Rep. Eva Dina Delgado

Filed: 3/16/2021

 

 


 

 


 
10200HB1747ham001LRB102 12090 SPS 23532 a

1
AMENDMENT TO HOUSE BILL 1747

2    AMENDMENT NO. ______. Amend House Bill 1747 by replacing
3everything after the enacting clause with the following:
 
4    "Section 5. The Illinois Power Agency Act is amended by
5changing Sections 1-5, 1-10, and 1-75 as follows:
 
6    (20 ILCS 3855/1-5)
7    Sec. 1-5. Legislative declarations and findings. The
8General Assembly finds and declares:
9        (1) The health, welfare, and prosperity of all
10    Illinois citizens require the provision of adequate,
11    reliable, affordable, efficient, and environmentally
12    sustainable electric service at the lowest total cost over
13    time, taking into account any benefits of price stability.
14        (2) (Blank).
15        (3) (Blank).
16        (4) It is necessary to improve the process of

 

 

10200HB1747ham001- 2 -LRB102 12090 SPS 23532 a

1    procuring electricity to serve Illinois residents, to
2    promote investment in energy efficiency and
3    demand-response measures, and to maintain and support
4    development of clean coal technologies, generation
5    resources that operate at all hours of the day and under
6    all weather conditions, zero emission facilities, and
7    renewable resources.
8        (5) Procuring a diverse electricity supply portfolio
9    will ensure the lowest total cost over time for adequate,
10    reliable, efficient, and environmentally sustainable
11    electric service.
12        (6) Including renewable resources and zero emission
13    credits from zero emission facilities in that portfolio
14    will reduce long-term direct and indirect costs to
15    consumers by decreasing environmental impacts and by
16    avoiding or delaying the need for new generation,
17    transmission, and distribution infrastructure. Developing
18    new renewable energy resources in Illinois, including
19    brownfield solar projects and community solar projects,
20    will help to diversify Illinois electricity supply, avoid
21    and reduce pollution, reduce peak demand, and enhance
22    public health and well-being of Illinois residents.
23        (7) Developing community solar projects in Illinois
24    will help to expand access to renewable energy resources
25    to more Illinois residents.
26        (8) Developing brownfield solar projects in Illinois

 

 

10200HB1747ham001- 3 -LRB102 12090 SPS 23532 a

1    will help return blighted or contaminated land to
2    productive use while enhancing public health and the
3    well-being of Illinois residents.
4        (9) Energy efficiency, demand-response measures, zero
5    emission energy, and renewable energy are resources
6    currently underused in Illinois. These resources should be
7    used, when cost effective, to reduce costs to consumers,
8    improve reliability, and improve environmental quality and
9    public health.
10        (10) The State should encourage the use of advanced
11    clean coal technologies that capture and sequester carbon
12    dioxide emissions to advance environmental protection
13    goals and to demonstrate the viability of coal and
14    coal-derived fuels in a carbon-constrained economy.
15        (11) The General Assembly enacted Public Act 96-0795
16    to reform the State's purchasing processes, recognizing
17    that government procurement is susceptible to abuse if
18    structural and procedural safeguards are not in place to
19    ensure independence, insulation, oversight, and
20    transparency.
21        (12) The principles that underlie the procurement
22    reform legislation apply also in the context of power
23    purchasing.
24        (13) The Governor of the State of Illinois has
25    committed the State to principles of the Paris Climate
26    Agreement to reduce greenhouse gas emissions. The Illinois

 

 

10200HB1747ham001- 4 -LRB102 12090 SPS 23532 a

1    Renewable Portfolio Standard is a resource to advance the
2    development of renewable energy resources in Illinois that
3    will reduce greenhouse gas emissions and stimulate
4    economic development in the State of Illinois.
5        (14) The Renewable Portfolio Standard, created in
6    2007, sets a goal for investor-owned utilities to procure
7    25% of their consumer load electricity from renewable
8    energy resources by the year 2025 through escalating
9    annual goals.
10        (15) The citizens and businesses of the State of
11    Illinois pay a monthly fee on their electric utility bills
12    to fund the Renewable Portfolio Standard program.
13        (16) The Illinois Power Agency has reported in
14    December 2020 that the annual incremental Renewable
15    Portfolio Standard goals are not being met. The Illinois
16    Power Agency projected the Renewable Portfolio Standard
17    will achieve less than 10% of the State's renewable energy
18    resource goal by the year 2030. The Illinois Power Agency
19    also reports the Renewable Portfolio Standard lacks
20    sufficient funding to implement the program between the
21    years 2021 and 2025, curtailing the development of
22    in-state renewable energy generation and economic
23    activity. Despite the failure to meet the Renewable
24    Portfolio Standard goals, residents and businesses of the
25    State of Illinois continue to pay monthly fees on their
26    electric utility bills to fund the Renewable Portfolio

 

 

10200HB1747ham001- 5 -LRB102 12090 SPS 23532 a

1    Standard program.
2        (17) The General Assembly therefore finds it is
3    necessary to create a voluntary market for the residents
4    and businesses of the State of Illinois to purchase
5    in-state renewable energy and associated renewable energy
6    credits, from businesses that are authorized to supply
7    electricity to Illinois electricity consumers. Residents
8    and businesses that choose to purchase in-state renewable
9    energy are eligible to receive a monthly utility credit
10    equivalent to their monthly renewable portfolio standard
11    program fee. The voluntary in-state Renewable Energy
12    Program does not increase electricity fees, rather it
13    relies on voluntary and market-based agreements between
14    consumers and suppliers of in-state renewable energy. A
15    business that supplies in-state renewable energy must
16    report all renewable energy credits to the Illinois Power
17    Agency to count toward the State's annual goal to achieve
18    25% of the State's electricity from a renewable energy
19    resources by the year 2025.
20        (18) Renewable energy, generated from wind and solar,
21    reduces greenhouse gas emissions, provides electricity,
22    and supports jobs as well as local, regional, national,
23    and global economies. Renewable energy policies to
24    generate more renewable energy generation in the State
25    must include opportunities to directly purchase in-state
26    renewable energy from a business that supplies renewable

 

 

10200HB1747ham001- 6 -LRB102 12090 SPS 23532 a

1    electricity.
2    The General Assembly therefore finds that it is necessary
3to create the Illinois Power Agency and that the goals and
4objectives of that Agency are to accomplish each of the
5following:
6        (A) Develop electricity procurement plans to ensure
7    adequate, reliable, affordable, efficient, and
8    environmentally sustainable electric service at the lowest
9    total cost over time, taking into account any benefits of
10    price stability, for electric utilities that on December
11    31, 2005 provided electric service to at least 100,000
12    customers in Illinois and for small multi-jurisdictional
13    electric utilities that (i) on December 31, 2005 served
14    less than 100,000 customers in Illinois and (ii) request a
15    procurement plan for their Illinois jurisdictional load.
16    The procurement plan shall be updated on an annual basis
17    and shall include renewable energy resources and,
18    beginning with the delivery year commencing June 1, 2017,
19    zero emission credits from zero emission facilities
20    sufficient to achieve the standards specified in this Act.
21        (B) Conduct the competitive procurement processes
22    identified in this Act.
23        (C) Develop electric generation and co-generation
24    facilities that use indigenous coal or renewable
25    resources, or both, financed with bonds issued by the
26    Illinois Finance Authority.

 

 

10200HB1747ham001- 7 -LRB102 12090 SPS 23532 a

1        (D) Supply electricity from the Agency's facilities at
2    cost to one or more of the following: municipal electric
3    systems, governmental aggregators, or rural electric
4    cooperatives in Illinois.
5        (E) Ensure that the process of power procurement is
6    conducted in an ethical and transparent fashion, immune
7    from improper influence.
8        (F) Continue to review its policies and practices to
9    determine how best to meet its mission of providing the
10    lowest cost power to the greatest number of people, at any
11    given point in time, in accordance with applicable law.
12        (G) Operate in a structurally insulated, independent,
13    and transparent fashion so that nothing impedes the
14    Agency's mission to secure power at the best prices the
15    market will bear, provided that the Agency meets all
16    applicable legal requirements.
17        (H) Implement renewable energy procurement and
18    training programs throughout the State to diversify
19    Illinois electricity supply, improve reliability, avoid
20    and reduce pollution, reduce peak demand, and enhance
21    public health and well-being of Illinois residents,
22    including low-income residents.
23(Source: P.A. 99-906, eff. 6-1-17.)
 
24    (20 ILCS 3855/1-10)
25    Sec. 1-10. Definitions.

 

 

10200HB1747ham001- 8 -LRB102 12090 SPS 23532 a

1    "Agency" means the Illinois Power Agency.
2    "Agency loan agreement" means any agreement pursuant to
3which the Illinois Finance Authority agrees to loan the
4proceeds of revenue bonds issued with respect to a project to
5the Agency upon terms providing for loan repayment
6installments at least sufficient to pay when due all principal
7of, interest and premium, if any, on those revenue bonds, and
8providing for maintenance, insurance, and other matters in
9respect of the project.
10    "Alternative retail electric supplier" has the same
11definition as found in Section 16-102 of the Public Utilities
12Act.
13    "Authority" means the Illinois Finance Authority.
14    "Brownfield site photovoltaic project" means photovoltaics
15that are:
16        (1) interconnected to an electric utility as defined
17    in this Section, a municipal utility as defined in this
18    Section, a public utility as defined in Section 3-105 of
19    the Public Utilities Act, or an electric cooperative, as
20    defined in Section 3-119 of the Public Utilities Act; and
21        (2) located at a site that is regulated by any of the
22    following entities under the following programs:
23            (A) the United States Environmental Protection
24        Agency under the federal Comprehensive Environmental
25        Response, Compensation, and Liability Act of 1980, as
26        amended;

 

 

10200HB1747ham001- 9 -LRB102 12090 SPS 23532 a

1            (B) the United States Environmental Protection
2        Agency under the Corrective Action Program of the
3        federal Resource Conservation and Recovery Act, as
4        amended;
5            (C) the Illinois Environmental Protection Agency
6        under the Illinois Site Remediation Program; or
7            (D) the Illinois Environmental Protection Agency
8        under the Illinois Solid Waste Program.
9    "Clean coal facility" means an electric generating
10facility that uses primarily coal as a feedstock and that
11captures and sequesters carbon dioxide emissions at the
12following levels: at least 50% of the total carbon dioxide
13emissions that the facility would otherwise emit if, at the
14time construction commences, the facility is scheduled to
15commence operation before 2016, at least 70% of the total
16carbon dioxide emissions that the facility would otherwise
17emit if, at the time construction commences, the facility is
18scheduled to commence operation during 2016 or 2017, and at
19least 90% of the total carbon dioxide emissions that the
20facility would otherwise emit if, at the time construction
21commences, the facility is scheduled to commence operation
22after 2017. The power block of the clean coal facility shall
23not exceed allowable emission rates for sulfur dioxide,
24nitrogen oxides, carbon monoxide, particulates and mercury for
25a natural gas-fired combined-cycle facility the same size as
26and in the same location as the clean coal facility at the time

 

 

10200HB1747ham001- 10 -LRB102 12090 SPS 23532 a

1the clean coal facility obtains an approved air permit. All
2coal used by a clean coal facility shall have high volatile
3bituminous rank and greater than 1.7 pounds of sulfur per
4million btu content, unless the clean coal facility does not
5use gasification technology and was operating as a
6conventional coal-fired electric generating facility on June
71, 2009 (the effective date of Public Act 95-1027).
8    "Clean coal SNG brownfield facility" means a facility that
9(1) has commenced construction by July 1, 2015 on an urban
10brownfield site in a municipality with at least 1,000,000
11residents; (2) uses a gasification process to produce
12substitute natural gas; (3) uses coal as at least 50% of the
13total feedstock over the term of any sourcing agreement with a
14utility and the remainder of the feedstock may be either
15petroleum coke or coal, with all such coal having a high
16bituminous rank and greater than 1.7 pounds of sulfur per
17million Btu content unless the facility reasonably determines
18that it is necessary to use additional petroleum coke to
19deliver additional consumer savings, in which case the
20facility shall use coal for at least 35% of the total feedstock
21over the term of any sourcing agreement; and (4) captures and
22sequesters at least 85% of the total carbon dioxide emissions
23that the facility would otherwise emit.
24    "Clean coal SNG facility" means a facility that uses a
25gasification process to produce substitute natural gas, that
26sequesters at least 90% of the total carbon dioxide emissions

 

 

