Rep. Robert Rita
Filed: 11/30/2016
| | 09900SB2814ham004 | | LRB099 19990 JWD 51891 a |
|
|
| 1 | | AMENDMENT TO SENATE BILL 2814
|
| 2 | | AMENDMENT NO. ______. Amend Senate Bill 2814, AS AMENDED, |
| 3 | | with reference to page and line numbers of House Amendment No. |
| 4 | | 3 as follows:
|
| 5 | | on page 2, line 23, after the semicolon, by inserting "and"; |
| 6 | | and |
| 7 | | on page 3, line 3, by replacing "; and" with "."; and |
| 8 | | on page 3, by deleting lines 4 through 11; and |
| 9 | | on page 3, by replacing lines 12 through 26 with the following: |
| 10 | | "(b) The General
Assembly finds that low-income customers |
| 11 | | should be included
within the State's efforts to expand the use |
| 12 | | of distributed
generation technologies and devices."; and |
| 13 | | on page 4, by deleting lines 1 and 2; and |
|
| | 09900SB2814ham004 | - 2 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | on page 18, line 22, after "16-115D" by inserting ", subsection |
| 2 | | (g) of Section 16-128A, and subsection (a) of Section 16-128B"; |
| 3 | | and |
| 4 | | on page 22, by replacing lines 23 through 25 with the |
| 5 | | following: |
| 6 | | "(B) Conduct the competitive procurement processes |
| 7 | | identified in this Act to
procure the supply resources |
| 8 | | identified in the procurement
plan."; and |
| 9 | | on page 27, line 22, after "Section", by inserting "that owns |
| 10 | | or operates electric distribution facilities"; and |
| 11 | | on page 29, line 26, after "Section", by inserting "that owns |
| 12 | | or operates electric distribution facilities"; and |
| 13 | | on page 37, lines 9 and 10, by deleting "the planning process |
| 14 | | for"; and |
| 15 | | on page 45, by replacing line 25 with "solar projects that are |
| 16 | | procured under procurement processes authorized by the |
| 17 | | long-term"; and |
| 18 | | on page 46, by replacing lines 8 and 9 with "Renewable Energy |
| 19 | | Resources Fund. Each contract that provides for the |
|
| | 09900SB2814ham004 | - 3 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | installation of solar facilities shall provide that the solar |
| 2 | | facilities will produce energy"; and |
| 3 | | on page 46, line 13, after "Fund", by inserting "and not |
| 4 | | otherwise committed to contracts executed under subsection (i) |
| 5 | | of this Section"; and |
| 6 | | on page 48, line 6, before the period, by inserting ", and |
| 7 | | shall endeavor to coordinate with the job training programs |
| 8 | | described in paragraph (1) of subsection (a) of Section |
| 9 | | 16-108.12 of the Public Utilities Act"; and |
| 10 | | on page 50, line 3, by replacing "use" with "uses"; and |
| 11 | | on page 52, line 23, by replacing "than they would otherwise |
| 12 | | be" with "than the prices from programs offered under |
| 13 | | subsection (c) of Section 1-75 of this Act"; and |
| 14 | | on page 55, line 12, after "participants", by inserting "and |
| 15 | | organizations"; and |
| 16 | | on page 55, line 19, after the semicolon, by inserting "the |
| 17 | | number of jobs or job opportunities created;"; and |
| 18 | | on page 56, by deleting lines 13 through 16; and |
|
| | 09900SB2814ham004 | - 4 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | on page 56, line 18, by replacing "program" with "long-term |
| 2 | | renewable resources procurement plan"; and |
| 3 | | on page 60, line 17, after the period, by inserting "Fees |
| 4 | | collected from bidders shall be deposited into the Renewable |
| 5 | | Energy Resources Fund."; and |
| 6 | | on page 73, line 5, by deleting "the planning process for"; and |
| 7 | | on page 73, line 8, after "(a)", by inserting ", except as |
| 8 | | provided in subsection (q) of Section 16-111.5 of the Public |
| 9 | | Utilities Act,"; and |
| 10 | | on page 82, line 21, before the period, by inserting "and that |
| 11 | | the project was installed by qualified persons in compliance |
| 12 | | with the requirements of Section 16-128A of the Public |
| 13 | | Utilities Act and any rules or regulations adopted thereunder"; |
| 14 | | and |
| 15 | | on page 83, line 3, before the period, by inserting "and that |
| 16 | | the project was installed by qualified persons in compliance |
| 17 | | with the requirements of Section 16-128A of the Public |
| 18 | | Utilities Act and any rules or regulations adopted thereunder"; |
| 19 | | and |
| 20 | | on page 83, by replacing lines 8 through 11 with the following: |
|
| | 09900SB2814ham004 | - 5 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | "For purposes of this Section, "prevailing |
| 2 | | wage" means the hourly cash wages plus fringe |
| 3 | | benefits for training and apprenticeship programs |
| 4 | | approved by the U.S. Department of Labor, Bureau of |
| 5 | | Apprenticeship and Training, health and welfare, |
| 6 | | insurance, vacations and pensions paid generally, |
| 7 | | in the locality in which the work is being |
| 8 | | performed, to employees engaged in work of a |
| 9 | | similar character on public works."; and |
| 10 | | on page 87, lines 8 and 23, by replacing "The" each time it |
| 11 | | appears with "Notwithstanding whether a long-term renewable |
| 12 | | resources procurement plan has been approved, the"; and |
| 13 | | on page 95, by replacing lines 8 through 19 with "located in |
| 14 | | this State. If the resources are not available in Illinois, the |
| 15 | | Agency shall further qualify renewable energy credits from |
| 16 | | facilities located in (i) any adjacent state, or (ii) if they |
| 17 | | are generated from facilities located in another state from |
| 18 | | which facilities transmission is contracted for with a direct |
| 19 | | current electric transmission facility that has a direct |
| 20 | | current to alternative current conversion facility located in |
| 21 | | Illinois, if the generator demonstrates and the Agency |
| 22 | | determines that the facility's location in an adjacent state or |
| 23 | | the facility's transmission contracts permit it to efficiently |
| 24 | | deliver electricity to Illinois residents and to promote the |
|
| | 09900SB2814ham004 | - 6 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | State's interest in the health, safety, and welfare of its |
| 2 | | residents based on the public interest criteria described |
| 3 | | above. To ensure that the public interest criteria are applied |
| 4 | | to the procurement and given full effect, the Agency's |
| 5 | | long-term procurement plan shall describe in detail how each |
| 6 | | public interest factor shall be considered and weighted for |
| 7 | | facilities located in states adjacent to Illinois or from |
| 8 | | facilities located in other states."; and |
| 9 | | on page 96, line 22, by deleting "either"; and |
| 10 | | on page 96, lines 22 and 23, by deleting "or Section 16-108.9 |
| 11 | | of the Public Utilities Act"; and |
| 12 | | on page 97, line 12, by replacing "declining block" with |
| 13 | | "Adjustable Block"; and |
| 14 | | on page 103, line 12, by replacing "including" with "to ensure |
| 15 | | robust participation opportunities for"; and |
| 16 | | on page 105, line 10, before the period, by inserting "; |
| 17 | | provided that for the delivery years beginning June 1, 2017, |
| 18 | | June 1, 2021, and June 1, 2025, the long-term renewable |
| 19 | | resources procurement plan shall allocate 10% of the funds |
| 20 | | available under the plan for the applicable delivery year, or |
| 21 | | $20,000,000 per delivery year, whichever is greater, and |
|
| | 09900SB2814ham004 | - 7 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | $10,000,000 of such funds in such year shall be used by an |
| 2 | | electric utility that serves more than 3,000,000 retail |
| 3 | | customers in the State to implement a Commission-approved plan |
| 4 | | under Section 16-108.12 of the Public Utilities Act"; and |
| 5 | | on page 107, line 21, by replacing "(Blank)." with "The owner |
| 6 | | of renewable energy facilities that are located in Illinois and |
| 7 | | that are energized after June 1, 2017, must certify that not |
| 8 | | less than the prevailing wage was or will be paid to employees |
| 9 | | who are engaged in construction activities associated with the |
| 10 | | project before the renewable energy facility may participate in |
| 11 | | a procurement event under this subsection (c)."; and |
| 12 | | on page 133, line 26, before the period, by inserting "ending |
| 13 | | May 31, 2027"; and |
| 14 | | on page 148, lines 13 and 14, by replacing "rolling 4-year
|
| 15 | | period" with "delivery year"; and |
| 16 | | on page 148, line 14, after "volume" by inserting "receiving |
| 17 | | payments in such year"; and |
| 18 | | on page 148, by replacing lines 16 and 17 with "net increase |
| 19 | | that delivery year to the costs of those credits included in"; |
| 20 | | and |
|
| | 09900SB2814ham004 | - 8 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | on page 149, line 1, by replacing "procured" with "paid"; and |
| 2 | | on page 148, line 6, after the period, by inserting "Unpaid |
| 3 | | contractual volume for any delivery year shall be paid in any |
| 4 | | subsequent delivery year in which such payments can be made |
| 5 | | without exceeding the amount specified in this paragraph (2)."; |
| 6 | | and |
| 7 | | on page 149, line 9, by replacing "procured" with "be paid"; |
| 8 | | and |
| 9 | | on page 151, lines 21 and 22, by replacing "of Section 16-108 |
| 10 | | of the Public Utilities Act." with "and (m) of Section 16-108 |
| 11 | | of the Public Utilities Act, and the contracts executed under |
| 12 | | this subsection (d-5) shall provide that the utilities' payment |
| 13 | | obligations under such contracts shall be reduced if an |
| 14 | | adjustment is required under subsection (m) of Section 16-108 |
| 15 | | of the Public Utilities Act."; and |
| 16 | | on page 156, line 1, before "subsections", by inserting |
| 17 | | "Section 1-56,"; and |
| 18 | | on page 162, line 14, after "Sections" by inserting "5-117,"; |
| 19 | | and |
| 20 | | on page 162, line 16, by replacing "and 16-127" with "16-127, |
|
| | 09900SB2814ham004 | - 9 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | and 16-128A"; and |
| 2 | | on page 162, line 17, by deleting "16-108.9"; and |
| 3 | | on page 162, line 17, by replacing "and 16-108.12" with |
| 4 | | "16-108.12, 16-108.15, and 16-108.16"; and |
| 5 | | on page 162, immediately below line 18, by inserting the |
| 6 | | following: |
| 7 | | "(220 ILCS 5/5-117) |
| 8 | | Sec. 5-117. Supplier diversity goals. |
