shall issue and enter
18        an interim order for the proposed determination, which
19        shall set forth all changes, if any, required in the
20        Agency's proposed determination. The interim order
21        shall comply with the requirements for final orders as
22        set forth in Section 33 of this Act. Issuance of an
23        interim order by the Board under this paragraph,
24        however, shall not affect the permit status and does
25        not constitute a final action for purposes of this Act
26        or the Administrative Review Law.

 

 

09900HB3341ham003- 76 -LRB099 10047 MGM 34300 a

1            iii. The Board shall cause a copy of its interim
2        order to be served upon all parties to the proceeding
3        as well as upon USEPA. The Agency shall submit the
4        proposed determination to USEPA in accordance with the
5        Board's Interim Order within 180 days after receipt of
6        the notification from USEPA.
7        c. USEPA shall review the proposed determination to
8    terminate, modify, or revoke and reissue the permit within
9    90 days after receipt.
10            i. When USEPA reviews the proposed determination
11        to terminate or revoke and reissue and does not object,
12        the Board shall, within 7 days after receipt of USEPA's
13        final approval, enter the interim order as a final
14        order. The final order may be appealed as provided by
15        Title XI of this Act. The Agency shall take final
16        action in accordance with the Board's final order.
17            ii. When USEPA reviews such proposed determination
18        to terminate or revoke and reissue and objects, the
19        Agency shall submit USEPA's objection and the Agency's
20        comments and recommendation on the objection to the
21        Board and permittee. The Board shall review its interim
22        order in response to USEPA's objection and the Agency's
23        comments and recommendation and issue a final order in
24        accordance with Sections 32 and 33 of this Act. The
25        Agency shall, within 90 days after receipt of such
26        objection, respond to USEPA's objection in accordance

 

 

09900HB3341ham003- 77 -LRB099 10047 MGM 34300 a

1        with the Board's final order.
2            iii. When USEPA reviews such proposed
3        determination to modify and objects, the Agency shall,
4        within 90 days after receipt of the objection, resolve
5        the objection and modify the permit in accordance with
6        USEPA's objection, based upon the record, the Clean Air
7        Act, regulations promulgated thereunder, this Act, and
8        regulations promulgated thereunder.
9        d. If the Agency fails to submit the proposed
10    determination pursuant to paragraph a of this subsection or
11    fails to resolve any USEPA objection pursuant to paragraph
12    c of this subsection, USEPA will terminate, modify, or
13    revoke and reissue the permit.
14        e. The Agency shall have the authority to adopt
15    procedural rules, in accordance with the Illinois
16    Administrative Procedure Act, as the Agency deems
17    necessary, to implement this subsection.
 
18    17. Title IV; Acid Rain Provisions.
19        a. The Agency shall act on initial CAAPP applications
20    for affected sources for acid deposition in accordance with
21    this Section and Title V of the Clean Air Act and
22    regulations promulgated thereunder, except as modified by
23    Title IV of the Clean Air Act and regulations promulgated
24    thereunder. The Agency shall issue initial CAAPP permits to
25    the affected sources for acid deposition which shall become

 

 

09900HB3341ham003- 78 -LRB099 10047 MGM 34300 a

1    effective no earlier than January 1, 1995, and which shall
2    terminate on December 31, 1999, in accordance with this
3    Section. Subsequent CAAPP permits issued to affected
4    sources for acid deposition shall be issued for a fixed
5    term of 5 years. Title IV of the Clean Air Act and
6    regulations promulgated thereunder, including but not
7    limited to 40 C.F.R. Part 72, as now or hereafter amended,
8    are applicable to and enforceable under this Act.
9        b. A designated representative of an affected source
10    for acid deposition shall submit a timely and complete
11    Phase II acid rain permit application and compliance plan
12    to the Agency, not later than January 1, 1996, that meets
13    the requirements of Titles IV and V of the Clean Air Act
14    and regulations. The Agency shall act on the Phase II acid
15    rain permit application and compliance plan in accordance
16    with this Section and Title V of the Clean Air Act and
17    regulations promulgated thereunder, except as modified by
18    Title IV of the Clean Air Act and regulations promulgated
19    thereunder. The Agency shall issue the Phase II acid rain
20    permit to an affected source for acid deposition no later
21    than December 31, 1997, which shall become effective on
22    January 1, 2000, in accordance with this Section, except as
23    modified by Title IV and regulations promulgated
24    thereunder; provided that the designated representative of
25    the source submitted a timely and complete Phase II permit
26    application and compliance plan to the Agency that meets