10200HB1747ham001- 11 -LRB102 12090 SPS 23532 a

1that the facility would otherwise emit, that uses at least 90%
2coal as a feedstock, with all such coal having a high
3bituminous rank and greater than 1.7 pounds of sulfur per
4million btu content, and that has a valid and effective permit
5to construct emission sources and air pollution control
6equipment and approval with respect to the federal regulations
7for Prevention of Significant Deterioration of Air Quality
8(PSD) for the plant pursuant to the federal Clean Air Act;
9provided, however, a clean coal SNG brownfield facility shall
10not be a clean coal SNG facility.
11    "Commission" means the Illinois Commerce Commission.
12    "Community renewable generation project" means an electric
13generating facility that:
14        (1) is powered by wind, solar thermal energy,
15    photovoltaic cells or panels, biodiesel, crops and
16    untreated and unadulterated organic waste biomass, tree
17    waste, and hydropower that does not involve new
18    construction or significant expansion of hydropower dams;
19        (2) is interconnected at the distribution system level
20    of an electric utility as defined in this Section, a
21    municipal utility as defined in this Section that owns or
22    operates electric distribution facilities, a public
23    utility as defined in Section 3-105 of the Public
24    Utilities Act, or an electric cooperative, as defined in
25    Section 3-119 of the Public Utilities Act;
26        (3) credits the value of electricity generated by the

 

 

10200HB1747ham001- 12 -LRB102 12090 SPS 23532 a

1    facility to the subscribers of the facility; and
2        (4) is limited in nameplate capacity to less than or
3    equal to 2,000 kilowatts.
4    "Costs incurred in connection with the development and
5construction of a facility" means:
6        (1) the cost of acquisition of all real property,
7    fixtures, and improvements in connection therewith and
8    equipment, personal property, and other property, rights,
9    and easements acquired that are deemed necessary for the
10    operation and maintenance of the facility;
11        (2) financing costs with respect to bonds, notes, and
12    other evidences of indebtedness of the Agency;
13        (3) all origination, commitment, utilization,
14    facility, placement, underwriting, syndication, credit
15    enhancement, and rating agency fees;
16        (4) engineering, design, procurement, consulting,
17    legal, accounting, title insurance, survey, appraisal,
18    escrow, trustee, collateral agency, interest rate hedging,
19    interest rate swap, capitalized interest, contingency, as
20    required by lenders, and other financing costs, and other
21    expenses for professional services; and
22        (5) the costs of plans, specifications, site study and
23    investigation, installation, surveys, other Agency costs
24    and estimates of costs, and other expenses necessary or
25    incidental to determining the feasibility of any project,
26    together with such other expenses as may be necessary or

 

 

10200HB1747ham001- 13 -LRB102 12090 SPS 23532 a

1    incidental to the financing, insuring, acquisition, and
2    construction of a specific project and starting up,
3    commissioning, and placing that project in operation.
4    "Delivery services" has the same definition as found in
5Section 16-102 of the Public Utilities Act.
6    "Delivery year" means the consecutive 12-month period
7beginning June 1 of a given year and ending May 31 of the
8following year.
9    "Department" means the Department of Commerce and Economic
10Opportunity.
11    "Director" means the Director of the Illinois Power
12Agency.
13    "Demand-response" means measures that decrease peak
14electricity demand or shift demand from peak to off-peak
15periods.
16    "Distributed renewable energy generation device" means a
17device that is:
18        (1) powered by wind, solar thermal energy,
19    photovoltaic cells or panels, biodiesel, crops and
20    untreated and unadulterated organic waste biomass, tree
21    waste, and hydropower that does not involve new
22    construction or significant expansion of hydropower dams;
23        (2) interconnected at the distribution system level of
24    either an electric utility as defined in this Section, a
25    municipal utility as defined in this Section that owns or
26    operates electric distribution facilities, or a rural

 

 

10200HB1747ham001- 14 -LRB102 12090 SPS 23532 a

1    electric cooperative as defined in Section 3-119 of the
2    Public Utilities Act;
3        (3) located on the customer side of the customer's
4    electric meter and is primarily used to offset that
5    customer's electricity load; and
6        (4) limited in nameplate capacity to less than or
7    equal to 2,000 kilowatts.
8    "Energy efficiency" means measures that reduce the amount
9of electricity or natural gas consumed in order to achieve a
10given end use. "Energy efficiency" includes voltage
11optimization measures that optimize the voltage at points on
12the electric distribution voltage system and thereby reduce
13electricity consumption by electric customers' end use
14devices. "Energy efficiency" also includes measures that
15reduce the total Btus of electricity, natural gas, and other
16fuels needed to meet the end use or uses.
17    "Electric utility" has the same definition as found in
18Section 16-102 of the Public Utilities Act.
19    "Facility" means an electric generating unit or a
20co-generating unit that produces electricity along with
21related equipment necessary to connect the facility to an
22electric transmission or distribution system.
23    "Governmental aggregator" means one or more units of local
24government that individually or collectively procure
25electricity to serve residential retail electrical loads
26located within its or their jurisdiction.

 

 

10200HB1747ham001- 15 -LRB102 12090 SPS 23532 a

1    "Local government" means a unit of local government as
2defined in Section 1 of Article VII of the Illinois
3Constitution.
4    "Municipality" means a city, village, or incorporated
5town.
6    "Municipal utility" means a public utility owned and
7operated by any subdivision or municipal corporation of this
8State.
9    "Nameplate capacity" means the aggregate inverter
10nameplate capacity in kilowatts AC.
11    "Person" means any natural person, firm, partnership,
12corporation, either domestic or foreign, company, association,
13limited liability company, joint stock company, or association
14and includes any trustee, receiver, assignee, or personal
15representative thereof.
16    "Project" means the planning, bidding, and construction of
17a facility.
18    "Public utility" has the same definition as found in
19Section 3-105 of the Public Utilities Act.
20    "Real property" means any interest in land together with
21all structures, fixtures, and improvements thereon, including
22lands under water and riparian rights, any easements,
23covenants, licenses, leases, rights-of-way, uses, and other
24interests, together with any liens, judgments, mortgages, or
25other claims or security interests related to real property.
26    "Renewable energy credit" means a tradable credit that

 

 

10200HB1747ham001- 16 -LRB102 12090 SPS 23532 a

1represents the environmental attributes of one megawatt hour
2of energy produced from a renewable energy resource.
3    "Renewable energy generator" means an electric generating
4facility that generates renewable energy resources.
5    "Renewable energy resources" includes energy and its
6associated renewable energy credit or renewable energy credits
7from wind, solar thermal energy, photovoltaic cells and
8panels, biodiesel, anaerobic digestion, crops and untreated
9and unadulterated organic waste biomass, tree waste, and
10hydropower that does not involve new construction or
11significant expansion of hydropower dams. For purposes of this
12Act, landfill gas produced in the State is considered a
13renewable energy resource. "Renewable energy resources" does
14not include the incineration or burning of tires, garbage,
15general household, institutional, and commercial waste,
16industrial lunchroom or office waste, landscape waste other
17than tree waste, railroad crossties, utility poles, or
18construction or demolition debris, other than untreated and
19unadulterated waste wood.
20    "Retail customer" has the same definition as found in
21Section 16-102 of the Public Utilities Act.
22    "Revenue bond" means any bond, note, or other evidence of
23indebtedness issued by the Authority, the principal and
24interest of which is payable solely from revenues or income
25derived from any project or activity of the Agency.
26    "Self-directing retail customer" means a retail customer

 

 

10200HB1747ham001- 17 -LRB102 12090 SPS 23532 a

1that is being supplied energy from a renewable energy
2generator located in Illinois under a self-supply renewable
3portfolio standard agreement with an alternative retail
4electric supplier in accordance with subsection (d-5) of
5Section 16-115D of the Public Utilities Act.
6    "Self-supply renewable portfolio standard agreement" means
7a contract under which an alternative retail electric supplier
8agrees to procure renewable energy resources from renewable
9energy generators located in Illinois for at least 25% of the
10metered electricity delivered by the alternative retail
11electric supplier to the retail customer over the term of the
12self-supply renewable portfolio standard agreement and retire
13the associated renewable energy credits procured from those
14renewable energy generators.
15    "Sequester" means permanent storage of carbon dioxide by
16injecting it into a saline aquifer, a depleted gas reservoir,
17or an oil reservoir, directly or through an enhanced oil
18recovery process that may involve intermediate storage,
19regardless of whether these activities are conducted by a
20clean coal facility, a clean coal SNG facility, a clean coal
21SNG brownfield facility, or a party with which a clean coal
22facility, clean coal SNG facility, or clean coal SNG
23brownfield facility has contracted for such purposes.
24    "Service area" has the same definition as found in Section
2516-102 of the Public Utilities Act.
26    "Sourcing agreement" means (i) in the case of an electric

 

 

10200HB1747ham001- 18 -LRB102 12090 SPS 23532 a

1utility, an agreement between the owner of a clean coal
2facility and such electric utility, which agreement shall have
3terms and conditions meeting the requirements of paragraph (3)
4of subsection (d) of Section 1-75, (ii) in the case of an
5alternative retail electric supplier, an agreement between the
6owner of a clean coal facility and such alternative retail
7electric supplier, which agreement shall have terms and
8conditions meeting the requirements of Section 16-115(d)(5) of
9the Public Utilities Act, and (iii) in case of a gas utility,
10an agreement between the owner of a clean coal SNG brownfield
11facility and the gas utility, which agreement shall have the
12terms and conditions meeting the requirements of subsection
13(h-1) of Section 9-220 of the Public Utilities Act.
14    "Subscriber" means a person who (i) takes delivery service
15from an electric utility, and (ii) has a subscription of no
16less than 200 watts to a community renewable generation
17project that is located in the electric utility's service
18area. No subscriber's subscriptions may total more than 40% of
19the nameplate capacity of an individual community renewable
20generation project. Entities that are affiliated by virtue of
21a common parent shall not represent multiple subscriptions
22that total more than 40% of the nameplate capacity of an
23individual community renewable generation project.
24    "Subscription" means an interest in a community renewable
25generation project expressed in kilowatts, which is sized
26primarily to offset part or all of the subscriber's

 

 

10200HB1747ham001- 19 -LRB102 12090 SPS 23532 a

1electricity usage.
2    "Substitute natural gas" or "SNG" means a gas manufactured
3by gasification of hydrocarbon feedstock, which is
4substantially interchangeable in use and distribution with
5conventional natural gas.
6    "Total resource cost test" or "TRC test" means a standard
7that is met if, for an investment in energy efficiency or
8demand-response measures, the benefit-cost ratio is greater
9than one. The benefit-cost ratio is the ratio of the net
10present value of the total benefits of the program to the net
11present value of the total costs as calculated over the
12lifetime of the measures. A total resource cost test compares
13the sum of avoided electric utility costs, representing the
14benefits that accrue to the system and the participant in the
15delivery of those efficiency measures and including avoided
16costs associated with reduced use of natural gas or other
17fuels, avoided costs associated with reduced water
18consumption, and avoided costs associated with reduced
19operation and maintenance costs, as well as other quantifiable
20societal benefits, to the sum of all incremental costs of
21end-use measures that are implemented due to the program
22(including both utility and participant contributions), plus
23costs to administer, deliver, and evaluate each demand-side
24program, to quantify the net savings obtained by substituting
25the demand-side program for supply resources. In calculating
26avoided costs of power and energy that an electric utility

 

 

10200HB1747ham001- 20 -LRB102 12090 SPS 23532 a

1would otherwise have had to acquire, reasonable estimates
2shall be included of financial costs likely to be imposed by
3future regulations and legislation on emissions of greenhouse
4gases. In discounting future societal costs and benefits for
5the purpose of calculating net present values, a societal
6discount rate based on actual, long-term Treasury bond yields
7should be used. Notwithstanding anything to the contrary, the
8TRC test shall not include or take into account a calculation
9of market price suppression effects or demand reduction
10induced price effects.
11    "Utility-scale solar project" means an electric generating
12facility that:
13        (1) generates electricity using photovoltaic cells;
14    and
15        (2) has a nameplate capacity that is greater than
16    2,000 kilowatts.
17    "Utility-scale wind project" means an electric generating
18facility that:
19        (1) generates electricity using wind; and
20        (2) has a nameplate capacity that is greater than
21    2,000 kilowatts.
22    "Zero emission credit" means a tradable credit that
23represents the environmental attributes of one megawatt hour
24of energy produced from a zero emission facility.
25    "Zero emission facility" means a facility that: (1) is
26fueled by nuclear power; and (2) is interconnected with PJM

 

 

10200HB1747ham001- 21 -LRB102 12090 SPS 23532 a

1Interconnection, LLC or the Midcontinent Independent System
2Operator, Inc., or their successors.
3(Source: P.A. 98-90, eff. 7-15-13; 99-906, eff. 6-1-17.)
 