| 9 | | (a) The public policy of this State is to collaboratively |
| 10 | | work with companies that serve Illinois residents to improve |
| 11 | | their supplier diversity in a non-antagonistic manner. |
| 12 | | (b) The Commission shall require all gas, electric, and |
| 13 | | water companies with at least 100,000 customers under its |
| 14 | | authority, as well as suppliers of wind energy, solar energy,
|
| 15 | | hydroelectricity, nuclear energy, and any other supplier of
|
| 16 | | energy within this State, to submit an annual report by April |
| 17 | | 15, 2015 and every April 15 thereafter, in a searchable Adobe |
| 18 | | PDF format, on all procurement goals and actual spending for |
| 19 | | female-owned, minority-owned, veteran-owned, and small |
| 20 | | business enterprises in the previous calendar year. These goals |
| 21 | | shall be expressed as a percentage of the total work performed |
| 22 | | by the entity submitting the report, and the actual spending |
|
| | 09900SB2814ham004 | - 10 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | for all female-owned, minority-owned, veteran-owned, and small |
| 2 | | business enterprises shall also be expressed as a percentage of |
| 3 | | the total work performed by the entity submitting the report. |
| 4 | | (c) Each participating company in its annual report shall |
| 5 | | include the following information: |
| 6 | | (1) an explanation of the plan for the next year to |
| 7 | | increase participation; |
| 8 | | (2) an explanation of the plan to increase the goals; |
| 9 | | (3) the areas of procurement each company shall be |
| 10 | | actively seeking more participation in in the next year; |
| 11 | | (4) an outline of the plan to alert and encourage |
| 12 | | potential vendors in that area to seek business from the |
| 13 | | company; |
| 14 | | (5) an explanation of the challenges faced in finding |
| 15 | | quality vendors and offer any suggestions for what the |
| 16 | | Commission could do to be helpful to identify those |
| 17 | | vendors; |
| 18 | | (6) a list of the certifications the company |
| 19 | | recognizes; |
| 20 | | (7) the point of contact for any potential vendor who |
| 21 | | wishes to do business with the company and explain the |
| 22 | | process for a vendor to enroll with the company as a |
| 23 | | minority-owned, women-owned, or veteran-owned company; and |
| 24 | | (8) any particular success stories to encourage other |
| 25 | | companies to emulate best practices. |
| 26 | | (d) Each annual report shall include as much State-specific |
|
| | 09900SB2814ham004 | - 11 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | data as possible. If the submitting entity does not submit |
| 2 | | State-specific data, then the company shall include any |
| 3 | | national data it does have and explain why it could not submit |
| 4 | | State-specific data and how it intends to do so in future |
| 5 | | reports, if possible. |
| 6 | | (e) Each annual report shall include the rules, |
| 7 | | regulations, and definitions used for the procurement goals in |
| 8 | | the company's annual report. |
| 9 | | (f) The Commission and all participating entities shall |
| 10 | | hold an annual workshop open to the public in 2015 and every |
| 11 | | year thereafter on the state of supplier diversity to |
| 12 | | collaboratively seek solutions to structural impediments to |
| 13 | | achieving stated goals, including testimony from each |
| 14 | | participating entity as well as subject matter experts and |
| 15 | | advocates. The Commission shall publish a database on its |
| 16 | | website of the point of contact for each participating entity |
| 17 | | for supplier diversity, along with a list of certifications |
| 18 | | each company recognizes from the information submitted in each |
| 19 | | annual report. The Commission shall publish each annual report |
| 20 | | on its website and shall maintain each annual report for at |
| 21 | | least 5 years.
|
| 22 | | (Source: P.A. 98-1056, eff. 8-26-14.)"; and |
| 23 | | on page 178, lines 24 and 25, by deleting "and energy |
| 24 | | efficiency measures
implemented under subsection (l) of this |
| 25 | | Section"; and |
|
| | 09900SB2814ham004 | - 12 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | on page 179, by replacing lines 5 through 10 with "Agency |
| 2 | | Act."; and |
| 3 | | on page 179, by replacing lines 17 and 18 with "cumulative |
| 4 | | persisting annual savings of 6.6% from energy efficiency |
| 5 | | measures and"; and |
| 6 | | on page 179, line 23, by replacing "The" with "For the purposes |
| 7 | | of this subsection (b) and subsection (b-5), the"; and |
| 8 | | on page 179, by replacing lines 24 through 26 with "and energy |
| 9 | | sales shall be reduced by the number of MWhs equal to the sum |
| 10 | | of the annual consumption of customers that are exempt from |
| 11 | | subsections (a) through (j) of this Section under subsection |
| 12 | | (l) of this Section, as averaged across the calendar years |
| 13 | | 2014, 2015, and 2016. After 2017, the deemed value of |
| 14 | | cumulative"; and |
| 15 | | on page 180, line 7, by deleting ", or 5,071,018 MWhs,"; and |
| 16 | | on page 180, line 10, by deleting ", or 4,553,371 MWhs,"; and |
| 17 | | on page 180, line 13, by deleting ", or 3,998,012 MWhs,"; and |
| 18 | | on page 180, line 16, by deleting ", or 3,533,219 MWhs,"; and |
|
| | 09900SB2814ham004 | - 13 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | on page 180, line 19, by deleting ", or 3,108,290 MWhs,"; and |
| 2 | | on page 180, line 22, by deleting ", or 2,738,689 MWhs,"; and |
| 3 | | on page 180, line 25, by deleting ", or 2,463,055 MWhs,"; and |
| 4 | | on page 181, line 2, by deleting ", or 2,221,716 MWhs,"; and |
| 5 | | on page 181, line 5, by deleting ", or 2,017,109 MWhs,"; and |
| 6 | | on page 181, line 8, by deleting ", or 1,822,754 MWhs,"; and |
| 7 | | on page 181, line 11, by deleting ", or 1,624,769 MWhs,"; and |
| 8 | | on page 181, line 14, by deleting ", or 1,460,039 MWhs,"; and |
| 9 | | on page 181, line 17, by deleting ", or 1,181,647 MWhs,"; and |
| 10 | | on page 182, line 7, by replacing "all Self-Direct Customers |
| 11 | | that elect such status" with "customers that are exempt from |
| 12 | | subsections (a) through (j) of this Section"; and |
| 13 | | on page 183, line 16, by deleting ", or 2,435,400 MWhs,"; and |
| 14 | | on page 183, line 21, by replacing "The" with "For the purposes |
|
| | 09900SB2814ham004 | - 14 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | of this subsection (b-10) and subsection (b-15), the"; and |
| 2 | | on page 183, by replacing lines 22 through 24 with "and energy |
| 3 | | sales shall be reduced by the number of MWhs equal to the sum |
| 4 | | of the annual consumption of customers that are exempt from |
| 5 | | subsections (a) through (j) of this Section under subsection |
| 6 | | (l) of this Section, as averaged across the calendar years |
| 7 | | 2014, 2015, and 2016. After 2017, the deemed value of |
| 8 | | cumulative"; and |
| 9 | | on page 184, line 5, by deleting ", or 2,140,200 MWhs,"; and |
| 10 | | on page 184, line 8, by deleting ", or 1,918,800 MWhs,"; and |
| 11 | | on page 184, line 11, by deleting ", or 1,660,500 MWhs,"; and |
| 12 | | on page 184, line 14, by deleting ", or 1,476,000 MWhs,"; and |
| 13 | | on page 184, line 17, by deleting ", or 1,291,500 MWhs,"; and |
| 14 | | on page 184, line 20, by deleting ", or 1,143,900 MWhs,"; and |
| 15 | | on page 184, line 23, by deleting ", or 1,033,200 MWhs,"; and |
| 16 | | on page 184, line 26, by deleting ", or 922,500 MWhs,"; and |
|
| | 09900SB2814ham004 | - 15 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | on page 185, line 3, by deleting ", or 848,700 MWhs,"; and |
| 2 | | on page 185, line 6, by deleting ", or 774,900 MWhs,"; and |
| 3 | | on page 185, line 9, by deleting ", or 664,200 MWhs,"; and |
| 4 | | on page 185, line 12, by deleting ", or 627,300 MWhs,"; and |
| 5 | | on page 185, line 15, by deleting ", or 553,500 MWhs,"; and |
| 6 | | on page 185, line 25, by replacing "all Self-Direct Customers |
| 7 | | that elect such status" with "customers that are exempt from |
| 8 | | subsections (a) through (j) of this Section"; and |
| 9 | | on page 206, line 10, after the comma, by inserting "for a |
| 10 | | utility that serves less than 3,000,000 retail customers, if"; |
| 11 | | and |
| 12 | | on page 206, line 19, by replacing "In no event shall" with |
| 13 | | "Except as provided in subsection (m) of this Section,"; and |
| 14 | | on page 206, line 21, after "period" by inserting "shall not"; |
| 15 | | and |
| 16 | | on page 207, line 19, by replacing "In no event shall" with |
| 17 | | "Except as provided in subsection (m) of this Section,"; and |
|
| | 09900SB2814ham004 | - 16 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | on page 207, line 21, after "period" by inserting "shall not"; |
| 2 | | and |
| 3 | | on page 208, line 20, by replacing "In no event shall" with |
| 4 | | "Except as provided in subsection (m) of this Section,"; and |
| 5 | | on page 208, line 22, after "period" by inserting "shall not"; |
| 6 | | and |
| 7 | | by deleting line 12 on page 215 through line 9 on page 216; and |
| 8 | | on page 218, immediately below line 8, by inserting the |
| 9 | | following: |
| 10 | | "(7.5) For purposes of this Section, the term |
| 11 | | "applicable
annual incremental goal" means the difference |
| 12 | | between the
cumulative persisting annual savings goal for |
| 13 | | the calendar
year that is the subject of the independent |
| 14 | | evaluator's
determination and the cumulative persisting |
| 15 | | annual savings
goal for the immediately preceding calendar |
| 16 | | year, as such
goals are defined in subsections (b-5) and |
| 17 | | (b-15) of this
Section and as these goals may have been |
| 18 | | modified as
provided for under subsection (b-20) and |
| 19 | | paragraphs (1)
through (3) of subsection (f) of this |
| 20 | | Section. Under
subsections (b), (b-5), (b-10), and (b-15) |
| 21 | | of this Section,
a utility must first replace energy |
|
| | 09900SB2814ham004 | - 17 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | savings from measures
that have reached the end of their |
| 2 | | measure lives and would
otherwise have to be replaced to |
| 3 | | meet the applicable
savings goals identified in subsection |
| 4 | | (b-5) or (b-15) of this Section before any progress towards |
| 5 | | achievement of its
applicable annual incremental goal may |
| 6 | | be counted.
