| | 09900HB4477ham003 | - 2 - | LRB099 18353 MLM 47891 a |
|
|
| 1 | | payments unless explicitly rejected by the contractor. |
| 2 | | (c) When a contract under this Code entered into by the |
| 3 | | Department of Transportation provides for mobilization |
| 4 | | payments and the contractor is using the services of a |
| 5 | | subcontractor, the subcontract shall include terms requiring |
| 6 | | mobilization payments be made to the subcontractor. |
| 7 | | Mobilization payments to a subcontractor shall be made on a |
| 8 | | tiered system based on the total value of the subcontract: |
|
| 9 | | Subcontract value | Mobilization percentage | |
| 10 | | Less than $10,000 | 25% | |
| 11 | | $10,000-$19,999 | 20% | |
| 12 | | $20,000-$39,999 | 18% | |
| 13 | | $40,000-$59,999 | 16% | |
| 14 | | $60,000-$79,999 | 14% | |
| 15 | | $80,000-$99,999 | 12% | |
| 16 | | $100,000-$249,999 | 10% | |
| 17 | | $250,000-$499,999 | 9% | |
| 18 | | $500,000-$750,000 | 8% | |
| 19 | | Over $750,000 | 7% |
|
| 20 | | (d) This Section only applies to contracts entered into by |