4    (20 ILCS 3855/1-75)
5    Sec. 1-75. Planning and Procurement Bureau. The Planning
6and Procurement Bureau has the following duties and
7responsibilities:
8    (a) The Planning and Procurement Bureau shall each year,
9beginning in 2008, develop procurement plans and conduct
10competitive procurement processes in accordance with the
11requirements of Section 16-111.5 of the Public Utilities Act
12for the eligible retail customers of electric utilities that
13on December 31, 2005 provided electric service to at least
14100,000 customers in Illinois. Beginning with the delivery
15year commencing on June 1, 2017, the Planning and Procurement
16Bureau shall develop plans and processes for the procurement
17of zero emission credits from zero emission facilities in
18accordance with the requirements of subsection (d-5) of this
19Section. The Planning and Procurement Bureau shall also
20develop procurement plans and conduct competitive procurement
21processes in accordance with the requirements of Section
2216-111.5 of the Public Utilities Act for the eligible retail
23customers of small multi-jurisdictional electric utilities
24that (i) on December 31, 2005 served less than 100,000
25customers in Illinois and (ii) request a procurement plan for

 

 

10200HB1747ham001- 22 -LRB102 12090 SPS 23532 a

1their Illinois jurisdictional load. This Section shall not
2apply to a small multi-jurisdictional utility until such time
3as a small multi-jurisdictional utility requests the Agency to
4prepare a procurement plan for their Illinois jurisdictional
5load. For the purposes of this Section, the term "eligible
6retail customers" has the same definition as found in Section
716-111.5(a) of the Public Utilities Act.
8    Beginning with the plan or plans to be implemented in the
92017 delivery year, the Agency shall no longer include the
10procurement of renewable energy resources in the annual
11procurement plans required by this subsection (a), except as
12provided in subsection (q) of Section 16-111.5 of the Public
13Utilities Act, and shall instead develop a long-term renewable
14resources procurement plan in accordance with subsection (c)
15of this Section and Section 16-111.5 of the Public Utilities
16Act.
17        (1) The Agency shall each year, beginning in 2008, as
18    needed, issue a request for qualifications for experts or
19    expert consulting firms to develop the procurement plans
20    in accordance with Section 16-111.5 of the Public
21    Utilities Act. In order to qualify an expert or expert
22    consulting firm must have:
23            (A) direct previous experience assembling
24        large-scale power supply plans or portfolios for
25        end-use customers;
26            (B) an advanced degree in economics, mathematics,

 

 

10200HB1747ham001- 23 -LRB102 12090 SPS 23532 a

1        engineering, risk management, or a related area of
2        study;
3            (C) 10 years of experience in the electricity
4        sector, including managing supply risk;
5            (D) expertise in wholesale electricity market
6        rules, including those established by the Federal
7        Energy Regulatory Commission and regional transmission
8        organizations;
9            (E) expertise in credit protocols and familiarity
10        with contract protocols;
11            (F) adequate resources to perform and fulfill the
12        required functions and responsibilities; and
13            (G) the absence of a conflict of interest and
14        inappropriate bias for or against potential bidders or
15        the affected electric utilities.
16        (2) The Agency shall each year, as needed, issue a
17    request for qualifications for a procurement administrator
18    to conduct the competitive procurement processes in
19    accordance with Section 16-111.5 of the Public Utilities
20    Act. In order to qualify an expert or expert consulting
21    firm must have:
22            (A) direct previous experience administering a
23        large-scale competitive procurement process;
24            (B) an advanced degree in economics, mathematics,
25        engineering, or a related area of study;
26            (C) 10 years of experience in the electricity

 

 

10200HB1747ham001- 24 -LRB102 12090 SPS 23532 a

1        sector, including risk management experience;
2            (D) expertise in wholesale electricity market
3        rules, including those established by the Federal
4        Energy Regulatory Commission and regional transmission
5        organizations;
6            (E) expertise in credit and contract protocols;
7            (F) adequate resources to perform and fulfill the
8        required functions and responsibilities; and
9            (G) the absence of a conflict of interest and
10        inappropriate bias for or against potential bidders or
11        the affected electric utilities.
12        (3) The Agency shall provide affected utilities and
13    other interested parties with the lists of qualified
14    experts or expert consulting firms identified through the
15    request for qualifications processes that are under
16    consideration to develop the procurement plans and to
17    serve as the procurement administrator. The Agency shall
18    also provide each qualified expert's or expert consulting
19    firm's response to the request for qualifications. All
20    information provided under this subparagraph shall also be
21    provided to the Commission. The Agency may provide by rule
22    for fees associated with supplying the information to
23    utilities and other interested parties. These parties
24    shall, within 5 business days, notify the Agency in
25    writing if they object to any experts or expert consulting
26    firms on the lists. Objections shall be based on:

 

 

10200HB1747ham001- 25 -LRB102 12090 SPS 23532 a

1            (A) failure to satisfy qualification criteria;
2            (B) identification of a conflict of interest; or
3            (C) evidence of inappropriate bias for or against
4        potential bidders or the affected utilities.
5        The Agency shall remove experts or expert consulting
6    firms from the lists within 10 days if there is a
7    reasonable basis for an objection and provide the updated
8    lists to the affected utilities and other interested
9    parties. If the Agency fails to remove an expert or expert
10    consulting firm from a list, an objecting party may seek
11    review by the Commission within 5 days thereafter by
12    filing a petition, and the Commission shall render a
13    ruling on the petition within 10 days. There is no right of
14    appeal of the Commission's ruling.
15        (4) The Agency shall issue requests for proposals to
16    the qualified experts or expert consulting firms to
17    develop a procurement plan for the affected utilities and
18    to serve as procurement administrator.
19        (5) The Agency shall select an expert or expert
20    consulting firm to develop procurement plans based on the
21    proposals submitted and shall award contracts of up to 5
22    years to those selected.
23        (6) The Agency shall select an expert or expert
24    consulting firm, with approval of the Commission, to serve
25    as procurement administrator based on the proposals
26    submitted. If the Commission rejects, within 5 days, the

 

 

10200HB1747ham001- 26 -LRB102 12090 SPS 23532 a

1    Agency's selection, the Agency shall submit another
2    recommendation within 3 days based on the proposals
3    submitted. The Agency shall award a 5-year contract to the
4    expert or expert consulting firm so selected with
5    Commission approval.
6    (b) The experts or expert consulting firms retained by the
7Agency shall, as appropriate, prepare procurement plans, and
8conduct a competitive procurement process as prescribed in
9Section 16-111.5 of the Public Utilities Act, to ensure
10adequate, reliable, affordable, efficient, and environmentally
11sustainable electric service at the lowest total cost over
12time, taking into account any benefits of price stability, for
13eligible retail customers of electric utilities that on
14December 31, 2005 provided electric service to at least
15100,000 customers in the State of Illinois, and for eligible
16Illinois retail customers of small multi-jurisdictional
17electric utilities that (i) on December 31, 2005 served less
18than 100,000 customers in Illinois and (ii) request a
19procurement plan for their Illinois jurisdictional load.
20    (c) Renewable portfolio standard.
21        (1)(A) The Agency shall develop a long-term renewable
22    resources procurement plan that shall include procurement
23    programs and competitive procurement events necessary to
24    meet the goals set forth in this subsection (c). The
25    initial long-term renewable resources procurement plan
26    shall be released for comment no later than 160 days after

 

 

10200HB1747ham001- 27 -LRB102 12090 SPS 23532 a

1    June 1, 2017 (the effective date of Public Act 99-906).
2    The Agency shall review, and may revise on an expedited
3    basis, the long-term renewable resources procurement plan
4    at least every 2 years, which shall be conducted in
5    conjunction with the procurement plan under Section
6    16-111.5 of the Public Utilities Act to the extent
7    practicable to minimize administrative expense. The
8    long-term renewable resources procurement plans shall be
9    subject to review and approval by the Commission under
10    Section 16-111.5 of the Public Utilities Act.
11        (B) Subject to subparagraph (F) of this paragraph (1),
12    the long-term renewable resources procurement plan shall
13    include the goals for procurement of renewable energy
14    credits to meet at least the following overall
15    percentages: 13% by the 2017 delivery year; increasing by
16    at least 1.5% each delivery year thereafter to at least
17    25% by the 2025 delivery year; and continuing at no less
18    than 25% for each delivery year thereafter. In the event
19    of a conflict between these goals and the new wind and new
20    photovoltaic procurement requirements described in items
21    (i) through (iii) of subparagraph (C) of this paragraph
22    (1), the long-term plan shall prioritize compliance with
23    the new wind and new photovoltaic procurement requirements
24    described in items (i) through (iii) of subparagraph (C)
25    of this paragraph (1) over the annual percentage targets
26    described in this subparagraph (B).

 

 

10200HB1747ham001- 28 -LRB102 12090 SPS 23532 a

1        For the delivery year beginning June 1, 2017, the
2    procurement plan shall include cost-effective renewable
3    energy resources equal to at least 13% of each utility's
4    load for eligible retail customers and 13% of the
5    applicable portion of each utility's load for retail
6    customers who are not eligible retail customers, which
7    applicable portion shall equal 50% of the utility's load
8    for retail customers who are not eligible retail customers
9    on February 28, 2017.
10        For the delivery year beginning June 1, 2018, the
11    procurement plan shall include cost-effective renewable
12    energy resources equal to at least 14.5% of each utility's
13    load for eligible retail customers and 14.5% of the
14    applicable portion of each utility's load for retail
15    customers who are not eligible retail customers, which
16    applicable portion shall equal 75% of the utility's load
17    for retail customers who are not eligible retail customers
18    on February 28, 2017.
19        For the delivery year beginning June 1, 2019, and for
20    each year thereafter, the procurement plans shall include
21    cost-effective renewable energy resources equal to a
22    minimum percentage of each utility's load for all retail
23    customers as follows: 16% by June 1, 2019; increasing by
24    1.5% each year thereafter to 25% by June 1, 2025; and 25%
25    by June 1, 2026 and each year thereafter.
26        For each delivery year, the Agency shall first

 

 

10200HB1747ham001- 29 -LRB102 12090 SPS 23532 a

1    recognize each utility's obligations for that delivery
2    year under existing contracts. Any renewable energy
3    credits under existing contracts, including renewable
4    energy credits as part of renewable energy resources and
5    all renewable energy credits procured by alternative
6    retail electric suppliers under the terms of self-supply
7    renewable portfolio standard agreements, shall be used to
8    meet the goals set forth in this subsection (c) for the
9    delivery year.
10        (C) Of the renewable energy credits procured under
11    this subsection (c), at least 75% shall come from wind and
12    photovoltaic projects. The long-term renewable resources
13    procurement plan described in subparagraph (A) of this
14    paragraph (1) shall include the procurement of renewable
15    energy credits in amounts equal to at least the following:
16            (i) By the end of the 2020 delivery year:
17                At least 2,000,000 renewable energy credits
18            for each delivery year shall come from new wind
19            projects; and
20                At least 2,000,000 renewable energy credits
21            for each delivery year shall come from new
22            photovoltaic projects; of that amount, to the
23            extent possible, the Agency shall procure: at
24            least 50% from solar photovoltaic projects using
25            the program outlined in subparagraph (K) of this
26            paragraph (1) from distributed renewable energy

 

 

10200HB1747ham001- 30 -LRB102 12090 SPS 23532 a

1            generation devices or community renewable
2            generation projects; at least 40% from
3            utility-scale solar projects; at least 2% from
4            brownfield site photovoltaic projects that are not
5            community renewable generation projects; and the
6            remainder shall be determined through the
7            long-term planning process described in
8            subparagraph (A) of this paragraph (1).
9            (ii) By the end of the 2025 delivery year:
10                At least 3,000,000 renewable energy credits
11            for each delivery year shall come from new wind
12            projects; and
13                At least 3,000,000 renewable energy credits
14            for each delivery year shall come from new
15            photovoltaic projects; of that amount, to the
16            extent possible, the Agency shall procure: at
17            least 50% from solar photovoltaic projects using
18            the program outlined in subparagraph (K) of this
19            paragraph (1) from distributed renewable energy
20            devices or community renewable generation
21            projects; at least 40% from utility-scale solar
22            projects; at least 2% from brownfield site
23            photovoltaic projects that are not community
24            renewable generation projects; and the remainder
25            shall be determined through the long-term planning
26            process described in subparagraph (A) of this

 

 

10200HB1747ham001- 31 -LRB102 12090 SPS 23532 a

1            paragraph (1).
2            (iii) By the end of the 2030 delivery year:
3                At least 4,000,000 renewable energy credits
4            for each delivery year shall come from new wind
5            projects; and
6                At least 4,000,000 renewable energy credits
7            for each delivery year shall come from new
8            photovoltaic projects; of that amount, to the
9            extent possible, the Agency shall procure: at
10            least 50% from solar photovoltaic projects using
11            the program outlined in subparagraph (K) of this
12            paragraph (1) from distributed renewable energy
13            devices or community renewable generation
14            projects; at least 40% from utility-scale solar
15            projects; at least 2% from brownfield site
16            photovoltaic projects that are not community
17            renewable generation projects; and the remainder
18            shall be determined through the long-term planning
19            process described in subparagraph (A) of this
20            paragraph (1).
21            For purposes of this Section:
22                "New wind projects" means wind renewable
23            energy facilities that are energized after June 1,
24            2017 for the delivery year commencing June 1, 2017
25            or within 3 years after the date the Commission
26            approves contracts for subsequent delivery years.