Notwithstanding anything else set forth in this |
| 7 | | Section,
the difference between the actual annual |
| 8 | | incremental
savings achieved in any given year, including |
| 9 | | the
replacement of energy savings from measures that have
|
| 10 | | expired, and the applicable annual incremental goal shall
|
| 11 | | not affect adjustments to the return on equity for
|
| 12 | | subsequent calendar years under this subsection (g)."; and |
| 13 | | on page 220, by replacing lines 6 and 7 with "goal shall use |
| 14 | | the unreduced applicable annual"; and |
| 15 | | by replacing line 21 on page 220 through line 3 on page 221 |
| 16 | | with the following: |
| 17 | | "(iii) For the period of January 1, 2026 |
| 18 | | through December 31, 2030, the calculation for |
| 19 | | determining achievement that is less than 134% but |
| 20 | | more than 100% of the applicable annual |
| 21 | | incremental goal shall use the reduced applicable |
| 22 | | annual incremental goal to set the value for 100% |
| 23 | | achievement of the goal and shall use the unreduced |
| 24 | | goal to set the value for 125% achievement. The 6 |
|
| | 09900SB2814ham004 | - 18 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | basis point value shall also be modified, as |
| 2 | | necessary, so that the 200 basis points are evenly |
| 3 | | apportioned among each percentage point value |
| 4 | | between 100% and 134% achievement."; and |
| 5 | | by deleting line 18 on page 222 through line 7 on page 223; and |
| 6 | | by replacing line 20 on page 225 through line 4 on page 234 |
| 7 | | with the following: |
| 8 | | "(l) For the calendar years covered by a multi-year plan |
| 9 | | commencing after December 31, 2017, subsections (a) through (j) |
| 10 | | of this Section do not apply to any retail customers of an |
| 11 | | electric utility that serves more than 3,000,000 retail |
| 12 | | customers in the State and whose total highest 30 minute demand |
| 13 | | was more than 10,000 kilowatts, or any retail customers of an |
| 14 | | electric utility that serves less than 3,000,000 retail |
| 15 | | customers but more than 500,000 retail customers in the State |
| 16 | | and whose total highest 15 minute demand was more than 10,000 |
| 17 | | kilowatts. For purposes of this subsection (l), "retail |
| 18 | | customer" has the meaning set forth in Section 16-102 of this |
| 19 | | Act. A determination of whether this subsection is applicable |
| 20 | | to a customer shall be made for each multi-year plan beginning |
| 21 | | after December 31, 2017. The criteria for determining whether a |
| 22 | | this subsection (l) is applicable to a retail customer shall be |
| 23 | | based on the 12 consecutive billing periods prior to the start |
| 24 | | of the first year of each such multi-year plan."; and |
|
| | 09900SB2814ham004 | - 19 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | on page 234, line 24, after "amount", by inserting "of"; and |
| 2 | | by replacing line 26 on page 234 through line 1 on page 235 |
| 3 | | with "utility's load attributable to customers who are exempt |
| 4 | | from subsections (a) through (j) of this Section under |
| 5 | | subsection (l) of this"; and |
| 6 | | on page 235, line 2, by replacing "Section." with "For purposes |
| 7 | | of this subsection (m), the amount paid per kilowatthour |
| 8 | | includes,
without limitation, estimated amounts paid for |
| 9 | | supply,
transmission, distribution, surcharges, and add-on |
| 10 | | taxes."; and |
| 11 | | on page 284, by replacing lines 15 and 16 with "2,000 kilowatts |
| 12 | | and is primarily used to offset that customer's electricity |
| 13 | | load;"; and |
| 14 | | on page 285, lines 3 and 4 by replacing "does not conflict" |
| 15 | | with "is consistent"; and |
| 16 | | on page 286, line 17, by replacing "$500" with "$250"; and |
| 17 | | on page 286, line 20, by replacing "(2)After" with "(2) After"; |
| 18 | | and |
|
| | 09900SB2814ham004 | - 20 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | on page 287, line 14, by replacing "(B)Non-residential" with |
| 2 | | "(B) Non-residential"; and |
| 3 | | on page 287, line 22, by replacing "(3)Upon" with "(3) Upon"; |
| 4 | | and |
| 5 | | on page 288, line 2, by replacing "(4)To" with "(4) To"; and |
| 6 | | on page 288, line 9, by replacing "(d)The" with "(d) The"; and |
| 7 | | on page 288, line 17, by replacing "(e)When" with "(e) When"; |
| 8 | | and |
| 9 | | on page 288, line 25, by deleting "based on best practices"; |
| 10 | | and |
| 11 | | on page 288, line 26, after "grid", by inserting "based on best |
| 12 | | practices"; and |
| 13 | | on page 289, line 18, by replacing "(f)Notwithstanding" with |
| 14 | | "(f) Notwithstanding"; and |
| 15 | | on page 290, line 8, by replacing "(g)No later than 180 days" |
| 16 | | with "(g) No later than 60 days"; and |
| 17 | | on page 290, line 15, by replacing "180" with "60"; and |
|
| | 09900SB2814ham004 | - 21 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | on page 310, immediately below line 23, by inserting the |
| 2 | | following: |
| 3 | | "(m)(1) An electric utility that recovers its costs of |
| 4 | | procuring zero emission credits from zero emission |
| 5 | | facilities through a cents-per-kilowatthour charge under |
| 6 | | to subsection (k) of this Section shall be subject to the |
| 7 | | requirements of this subsection (m). Notwithstanding |
| 8 | | anything to the contrary, such electric utility shall, |
| 9 | | beginning on April 30, 2018, and each April 30 thereafter |
| 10 | | until April 30, 2026, calculate whether any reduction must |
| 11 | | be applied to such cents-per-kilowatthour charge that is |
| 12 | | paid by retail customers of the electric utility that are |
| 13 | | exempt from subsections (a) through (j) of Section 8-103B |
| 14 | | of this Act under subsection (l) of Section 8-103B. Such |
| 15 | | charge shall be reduced for such customers for the next |
| 16 | | delivery year commencing on June 1 based on the amount |
| 17 | | necessary, if any, to limit the annual estimated average |
| 18 | | net increase for the prior calendar year due to the future |
| 19 | | energy investment costs to no more than 1.3% of 5.98 cents |
| 20 | | per kilowatt-hour, which is the average amount paid per |
| 21 | | kilowatthour for electric service during the year ending |
| 22 | | December 31, 2015 by Illinois industrial retail customers, |
| 23 | | as reported to the Edison Electric Institute. |
| 24 | | The calculations required by this subsection (m) shall |
| 25 | | be made only once for each year, and no subsequent rate |
|
| | 09900SB2814ham004 | - 22 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | impact determinations shall be made. |
| 2 | | (2) For purposes of this Section, "future energy |
| 3 | | investment costs" shall be calculated by subtracting the |
| 4 | | cents-per-kilowatthour charge identified in subparagraph |
| 5 | | (A) of this paragraph (2) from the sum of the |
| 6 | | cents-per-kilowatthour charges identified in subparagraph |
| 7 | | (B) of this paragraph (2): |
| 8 | | (A) The cents-per-kilowatthour charge identified |
| 9 | | in the electric utility's tariff placed into effect |
| 10 | | under Section 8-103 of the Public Utilities Act that, |
| 11 | | on December 1, 2016, was applicable to those retail |
| 12 | | customers that are exempt from subsections (a) through |
| 13 | | (j) of Section 8-103B of this Act under subsection (l) |
| 14 | | of Section 8-103B. |
| 15 | | (B) The sum of the following |
| 16 | | cents-per-kilowatthour charges applicable to those |
| 17 | | retail customers that are exempt from subsections (a) |
| 18 | | through (j) of Section 8-103B of this Act under |
| 19 | | subsection (l) of Section 8-103B, provided that if one |
| 20 | | or more of the following charges has been in effect and |
| 21 | | applied to such customers for more than one calendar |
| 22 | | year, then each charge shall be equal to the average of |
| 23 | | the charges applied over a period that commences with |
| 24 | | the calendar year ending December 31, 2017 and ends |
| 25 | | with the most recently completed calendar year prior to |
| 26 | | the calculation required by this subsection (m): |
|
| | 09900SB2814ham004 | - 23 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | (i) the cents-per-kilowatthour charge to |
| 2 | | recover the costs incurred by the utility under |
| 3 | | subsection (d-5) of Section 1-75 of the Illinois |
| 4 | | Power Agency Act, adjusted for any reductions |
| 5 | | required under this subsection (m); and |
| 6 | | (ii) the cents-per-kilowatthour charge to |
| 7 | | recover the costs incurred by the utility under |
| 8 | | Section 16-107.6 of the Public Utilities Act. |
| 9 | | If no charge was applied for a given calendar year |
| 10 | | under item (i) or (ii) of this subparagraph (B), then |
| 11 | | the value of the charge for that year shall be zero. |
| 12 | | (3) If a reduction is required by the calculation |
| 13 | | performed under this subsection (m), then the amount of the |
| 14 | | reduction shall be multiplied by the number of years |
| 15 | | reflected in the averages calculated under subparagraph |
| 16 | | (B) of paragraph (2) of this subsection (m). Such reduction |
| 17 | | shall be applied to the cents-per-kilowatthour charge that |
| 18 | | is applicable to those retail customers that are exempt |
| 19 | | from subsections (a) through (j) of Section 8-103B of this |
| 20 | | Act under subsection (l) of Section 8-103B beginning with |
| 21 | | the next delivery year commencing after the date of the |
| 22 | | calculation required by this subsection (m). |
| 23 | | (4) The electric utility shall file a notice with the |
| 24 | | Commission on May 1 of 2018 and each May 1 thereafter until |
| 25 | | May 1, 2026 containing the reduction, if any, which must be |
| 26 | | applied for the delivery year which begins in the year of |
|
| | 09900SB2814ham004 | - 24 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | the filing. The notice shall contain the calculations made |
| 2 | | pursuant to this section. By October 1 of each year |
| 3 | | beginning in 2018, each electric utility shall notify the |
| 4 | | Commission if it appears, based on an estimate of the |
| 5 | | calculation required in this subsection (m), that a |
| 6 | | reduction will be required in the next year."; and |
| 7 | | by deleting line 24 on page 358 through line 20 on page 380; |
| 8 | | and |
| 9 | | on page 383, by replacing lines 18 through 20 with the |
| 10 | | following: |
| 11 | | "(a) An electric utility that serves more than 3,000,000 |
| 12 | | customers in the State shall spend $10,000,000 per year in |
| 13 | | 2017, 2021, and 2025 to fund the programs described in this |
| 14 | | Section."; and |
| 15 | | on page 383, line 22, by deleting "annually over 5 years"; and |
| 16 | | on page 384, line 19, by deleting "qualified"; and |
| 17 | | on page 384, line 20, by replacing "may" with "shall"; and |
| 18 | | on page 384, line 22, by replacing "individuals" with |
| 19 | | "persons"; and |
|
| | 09900SB2814ham004 | - 25 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | on page 384, line 26, after "communities", by inserting "and |
| 2 | | that 2,000 jobs are created for persons who are or were foster |
| 3 | | children and persons with a record"; and |
| 4 | | on page 385, line 2, by deleting "annually over 5 years"; and |