 

 

09900HB3341ham003- 79 -LRB099 10047 MGM 34300 a

1    the requirements of Title IV and V of the Clean Air Act and
2    regulations.
3        c. Each Phase II acid rain permit issued in accordance
4    with this subsection shall have a fixed term of 5 years.
5    Except as provided in paragraph b above, the Agency shall
6    issue or deny a Phase II acid rain permit within 18 months
7    of receiving a complete Phase II permit application and
8    compliance plan.
9        d. A designated representative of a new unit, as
10    defined in Section 402 of the Clean Air Act, shall submit a
11    timely and complete Phase II acid rain permit application
12    and compliance plan that meets the requirements of Titles
13    IV and V of the Clean Air Act and its regulations. The
14    Agency shall act on the new unit's Phase II acid rain
15    permit application and compliance plan in accordance with
16    this Section and Title V of the Clean Air Act and its
17    regulations, except as modified by Title IV of the Clean
18    Air Act and its regulations. The Agency shall reopen the
19    new unit's CAAPP permit for cause to incorporate the
20    approved Phase II acid rain permit in accordance with this
21    Section. The Phase II acid rain permit for the new unit
22    shall become effective no later than the date required
23    under Title IV of the Clean Air Act and its regulations.
24        e. A designated representative of an affected source
25    for acid deposition shall submit a timely and complete
26    Title IV NOx permit application to the Agency, not later

 

 

09900HB3341ham003- 80 -LRB099 10047 MGM 34300 a

1    than January 1, 1998, that meets the requirements of Titles
2    IV and V of the Clean Air Act and its regulations. The
3    Agency shall reopen the Phase II acid rain permit for cause
4    and incorporate the approved NOx provisions into the Phase
5    II acid rain permit not later than January 1, 1999, in
6    accordance with this Section, except as modified by Title
7    IV of the Clean Air Act and regulations promulgated
8    thereunder. Such reopening shall not affect the term of the
9    Phase II acid rain permit.
10        f. The designated representative of the affected
11    source for acid deposition shall renew the initial CAAPP
12    permit and Phase II acid rain permit in accordance with
13    this Section and Title V of the Clean Air Act and
14    regulations promulgated thereunder, except as modified by
15    Title IV of the Clean Air Act and regulations promulgated
16    thereunder.
17        g. In the case of an affected source for acid
18    deposition for which a complete Phase II acid rain permit
19    application and compliance plan are timely received under
20    this subsection, the complete permit application and
21    compliance plan, including amendments thereto, shall be
22    binding on the owner, operator and designated
23    representative, all affected units for acid deposition at
24    the affected source, and any other unit, as defined in
25    Section 402 of the Clean Air Act, governed by the Phase II
26    acid rain permit application and shall be enforceable as an

 

 

09900HB3341ham003- 81 -LRB099 10047 MGM 34300 a

1    acid rain permit for purposes of Titles IV and V of the
2    Clean Air Act, from the date of submission of the acid rain
3    permit application until a Phase II acid rain permit is
4    issued or denied by the Agency.
5        h. The Agency shall not include or implement any
6    measure which would interfere with or modify the
7    requirements of Title IV of the Clean Air Act or
8    regulations promulgated thereunder.
9        i. Nothing in this Section shall be construed as
10    affecting allowances or USEPA's decision regarding an
11    excess emissions offset plan, as set forth in Title IV of
12    the Clean Air Act or regulations promulgated thereunder.
13            i. No permit revision shall be required for
14        increases in emissions that are authorized by
15        allowances acquired pursuant to the acid rain program,
16        provided that such increases do not require a permit
17        revision under any other applicable requirement.
18            ii. No limit shall be placed on the number of
19        allowances held by the source. The source may not,
20        however, use allowances as a defense to noncompliance
21        with any other applicable requirement.
22            iii. Any such allowance shall be accounted for
23        according to the procedures established in regulations
24        promulgated under Title IV of the Clean Air Act.
25        j. To the extent that the federal regulations
26    promulgated under Title IV, including but not limited to 40