 

 

10200HB1747ham001- 32 -LRB102 12090 SPS 23532 a

1                "New photovoltaic projects" means photovoltaic
2            renewable energy facilities that are energized
3            after June 1, 2017. Photovoltaic projects
4            developed under Section 1-56 of this Act shall not
5            apply towards the new photovoltaic project
6            requirements in this subparagraph (C).
7        (D) Renewable energy credits shall be cost effective.
8    For purposes of this subsection (c), "cost effective"
9    means that the costs of procuring renewable energy
10    resources do not cause the limit stated in subparagraph
11    (E) of this paragraph (1) to be exceeded and, for
12    renewable energy credits procured through a competitive
13    procurement event, do not exceed benchmarks based on
14    market prices for like products in the region. For
15    purposes of this subsection (c), "like products" means
16    contracts for renewable energy credits from the same or
17    substantially similar technology, same or substantially
18    similar vintage (new or existing), the same or
19    substantially similar quantity, and the same or
20    substantially similar contract length and structure.
21    Benchmarks shall be developed by the procurement
22    administrator, in consultation with the Commission staff,
23    Agency staff, and the procurement monitor and shall be
24    subject to Commission review and approval. If price
25    benchmarks for like products in the region are not
26    available, the procurement administrator shall establish

 

 

10200HB1747ham001- 33 -LRB102 12090 SPS 23532 a

1    price benchmarks based on publicly available data on
2    regional technology costs and expected current and future
3    regional energy prices. The benchmarks in this Section
4    shall not be used to curtail or otherwise reduce
5    contractual obligations entered into by or through the
6    Agency prior to June 1, 2017 (the effective date of Public
7    Act 99-906).
8        (E) For purposes of this subsection (c), the required
9    procurement of cost-effective renewable energy resources
10    for a particular year commencing prior to June 1, 2017
11    shall be measured as a percentage of the actual amount of
12    electricity (megawatt-hours) supplied by the electric
13    utility to eligible retail customers in the delivery year
14    ending immediately prior to the procurement, and, for
15    delivery years commencing on and after June 1, 2017, the
16    required procurement of cost-effective renewable energy
17    resources for a particular year shall be measured as a
18    percentage of the actual amount of electricity
19    (megawatt-hours) delivered by the electric utility in the
20    delivery year ending immediately prior to the procurement,
21    to all retail customers in its service territory. For
22    purposes of this subsection (c), the amount paid per
23    kilowatthour means the total amount paid for electric
24    service expressed on a per kilowatthour basis. For
25    purposes of this subsection (c), the total amount paid for
26    electric service includes without limitation amounts paid

 

 

10200HB1747ham001- 34 -LRB102 12090 SPS 23532 a

1    for supply, transmission, distribution, surcharges, and
2    add-on taxes.
3        Notwithstanding the requirements of this subsection
4    (c), the total of renewable energy resources procured
5    under the procurement plan for any single year shall be
6    subject to the limitations of this subparagraph (E). Such
7    procurement shall be reduced for all retail customers
8    based on the amount necessary to limit the annual
9    estimated average net increase due to the costs of these
10    resources included in the amounts paid by eligible retail
11    customers in connection with electric service to no more
12    than the greater of 2.015% of the amount paid per
13    kilowatthour by those customers during the year ending May
14    31, 2007 or the incremental amount per kilowatthour paid
15    for these resources in 2011. To arrive at a maximum dollar
16    amount of renewable energy resources to be procured for
17    the particular delivery year, the resulting per
18    kilowatthour amount shall be applied to the actual amount
19    of kilowatthours of electricity delivered, or applicable
20    portion of such amount as specified in paragraph (1) of
21    this subsection (c), as applicable, by the electric
22    utility in the delivery year immediately prior to the
23    procurement to all retail customers in its service
24    territory. The calculations required by this subparagraph
25    (E) shall be made only once for each delivery year at the
26    time that the renewable energy resources are procured.

 

 

10200HB1747ham001- 35 -LRB102 12090 SPS 23532 a

1    Once the determination as to the amount of renewable
2    energy resources to procure is made based on the
3    calculations set forth in this subparagraph (E) and the
4    contracts procuring those amounts are executed, no
5    subsequent rate impact determinations shall be made and no
6    adjustments to those contract amounts shall be allowed.
7    All costs incurred under such contracts shall be fully
8    recoverable by the electric utility as provided in this
9    Section.
10        (F) If the limitation on the amount of renewable
11    energy resources procured in subparagraph (E) of this
12    paragraph (1) prevents the Agency from meeting all of the
13    goals in this subsection (c), the Agency's long-term plan
14    shall prioritize compliance with the requirements of this
15    subsection (c) regarding renewable energy credits in the
16    following order:
17            (i) renewable energy credits under existing
18        contractual obligations;
19            (i-5) funding for the Illinois Solar for All
20        Program, as described in subparagraph (O) of this
21        paragraph (1);
22            (ii) renewable energy credits necessary to comply
23        with the new wind and new photovoltaic procurement
24        requirements described in items (i) through (iii) of
25        subparagraph (C) of this paragraph (1); and
26            (iii) renewable energy credits necessary to meet

 

 

10200HB1747ham001- 36 -LRB102 12090 SPS 23532 a

1        the remaining requirements of this subsection (c).
2        (G) The following provisions shall apply to the
3    Agency's procurement of renewable energy credits under
4    this subsection (c):
5            (i) Notwithstanding whether a long-term renewable
6        resources procurement plan has been approved, the
7        Agency shall conduct an initial forward procurement
8        for renewable energy credits from new utility-scale
9        wind projects within 160 days after June 1, 2017 (the
10        effective date of Public Act 99-906). For the purposes
11        of this initial forward procurement, the Agency shall
12        solicit 15-year contracts for delivery of 1,000,000
13        renewable energy credits delivered annually from new
14        utility-scale wind projects to begin delivery on June
15        1, 2019, if available, but not later than June 1, 2021,
16        unless the project has delays in the establishment of
17        an operating interconnection with the applicable
18        transmission or distribution system as a result of the
19        actions or inactions of the transmission or
20        distribution provider, or other causes for force
21        majeure as outlined in the procurement contract, in
22        which case, not later than June 1, 2022. Payments to
23        suppliers of renewable energy credits shall commence
24        upon delivery. Renewable energy credits procured under
25        this initial procurement shall be included in the
26        Agency's long-term plan and shall apply to all

 

 

10200HB1747ham001- 37 -LRB102 12090 SPS 23532 a

1        renewable energy goals in this subsection (c).
2            (ii) Notwithstanding whether a long-term renewable
3        resources procurement plan has been approved, the
4        Agency shall conduct an initial forward procurement
5        for renewable energy credits from new utility-scale
6        solar projects and brownfield site photovoltaic
7        projects within one year after June 1, 2017 (the
8        effective date of Public Act 99-906). For the purposes
9        of this initial forward procurement, the Agency shall
10        solicit 15-year contracts for delivery of 1,000,000
11        renewable energy credits delivered annually from new
12        utility-scale solar projects and brownfield site
13        photovoltaic projects to begin delivery on June 1,
14        2019, if available, but not later than June 1, 2021,
15        unless the project has delays in the establishment of
16        an operating interconnection with the applicable
17        transmission or distribution system as a result of the
18        actions or inactions of the transmission or
19        distribution provider, or other causes for force
20        majeure as outlined in the procurement contract, in
21        which case, not later than June 1, 2022. The Agency may
22        structure this initial procurement in one or more
23        discrete procurement events. Payments to suppliers of
24        renewable energy credits shall commence upon delivery.
25        Renewable energy credits procured under this initial
26        procurement shall be included in the Agency's

 

 

10200HB1747ham001- 38 -LRB102 12090 SPS 23532 a

1        long-term plan and shall apply to all renewable energy
2        goals in this subsection (c).
3            (iii) Subsequent forward procurements for
4        utility-scale wind projects shall solicit at least
5        1,000,000 renewable energy credits delivered annually
6        per procurement event and shall be planned, scheduled,
7        and designed such that the cumulative amount of
8        renewable energy credits delivered from all new wind
9        projects in each delivery year shall not exceed the
10        Agency's projection of the cumulative amount of
11        renewable energy credits that will be delivered from
12        all new photovoltaic projects, including utility-scale
13        and distributed photovoltaic devices, in the same
14        delivery year at the time scheduled for wind contract
15        delivery.
16            (iv) If, at any time after the time set for
17        delivery of renewable energy credits pursuant to the
18        initial procurements in items (i) and (ii) of this
19        subparagraph (G), the cumulative amount of renewable
20        energy credits projected to be delivered from all new
21        wind projects in a given delivery year exceeds the
22        cumulative amount of renewable energy credits
23        projected to be delivered from all new photovoltaic
24        projects in that delivery year by 200,000 or more
25        renewable energy credits, then the Agency shall within
26        60 days adjust the procurement programs in the

 

 

10200HB1747ham001- 39 -LRB102 12090 SPS 23532 a

1        long-term renewable resources procurement plan to
2        ensure that the projected cumulative amount of
3        renewable energy credits to be delivered from all new
4        wind projects does not exceed the projected cumulative
5        amount of renewable energy credits to be delivered
6        from all new photovoltaic projects by 200,000 or more
7        renewable energy credits, provided that nothing in
8        this Section shall preclude the projected cumulative
9        amount of renewable energy credits to be delivered
10        from all new photovoltaic projects from exceeding the
11        projected cumulative amount of renewable energy
12        credits to be delivered from all new wind projects in
13        each delivery year and provided further that nothing
14        in this item (iv) shall require the curtailment of an
15        executed contract. The Agency shall update, on a
16        quarterly basis, its projection of the renewable
17        energy credits to be delivered from all projects in
18        each delivery year. Notwithstanding anything to the
19        contrary, the Agency may adjust the timing of
20        procurement events conducted under this subparagraph
21        (G). The long-term renewable resources procurement
22        plan shall set forth the process by which the
23        adjustments may be made.
24            (v) All procurements under this subparagraph (G)
25        shall comply with the geographic requirements in
26        subparagraph (I) of this paragraph (1) and shall

 

 

10200HB1747ham001- 40 -LRB102 12090 SPS 23532 a

1        follow the procurement processes and procedures
2        described in this Section and Section 16-111.5 of the
3        Public Utilities Act to the extent practicable, and
4        these processes and procedures may be expedited to
5        accommodate the schedule established by this
6        subparagraph (G).
7        (H) The procurement of renewable energy resources for
8    a given delivery year shall be reduced as described in
9    this subparagraph (H) if an alternative retail electric
10    supplier meets the requirements described in this
11    subparagraph (H).
12            (i) Within 45 days after June 1, 2017 (the
13        effective date of Public Act 99-906), an alternative
14        retail electric supplier or its successor shall submit
15        an informational filing to the Illinois Commerce
16        Commission certifying that, as of December 31, 2015,
17        the alternative retail electric supplier owned one or
18        more electric generating facilities that generates
19        renewable energy resources as defined in Section 1-10
20        of this Act, provided that such facilities are not
21        powered by wind or photovoltaics, and the facilities
22        generate one renewable energy credit for each
23        megawatthour of energy produced from the facility.
24            The informational filing shall identify each
25        facility that was eligible to satisfy the alternative
26        retail electric supplier's obligations under Section

 

 

10200HB1747ham001- 41 -LRB102 12090 SPS 23532 a

1        16-115D of the Public Utilities Act as described in
2        this item (i).
3            (ii) For a given delivery year, the alternative
4        retail electric supplier may elect to supply its
5        retail customers with renewable energy credits from
6        the facility or facilities described in item (i) of
7        this subparagraph (H) that continue to be owned by the
8        alternative retail electric supplier.
9            (iii) The alternative retail electric supplier
10        shall notify the Agency and the applicable utility, no
11        later than February 28 of the year preceding the
12        applicable delivery year or 15 days after June 1, 2017
13        (the effective date of Public Act 99-906), whichever
14        is later, of its election under item (ii) of this
15        subparagraph (H) to supply renewable energy credits to
16        retail customers of the utility. Such election shall
17        identify the amount of renewable energy credits to be
18        supplied by the alternative retail electric supplier
19        to the utility's retail customers and the source of
20        the renewable energy credits identified in the
21        informational filing as described in item (i) of this
22        subparagraph (H), subject to the following
23        limitations:
24                For the delivery year beginning June 1, 2018,
25            the maximum amount of renewable energy credits to
26            be supplied by an alternative retail electric

 

 

10200HB1747ham001- 42 -LRB102 12090 SPS 23532 a

1            supplier under this subparagraph (H) shall be 68%
2            multiplied by 25% multiplied by 14.5% multiplied
3            by the amount of metered electricity
4            (megawatt-hours) delivered by the alternative
5            retail electric supplier to Illinois retail
6            customers during the delivery year ending May 31,
7            2016.
8                For delivery years beginning June 1, 2019 and
9            each year thereafter, the maximum amount of
10            renewable energy credits to be supplied by an
11            alternative retail electric supplier under this
12            subparagraph (H) shall be 68% multiplied by 50%
13            multiplied by 16% multiplied by the amount of
14            metered electricity (megawatt-hours) delivered by
15            the alternative retail electric supplier to
16            Illinois retail customers during the delivery year
17            ending May 31, 2016, provided that the 16% value
18            shall increase by 1.5% each delivery year
19            thereafter to 25% by the delivery year beginning
20            June 1, 2025, and thereafter the 25% value shall
21            apply to each delivery year.
22            For each delivery year, the total amount of
23        renewable energy credits supplied by all alternative
24        retail electric suppliers under this subparagraph (H)
25        shall not exceed 9% of the Illinois target renewable
26        energy credit quantity. The Illinois target renewable

 

 

10200HB1747ham001- 43 -LRB102 12090 SPS 23532 a

1        energy credit quantity for the delivery year beginning
2        June 1, 2018 is 14.5% multiplied by the total amount of
3        metered electricity (megawatt-hours) delivered in the
4        delivery year immediately preceding that delivery
5        year, provided that the 14.5% shall increase by 1.5%
6        each delivery year thereafter to 25% by the delivery
7        year beginning June 1, 2025, and thereafter the 25%
8        value shall apply to each delivery year.
9            If the requirements set forth in items (i) through
10        (iii) of this subparagraph (H) are met, the charges
11        that would otherwise be applicable to the retail
12        customers of the alternative retail electric supplier
13        under paragraph (6) of this subsection (c) for the
14        applicable delivery year shall be reduced by the ratio
15        of the quantity of renewable energy credits supplied
16        by the alternative retail electric supplier compared
17        to that supplier's target renewable energy credit
18        quantity. The supplier's target renewable energy
19        credit quantity for the delivery year beginning June
20        1, 2018 is 14.5% multiplied by the total amount of
21        metered electricity (megawatt-hours) delivered by the
22        alternative retail supplier in that delivery year,
23        provided that the 14.5% shall increase by 1.5% each
24        delivery year thereafter to 25% by the delivery year
25        beginning June 1, 2025, and thereafter the 25% value
26        shall apply to each delivery year.