| 5 | | on page 385, line 4, by replacing "5" with "4"; and |
| 6 | | on page 385, line 9, by deleting "annually over 5 years"; and |
| 7 | | on page 385, line 10, by replacing "annually" with "in the |
| 8 | | applicable year"; and |
| 9 | | on page 385, line 11, by replacing "(E)" with "(F)"; and |
| 10 | | on page 385, line 13, by replacing "5" with "4"; and |
| 11 | | on page 385, line 14, by replacing "$1,000,000" with |
| 12 | | "$500,000"; and |
| 13 | | on page 385, immediately below line 20, by inserting the |
| 14 | | following: |
| 15 | | "(F) $500,000 to a nonprofit organization that |
| 16 | | provides family services, housing education, job and |
| 17 | | career education opportunities that has successfully |
| 18 | | partnered with the utility on electric industry job |
|
| | 09900SB2814ham004 | - 26 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | training."; and |
| 2 | | on page 386, line 21, by deleting "qualified"; and |
| 3 | | on page 387, line 4, by replacing "(b)Within" with "(b) |
| 4 | | Within"; and |
| 5 | | on page 387, by replacing lines 12 through 15 with "which time |
| 6 | | the utility shall file a new plan. The utility shall use the |
| 7 | | funds described in subparagraph (O) of paragraph (1) of |
| 8 | | subsection (c) of Section 1-75 of the Illinois Power Agency Act |
| 9 | | to pay for the Commission approved programs under this |
| 10 | | Section."; and |
| 11 | | on page 387, immediately below line 15, by inserting the |
| 12 | | following: |
| 13 | | "(220 ILCS 5/16-108.15 new) |
| 14 | | Sec. 16-108.15. Rate impacts. |
| 15 | | (a) Each electric utility that serves more than 500,000 |
| 16 | | retail customers in the State shall file with the Commission |
| 17 | | the reports required by this Section, which shall identify the |
| 18 | | actual and projected average monthly increases in residential |
| 19 | | retail customers' electric bills due to future energy |
| 20 | | investment costs for the applicable period or periods. |
| 21 | | (b) The average monthly increase calculation shall be |
|
| | 09900SB2814ham004 | - 27 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | comprised of the following components: |
| 2 | | (1) Beginning with the 2017 calendar year, the average |
| 3 | | monthly amount paid by residential retail customers, |
| 4 | | expressed on a cents-per-kilowatthour basis, to recover |
| 5 | | future energy investment costs, which include the charges |
| 6 | | to recover the costs incurred by the utility under the |
| 7 | | following provisions: |
| 8 | | (A) Sections 8-103, Section 8-103B, and 16-111.5B |
| 9 | | of this Act, as applicable, and as such costs may be |
| 10 | | recovered under Sections 8-103, 8-103B, 16-111.5B or |
| 11 | | Section 16-108.5 of this Act; |
| 12 | | (B) subsection (d-5) of Section 1-75 of the |
| 13 | | Illinois Power Agency Act, as such costs may be |
| 14 | | recovered under subsection (k) of Section 16-108 of |
| 15 | | this Act; and |
| 16 | | (C) Section 16-107.6 of this Act. |
| 17 | | Beginning with the 2018 calendar year, each of the |
| 18 | | average monthly charges calculated in subparagraphs (A) |
| 19 | | through (C) of this paragraph (1) shall be equal to the |
| 20 | | average of each such charge applied over a period that |
| 21 | | commences with the calendar year ending December 31, 2017 |
| 22 | | and ends with the most recently completed calendar year |
| 23 | | prior to the calculation or calculations required by this |
| 24 | | Section. |
| 25 | | (2) The sum of the following: |
| 26 | | (A) net energy savings to residential retail |
|
| | 09900SB2814ham004 | - 28 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | customers that are attributable to the implementation |
| 2 | | of voltage optimization measures under Section 8-103B |
| 3 | | of this Act, expressed on a cents-per-kilowatthour |
| 4 | | basis, which are estimated energy and capacity |
| 5 | | benefits for residential retail customers minus the |
| 6 | | measure costs recovered from those customers, divided |
| 7 | | by the total number of residential retail customers, |
| 8 | | which quotient shall be divided by the months in the |
| 9 | | relevant period; notwithstanding this subparagraph |
| 10 | | (A), a utility may elect not to include an estimate of |
| 11 | | net energy savings as described in this subparagraph |
| 12 | | (A), in which case the value under this subparagraph |
| 13 | | (A) shall be zero; and |
| 14 | | (B) for an electric utility that serves more than |
| 15 | | 3,000,000 retail customers in the State, the benefits |
| 16 | | of the programs described in Section 16-108.10 of this |
| 17 | | Act, which are $0.00030 per kilowatthour for the 2017, |
| 18 | | 2018, 2019, 2020, and 2021 calendar years. |
| 19 | | Beginning with the 2018 calendar year, each of the |
| 20 | | values identified in subparagraphs (A) and (B) of this |
| 21 | | paragraph (2) shall be equal to the average of each |
| 22 | | such value during a period that commences with the |
| 23 | | calendar year ending December 31, 2017 and ends with |
| 24 | | the most recently completed calendar year prior to the |
| 25 | | calculation or calculations required by this Section. |
| 26 | | (3) For an electric utility that serves more than |
|
| | 09900SB2814ham004 | - 29 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | 3,000,000 retail customers in the State, the residential |
| 2 | | retail customer energy efficiency charges shall be $2.33 |
| 3 | | per month for the 2017 calendar year, provided that such |
| 4 | | charge shall be increased by 4% per year thereafter; for an |
| 5 | | electric utility that serves more than 500,000 but less |
| 6 | | than 3,000,000 retail customers in the State, the |
| 7 | | residential retail customer energy efficiency charges |
| 8 | | shall be $3.94 per month for the 2017 calendar year, |
| 9 | | provided that such charge shall be increased by 4% per year |
| 10 | | thereafter. Beginning with the 2018 calendar year, this |
| 11 | | charge shall be equal to the average of the charges applied |
| 12 | | over a period that commences with the calendar year ending |
| 13 | | December 31, 2017 and ends with the most recently completed |
| 14 | | calendar year prior to the calculation or calculations |
| 15 | | required by this Section. |
| 16 | | (c)(1) No later than June 30, 2017, an electric utility |
| 17 | | subject to this Section shall submit a report to the |
| 18 | | Commission that sets forth the utility's rolling 10-year |
| 19 | | projection of the values of each of the components |
| 20 | | described in paragraphs (1) through (3) of subsection (b) |
| 21 | | of this Section. No later than February 15, 2018 and every |
| 22 | | February 15 thereafter until February 15, 2031, each |
| 23 | | utility shall submit a report to the Commission that |
| 24 | | identifies the value of the actual charges applied during |
| 25 | | the immediately preceding calendar year and updates its |
| 26 | | rolling 10-year projection based on such actual charges. |
|
| | 09900SB2814ham004 | - 30 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | Each report submitted under this subsection (c) shall |
| 2 | | calculate the actual average monthly increase in |
| 3 | | residential retail customers' electric bills due to future |
| 4 | | energy investment costs during the immediately preceding |
| 5 | | calendar year and shall also calculate the projected |
| 6 | | average monthly increase in residential retail customers' |
| 7 | | electric bills due to such costs over the rolling 10-year |
| 8 | | period. Such calculations shall be performed by |
| 9 | | subtracting the sum of paragraph (2) of subsection (b) of |
| 10 | | this Section from the sum of paragraph (1) of such |
| 11 | | subsection (b), multiplying such difference by, as |
| 12 | | applicable, the actual or forecasted average monthly |
| 13 | | kilowatthour consumption for the residential retail |
| 14 | | customer class for the applicable period, and subtracting |
| 15 | | from such product the applicable value identified under |
| 16 | | paragraph (3) of such subsection (b). |
| 17 | | If the actual or projected average monthly increase for |
| 18 | | residential retail customers of electric utility that |
| 19 | | serves more than 3 million retail customers in the State |
| 20 | | exceeds $0.25, or the actual or projected average monthly |
| 21 | | increase for residential retail customers of an electric |
| 22 | | utility that serves more than 500,000 but less than 3 |
| 23 | | million retail customers in the State exceeds $0.35, then |
| 24 | | the applicable utility shall comply with the provisions of |
| 25 | | paragraphs (2) through (4) of this subsection (c), as |
| 26 | | applicable. |
|
| | 09900SB2814ham004 | - 31 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | (2) If the projected average monthly increase for |
| 2 | | residential retail customers during a calendar year |
| 3 | | exceeds the applicable limitation set forth in paragraph |
| 4 | | (1) of this subsection (c), then the utility shall comply |
| 5 | | with the following provisions, as applicable: |
| 6 | | (A) If an exceedance is projected during the first |
| 7 | | four calendar year of the rolling 10-year projection, |
| 8 | | then the utility shall include in its report submitted |
| 9 | | under paragraph (1) of this subsection (c) the |
| 10 | | utility's proposal or proposals to decrease the future |
| 11 | | energy investment costs described in paragraph (1) of |
| 12 | | subsection (b) of this Section to ensure that the |
| 13 | | limitation set forth in such paragraph (1) is not |
| 14 | | exceeded. The Commission shall, after notice and |
| 15 | | hearing, enter an order directing the utility to |
| 16 | | implement one or more proposals, as such proposals may |
| 17 | | be modified by the Commission. The Commission shall |
| 18 | | have the authority under this subparagraph (A) to |
| 19 | | approve modifications to the contracts executed under |
| 20 | | subsection (d-5) of Section 1-75 of the Illinois Power |
| 21 | | Agency Act. If the Commission approves modifications |
| 22 | | to such contracts, then the supplier shall have the |
| 23 | | option of accepting the modifications or terminating |
| 24 | | the modified contract or contracts, subject to the |
| 25 | | termination requirements and notice provisions set |
| 26 | | forth in item (i) of subparagraph (B) of paragraph (4) |
|
| | 09900SB2814ham004 | - 32 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | of this Section. |
| 2 | | (B) If an exceedance is projected during any |
| 3 | | calendar year during the last 6 years of the 10-year |
| 4 | | projection, then the utility shall demonstrate in its |
| 5 | | report submitted under paragraph (1) of this |
| 6 | | subsection (c) how the utility will reduce the future |
| 7 | | energy investment costs described in paragraph (1) of |
| 8 | | subsection (b) of this Section to ensure that the |
| 9 | | limitation set forth in such paragraph (1) is not |
| 10 | | exceeded. |
| 11 | | (3) If the actual average monthly increase for |
| 12 | | residential retail customers during a calendar year |
| 13 | | exceeded the limitation set forth in paragraph (1) of this |
| 14 | | subsection (c), then the utility shall prepare and file |
| 15 | | with the Commission, at the time it submits its report |