 

 

09900HB3341ham003- 82 -LRB099 10047 MGM 34300 a

1    C.F.R. Part 72, as now or hereafter amended, are
2    inconsistent with the federal regulations promulgated
3    under Title V, the federal regulations promulgated under
4    Title IV shall take precedence.
5        k. The USEPA may intervene as a matter of right in any
6    permit appeal involving a Phase II acid rain permit
7    provision or denial of a Phase II acid rain permit.
8        l. It is unlawful for any owner or operator to violate
9    any terms or conditions of a Phase II acid rain permit
10    issued under this subsection, to operate any affected
11    source for acid deposition except in compliance with a
12    Phase II acid rain permit issued by the Agency under this
13    subsection, or to violate any other applicable
14    requirements.
15        m. The designated representative of an affected source
16    for acid deposition shall submit to the Agency the data and
17    information submitted quarterly to USEPA, pursuant to 40
18    CFR 75.64, concurrently with the submission to USEPA. The
19    submission shall be in the same electronic format as
20    specified by USEPA.
21        n. The Agency shall act on any petition for exemption
22    of a new unit or retired unit, as those terms are defined
23    in Section 402 of the Clean Air Act, from the requirements
24    of the acid rain program in accordance with Title IV of the
25    Clean Air Act and its regulations.
26        o. The Agency shall have the authority to adopt

 

 

09900HB3341ham003- 83 -LRB099 10047 MGM 34300 a

1    procedural rules, in accordance with the Illinois
2    Administrative Procedure Act, as the Agency deems
3    necessary to implement this subsection.
 
4    18. Fee Provisions.
5        a. A source subject to this Section or excluded under
6    subsection 1.1 or paragraph (c) of subsection 3 of this
7    Section, shall pay a fee as provided in this paragraph (a)
8    of subsection 18. However, a source that has been excluded
9    from the provisions of this Section under subsection 1.1 or
10    under paragraph (c) of subsection 3 of this Section because
11    the source emits less than 25 tons per year of any
12    combination of regulated air pollutants, except greenhouse
13    gases, shall pay fees in accordance with paragraph (1) of
14    subsection (b) of Section 9.6.
15            i. The fee for a source allowed to emit less than
16        100 tons per year of any combination of regulated air
17        pollutants, except greenhouse gases, shall be $1,800
18        per year, and that fee shall increase, beginning
19        January 1, 2012, to $2,150 per year.
20            ii. The fee for a source allowed to emit 100 tons
21        or more per year of any combination of regulated air
22        pollutants, except greenhouse gases and those
23        regulated air pollutants excluded in paragraph(f) of
24        this subsection 18, shall be as follows:
25                A. The Agency shall assess a fee of $18 per

 

 

09900HB3341ham003- 84 -LRB099 10047 MGM 34300 a

1            ton, per year for the allowable emissions of
2            regulated air pollutants subject to this
3            subparagraph (ii) of paragraph (a) of subsection
4            18, and that fee shall increase, beginning January
5            1, 2012, to $21.50 per ton, per year. These fees
6            shall be used by the Agency and the Board to fund
7            the activities required by Title V of the Clean Air
8            Act including such activities as may be carried out
9            by other State or local agencies pursuant to
10            paragraph (d) of this subsection. The amount of
11            such fee shall be based on the information supplied
12            by the applicant in its complete CAAPP permit
13            application or in the CAAPP permit if the permit
14            has been granted and shall be determined by the
15            amount of emissions that the source is allowed to
16            emit annually, provided however, that the maximum
17            fee for a CAAPP permit under this subparagraph (ii)
18            of paragraph (a) of subsection 18 is $250,000, and
19            increases, beginning January 1, 2012, to $294,000.
20            Beginning January 1, 2012, the maximum fee under
21            this subparagraph (ii) of paragraph (a) of
22            subsection 18 for a source that has been excluded
23            under subsection 1.1 of this Section or under
24            paragraph (c) of subsection 3 of this Section is
25            $4,112. The Agency shall provide as part of the
26            permit application form required under subsection