 

 

10200HB1747ham001- 44 -LRB102 12090 SPS 23532 a

1            On or before April 1 of each year, the Agency shall
2        annually publish a report on its website that
3        identifies the aggregate amount of renewable energy
4        credits supplied by alternative retail electric
5        suppliers under this subparagraph (H).
6        (I) The Agency shall design its long-term renewable
7    energy procurement plan to maximize the State's interest
8    in the health, safety, and welfare of its residents,
9    including but not limited to minimizing sulfur dioxide,
10    nitrogen oxide, particulate matter and other pollution
11    that adversely affects public health in this State,
12    increasing fuel and resource diversity in this State,
13    enhancing the reliability and resiliency of the
14    electricity distribution system in this State, meeting
15    goals to limit carbon dioxide emissions under federal or
16    State law, and contributing to a cleaner and healthier
17    environment for the citizens of this State. In order to
18    further these legislative purposes, renewable energy
19    credits shall be eligible to be counted toward the
20    renewable energy requirements of this subsection (c) if
21    they are generated from facilities located in this State.
22    The Agency may qualify renewable energy credits from
23    facilities located in states adjacent to Illinois if the
24    generator demonstrates and the Agency determines that the
25    operation of such facility or facilities will help promote
26    the State's interest in the health, safety, and welfare of

 

 

10200HB1747ham001- 45 -LRB102 12090 SPS 23532 a

1    its residents based on the public interest criteria
2    described above. To ensure that the public interest
3    criteria are applied to the procurement and given full
4    effect, the Agency's long-term procurement plan shall
5    describe in detail how each public interest factor shall
6    be considered and weighted for facilities located in
7    states adjacent to Illinois.
8        (J) In order to promote the competitive development of
9    renewable energy resources in furtherance of the State's
10    interest in the health, safety, and welfare of its
11    residents, renewable energy credits shall not be eligible
12    to be counted toward the renewable energy requirements of
13    this subsection (c) if they are sourced from a generating
14    unit whose costs were being recovered through rates
15    regulated by this State or any other state or states on or
16    after January 1, 2017. Each contract executed to purchase
17    renewable energy credits under this subsection (c) shall
18    provide for the contract's termination if the costs of the
19    generating unit supplying the renewable energy credits
20    subsequently begin to be recovered through rates regulated
21    by this State or any other state or states; and each
22    contract shall further provide that, in that event, the
23    supplier of the credits must return 110% of all payments
24    received under the contract. Amounts returned under the
25    requirements of this subparagraph (J) shall be retained by
26    the utility and all of these amounts shall be used for the

 

 

10200HB1747ham001- 46 -LRB102 12090 SPS 23532 a

1    procurement of additional renewable energy credits from
2    new wind or new photovoltaic resources as defined in this
3    subsection (c). The long-term plan shall provide that
4    these renewable energy credits shall be procured in the
5    next procurement event.
6        Notwithstanding the limitations of this subparagraph
7    (J), renewable energy credits sourced from generating
8    units that are constructed, purchased, owned, or leased by
9    an electric utility as part of an approved project,
10    program, or pilot under Section 1-56 of this Act shall be
11    eligible to be counted toward the renewable energy
12    requirements of this subsection (c), regardless of how the
13    costs of these units are recovered.
14        (K) The long-term renewable resources procurement plan
15    developed by the Agency in accordance with subparagraph
16    (A) of this paragraph (1) shall include an Adjustable
17    Block program for the procurement of renewable energy
18    credits from new photovoltaic projects that are
19    distributed renewable energy generation devices or new
20    photovoltaic community renewable generation projects. The
21    Adjustable Block program shall be designed to provide a
22    transparent schedule of prices and quantities to enable
23    the photovoltaic market to scale up and for renewable
24    energy credit prices to adjust at a predictable rate over
25    time. The prices set by the Adjustable Block program can
26    be reflected as a set value or as the product of a formula.

 

 

10200HB1747ham001- 47 -LRB102 12090 SPS 23532 a

1        The Adjustable Block program shall include for each
2    category of eligible projects: a schedule of standard
3    block purchase prices to be offered; a series of steps,
4    with associated nameplate capacity and purchase prices
5    that adjust from step to step; and automatic opening of
6    the next step as soon as the nameplate capacity and
7    available purchase prices for an open step are fully
8    committed or reserved. Only projects energized on or after
9    June 1, 2017 shall be eligible for the Adjustable Block
10    program. For each block group the Agency shall determine
11    the number of blocks, the amount of generation capacity in
12    each block, and the purchase price for each block,
13    provided that the purchase price provided and the total
14    amount of generation in all blocks for all block groups
15    shall be sufficient to meet the goals in this subsection
16    (c). The Agency may periodically review its prior
17    decisions establishing the number of blocks, the amount of
18    generation capacity in each block, and the purchase price
19    for each block, and may propose, on an expedited basis,
20    changes to these previously set values, including but not
21    limited to redistributing these amounts and the available
22    funds as necessary and appropriate, subject to Commission
23    approval as part of the periodic plan revision process
24    described in Section 16-111.5 of the Public Utilities Act.
25    The Agency may define different block sizes, purchase
26    prices, or other distinct terms and conditions for

 

 

10200HB1747ham001- 48 -LRB102 12090 SPS 23532 a

1    projects located in different utility service territories
2    if the Agency deems it necessary to meet the goals in this
3    subsection (c).
4        The Adjustable Block program shall include at least
5    the following block groups in at least the following
6    amounts, which may be adjusted upon review by the Agency
7    and approval by the Commission as described in this
8    subparagraph (K):
9            (i) At least 25% from distributed renewable energy
10        generation devices with a nameplate capacity of no
11        more than 10 kilowatts.
12            (ii) At least 25% from distributed renewable
13        energy generation devices with a nameplate capacity of
14        more than 10 kilowatts and no more than 2,000
15        kilowatts. The Agency may create sub-categories within
16        this category to account for the differences between
17        projects for small commercial customers, large
18        commercial customers, and public or non-profit
19        customers.
20            (iii) At least 25% from photovoltaic community
21        renewable generation projects.
22            (iv) The remaining 25% shall be allocated as
23        specified by the Agency in the long-term renewable
24        resources procurement plan.
25        The Adjustable Block program shall be designed to
26    ensure that renewable energy credits are procured from

 

 

10200HB1747ham001- 49 -LRB102 12090 SPS 23532 a

1    photovoltaic distributed renewable energy generation
2    devices and new photovoltaic community renewable energy
3    generation projects in diverse locations and are not
4    concentrated in a few geographic areas.
5        (L) The procurement of photovoltaic renewable energy
6    credits under items (i) through (iv) of subparagraph (K)
7    of this paragraph (1) shall be subject to the following
8    contract and payment terms:
9            (i) The Agency shall procure contracts of at least
10        15 years in length.
11            (ii) For those renewable energy credits that
12        qualify and are procured under item (i) of
13        subparagraph (K) of this paragraph (1), the renewable
14        energy credit purchase price shall be paid in full by
15        the contracting utilities at the time that the
16        facility producing the renewable energy credits is
17        interconnected at the distribution system level of the
18        utility and energized. The electric utility shall
19        receive and retire all renewable energy credits
20        generated by the project for the first 15 years of
21        operation.
22            (iii) For those renewable energy credits that
23        qualify and are procured under item (ii) and (iii) of
24        subparagraph (K) of this paragraph (1) and any
25        additional categories of distributed generation
26        included in the long-term renewable resources

 

 

10200HB1747ham001- 50 -LRB102 12090 SPS 23532 a

1        procurement plan and approved by the Commission, 20
2        percent of the renewable energy credit purchase price
3        shall be paid by the contracting utilities at the time
4        that the facility producing the renewable energy
5        credits is interconnected at the distribution system
6        level of the utility and energized. The remaining
7        portion shall be paid ratably over the subsequent
8        4-year period. The electric utility shall receive and
9        retire all renewable energy credits generated by the
10        project for the first 15 years of operation.
11            (iv) Each contract shall include provisions to
12        ensure the delivery of the renewable energy credits
13        for the full term of the contract.
14            (v) The utility shall be the counterparty to the
15        contracts executed under this subparagraph (L) that
16        are approved by the Commission under the process
17        described in Section 16-111.5 of the Public Utilities
18        Act. No contract shall be executed for an amount that
19        is less than one renewable energy credit per year.
20            (vi) If, at any time, approved applications for
21        the Adjustable Block program exceed funds collected by
22        the electric utility or would cause the Agency to
23        exceed the limitation described in subparagraph (E) of
24        this paragraph (1) on the amount of renewable energy
25        resources that may be procured, then the Agency shall
26        consider future uncommitted funds to be reserved for

 

 

10200HB1747ham001- 51 -LRB102 12090 SPS 23532 a

1        these contracts on a first-come, first-served basis,
2        with the delivery of renewable energy credits required
3        beginning at the time that the reserved funds become
4        available.
5            (vii) Nothing in this Section shall require the
6        utility to advance any payment or pay any amounts that
7        exceed the actual amount of revenues collected by the
8        utility under paragraph (6) of this subsection (c) and
9        subsection (k) of Section 16-108 of the Public
10        Utilities Act, and contracts executed under this
11        Section shall expressly incorporate this limitation.
12        (M) The Agency shall be authorized to retain one or
13    more experts or expert consulting firms to develop,
14    administer, implement, operate, and evaluate the
15    Adjustable Block program described in subparagraph (K) of
16    this paragraph (1), and the Agency shall retain the
17    consultant or consultants in the same manner, to the
18    extent practicable, as the Agency retains others to
19    administer provisions of this Act, including, but not
20    limited to, the procurement administrator. The selection
21    of experts and expert consulting firms and the procurement
22    process described in this subparagraph (M) are exempt from
23    the requirements of Section 20-10 of the Illinois
24    Procurement Code, under Section 20-10 of that Code. The
25    Agency shall strive to minimize administrative expenses in
26    the implementation of the Adjustable Block program.