| 16 | | under paragraph (1) of this subsection (c), a corrective |
| 17 | | action plan that identifies how the utility will |
| 18 | | immediately reduce expenditures so that the utility will be |
| 19 | | in compliance with such limitation beginning on January 1 |
| 20 | | of the next calendar year. The Commission shall initiate an |
| 21 | | investigation to determine the factors that contributed to |
| 22 | | the actual average monthly increase exceeding such |
| 23 | | limitation for the applicable calendar year, and shall, |
| 24 | | after notice and hearing, enter an order approving, or |
| 25 | | approving with modification, the utility's corrective |
| 26 | | action plan within 120 days after the utility files such |
|
| | 09900SB2814ham004 | - 33 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | plan. The Commission shall also submit a report to the |
| 2 | | General Assembly no later than 30 days after it enters such |
| 3 | | order, and the report shall explain the results of the |
| 4 | | Commission's investigation and findings and conclusions of |
| 5 | | its order. |
| 6 | | (4) If the actual average monthly increase for |
| 7 | | residential retail customers during a calendar year |
| 8 | | exceeds the limitation set forth in paragraph (1) of this |
| 9 | | subsection (c) for two consecutive years, then the utility |
| 10 | | shall indicate in its report filed under paragraph (1) of |
| 11 | | this subsection (c) whether the utility will proceed with |
| 12 | | or terminate the future energy investments described and |
| 13 | | authorized under subsection (d-5) of the Illinois Power |
| 14 | | Agency Act and Sections 8-103B and 16-107.6 of this Act. |
| 15 | | The utility shall be subject to the requirements of |
| 16 | | subparagraph (A) or (B) of this paragraph (4), as |
| 17 | | applicable. |
| 18 | | (A) If the utility indicates that it will proceed |
| 19 | | with the future energy investments, then it shall be |
| 20 | | subject to the corrective action plan requirements set |
| 21 | | forth in paragraph (3) of this subsection (c). In |
| 22 | | addition, the utility must commit to apply a credit to |
| 23 | | residential retail customers' bills if the actual |
| 24 | | average monthly increase for such customers exceeds |
| 25 | | the limitation set forth in paragraph (1) of this |
| 26 | | subsection (c) for the year in which the utility files |
|
| | 09900SB2814ham004 | - 34 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | its corrective action plan, which credit shall be in an |
| 2 | | amount that equals the portion by which the increase |
| 3 | | exceeds such limitation. The Commission shall initiate |
| 4 | | an investigation to determine the factors that |
| 5 | | contributed to the actual average monthly increase |
| 6 | | exceeding such limitation for the applicable calendar |
| 7 | | year, including an analysis of the factors |
| 8 | | contributing to the limitation being exceeded for two |
| 9 | | consecutive years, and shall, after notice and |
| 10 | | hearing, enter an order approving, or approving with |
| 11 | | modification, the utility's corrective action plan |
| 12 | | within 120 days after the utility files such plan. The |
| 13 | | Commission shall also submit a supplemental report to |
| 14 | | the General Assembly no later than 30 days after it |
| 15 | | enters such order, and the report shall explain the |
| 16 | | results of the Commission's investigation and findings |
| 17 | | and conclusions of its order. |
| 18 | | (B) If the utility indicates that it will terminate |
| 19 | | future energy investments, then the Commission shall, |
| 20 | | notwithstanding anything to the contrary: |
| 21 | | (i) Order the utility to terminate the |
| 22 | | contract or contracts executed under subsection |
| 23 | | (d-5) of Section 1-75 of the Illinois Power Agency |
| 24 | | Act, pursuant to the contract termination |
| 25 | | provisions set forth in such subsection (d-5), |
| 26 | | provided that notice of such termination must be |
|
| | 09900SB2814ham004 | - 35 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | made at least 3 years and 75 days prior to the |
| 2 | | effective date of such termination. In the event |
| 3 | | that only a portion of the contracts executed under |
| 4 | | such subsection (d-5) are terminated for a |
| 5 | | particular zero emission facility, then the zero |
| 6 | | emission facility may elect to terminate all of the |
| 7 | | contracts executed for that facility under such |
| 8 | | subsection (d-5). |
| 9 | | (ii) Within 30 days after the utility submits |
| 10 | | its report indicates that it will terminate future |
| 11 | | energy investments, initiate a proceeding to |
| 12 | | approve the process for terminating future |
| 13 | | expenditures under Section 16-107.6 of the Public |
| 14 | | Utilities Act. The Commission shall, after notice |
| 15 | | and hearing, enter its order approving such |
| 16 | | process no later than 120 days after initiating |
| 17 | | such proceeding. |
| 18 | | (iii) Within 30 days after the utility submits |
| 19 | | its report indicates that it will terminate future |
| 20 | | energy investments, initiate a proceeding under |
| 21 | | Section 8-103B of this Act to reduce the cumulative |
| 22 | | persisting annual savings goals previously |
| 23 | | approved by the Commission under such Section to |
| 24 | | ensure just and reasonable rates. The Commission |
| 25 | | shall, after notice and hearing, enter its order |
| 26 | | approving such goal reductions no later than 120 |
|
| | 09900SB2814ham004 | - 36 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | days after initiating such proceeding. |
| 2 | | Notwithstanding the termination of future energy |
| 3 | | investments pursuant to this subparagraph (B), the |
| 4 | | utility shall be permitted to continue to recover the |
| 5 | | costs of such investments that were incurred prior to |
| 6 | | such termination, including but not limited to all |
| 7 | | costs that are recovered through regulatory assets |
| 8 | | created under Sections 8-103B and 16-107.6 of this Act. |
| 9 | | Nothing in this Section shall limit the utility's |
| 10 | | ability to fully recover such costs. The utility shall |
| 11 | | also be permitted to continue to recover the costs of |
| 12 | | all payments made under contracts executed under |
| 13 | | subsection (d-5) until the effective date of the |
| 14 | | contract's termination. |
| 15 | | (220 ILCS 5/16-108.16 new) |
| 16 | | Sec. 16-108.16. Commercial Rate Impacts. |
| 17 | | (a) Each electric utility that serves more than 500,000 |
| 18 | | retail customers in the State shall file with the Commission |
| 19 | | the reports required by this Section, which shall identify the |
| 20 | | annual average increases due to future energy investment costs |
| 21 | | for the applicable period or periods in electric bills to |
| 22 | | commercial and industrial retail customers. For purposes of |
| 23 | | this Section, "commercial and industrial retail customers" |
| 24 | | means non-residential retail customers other than those |
| 25 | | customers who are exempt from subsections (a) through (j) of |
|
| | 09900SB2814ham004 | - 37 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | Section 8-103B of this Act under subsection (l) of Section |
| 2 | | 8-103B. |
| 3 | | (b) The increase determination required by subsection (a) |
| 4 | | of this Section shall be based on a calculation comprised of |
| 5 | | the following components: |
| 6 | | (1 )Beginning with the 2017 calendar year, the average |
| 7 | | annual amount paid by commercial and industrial retail |
| 8 | | customers, expressed on a cents-per-kilowatthour basis, to |
| 9 | | recover future energy investment costs, which include the |
| 10 | | charges to recover the costs incurred by the utility under |
| 11 | | the following provisions: |
| 12 | | (A) Sections 8-103, Section 8-103B, and 16-111.5B |
| 13 | | of this Act, as applicable, and as such costs may be |
| 14 | | recovered under Sections 8-103, 8-103B, 16-111.5B or |
| 15 | | Section 16-108.5 of this Act; |
| 16 | | (B) subsection (d-5) of Section 1-75 of the |
| 17 | | Illinois Power Agency Act, as such costs may be |
| 18 | | recovered under subsection (k) of Section 16-108 of |
| 19 | | this Act; and |
| 20 | | (C) Section 16-107.6 of this Act. |
| 21 | | Beginning with the 2018 calendar year, each of the |
| 22 | | average annual charges calculated in subparagraphs (A) |
| 23 | | through (C) of this paragraph (1) shall be equal to the |
| 24 | | average of each such charge applied over a period that |
| 25 | | commences with the calendar year ending December 31, 2017 |
| 26 | | and ends with the most recently completed calendar year |
|
| | 09900SB2814ham004 | - 38 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | prior to the calculation or calculations required by this |
| 2 | | Section. |
| 3 | | (2) The sum of the following: |
| 4 | | (A) annual net energy savings to commercial and |
| 5 | | industrial retail customers that are attributable to |
| 6 | | the implementation of voltage optimization measures |
| 7 | | under Section 8-103B of this Act, expressed on a |
| 8 | | cents-per-kilowatthour basis, which are estimated |
| 9 | | energy and capacity benefits for commercial and |
| 10 | | industrial retail customers minus the measure costs |
| 11 | | recovered from those customers, divided by the average |
| 12 | | annual kilowatt-hour consumption of commercial and |
| 13 | | industrial retail customers; notwithstanding this |
| 14 | | subparagraph (A), a utility may elect not to include an |
| 15 | | estimate of net energy savings as described in this |
| 16 | | subparagraph (A), in which case the value under this |
| 17 | | subparagraph (A) shall be zero; |
| 18 | | (B) the average annual cents-per-kilowatthour |
| 19 | | charge applied under Section 8-103 of this Act to |
| 20 | | commercial and industrial retail customers during |
| 21 | | calendar year 2016 to recover the costs authorized by |
| 22 | | such Section; and |
| 23 | | (C) incremental energy efficiency savings, which |
| 24 | | shall be calculated by subtracting the value |
| 25 | | determined in item (ii) of this subparagraph (C) from |
| 26 | | the value determined in item (i) of this subparagraph |
|
| | 09900SB2814ham004 | - 39 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | and dividing the difference by the value identified in |
| 2 | | item (iii) of this subparagraph: |
| 3 | | (i) Total value, in dollars, of the cumulative |
| 4 | | persisting annual saving achieved from the |
| 5 | | installation or implementation of all energy |
| 6 | | efficiency measures for commercial and industrial |
| 7 | | retail customers under Sections 8-103, 8-103B and |
| 8 | | 16-111.5 of this Act, net of the cumulative annual |
| 9 | | percentage savings in kilowatt-hours, if any, |
| 10 | | calculated under subparagraph (A) of this |
| 11 | | paragraph (2). |
| 12 | | (ii) 2016 value, which shall equal the value |
| 13 | | calculated under item (i) of this subparagraph (C) |
| 14 | | multiplied by the quotient of (aa) the cumulative |
| 15 | | persisting annual savings, in kilowatt-hours, |
| 16 | | achieved from the installation or implementation |
| 17 | | of all energy efficiency measures for commercial |
| 18 | | and industrial retail customers under Sections |
| 19 | | 8-103, 8-103B and 16-111.5B of this Act as of |