 

 

09900HB3341ham003- 85 -LRB099 10047 MGM 34300 a

1            5 of this Section a separate fee calculation form
2            which will allow the applicant to identify the
3            allowable emissions and calculate the fee. In no
4            event shall the Agency raise the amount of
5            allowable emissions requested by the applicant
6            unless such increases are required to demonstrate
7            compliance with terms of a CAAPP permit.
8                Notwithstanding the above, any applicant may
9            seek a change in its permit which would result in
10            increases in allowable emissions due to an
11            increase in the hours of operation or production
12            rates of an emission unit or units and such a
13            change shall be consistent with the construction
14            permit requirements of the existing State permit
15            program, under subsection (a) of Section 39 of this
16            Act and applicable provisions of this Section.
17            Where a construction permit is required, the
18            Agency shall expeditiously grant such construction
19            permit and shall, if necessary, modify the CAAPP
20            permit based on the same application.
21                B. The applicant or permittee may pay the fee
22            annually or semiannually for those fees greater
23            than $5,000. However, any applicant paying a fee
24            equal to or greater than $100,000 shall pay the
25            full amount on July 1, for the subsequent fiscal
26            year, or pay 50% of the fee on July 1 and the

 

 

09900HB3341ham003- 86 -LRB099 10047 MGM 34300 a

1            remaining 50% by the next January 1. The Agency may
2            change any annual billing date upon reasonable
3            notice, but shall prorate the new bill so that the
4            permittee or applicant does not pay more than its
5            required fees for the fee period for which payment
6            is made.
7        b. (Blank).
8        c. (Blank).
9        d. There is hereby created in the State Treasury a
10    special fund to be known as the "CAA Permit Fund". All
11    Funds collected by the Agency pursuant to this subsection
12    shall be deposited into the Fund. The General Assembly
13    shall appropriate monies from this Fund to the Agency and
14    to the Board to carry out their obligations under this
15    Section. The General Assembly may also authorize monies to
16    be granted by the Agency from this Fund to other State and
17    local agencies which perform duties related to the CAAPP.
18    Interest generated on the monies deposited in this Fund
19    shall be returned to the Fund.
20        e. The Agency shall have the authority to adopt
21    procedural rules, in accordance with the Illinois
22    Administrative Procedure Act, as the Agency deems
23    necessary to implement this subsection.
24        f. For purposes of this subsection, the term "regulated
25    air pollutant" shall have the meaning given to it under
26    subsection 1 of this Section but shall exclude the

 

 

09900HB3341ham003- 87 -LRB099 10047 MGM 34300 a

1    following:
2            i. carbon monoxide;
3            ii. any Class I or II substance which is a
4        regulated air pollutant solely because it is listed
5        pursuant to Section 602 of the Clean Air Act; and
6            iii. any pollutant that is a regulated air
7        pollutant solely because it is subject to a standard or
8        regulation under Section 112(r) of the Clean Air Act
9        based on the emissions allowed in the permit effective
10        in that calendar year, at the time the applicable bill
11        is generated.
 
12    19. Air Toxics Provisions.
13        a. In the event that the USEPA fails to promulgate in a
14    timely manner a standard pursuant to Section 112(d) of the
15    Clean Air Act, the Agency shall have the authority to issue
16    permits, pursuant to Section 112(j) of the Clean Air Act
17    and regulations promulgated thereunder, which contain
18    emission limitations which are equivalent to the emission
19    limitations that would apply to a source if an emission
20    standard had been promulgated in a timely manner by USEPA
21    pursuant to Section 112(d). Provided, however, that the
22    owner or operator of a source shall have the opportunity to
23    submit to the Agency a proposed emission limitation which
24    it determines to be equivalent to the emission limitations
25    that would apply to such source if an emission standard had