 

 

10200HB1747ham001- 52 -LRB102 12090 SPS 23532 a

1        The Agency and its consultant or consultants shall
2    monitor block activity, share program activity with
3    stakeholders and conduct regularly scheduled meetings to
4    discuss program activity and market conditions. If
5    necessary, the Agency may make prospective administrative
6    adjustments to the Adjustable Block program design, such
7    as redistributing available funds or making adjustments to
8    purchase prices as necessary to achieve the goals of this
9    subsection (c). Program modifications to any price,
10    capacity block, or other program element that do not
11    deviate from the Commission's approved value by more than
12    25% shall take effect immediately and are not subject to
13    Commission review and approval. Program modifications to
14    any price, capacity block, or other program element that
15    deviate more than 25% from the Commission's approved value
16    must be approved by the Commission as a long-term plan
17    amendment under Section 16-111.5 of the Public Utilities
18    Act. The Agency shall consider stakeholder feedback when
19    making adjustments to the Adjustable Block design and
20    shall notify stakeholders in advance of any planned
21    changes.
22        (N) The long-term renewable resources procurement plan
23    required by this subsection (c) shall include a community
24    renewable generation program. The Agency shall establish
25    the terms, conditions, and program requirements for
26    community renewable generation projects with a goal to

 

 

10200HB1747ham001- 53 -LRB102 12090 SPS 23532 a

1    expand renewable energy generating facility access to a
2    broader group of energy consumers, to ensure robust
3    participation opportunities for residential and small
4    commercial customers and those who cannot install
5    renewable energy on their own properties. Any plan
6    approved by the Commission shall allow subscriptions to
7    community renewable generation projects to be portable and
8    transferable. For purposes of this subparagraph (N),
9    "portable" means that subscriptions may be retained by the
10    subscriber even if the subscriber relocates or changes its
11    address within the same utility service territory; and
12    "transferable" means that a subscriber may assign or sell
13    subscriptions to another person within the same utility
14    service territory.
15        Electric utilities shall provide a monetary credit to
16    a subscriber's subsequent bill for service for the
17    proportional output of a community renewable generation
18    project attributable to that subscriber as specified in
19    Section 16-107.5 of the Public Utilities Act.
20        The Agency shall purchase renewable energy credits
21    from subscribed shares of photovoltaic community renewable
22    generation projects through the Adjustable Block program
23    described in subparagraph (K) of this paragraph (1) or
24    through the Illinois Solar for All Program described in
25    Section 1-56 of this Act. The electric utility shall
26    purchase any unsubscribed energy from community renewable

 

 

10200HB1747ham001- 54 -LRB102 12090 SPS 23532 a

1    generation projects that are Qualifying Facilities ("QF")
2    under the electric utility's tariff for purchasing the
3    output from QFs under Public Utilities Regulatory Policies
4    Act of 1978.
5        The owners of and any subscribers to a community
6    renewable generation project shall not be considered
7    public utilities or alternative retail electricity
8    suppliers under the Public Utilities Act solely as a
9    result of their interest in or subscription to a community
10    renewable generation project and shall not be required to
11    become an alternative retail electric supplier by
12    participating in a community renewable generation project
13    with a public utility.
14        (O) For the delivery year beginning June 1, 2018, the
15    long-term renewable resources procurement plan required by
16    this subsection (c) shall provide for the Agency to
17    procure contracts to continue offering the Illinois Solar
18    for All Program described in subsection (b) of Section
19    1-56 of this Act, and the contracts approved by the
20    Commission shall be executed by the utilities that are
21    subject to this subsection (c). The long-term renewable
22    resources procurement plan shall allocate 5% of the funds
23    available under the plan for the applicable delivery year,
24    or $10,000,000 per delivery year, whichever is greater, to
25    fund the programs, and the plan shall determine the amount
26    of funding to be apportioned to the programs identified in

 

 

10200HB1747ham001- 55 -LRB102 12090 SPS 23532 a

1    subsection (b) of Section 1-56 of this Act; provided that
2    for the delivery years beginning June 1, 2017, June 1,
3    2021, and June 1, 2025, the long-term renewable resources
4    procurement plan shall allocate 10% of the funds available
5    under the plan for the applicable delivery year, or
6    $20,000,000 per delivery year, whichever is greater, and
7    $10,000,000 of such funds in such year shall be used by an
8    electric utility that serves more than 3,000,000 retail
9    customers in the State to implement a Commission-approved
10    plan under Section 16-108.12 of the Public Utilities Act.
11    In making the determinations required under this
12    subparagraph (O), the Commission shall consider the
13    experience and performance under the programs and any
14    evaluation reports. The Commission shall also provide for
15    an independent evaluation of those programs on a periodic
16    basis that are funded under this subparagraph (O).
17        (2) (Blank).
18        (3) (Blank).
19        (4) The electric utility shall retire all renewable
20    energy credits used to comply with the standard.
21        (5) Beginning with the 2010 delivery year and ending
22    June 1, 2017, an electric utility subject to this
23    subsection (c) shall apply the lesser of the maximum
24    alternative compliance payment rate or the most recent
25    estimated alternative compliance payment rate for its
26    service territory for the corresponding compliance period,

 

 

10200HB1747ham001- 56 -LRB102 12090 SPS 23532 a

1    established pursuant to subsection (d) of Section 16-115D
2    of the Public Utilities Act to its retail customers that
3    take service pursuant to the electric utility's hourly
4    pricing tariff or tariffs. The electric utility shall
5    retain all amounts collected as a result of the
6    application of the alternative compliance payment rate or
7    rates to such customers, and, beginning in 2011, the
8    utility shall include in the information provided under
9    item (1) of subsection (d) of Section 16-111.5 of the
10    Public Utilities Act the amounts collected under the
11    alternative compliance payment rate or rates for the prior
12    year ending May 31. Notwithstanding any limitation on the
13    procurement of renewable energy resources imposed by item
14    (2) of this subsection (c), the Agency shall increase its
15    spending on the purchase of renewable energy resources to
16    be procured by the electric utility for the next plan year
17    by an amount equal to the amounts collected by the utility
18    under the alternative compliance payment rate or rates in
19    the prior year ending May 31.
20        (6) The electric utility shall be entitled to recover
21    all of its costs associated with the procurement of
22    renewable energy credits under plans approved under this
23    Section and Section 16-111.5 of the Public Utilities Act.
24    These costs shall include associated reasonable expenses
25    for implementing the procurement programs, including, but
26    not limited to, the costs of administering and evaluating

 

 

10200HB1747ham001- 57 -LRB102 12090 SPS 23532 a

1    the Adjustable Block program, through an automatic
2    adjustment clause tariff in accordance with subsection (k)
3    of Section 16-108 of the Public Utilities Act.
4        (7) Renewable energy credits procured from new
5    photovoltaic projects or new distributed renewable energy
6    generation devices under this Section after June 1, 2017
7    (the effective date of Public Act 99-906) must be procured
8    from devices installed by a qualified person in compliance
9    with the requirements of Section 16-128A of the Public
10    Utilities Act and any rules or regulations adopted
11    thereunder.
12        In meeting the renewable energy requirements of this
13    subsection (c), to the extent feasible and consistent with
14    State and federal law, the renewable energy credit
15    procurements, Adjustable Block solar program, and
16    community renewable generation program shall provide
17    employment opportunities for all segments of the
18    population and workforce, including minority-owned and
19    female-owned business enterprises, and shall not,
20    consistent with State and federal law, discriminate based
21    on race or socioeconomic status.
22    (d) Clean coal portfolio standard.
23        (1) The procurement plans shall include electricity
24    generated using clean coal. Each utility shall enter into
25    one or more sourcing agreements with the initial clean
26    coal facility, as provided in paragraph (3) of this

 

 

10200HB1747ham001- 58 -LRB102 12090 SPS 23532 a

1    subsection (d), covering electricity generated by the
2    initial clean coal facility representing at least 5% of
3    each utility's total supply to serve the load of eligible
4    retail customers in 2015 and each year thereafter, as
5    described in paragraph (3) of this subsection (d), subject
6    to the limits specified in paragraph (2) of this
7    subsection (d). It is the goal of the State that by January
8    1, 2025, 25% of the electricity used in the State shall be
9    generated by cost-effective clean coal facilities. For
10    purposes of this subsection (d), "cost-effective" means
11    that the expenditures pursuant to such sourcing agreements
12    do not cause the limit stated in paragraph (2) of this
13    subsection (d) to be exceeded and do not exceed cost-based
14    benchmarks, which shall be developed to assess all
15    expenditures pursuant to such sourcing agreements covering
16    electricity generated by clean coal facilities, other than
17    the initial clean coal facility, by the procurement
18    administrator, in consultation with the Commission staff,
19    Agency staff, and the procurement monitor and shall be
20    subject to Commission review and approval.
21        A utility party to a sourcing agreement shall
22    immediately retire any emission credits that it receives
23    in connection with the electricity covered by such
24    agreement.
25        Utilities shall maintain adequate records documenting
26    the purchases under the sourcing agreement to comply with

 

 

10200HB1747ham001- 59 -LRB102 12090 SPS 23532 a

1    this subsection (d) and shall file an accounting with the
2    load forecast that must be filed with the Agency by July 15
3    of each year, in accordance with subsection (d) of Section
4    16-111.5 of the Public Utilities Act.
5        A utility shall be deemed to have complied with the
6    clean coal portfolio standard specified in this subsection
7    (d) if the utility enters into a sourcing agreement as
8    required by this subsection (d).
9        (2) For purposes of this subsection (d), the required
10    execution of sourcing agreements with the initial clean
11    coal facility for a particular year shall be measured as a
12    percentage of the actual amount of electricity
13    (megawatt-hours) supplied by the electric utility to
14    eligible retail customers in the planning year ending
15    immediately prior to the agreement's execution. For
16    purposes of this subsection (d), the amount paid per
17    kilowatthour means the total amount paid for electric
18    service expressed on a per kilowatthour basis. For
19    purposes of this subsection (d), the total amount paid for
20    electric service includes without limitation amounts paid
21    for supply, transmission, distribution, surcharges and
22    add-on taxes.
23        Notwithstanding the requirements of this subsection
24    (d), the total amount paid under sourcing agreements with
25    clean coal facilities pursuant to the procurement plan for
26    any given year shall be reduced by an amount necessary to

 

 

10200HB1747ham001- 60 -LRB102 12090 SPS 23532 a

1    limit the annual estimated average net increase due to the
2    costs of these resources included in the amounts paid by
3    eligible retail customers in connection with electric
4    service to:
5            (A) in 2010, no more than 0.5% of the amount paid
6        per kilowatthour by those customers during the year
7        ending May 31, 2009;
8            (B) in 2011, the greater of an additional 0.5% of
9        the amount paid per kilowatthour by those customers
10        during the year ending May 31, 2010 or 1% of the amount
11        paid per kilowatthour by those customers during the
12        year ending May 31, 2009;
13            (C) in 2012, the greater of an additional 0.5% of
14        the amount paid per kilowatthour by those customers
15        during the year ending May 31, 2011 or 1.5% of the
16        amount paid per kilowatthour by those customers during
17        the year ending May 31, 2009;
18            (D) in 2013, the greater of an additional 0.5% of
19        the amount paid per kilowatthour by those customers
20        during the year ending May 31, 2012 or 2% of the amount
21        paid per kilowatthour by those customers during the
22        year ending May 31, 2009; and
23            (E) thereafter, the total amount paid under
24        sourcing agreements with clean coal facilities
25        pursuant to the procurement plan for any single year
26        shall be reduced by an amount necessary to limit the

 

 

10200HB1747ham001- 61 -LRB102 12090 SPS 23532 a

1        estimated average net increase due to the cost of
2        these resources included in the amounts paid by
3        eligible retail customers in connection with electric
4        service to no more than the greater of (i) 2.015% of
5        the amount paid per kilowatthour by those customers
6        during the year ending May 31, 2009 or (ii) the
7        incremental amount per kilowatthour paid for these
8        resources in 2013. These requirements may be altered
9        only as provided by statute.
10        No later than June 30, 2015, the Commission shall
11    review the limitation on the total amount paid under
12    sourcing agreements, if any, with clean coal facilities
13    pursuant to this subsection (d) and report to the General
14    Assembly its findings as to whether that limitation unduly
15    constrains the amount of electricity generated by
16    cost-effective clean coal facilities that is covered by
17    sourcing agreements.
18        (3) Initial clean coal facility. In order to promote
19    development of clean coal facilities in Illinois, each
20    electric utility subject to this Section shall execute a
21    sourcing agreement to source electricity from a proposed
22    clean coal facility in Illinois (the "initial clean coal
23    facility") that will have a nameplate capacity of at least
24    500 MW when commercial operation commences, that has a
25    final Clean Air Act permit on June 1, 2009 (the effective
26    date of Public Act 95-1027), and that will meet the

 

 

10200HB1747ham001- 62 -LRB102 12090 SPS 23532 a

1    definition of clean coal facility in Section 1-10 of this
2    Act when commercial operation commences. The sourcing
3    agreements with this initial clean coal facility shall be
4    subject to both approval of the initial clean coal
5    facility by the General Assembly and satisfaction of the
6    requirements of paragraph (4) of this subsection (d) and
7    shall be executed within 90 days after any such approval
8    by the General Assembly. The Agency and the Commission
9    shall have authority to inspect all books and records
10    associated with the initial clean coal facility during the
11    term of such a sourcing agreement. A utility's sourcing
12    agreement for electricity produced by the initial clean
13    coal facility shall include:
14            (A) a formula contractual price (the "contract
15        price") approved pursuant to paragraph (4) of this
16        subsection (d), which shall:
17                (i) be determined using a cost of service
18            methodology employing either a level or deferred
19            capital recovery component, based on a capital
20            structure consisting of 45% equity and 55% debt,
21            and a return on equity as may be approved by the
22            Federal Energy Regulatory Commission, which in any
23            case may not exceed the lower of 11.5% or the rate
24            of return approved by the General Assembly
25            pursuant to paragraph (4) of this subsection (d);
26            and

 

 