| 20 | | December 31, 2016, divided by (bb) the cumulative |
| 21 | | persisting annual savings, in kilowatt-hours, from |
| 22 | | the installation or implementation of all energy |
| 23 | | efficiency measures for commercial and industrial |
| 24 | | retail customers under Sections 8-103, 8-103B and |
| 25 | | 16-111.5 of this Act, net of the cumulative annual |
| 26 | | percentage savings in kilowatt-hours, if any, |
|
| | 09900SB2814ham004 | - 40 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | calculated under subparagraph (A) of this |
| 2 | | paragraph (2). |
| 3 | | (iii) The average annual kilowatt-hour |
| 4 | | consumption of those commercial and industrial |
| 5 | | retail customers that installed or implemented |
| 6 | | energy efficiency measures under energy efficiency |
| 7 | | programs or plans approved pursuant to Sections |
| 8 | | 8-103, 8-103B or 16-111.5B of this Act. |
| 9 | | Beginning with the 2018 calendar year, each of the |
| 10 | | values identified in subparagraphs (A) and (C) of this |
| 11 | | paragraph (2) shall be equal to the average of each |
| 12 | | such value during a period that commences with the |
| 13 | | calendar year ending December 31, 2017 and ends with |
| 14 | | the most recently completed calendar year prior to the |
| 15 | | calculation or calculations required by this Section. |
| 16 | | For purposes of this Section, cumulative |
| 17 | | persisting annual savings shall have the meaning set |
| 18 | | forth in Section 8-103B of this Act, and energy |
| 19 | | efficiency measures shall have the meaning set forth in |
| 20 | | Section 1-10 of the Illinois Power Agency Act. |
| 21 | | (c)(1) No later than June 30, 2017, and every June 30 |
| 22 | | thereafter until June 30, 2027, an electric utility subject |
| 23 | | to this Section shall submit a report to the Commission |
| 24 | | that sets forth the utility's 10-year projection of the |
| 25 | | values of each of the components described in paragraphs |
| 26 | | (1) and (2) of subsection (b) of this Section. Each |
|
| | 09900SB2814ham004 | - 41 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | utility's report to the Commission shall identify the |
| 2 | | result of the computation performed under this Section for |
| 3 | | the immediately preceding calendar year and update its |
| 4 | | 10-year projection. Such calculations shall be performed |
| 5 | | by subtracting the sum of paragraph (2) of subsection (b) |
| 6 | | of this Section from the sum of paragraph (1) of such |
| 7 | | subsection (b). |
| 8 | | In the event that the actual or projected average |
| 9 | | annual increase for commercial and industrial retail |
| 10 | | customers exceeds 1.3% of 8.90 cents-per-kilowatthour, |
| 11 | | which is the average amount paid per kilowatt-hour for |
| 12 | | electric service during the year ending December 31, 2015 |
| 13 | | by Illinois commercial retail customers, as reported to the |
| 14 | | Edison Electric Institute, then the applicable utility |
| 15 | | shall comply with the provisions of paragraphs (2) through |
| 16 | | (4) of this subsection (c), as applicable. |
| 17 | | (2) In the event that the projected average annual |
| 18 | | increase for commercial and industrial retail customers |
| 19 | | during a calendar year exceeds the applicable limitation |
| 20 | | set forth in paragraph (1) of this subsection (c), then the |
| 21 | | utility shall comply with the following provisions, as |
| 22 | | applicable: |
| 23 | | (A) If an exceedance is projected during the first |
| 24 | | four calendar years of the 10-year projection, then the |
| 25 | | utility shall include in its report submitted under |
| 26 | | paragraph (1) of this subsection (c) the utility's |
|
| | 09900SB2814ham004 | - 42 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | proposal or proposals to decrease the future energy |
| 2 | | investment costs described in paragraph (1) of |
| 3 | | subsection (b) of this Section to ensure that the |
| 4 | | limitation set forth in such paragraph (1) is not |
| 5 | | exceeded. The Commission shall, after notice and |
| 6 | | hearing, enter an order directing the utility to |
| 7 | | implement one or more proposals, as such proposals may |
| 8 | | be modified by the Commission. The Commission shall |
| 9 | | have the authority under this subparagraph (A) to |
| 10 | | approve modifications to the contracts executed under |
| 11 | | subsection (d-5) of Section 1-75 of the Illinois Power |
| 12 | | Agency Act. If the Commission approves modifications |
| 13 | | to such contracts that are in an amount that reduces |
| 14 | | the quantities to be procured under such contracts by |
| 15 | | more than 7%, then the supplier shall have the option |
| 16 | | of accepting the modifications or terminating the |
| 17 | | modified contract or contracts, subject to the |
| 18 | | termination requirements and notice provisions set |
| 19 | | forth in item (i) of subparagraph (B) of paragraph (4) |
| 20 | | of this Section. |
| 21 | | (B) If an exceedance is projected during any |
| 22 | | calendar year during the last 6 years of the 10-year |
| 23 | | projection, then the utility shall demonstrate in its |
| 24 | | report submitted under paragraph (1) of this |
| 25 | | subsection (c) how the utility will reduce the future |
| 26 | | energy investment costs described in paragraph (1) of |
|
| | 09900SB2814ham004 | - 43 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | subsection (b) of this Section to ensure that the |
| 2 | | limitation set forth in such paragraph (1) is not |
| 3 | | exceeded. |
| 4 | | (3) If the actual average annual increase for |
| 5 | | commercial and industrial retail customers during a |
| 6 | | calendar year exceeded the limitation set forth in |
| 7 | | paragraph (1) of this subsection (c), then the utility |
| 8 | | shall prepare and file with the Commission, at the time it |
| 9 | | submits its report under paragraph (1) of this subsection |
| 10 | | (c), a corrective action plan. The Commission shall |
| 11 | | initiate an investigation to determine the factors that |
| 12 | | contributed to the actual average annual increase |
| 13 | | exceeding such limitation for the applicable calendar |
| 14 | | year, and shall, after notice and hearing, enter an order |
| 15 | | approving, or approving with modification, the utility's |
| 16 | | corrective action plan within 120 days after the utility |
| 17 | | files such plan. The Commission shall also submit a report |
| 18 | | to the General Assembly no later than 30 days after it |
| 19 | | enters such order, and the report shall explain the results |
| 20 | | of the Commission's investigation and findings and |
| 21 | | conclusions of its order. |
| 22 | | (4) If the actual average annual increase for |
| 23 | | commercial and industrial retail customers during a |
| 24 | | calendar year exceeds the limitation set forth in paragraph |
| 25 | | (1) of this subsection (c) for two consecutive years, then |
| 26 | | the utility shall indicate in its report filed under |
|
| | 09900SB2814ham004 | - 44 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | paragraph (1) of this subsection (c) whether the utility |
| 2 | | will proceed with or terminate the future energy |
| 3 | | investments described and authorized under subsection |
| 4 | | (d-5) of the Illinois Power Agency Act and Sections 8-103B |
| 5 | | and 16-107.6 of this Act. The utility's election shall be |
| 6 | | subject to the requirements of subparagraph (A) or (B) of |
| 7 | | this paragraph (4), as applicable. |
| 8 | | (A) If the utility elects to proceed with the |
| 9 | | future energy investments, then it shall be subject to |
| 10 | | the corrective action plan requirements set forth in |
| 11 | | paragraph (3) of this subsection (c). In addition, the |
| 12 | | utility must commit to apply a credit to commercial and |
| 13 | | industrial retail customers' bills if the actual |
| 14 | | average annual increase for such customers exceeds the |
| 15 | | limitation set forth in paragraph (1) of this |
| 16 | | subsection (c) for the year in which the utility files |
| 17 | | its corrective action plan, which credit shall be in an |
| 18 | | amount that equals the portion by which the increase |
| 19 | | exceeds such limitation. The Commission shall initiate |
| 20 | | an investigation to determine the factors that |
| 21 | | contributed to the actual average annual increase |
| 22 | | exceeding such limitation for the applicable calendar |
| 23 | | year, including an analysis of the factors |
| 24 | | contributing to the limitation being exceeded for two |
| 25 | | consecutive years, and shall, after notice and |
| 26 | | hearing, enter an order approving, or approving with |
|
| | 09900SB2814ham004 | - 45 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | modification, the utility's corrective action plan |
| 2 | | within 120 days after the utility files such plan. The |
| 3 | | Commission shall also submit a supplemental report to |
| 4 | | the General Assembly no later than 30 days after it |
| 5 | | enters such order, and the report shall explain the |
| 6 | | results of the Commission's investigation and findings |
| 7 | | and conclusions of its order. |
| 8 | | (B) If the utility elects to terminate future |
| 9 | | energy investments, then the Commission shall, |
| 10 | | notwithstanding anything to the contrary: |
| 11 | | (i) Order the utility to terminate the |
| 12 | | contract or contracts executed under subsection |
| 13 | | (d-5) of Section 1-75 of the Illinois Power Agency |
| 14 | | Act, pursuant to the contract termination |
| 15 | | provisions set forth in such subsection (d-5), |
| 16 | | provided that notice of such termination must be |
| 17 | | made at least 3 years and 75 days prior to the |
| 18 | | effective date of such termination. In the event |
| 19 | | that only a portion of the contracts executed under |
| 20 | | such subsection (d-5) are terminated for a |
| 21 | | particular zero emission facility, then the zero |
| 22 | | emission facility may elect to terminate all of the |
| 23 | | contracts executed for that facility under such |
| 24 | | subsection (d-5). |
| 25 | | (ii) Within 30 days of the utility's report |
| 26 | | identifying its election to terminate future |
|
| | 09900SB2814ham004 | - 46 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | energy investments, initiate a proceeding to |
| 2 | | approve the process for terminating future |
| 3 | | expenditures under Sections 16-107.6 of the Public |
| 4 | | Utilities Act. The Commission shall, after notice |
| 5 | | and hearing, enter its order approving such |
| 6 | | process no later than 120 days after initiating |
| 7 | | such proceeding. |
| 8 | | (iii) Within 30 days of the utility's report |
| 9 | | identifying its election to terminate future |
| 10 | | energy investments, initiate a proceeding under |
| 11 | | Section 8-103B of this Act to reduce the cumulative |
| 12 | | persisting annual savings goals previously |
| 13 | | approved by the Commission under such Section to |
| 14 | | ensure just and reasonable rates. The Commission |
| 15 | | shall, after notice and hearing, enter its order |
| 16 | | approving such goal reductions no later than 120 |
| 17 | | days after initiating such proceeding. |
| 18 | | Notwithstanding the termination of future energy |
| 19 | | investments pursuant to this subparagraph (B), the |