 

 

09900HB3341ham003- 88 -LRB099 10047 MGM 34300 a

1    been promulgated in a timely manner by USEPA. If the Agency
2    refuses to include the emission limitation proposed by the
3    owner or operator in a CAAPP permit, the owner or operator
4    may petition the Board to establish whether the emission
5    limitation proposal submitted by the owner or operator
6    provides for emission limitations which are equivalent to
7    the emission limitations that would apply to the source if
8    the emission standard had been promulgated by USEPA in a
9    timely manner. The Board shall determine whether the
10    emission limitation proposed by the owner or operator or an
11    alternative emission limitation proposed by the Agency
12    provides for the level of control required under Section
13    112 of the Clean Air Act, or shall otherwise establish an
14    appropriate emission limitation, pursuant to Section 112
15    of the Clean Air Act.
16        b. Any Board proceeding brought under paragraph (a) or
17    (e) of this subsection shall be conducted according to the
18    Board's procedures for adjudicatory hearings and the Board
19    shall render its decision within 120 days of the filing of
20    the petition. Any such decision shall be subject to review
21    pursuant to Section 41 of this Act. Where USEPA promulgates
22    an applicable emission standard prior to the issuance of
23    the CAAPP permit, the Agency shall include in the permit
24    the promulgated standard, provided that the source shall
25    have the compliance period provided under Section 112(i) of
26    the Clean Air Act. Where USEPA promulgates an applicable

 

 

09900HB3341ham003- 89 -LRB099 10047 MGM 34300 a

1    standard subsequent to the issuance of the CAAPP permit,
2    the Agency shall revise such permit upon the next renewal
3    to reflect the promulgated standard, providing a
4    reasonable time for the applicable source to comply with
5    the standard, but no longer than 8 years after the date on
6    which the source is first required to comply with the
7    emissions limitation established under this subsection.
8        c. The Agency shall have the authority to implement and
9    enforce complete or partial emission standards promulgated
10    by USEPA pursuant to Section 112(d), and standards
11    promulgated by USEPA pursuant to Sections 112(f), 112(h),
12    112(m), and 112(n), and may accept delegation of authority
13    from USEPA to implement and enforce Section 112(l) and
14    requirements for the prevention and detection of
15    accidental releases pursuant to Section 112(r) of the Clean
16    Air Act.
17        d. The Agency shall have the authority to issue permits
18    pursuant to Section 112(i)(5) of the Clean Air Act.
19        e. The Agency has the authority to implement Section
20    112(g) of the Clean Air Act consistent with the Clean Air
21    Act and federal regulations promulgated thereunder. If the
22    Agency refuses to include the emission limitations
23    proposed in an application submitted by an owner or
24    operator for a case-by-case maximum achievable control
25    technology (MACT) determination, the owner or operator may
26    petition the Board to determine whether the emission

 

 

09900HB3341ham003- 90 -LRB099 10047 MGM 34300 a

1    limitation proposed by the owner or operator or an
2    alternative emission limitation proposed by the Agency
3    provides for a level of control required by Section 112 of
4    the Clean Air Act, or to otherwise establish an appropriate
5    emission limitation under Section 112 of the Clean Air Act.
 
6    20. Small Business.
7        a. For purposes of this subsection:
8        "Program" is the Small Business Stationary Source
9    Technical and Environmental Compliance Assistance Program
10    created within this State pursuant to Section 507 of the
11    Clean Air Act and guidance promulgated thereunder, to
12    provide technical assistance and compliance information to
13    small business stationary sources;
14        "Small Business Assistance Program" is a component of
15    the Program responsible for providing sufficient
16    communications with small businesses through the
17    collection and dissemination of information to small
18    business stationary sources; and
19        "Small Business Stationary Source" means a stationary
20    source that:
21            1. is owned or operated by a person that employs
22        100 or fewer individuals;
23            2. is a small business concern as defined in the
24        "Small Business Act";
25            3. is not a major source as that term is defined in

 

 