10200HB1747ham001- 63 -LRB102 12090 SPS 23532 a

1                (ii) provide that all miscellaneous net
2            revenue, including but not limited to net revenue
3            from the sale of emission allowances, if any,
4            substitute natural gas, if any, grants or other
5            support provided by the State of Illinois or the
6            United States Government, firm transmission
7            rights, if any, by-products produced by the
8            facility, energy or capacity derived from the
9            facility and not covered by a sourcing agreement
10            pursuant to paragraph (3) of this subsection (d)
11            or item (5) of subsection (d) of Section 16-115 of
12            the Public Utilities Act, whether generated from
13            the synthesis gas derived from coal, from SNG, or
14            from natural gas, shall be credited against the
15            revenue requirement for this initial clean coal
16            facility;
17            (B) power purchase provisions, which shall:
18                (i) provide that the utility party to such
19            sourcing agreement shall pay the contract price
20            for electricity delivered under such sourcing
21            agreement;
22                (ii) require delivery of electricity to the
23            regional transmission organization market of the
24            utility that is party to such sourcing agreement;
25                (iii) require the utility party to such
26            sourcing agreement to buy from the initial clean

 

 

10200HB1747ham001- 64 -LRB102 12090 SPS 23532 a

1            coal facility in each hour an amount of energy
2            equal to all clean coal energy made available from
3            the initial clean coal facility during such hour
4            times a fraction, the numerator of which is such
5            utility's retail market sales of electricity
6            (expressed in kilowatthours sold) in the State
7            during the prior calendar month and the
8            denominator of which is the total retail market
9            sales of electricity (expressed in kilowatthours
10            sold) in the State by utilities during such prior
11            month and the sales of electricity (expressed in
12            kilowatthours sold) in the State by alternative
13            retail electric suppliers during such prior month
14            that are subject to the requirements of this
15            subsection (d) and paragraph (5) of subsection (d)
16            of Section 16-115 of the Public Utilities Act,
17            provided that the amount purchased by the utility
18            in any year will be limited by paragraph (2) of
19            this subsection (d); and
20                (iv) be considered pre-existing contracts in
21            such utility's procurement plans for eligible
22            retail customers;
23            (C) contract for differences provisions, which
24        shall:
25                (i) require the utility party to such sourcing
26            agreement to contract with the initial clean coal

 

 

10200HB1747ham001- 65 -LRB102 12090 SPS 23532 a

1            facility in each hour with respect to an amount of
2            energy equal to all clean coal energy made
3            available from the initial clean coal facility
4            during such hour times a fraction, the numerator
5            of which is such utility's retail market sales of
6            electricity (expressed in kilowatthours sold) in
7            the utility's service territory in the State
8            during the prior calendar month and the
9            denominator of which is the total retail market
10            sales of electricity (expressed in kilowatthours
11            sold) in the State by utilities during such prior
12            month and the sales of electricity (expressed in
13            kilowatthours sold) in the State by alternative
14            retail electric suppliers during such prior month
15            that are subject to the requirements of this
16            subsection (d) and paragraph (5) of subsection (d)
17            of Section 16-115 of the Public Utilities Act,
18            provided that the amount paid by the utility in
19            any year will be limited by paragraph (2) of this
20            subsection (d);
21                (ii) provide that the utility's payment
22            obligation in respect of the quantity of
23            electricity determined pursuant to the preceding
24            clause (i) shall be limited to an amount equal to
25            (1) the difference between the contract price
26            determined pursuant to subparagraph (A) of

 

 

10200HB1747ham001- 66 -LRB102 12090 SPS 23532 a

1            paragraph (3) of this subsection (d) and the
2            day-ahead price for electricity delivered to the
3            regional transmission organization market of the
4            utility that is party to such sourcing agreement
5            (or any successor delivery point at which such
6            utility's supply obligations are financially
7            settled on an hourly basis) (the "reference
8            price") on the day preceding the day on which the
9            electricity is delivered to the initial clean coal
10            facility busbar, multiplied by (2) the quantity of
11            electricity determined pursuant to the preceding
12            clause (i); and
13                (iii) not require the utility to take physical
14            delivery of the electricity produced by the
15            facility;
16            (D) general provisions, which shall:
17                (i) specify a term of no more than 30 years,
18            commencing on the commercial operation date of the
19            facility;
20                (ii) provide that utilities shall maintain
21            adequate records documenting purchases under the
22            sourcing agreements entered into to comply with
23            this subsection (d) and shall file an accounting
24            with the load forecast that must be filed with the
25            Agency by July 15 of each year, in accordance with
26            subsection (d) of Section 16-111.5 of the Public

 

 

10200HB1747ham001- 67 -LRB102 12090 SPS 23532 a

1            Utilities Act;
2                (iii) provide that all costs associated with
3            the initial clean coal facility will be
4            periodically reported to the Federal Energy
5            Regulatory Commission and to purchasers in
6            accordance with applicable laws governing
7            cost-based wholesale power contracts;
8                (iv) permit the Illinois Power Agency to
9            assume ownership of the initial clean coal
10            facility, without monetary consideration and
11            otherwise on reasonable terms acceptable to the
12            Agency, if the Agency so requests no less than 3
13            years prior to the end of the stated contract
14            term;
15                (v) require the owner of the initial clean
16            coal facility to provide documentation to the
17            Commission each year, starting in the facility's
18            first year of commercial operation, accurately
19            reporting the quantity of carbon emissions from
20            the facility that have been captured and
21            sequestered and report any quantities of carbon
22            released from the site or sites at which carbon
23            emissions were sequestered in prior years, based
24            on continuous monitoring of such sites. If, in any
25            year after the first year of commercial operation,
26            the owner of the facility fails to demonstrate

 

 

10200HB1747ham001- 68 -LRB102 12090 SPS 23532 a

1            that the initial clean coal facility captured and
2            sequestered at least 50% of the total carbon
3            emissions that the facility would otherwise emit
4            or that sequestration of emissions from prior
5            years has failed, resulting in the release of
6            carbon dioxide into the atmosphere, the owner of
7            the facility must offset excess emissions. Any
8            such carbon offsets must be permanent, additional,
9            verifiable, real, located within the State of
10            Illinois, and legally and practicably enforceable.
11            The cost of such offsets for the facility that are
12            not recoverable shall not exceed $15 million in
13            any given year. No costs of any such purchases of
14            carbon offsets may be recovered from a utility or
15            its customers. All carbon offsets purchased for
16            this purpose and any carbon emission credits
17            associated with sequestration of carbon from the
18            facility must be permanently retired. The initial
19            clean coal facility shall not forfeit its
20            designation as a clean coal facility if the
21            facility fails to fully comply with the applicable
22            carbon sequestration requirements in any given
23            year, provided the requisite offsets are
24            purchased. However, the Attorney General, on
25            behalf of the People of the State of Illinois, may
26            specifically enforce the facility's sequestration

 

 

10200HB1747ham001- 69 -LRB102 12090 SPS 23532 a

1            requirement and the other terms of this contract
2            provision. Compliance with the sequestration
3            requirements and offset purchase requirements
4            specified in paragraph (3) of this subsection (d)
5            shall be reviewed annually by an independent
6            expert retained by the owner of the initial clean
7            coal facility, with the advance written approval
8            of the Attorney General. The Commission may, in
9            the course of the review specified in item (vii),
10            reduce the allowable return on equity for the
11            facility if the facility willfully fails to comply
12            with the carbon capture and sequestration
13            requirements set forth in this item (v);
14                (vi) include limits on, and accordingly
15            provide for modification of, the amount the
16            utility is required to source under the sourcing
17            agreement consistent with paragraph (2) of this
18            subsection (d);
19                (vii) require Commission review: (1) to
20            determine the justness, reasonableness, and
21            prudence of the inputs to the formula referenced
22            in subparagraphs (A)(i) through (A)(iii) of
23            paragraph (3) of this subsection (d), prior to an
24            adjustment in those inputs including, without
25            limitation, the capital structure and return on
26            equity, fuel costs, and other operations and

 

 

10200HB1747ham001- 70 -LRB102 12090 SPS 23532 a

1            maintenance costs and (2) to approve the costs to
2            be passed through to customers under the sourcing
3            agreement by which the utility satisfies its
4            statutory obligations. Commission review shall
5            occur no less than every 3 years, regardless of
6            whether any adjustments have been proposed, and
7            shall be completed within 9 months;
8                (viii) limit the utility's obligation to such
9            amount as the utility is allowed to recover
10            through tariffs filed with the Commission,
11            provided that neither the clean coal facility nor
12            the utility waives any right to assert federal
13            pre-emption or any other argument in response to a
14            purported disallowance of recovery costs;
15                (ix) limit the utility's or alternative retail
16            electric supplier's obligation to incur any
17            liability until such time as the facility is in
18            commercial operation and generating power and
19            energy and such power and energy is being
20            delivered to the facility busbar;
21                (x) provide that the owner or owners of the
22            initial clean coal facility, which is the
23            counterparty to such sourcing agreement, shall
24            have the right from time to time to elect whether
25            the obligations of the utility party thereto shall
26            be governed by the power purchase provisions or

 

 

10200HB1747ham001- 71 -LRB102 12090 SPS 23532 a

1            the contract for differences provisions;
2                (xi) append documentation showing that the
3            formula rate and contract, insofar as they relate
4            to the power purchase provisions, have been
5            approved by the Federal Energy Regulatory
6            Commission pursuant to Section 205 of the Federal
7            Power Act;
8                (xii) provide that any changes to the terms of
9            the contract, insofar as such changes relate to
10            the power purchase provisions, are subject to
11            review under the public interest standard applied
12            by the Federal Energy Regulatory Commission
13            pursuant to Sections 205 and 206 of the Federal
14            Power Act; and
15                (xiii) conform with customary lender
16            requirements in power purchase agreements used as
17            the basis for financing non-utility generators.
18        (4) Effective date of sourcing agreements with the
19    initial clean coal facility. Any proposed sourcing
20    agreement with the initial clean coal facility shall not
21    become effective unless the following reports are prepared
22    and submitted and authorizations and approvals obtained:
23            (i) Facility cost report. The owner of the initial
24        clean coal facility shall submit to the Commission,
25        the Agency, and the General Assembly a front-end
26        engineering and design study, a facility cost report,

 

 

10200HB1747ham001- 72 -LRB102 12090 SPS 23532 a

1        method of financing (including but not limited to
2        structure and associated costs), and an operating and
3        maintenance cost quote for the facility (collectively
4        "facility cost report"), which shall be prepared in
5        accordance with the requirements of this paragraph (4)
6        of subsection (d) of this Section, and shall provide
7        the Commission and the Agency access to the work
8        papers, relied upon documents, and any other backup
9        documentation related to the facility cost report.
10            (ii) Commission report. Within 6 months following
11        receipt of the facility cost report, the Commission,
12        in consultation with the Agency, shall submit a report
13        to the General Assembly setting forth its analysis of
14        the facility cost report. Such report shall include,
15        but not be limited to, a comparison of the costs
16        associated with electricity generated by the initial
17        clean coal facility to the costs associated with
18        electricity generated by other types of generation
19        facilities, an analysis of the rate impacts on
20        residential and small business customers over the life
21        of the sourcing agreements, and an analysis of the
22        likelihood that the initial clean coal facility will
23        commence commercial operation by and be delivering
24        power to the facility's busbar by 2016. To assist in
25        the preparation of its report, the Commission, in
26        consultation with the Agency, may hire one or more

 

 

10200HB1747ham001- 73 -LRB102 12090 SPS 23532 a

1        experts or consultants, the costs of which shall be
2        paid for by the owner of the initial clean coal
3        facility. The Commission and Agency may begin the
4        process of selecting such experts or consultants prior
5        to receipt of the facility cost report.
6            (iii) General Assembly approval. The proposed
7        sourcing agreements shall not take effect unless,
8        based on the facility cost report and the Commission's
9        report, the General Assembly enacts authorizing
10        legislation approving (A) the projected price, stated
11        in cents per kilowatthour, to be charged for
12        electricity generated by the initial clean coal
13        facility, (B) the projected impact on residential and
14        small business customers' bills over the life of the
15        sourcing agreements, and (C) the maximum allowable
16        return on equity for the project; and
17            (iv) Commission review. If the General Assembly
18        enacts authorizing legislation pursuant to
19        subparagraph (iii) approving a sourcing agreement, the
20        Commission shall, within 90 days of such enactment,
21        complete a review of such sourcing agreement. During
22        such time period, the Commission shall implement any
23        directive of the General Assembly, resolve any
24        disputes between the parties to the sourcing agreement
25        concerning the terms of such agreement, approve the
26        form of such agreement, and issue an order finding

 

 

10200HB1747ham001- 74 -LRB102 12090 SPS 23532 a

1        that the sourcing agreement is prudent and reasonable.
2        The facility cost report shall be prepared as follows:
3            (A) The facility cost report shall be prepared by
4        duly licensed engineering and construction firms
5        detailing the estimated capital costs payable to one
6        or more contractors or suppliers for the engineering,
7        procurement and construction of the components
8        comprising the initial clean coal facility and the
9        estimated costs of operation and maintenance of the
10        facility. The facility cost report shall include:
11                (i) an estimate of the capital cost of the
12            core plant based on one or more front end
13            engineering and design studies for the
14            gasification island and related facilities. The
15            core plant shall include all civil, structural,
16            mechanical, electrical, control, and safety
17            systems.
18                (ii) an estimate of the capital cost of the
19            balance of the plant, including any capital costs
20            associated with sequestration of carbon dioxide
21            emissions and all interconnects and interfaces
22            required to operate the facility, such as
23            transmission of electricity, construction or
24            backfeed power supply, pipelines to transport
25            substitute natural gas or carbon dioxide, potable
26            water supply, natural gas supply, water supply,