| 20 | | utility shall be permitted to continue to recover the |
| 21 | | costs of such investments that were incurred prior to |
| 22 | | such termination, including but not limited to all |
| 23 | | costs that are recovered through regulatory assets |
| 24 | | created under Sections 8-103B and 16-107.6 of this Act. |
| 25 | | Nothing in this Section shall limit the utility's |
| 26 | | ability to fully recover such costs. The utility shall |
|
| | 09900SB2814ham004 | - 47 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | also be permitted to continue to recover the costs of |
| 2 | | all payments made under contracts executed under |
| 3 | | subsection (d-5) until the effective date of the |
| 4 | | contract's termination. |
| 5 | | (5) Notwithstanding anything to the contrary, if, |
| 6 | | under this Section or subsection (m) of Section 16-108 of |
| 7 | | this Act, modifications to the contracts executed under |
| 8 | | subsection (d-5) of Section 1-75 of the Illinois Power |
| 9 | | Agency Act are, in total, in an amount that reduces the |
| 10 | | quantities to procured under such contracts by more than |
| 11 | | 10%, then the supplier shall have the option of accepting |
| 12 | | the modifications or terminating the modified contract or |
| 13 | | contracts, subject to the termination requirements and |
| 14 | | notice provisions set forth in item (i) of subparagraph (B) |
| 15 | | of paragraph (4) of this Section."; and |
| 16 | | on page 389, line 10, by replacing "one" with "2 one"; and |
| 17 | | on page 428, line 19, by replacing the period with "and, for an |
| 18 | | electric utility that serves less than 100,000 retail customers |
| 19 | | in the State, other than the procurement of renewable energy |
| 20 | | credits for distributed renewable energy generation devices."; |
| 21 | | and |
| 22 | | on page 467, immediately below line 3, by inserting the |
| 23 | | following: |
|
| | 09900SB2814ham004 | - 48 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | "(220 ILCS 5/16-128A) |
| 2 | | Sec. 16-128A. Certification of installers, maintainers, or |
| 3 | | repairers. |
| 4 | | (a) Within 18 months of the effective date of this |
| 5 | | amendatory Act of the 97th General Assembly, the Commission |
| 6 | | shall adopt rules, including emergency rules, establishing |
| 7 | | certification requirements ensuring that entities installing |
| 8 | | distributed generation facilities are in compliance with the |
| 9 | | requirements of subsection (a) of Section 16-128 of this Act. |
| 10 | | For purposes of this Section, the phrase "entities |
| 11 | | installing distributed generation facilities" shall include, |
| 12 | | but not be limited to, all entities that are exempt from the |
| 13 | | definition of "alternative retail electric supplier" under |
| 14 | | item (v) of Section 16-102 of this Act.
For purposes of this |
| 15 | | Section, the phrase "self-installer" means an individual who |
| 16 | | (i) leases or purchases a cogeneration facility for his or her |
| 17 | | own personal use and (ii) installs such cogeneration or |
| 18 | | self-generation facility on his or her own premises without the |
| 19 | | assistance of any other person. |
| 20 | | (b) In addition to any authority granted to the Commission |
| 21 | | under this Act, the Commission is also authorized to: (1) |
| 22 | | determine which entities are subject to certification under |
| 23 | | this Section; (2) impose reasonable certification fees and |
| 24 | | penalties; (3) adopt disciplinary procedures; (4) investigate |
| 25 | | any and all activities subject to this Section, including |
|
| | 09900SB2814ham004 | - 49 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | violations thereof; (5) adopt procedures to issue or renew, or |
| 2 | | to refuse to issue or renew, a certification or to revoke, |
| 3 | | suspend, place on probation, reprimand, or otherwise |
| 4 | | discipline a certified entity under this Act or take other |
| 5 | | enforcement action against an entity subject to this Section; |
| 6 | | and (6) prescribe forms to be issued for the administration and |
| 7 | | enforcement of this Section. |
| 8 | | (c) No electric utility shall provide a retail customer |
| 9 | | with net metering service related to interconnection of that |
| 10 | | customer's distributed generation facility unless the customer |
| 11 | | provides the electric utility with (i) a certification that the |
| 12 | | customer installing the distributed generation facility was a |
| 13 | | self-installer or (ii) evidence that the distributed |
| 14 | | generation facility was installed by an entity certified under |
| 15 | | this Section that is also in good standing with the Commission. |
| 16 | | For purposes of this subsection, a retail customer includes |
| 17 | | that customer's employees, officers, and agents. An electric |
| 18 | | utility shall file a tariff or tariffs with the Commission |
| 19 | | setting forth the documentation, as specified by Commission |
| 20 | | rule, that a retail customer must provide to an electric |
| 21 | | utility. The provisions of this subsection (c) shall apply on |
| 22 | | or after the effective date of the Commission's rules |
| 23 | | prescribed pursuant to subsection (a) of this Section. |
| 24 | | (d) Within 180 days after the effective date of this |
| 25 | | amendatory Act of the 97th General Assembly, the Commission |
| 26 | | shall initiate a rulemaking proceeding to establish |
|
| | 09900SB2814ham004 | - 50 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | certification requirements that shall be applicable to persons |
| 2 | | or entities that install, maintain, or repair electric vehicle |
| 3 | | charging stations. The notification and certification |
| 4 | | requirements of this Section shall only be applicable to |
| 5 | | individuals or entities that perform work on or within an |
| 6 | | electric vehicle charging station, including, but not limited |
| 7 | | to, connection of power to an electric vehicle charging |
| 8 | | station. |
| 9 | | For the purposes of this Section "electric vehicle charging |
| 10 | | station" means any facility or equipment that is used to charge |
| 11 | | a battery or other energy storage device of an electric |
| 12 | | vehicle.
|
| 13 | | Rules regulating the installation, maintenance, or repair |
| 14 | | of electric vehicle charging stations, in which the Commission |
| 15 | | may establish separate requirements based upon the |
| 16 | | characteristics of electric vehicle charging stations, so long |
| 17 | | as it is in accordance with the requirements of subsection (a) |
| 18 | | of Section 16-128 and Section 16-128A of this Act, shall: |
| 19 | | (1) establish a certification process for persons or |
| 20 | | entities that install, maintain, or repair of electric |
| 21 | | vehicle charging stations; |
| 22 | | (2) require persons or entities that install, |
| 23 | | maintain, or repair electric vehicle stations to be |
| 24 | | certified to do business and to be bonded in the State; |
| 25 | | (3) ensure that persons or entities that install, |
| 26 | | maintain, or repair electric vehicle charging stations |
|
| | 09900SB2814ham004 | - 51 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | have the requisite knowledge, skills, training, |
| 2 | | experience, and competence to perform functions in a safe |
| 3 | | and reliable manner as required under subsection (a) of |
| 4 | | Section 16-128 of this Act; |
| 5 | | (4) impose reasonable certification fees and penalties |
| 6 | | on persons or entities that install, maintain, or repair of |
| 7 | | electric vehicle charging stations for noncompliance of |
| 8 | | the rules adopted under this subsection; |
| 9 | | (5) ensure that all persons or entities that install, |
| 10 | | maintain, or repair electric vehicle charging stations |
| 11 | | conform to applicable building and electrical codes; |
| 12 | | (6) ensure that all electric vehicle charging stations |
| 13 | | meet recognized industry standards as the Commission deems |
| 14 | | appropriate, such as the National Electric Code (NEC) and |
| 15 | | standards developed or created by the Institute of |
| 16 | | Electrical and Electronics Engineers (IEEE), the Electric |
| 17 | | Power Research Institute (EPRI), the Detroit Edison |
| 18 | | Institute (DTE), the Underwriters Laboratory (UL), the |
| 19 | | Society of Automotive Engineers (SAE), and the National |
| 20 | | Institute of Standards and Technology (NIST); |
| 21 | | (7) include any additional requirements that the |
| 22 | | Commission deems reasonable to ensure that persons or |
| 23 | | entities that install, maintain, or repair electric |
| 24 | | vehicle charging stations meet adequate training, |
| 25 | | financial, and competency requirements; |
| 26 | | (8) ensure that the obligations required under this |
|
| | 09900SB2814ham004 | - 52 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | Section and subsection (a) of Section 16-128 of this Act |
| 2 | | are met prior to the interconnection of any electric |
| 3 | | vehicle charging station; |
| 4 | | (9) ensure electric vehicle charging stations |
| 5 | | installed by a self-installer are not used for any |
| 6 | | commercial purpose; |
| 7 | | (10) establish an inspection procedure for the |
| 8 | | conversion of electric vehicle charging stations installed |
| 9 | | by a self-installer if it is determined that the |
| 10 | | self-installed electric vehicle charging station is being |
| 11 | | used for commercial purposes; |
| 12 | | (11) establish the requirement that all persons or |
| 13 | | entities that install electric vehicle charging stations |
| 14 | | shall notify the servicing electric utility in writing of |
| 15 | | plans to install an electric vehicle charging station and |
| 16 | | shall notify the servicing electric utility in writing when |
| 17 | | installation is complete; |
| 18 | | (12) ensure that all persons or entities that install, |
| 19 | | maintain, or repair electric vehicle charging stations |
| 20 | | obtain certificates of insurance in sufficient amounts and |
| 21 | | coverages that the Commission so determines and, if |
| 22 | | necessary as determined by the Commission, names the |
| 23 | | affected public utility as an additional insured; and |
| 24 | | (13) identify and determine the training or other |
| 25 | | programs by which persons or entities may obtain the |
| 26 | | requisite training, skills, or experience necessary to |
|
| | 09900SB2814ham004 | - 53 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | achieve and maintain compliance with the requirements set |
| 2 | | forth in this subsection and subsection (a) of Section |
| 3 | | 16-128 to install, maintain, or repair electric vehicle |
| 4 | | charging stations. |
| 5 | | Within 18 months after the effective date of this |
| 6 | | amendatory Act of the 97th General Assembly, the Commission |
| 7 | | shall adopt rules, and may, if it deems necessary, adopt |
| 8 | | emergency rules, for the installation, maintenance, or repair |
| 9 | | of electric vehicle charging stations. |
| 10 | | All retail customers who own, maintain, or repair an |
| 11 | | electric vehicle charging station shall provide the servicing |
| 12 | | electric utility (i) a certification that the customer |
| 13 | | installing the electric vehicle charging station was a |