09900HB3341ham003- 91 -LRB099 10047 MGM 34300 a

1        subsection 2 of this Section;
2            4. does not emit 50 tons or more per year of any
3        regulated air pollutant, except greenhouse gases; and
4            5. emits less than 75 tons per year of all
5        regulated pollutants, except greenhouse gases.
6        b. The Agency shall adopt and submit to USEPA, after
7    reasonable notice and opportunity for public comment, as a
8    revision to the Illinois state implementation plan, plans
9    for establishing the Program.
10        c. The Agency shall have the authority to enter into
11    such contracts and agreements as the Agency deems necessary
12    to carry out the purposes of this subsection.
13        d. The Agency may establish such procedures as it may
14    deem necessary for the purposes of implementing and
15    executing its responsibilities under this subsection.
16        e. There shall be appointed a Small Business Ombudsman
17    (hereinafter in this subsection referred to as
18    "Ombudsman") to monitor the Small Business Assistance
19    Program. The Ombudsman shall be a nonpartisan designated
20    official, with the ability to independently assess whether
21    the goals of the Program are being met.
22        f. The State Ombudsman Office shall be located in an
23    existing Ombudsman office within the State or in any State
24    Department.
25        g. There is hereby created a State Compliance Advisory
26    Panel (hereinafter in this subsection referred to as

 

 

09900HB3341ham003- 92 -LRB099 10047 MGM 34300 a

1    "Panel") for determining the overall effectiveness of the
2    Small Business Assistance Program within this State.
3        h. The selection of Panel members shall be by the
4    following method:
5            1. The Governor shall select two members who are
6        not owners or representatives of owners of small
7        business stationary sources to represent the general
8        public;
9            2. The Director of the Agency shall select one
10        member to represent the Agency; and
11            3. The State Legislature shall select four members
12        who are owners or representatives of owners of small
13        business stationary sources. Both the majority and
14        minority leadership in both Houses of the Legislature
15        shall appoint one member of the panel.
16        i. Panel members should serve without compensation but
17    will receive full reimbursement for expenses including
18    travel and per diem as authorized within this State.
19        j. The Panel shall select its own Chair by a majority
20    vote. The Chair may meet and consult with the Ombudsman and
21    the head of the Small Business Assistance Program in
22    planning the activities for the Panel.
 
23    21. Temporary Sources.
24        a. The Agency may issue a single permit authorizing
25    emissions from similar operations by the same source owner

 

 

09900HB3341ham003- 93 -LRB099 10047 MGM 34300 a

1    or operator at multiple temporary locations, except for
2    sources which are affected sources for acid deposition
3    under Title IV of the Clean Air Act.
4        b. The applicant must demonstrate that the operation is
5    temporary and will involve at least one change of location
6    during the term of the permit.
7        c. Any such permit shall meet all applicable
8    requirements of this Section and applicable regulations,
9    and include conditions assuring compliance with all
10    applicable requirements at all authorized locations and
11    requirements that the owner or operator notify the Agency
12    at least 10 days in advance of each change in location.
 
13    22. Solid Waste Incineration Units.
14        a. A CAAPP permit for a solid waste incineration unit
15    combusting municipal waste subject to standards
16    promulgated under Section 129(e) of the Clean Air Act shall
17    be issued for a period of 12 years and shall be reviewed
18    every 5 years, unless the Agency requires more frequent
19    review through Agency procedures.
20        b. During the review in paragraph (a) of this
21    subsection, the Agency shall fully review the previously
22    submitted CAAPP permit application and corresponding
23    reports subsequently submitted to determine whether the
24    source is in compliance with all applicable requirements.
25        c. If the Agency determines that the source is not in

 

 

09900HB3341ham003- 94 -LRB099 10047 MGM 34300 a

1    compliance with all applicable requirements it shall
2    revise the CAAPP permit as appropriate.
3        d. The Agency shall have the authority to adopt
4    procedural rules, in accordance with the Illinois
5    Administrative Procedure Act, as the Agency deems
6    necessary, to implement this subsection.
7(Source: P.A. 97-95, eff. 7-12-11.)
 
8    Section 99. Effective date. This Act takes effect upon
9becoming law.".