| 14 | | self-installer or (ii) evidence that the electric vehicle |
| 15 | | charging station was installed by an entity certified under |
| 16 | | this subsection (d) that is also in good standing with the |
| 17 | | Commission. For purposes of this subsection (d), a retail |
| 18 | | customer includes that retail customer's employees, officers, |
| 19 | | and agents. If the electric vehicle charging station was not |
| 20 | | installed by a self-installer, then the person or entity that |
| 21 | | plans to install the electric vehicle charging station shall |
| 22 | | provide notice to the servicing electric utility prior to |
| 23 | | installation and when installation is complete and provide any |
| 24 | | other information required by the Commission's rules |
| 25 | | established under subsection (d) of this Section. An electric |
| 26 | | utility shall file a tariff or tariffs with the Commission |
|
| | 09900SB2814ham004 | - 54 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | setting forth the documentation, as specified by Commission |
| 2 | | rule, that a retail customer who owns, uses, operates, or |
| 3 | | maintains an electric vehicle charging station must provide to |
| 4 | | an electric utility. |
| 5 | | For the purposes of this subsection, an electric vehicle |
| 6 | | charging station shall constitute a distribution facility or |
| 7 | | equipment as that term is used in subsection (a) of Section |
| 8 | | 16-128 of this Act. The phrase "self-installer" means an |
| 9 | | individual who (i) leases or purchases an electric vehicle |
| 10 | | charging station for his or her own personal use and (ii) |
| 11 | | installs an electric vehicle charging station on his or her own |
| 12 | | premises without the assistance of any other person. |
| 13 | | (e) Fees and penalties collected under this Section shall |
| 14 | | be deposited into the Public Utility Fund and used to fund the |
| 15 | | Commission's compliance with the obligations imposed by this |
| 16 | | Section. |
| 17 | | (f) The rules established under subsection (d) of this |
| 18 | | Section shall specify the initial dates for compliance with the |
| 19 | | rules. |
| 20 | | (g) Within 18 months of the effective date of this |
| 21 | | amendatory Act of the 99th General Assembly, the Commission |
| 22 | | shall adopt rules, including emergency rules, establishing a |
| 23 | | process for entities installing a new utility-scale wind |
| 24 | | project or a new utility-scale solar project to certify |
| 25 | | compliance with the requirements of this Section. For purposes |
| 26 | | of this Section, the phrase "entities installing a new |
|
| | 09900SB2814ham004 | - 55 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | utility-scale wind project or a new utility-scale solar |
| 2 | | project" shall include, but is not limited to, any entity |
| 3 | | installing new wind projects or new photovoltaic projects as |
| 4 | | such terms are defined in subsection (c) of Section 1-75 of the |
| 5 | | Illinois Power Agency Act. |
| 6 | | The process shall include an option to complete the |
| 7 | | certification electronically by completing forms on-line. An |
| 8 | | entity installing a new utility-scale wind project or a new |
| 9 | | utility-scale solar project shall be permitted to complete |
| 10 | | certification after the subject work has been completed. The |
| 11 | | Commission shall maintain on its website a list of entities |
| 12 | | installing new utility-scale wind projects or new |
| 13 | | utility-scale solar projects measures that have successfully |
| 14 | | completed the certification process. |
| 15 | | (h) In addition to any authority granted to the Commission |
| 16 | | under this Act, the Commission is also authorized to: (1) |
| 17 | | determine which entities are subject to certification under |
| 18 | | subsection (g) of this Section; (2) impose reasonable |
| 19 | | certification fees and penalties; (3) adopt disciplinary |
| 20 | | procedures; (4) investigate any and all activities subject to |
| 21 | | subsection (g) or this subsection (h) of this Section, |
| 22 | | including violations thereof; (5) adopt procedures to issue or |
| 23 | | renew, or to refuse to issue or renew, a certification or to |
| 24 | | revoke, suspend, place on probation, reprimand, or otherwise |
| 25 | | discipline a certified entity under subsection (g) of this |
| 26 | | Section or take other enforcement action against an entity |
|
| | 09900SB2814ham004 | - 56 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | subject to subsection (g) or this subsection (h) of this |
| 2 | | Section; (6) prescribe forms to be issued for the |
| 3 | | administration and enforcement of subsection (g) and this |
| 4 | | subsection (h) of this Section; and (7) establish requirements |
| 5 | | to ensure that entities installing a new wind project or a new |
| 6 | | photovoltaic project have the requisite knowledge, skills, |
| 7 | | training, experience, and competence to perform in a safe and |
| 8 | | reliable manner as required by subsection (a) of Section 16-128 |
| 9 | | of this Act. |
| 10 | | The certification of persons or entities that install, |
| 11 | | maintain, or repair new wind projects, new photovoltaic |
| 12 | | projects, distributed generation facilities, and electric |
| 13 | | vehicle charging stations as set forth in this Section is an |
| 14 | | exclusive power and function of the State. A home rule unit or |
| 15 | | other units of local government authority may subject persons |
| 16 | | or entities that install, maintain, or repair new wind |
| 17 | | projects, new photovoltaic projects, distributed generation |
| 18 | | facilities, or electric vehicle charging stations as set forth |
| 19 | | in this Section to any applicable local licensing, siting, and |
| 20 | | permitting requirements otherwise permitted under law so long |
| 21 | | as only Commission-certified persons or entities are |
| 22 | | authorized to install, maintain, or repair new wind projects, |
| 23 | | new photovoltaic projects, distributed generation facilities, |
| 24 | | or electric vehicle charging stations. This Section is a |
| 25 | | limitation under subsection (h) of Section 6 of Article VII of |
| 26 | | the Illinois Constitution on the exercise by home rule units of |
|
| | 09900SB2814ham004 | - 57 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | powers and functions exclusively exercised by the State. |
| 2 | | (Source: P.A. 97-616, eff. 10-26-11; 97-1128, eff. 8-28-12.) |
| 3 | | (220 ILCS 5/16-128B new) |
| 4 | | Sec. 16-128B. Qualified energy efficiency installers. |
| 5 | | (a) Within 18 months after the effective date of this |
| 6 | | amendatory Act of the 99th General Assembly, the Commission |
| 7 | | shall adopt rules, including emergency rules, establishing a |
| 8 | | process for entities installing energy efficiency measures to |
| 9 | | certify compliance with the requirements of this Section. |
| 10 | | The process shall include an option to complete the |
| 11 | | certification electronically by completing forms on-line. An |
| 12 | | entity installing energy efficiency measures shall be |
| 13 | | permitted to complete the certification after the subject work |
| 14 | | has been completed. |
| 15 | | The Commission shall maintain on its website a list of |
| 16 | | entities installing energy efficiency measures that have |
| 17 | | successfully completed the certification process. |
| 18 | | (b) In addition to any authority granted to the Commission |
| 19 | | under this Act, the Commission may: |
| 20 | | (1) determine which entities are subject to |
| 21 | | certification under this Section; |
| 22 | | (2) impose reasonable certification fees and |
| 23 | | penalties; |
| 24 | | (3) adopt disciplinary procedures; |
| 25 | | (4) investigate any and all activities subject to this |
|
| | 09900SB2814ham004 | - 58 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | Section, including violations thereof; |
| 2 | | (5) adopt procedures to issue or renew, or to refuse to |
| 3 | | issue or renew, a certification or to revoke, suspend, |
| 4 | | place on probation, reprimand, or otherwise discipline a |
| 5 | | certified entity under this Act or take other enforcement |
| 6 | | action against an entity subject to this Section; and |
| 7 | | (6) prescribe forms to be issued for the administration |
| 8 | | and enforcement of this Section. |
| 9 | | (c) An electric utility may not provide a retail customer |
| 10 | | with a rebate or other energy efficiency incentive for a |
| 11 | | measure that exceeds a minimal amount determined by the |
| 12 | | Commission unless the customer provides the electric utility |
| 13 | | with (1) a certification that the person installing the energy |
| 14 | | efficiency measure was a self-installer; or (2) evidence that |
| 15 | | the energy efficiency measure was installed by an entity |
| 16 | | certified under this Section that is also in good standing with |
| 17 | | the Commission. |
| 18 | | (d) The Commission shall: |
| 19 | | (1) require entities installing energy efficiency |
| 20 | | measures to be certified to do business and to be bonded in |
| 21 | | this State; |
| 22 | | (2) ensure that entities installing energy efficiency |
| 23 | | measures have the requisite knowledge, skill, training, |
| 24 | | experience, and competence to perform functions in a safe |
| 25 | | and reliable manner as required under subsection (a) of |
| 26 | | Section 16-128 of this Act; |
|
| | 09900SB2814ham004 | - 59 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | (3) ensure that entities installing energy efficiency |
| 2 | | measures conform to applicable building and electrical |
| 3 | | codes; |
| 4 | | (4) ensure that all entities installing energy |
| 5 | | efficiency measures meet recognized industry standards as |
| 6 | | the Commission deems appropriate; |
| 7 | | (5) include any additional requirements that the |
| 8 | | Commission deems reasonable to ensure that entities |
| 9 | | installing energy efficiency measures meet adequate |
| 10 | | training, financial, and competency requirements; |
| 11 | | (6) ensure that all entities installing energy |
| 12 | | efficiency measures obtain certificates of insurance in |
| 13 | | sufficient amounts and coverages that the Commission so |
| 14 | | determines; and |
| 15 | | (7) identify and determine the training or other |
| 16 | | programs by which persons or entities may obtain the |
| 17 | | requisite training, skill, or experience necessary to |
| 18 | | achieve and maintain compliance with the requirements of |
| 19 | | this Section. |
| 20 | | (e) Fees and penalties collected under this Section shall |
| 21 | | be deposited into the Public Utility Fund and used to fund the |
| 22 | | Commission's compliance with the obligations imposed by this |
| 23 | | Section. |
| 24 | | (f) The rules adopted under this Section shall specify the |
| 25 | | initial dates for compliance with the rules. |
| 26 | | (g) For purposes of this Section, entities installing |
|
| | 09900SB2814ham004 | - 60 - | LRB099 19990 JWD 51891 a |
|
|
| 1 | | energy efficiency measures shall endeavor to support the |
| 2 | | diversity goals of this State by attracting, developing, |
| 3 | | retaining, and providing opportunities to employees of all |
| 4 | | backgrounds and by supporting female-owned, minority-owned, |
| 5 | | veteran-owned, and small businesses.".
|