 

 

10200HB1747ham001- 75 -LRB102 12090 SPS 23532 a

1            water discharge, landfill, access roads, and coal
2            delivery.
3            The quoted construction costs shall be expressed
4        in nominal dollars as of the date that the quote is
5        prepared and shall include capitalized financing costs
6        during construction, taxes, insurance, and other
7        owner's costs, and an assumed escalation in materials
8        and labor beyond the date as of which the construction
9        cost quote is expressed.
10            (B) The front end engineering and design study for
11        the gasification island and the cost study for the
12        balance of plant shall include sufficient design work
13        to permit quantification of major categories of
14        materials, commodities and labor hours, and receipt of
15        quotes from vendors of major equipment required to
16        construct and operate the clean coal facility.
17            (C) The facility cost report shall also include an
18        operating and maintenance cost quote that will provide
19        the estimated cost of delivered fuel, personnel,
20        maintenance contracts, chemicals, catalysts,
21        consumables, spares, and other fixed and variable
22        operations and maintenance costs. The delivered fuel
23        cost estimate will be provided by a recognized third
24        party expert or experts in the fuel and transportation
25        industries. The balance of the operating and
26        maintenance cost quote, excluding delivered fuel

 

 

10200HB1747ham001- 76 -LRB102 12090 SPS 23532 a

1        costs, will be developed based on the inputs provided
2        by duly licensed engineering and construction firms
3        performing the construction cost quote, potential
4        vendors under long-term service agreements and plant
5        operating agreements, or recognized third party plant
6        operator or operators.
7            The operating and maintenance cost quote
8        (including the cost of the front end engineering and
9        design study) shall be expressed in nominal dollars as
10        of the date that the quote is prepared and shall
11        include taxes, insurance, and other owner's costs, and
12        an assumed escalation in materials and labor beyond
13        the date as of which the operating and maintenance
14        cost quote is expressed.
15            (D) The facility cost report shall also include an
16        analysis of the initial clean coal facility's ability
17        to deliver power and energy into the applicable
18        regional transmission organization markets and an
19        analysis of the expected capacity factor for the
20        initial clean coal facility.
21            (E) Amounts paid to third parties unrelated to the
22        owner or owners of the initial clean coal facility to
23        prepare the core plant construction cost quote,
24        including the front end engineering and design study,
25        and the operating and maintenance cost quote will be
26        reimbursed through Coal Development Bonds.

 

 

10200HB1747ham001- 77 -LRB102 12090 SPS 23532 a

1        (5) Re-powering and retrofitting coal-fired power
2    plants previously owned by Illinois utilities to qualify
3    as clean coal facilities. During the 2009 procurement
4    planning process and thereafter, the Agency and the
5    Commission shall consider sourcing agreements covering
6    electricity generated by power plants that were previously
7    owned by Illinois utilities and that have been or will be
8    converted into clean coal facilities, as defined by
9    Section 1-10 of this Act. Pursuant to such procurement
10    planning process, the owners of such facilities may
11    propose to the Agency sourcing agreements with utilities
12    and alternative retail electric suppliers required to
13    comply with subsection (d) of this Section and item (5) of
14    subsection (d) of Section 16-115 of the Public Utilities
15    Act, covering electricity generated by such facilities. In
16    the case of sourcing agreements that are power purchase
17    agreements, the contract price for electricity sales shall
18    be established on a cost of service basis. In the case of
19    sourcing agreements that are contracts for differences,
20    the contract price from which the reference price is
21    subtracted shall be established on a cost of service
22    basis. The Agency and the Commission may approve any such
23    utility sourcing agreements that do not exceed cost-based
24    benchmarks developed by the procurement administrator, in
25    consultation with the Commission staff, Agency staff and
26    the procurement monitor, subject to Commission review and

 

 

10200HB1747ham001- 78 -LRB102 12090 SPS 23532 a

1    approval. The Commission shall have authority to inspect
2    all books and records associated with these clean coal
3    facilities during the term of any such contract.
4        (6) Costs incurred under this subsection (d) or
5    pursuant to a contract entered into under this subsection
6    (d) shall be deemed prudently incurred and reasonable in
7    amount and the electric utility shall be entitled to full
8    cost recovery pursuant to the tariffs filed with the
9    Commission.
10    (d-5) Zero emission standard.
11        (1) Beginning with the delivery year commencing on
12    June 1, 2017, the Agency shall, for electric utilities
13    that serve at least 100,000 retail customers in this
14    State, procure contracts with zero emission facilities
15    that are reasonably capable of generating cost-effective
16    zero emission credits in an amount approximately equal to
17    16% of the actual amount of electricity delivered by each
18    electric utility to retail customers in the State during
19    calendar year 2014. For an electric utility serving fewer
20    than 100,000 retail customers in this State that
21    requested, under Section 16-111.5 of the Public Utilities
22    Act, that the Agency procure power and energy for all or a
23    portion of the utility's Illinois load for the delivery
24    year commencing June 1, 2016, the Agency shall procure
25    contracts with zero emission facilities that are
26    reasonably capable of generating cost-effective zero

 

 

10200HB1747ham001- 79 -LRB102 12090 SPS 23532 a

1    emission credits in an amount approximately equal to 16%
2    of the portion of power and energy to be procured by the
3    Agency for the utility. The duration of the contracts
4    procured under this subsection (d-5) shall be for a term
5    of 10 years ending May 31, 2027. The quantity of zero
6    emission credits to be procured under the contracts shall
7    be all of the zero emission credits generated by the zero
8    emission facility in each delivery year; however, if the
9    zero emission facility is owned by more than one entity,
10    then the quantity of zero emission credits to be procured
11    under the contracts shall be the amount of zero emission
12    credits that are generated from the portion of the zero
13    emission facility that is owned by the winning supplier.
14        The 16% value identified in this paragraph (1) is the
15    average of the percentage targets in subparagraph (B) of
16    paragraph (1) of subsection (c) of this Section for the 5
17    delivery years beginning June 1, 2017.
18        The procurement process shall be subject to the
19    following provisions:
20            (A) Those zero emission facilities that intend to
21        participate in the procurement shall submit to the
22        Agency the following eligibility information for each
23        zero emission facility on or before the date
24        established by the Agency:
25                (i) the in-service date and remaining useful
26            life of the zero emission facility;

 

 

10200HB1747ham001- 80 -LRB102 12090 SPS 23532 a

1                (ii) the amount of power generated annually
2            for each of the years 2005 through 2015, and the
3            projected zero emission credits to be generated
4            over the remaining useful life of the zero
5            emission facility, which shall be used to
6            determine the capability of each facility;
7                (iii) the annual zero emission facility cost
8            projections, expressed on a per megawatthour
9            basis, over the next 6 delivery years, which shall
10            include the following: operation and maintenance
11            expenses; fully allocated overhead costs, which
12            shall be allocated using the methodology developed
13            by the Institute for Nuclear Power Operations;
14            fuel expenditures; non-fuel capital expenditures;
15            spent fuel expenditures; a return on working
16            capital; the cost of operational and market risks
17            that could be avoided by ceasing operation; and
18            any other costs necessary for continued
19            operations, provided that "necessary" means, for
20            purposes of this item (iii), that the costs could
21            reasonably be avoided only by ceasing operations
22            of the zero emission facility; and
23                (iv) a commitment to continue operating, for
24            the duration of the contract or contracts executed
25            under the procurement held under this subsection
26            (d-5), the zero emission facility that produces

 

 

10200HB1747ham001- 81 -LRB102 12090 SPS 23532 a

1            the zero emission credits to be procured in the
2            procurement.
3            The information described in item (iii) of this
4        subparagraph (A) may be submitted on a confidential
5        basis and shall be treated and maintained by the
6        Agency, the procurement administrator, and the
7        Commission as confidential and proprietary and exempt
8        from disclosure under subparagraphs (a) and (g) of
9        paragraph (1) of Section 7 of the Freedom of
10        Information Act. The Office of Attorney General shall
11        have access to, and maintain the confidentiality of,
12        such information pursuant to Section 6.5 of the
13        Attorney General Act.
14            (B) The price for each zero emission credit
15        procured under this subsection (d-5) for each delivery
16        year shall be in an amount that equals the Social Cost
17        of Carbon, expressed on a price per megawatthour
18        basis. However, to ensure that the procurement remains
19        affordable to retail customers in this State if
20        electricity prices increase, the price in an
21        applicable delivery year shall be reduced below the
22        Social Cost of Carbon by the amount ("Price
23        Adjustment") by which the market price index for the
24        applicable delivery year exceeds the baseline market
25        price index for the consecutive 12-month period ending
26        May 31, 2016. If the Price Adjustment is greater than

 

 

10200HB1747ham001- 82 -LRB102 12090 SPS 23532 a

1        or equal to the Social Cost of Carbon in an applicable
2        delivery year, then no payments shall be due in that
3        delivery year. The components of this calculation are
4        defined as follows:
5                (i) Social Cost of Carbon: The Social Cost of
6            Carbon is $16.50 per megawatthour, which is based
7            on the U.S. Interagency Working Group on Social
8            Cost of Carbon's price in the August 2016
9            Technical Update using a 3% discount rate,
10            adjusted for inflation for each year of the
11            program. Beginning with the delivery year
12            commencing June 1, 2023, the price per
13            megawatthour shall increase by $1 per
14            megawatthour, and continue to increase by an
15            additional $1 per megawatthour each delivery year
16            thereafter.
17                (ii) Baseline market price index: The baseline
18            market price index for the consecutive 12-month
19            period ending May 31, 2016 is $31.40 per
20            megawatthour, which is based on the sum of (aa)
21            the average day-ahead energy price across all
22            hours of such 12-month period at the PJM
23            Interconnection LLC Northern Illinois Hub, (bb)
24            50% multiplied by the Base Residual Auction, or
25            its successor, capacity price for the rest of the
26            RTO zone group determined by PJM Interconnection

 

 

10200HB1747ham001- 83 -LRB102 12090 SPS 23532 a

1            LLC, divided by 24 hours per day, and (cc) 50%
2            multiplied by the Planning Resource Auction, or
3            its successor, capacity price for Zone 4
4            determined by the Midcontinent Independent System
5            Operator, Inc., divided by 24 hours per day.
6                (iii) Market price index: The market price
7            index for a delivery year shall be the sum of
8            projected energy prices and projected capacity
9            prices determined as follows:
10                    (aa) Projected energy prices: the
11                projected energy prices for the applicable
12                delivery year shall be calculated once for the
13                year using the forward market price for the
14                PJM Interconnection, LLC Northern Illinois
15                Hub. The forward market price shall be
16                calculated as follows: the energy forward
17                prices for each month of the applicable
18                delivery year averaged for each trade date
19                during the calendar year immediately preceding
20                that delivery year to produce a single energy
21                forward price for the delivery year. The
22                forward market price calculation shall use
23                data published by the Intercontinental
24                Exchange, or its successor.
25                    (bb) Projected capacity prices:
26                        (I) For the delivery years commencing

 

 

10200HB1747ham001- 84 -LRB102 12090 SPS 23532 a

1                    June 1, 2017, June 1, 2018, and June 1,
2                    2019, the projected capacity price shall
3                    be equal to the sum of (1) 50% multiplied
4                    by the Base Residual Auction, or its
5                    successor, price for the rest of the RTO
6                    zone group as determined by PJM
7                    Interconnection LLC, divided by 24 hours
8                    per day and, (2) 50% multiplied by the
9                    resource auction price determined in the
10                    resource auction administered by the
11                    Midcontinent Independent System Operator,
12                    Inc., in which the largest percentage of
13                    load cleared for Local Resource Zone 4,
14                    divided by 24 hours per day, and where
15                    such price is determined by the
16                    Midcontinent Independent System Operator,
17                    Inc.
18                        (II) For the delivery year commencing
19                    June 1, 2020, and each year thereafter,
20                    the projected capacity price shall be
21                    equal to the sum of (1) 50% multiplied by
22                    the Base Residual Auction, or its
23                    successor, price for the ComEd zone as
24                    determined by PJM Interconnection LLC,
25                    divided by 24 hours per day, and (2) 50%
26                    multiplied by the resource auction price

 

 

10200HB1747ham001- 85 -LRB102 12090 SPS 23532 a

1                    determined in the resource auction
2                    administered by the Midcontinent
3                    Independent System Operator, Inc., in
4                    which the largest percentage of load
5                    cleared for Local Resource Zone 4, divided
6                    by 24 hours per day, and where such price
7                    is determined by the Midcontinent
8                    Independent System Operator, Inc.
9            For purposes of this subsection (d-5):
10                "Rest of the RTO" and "ComEd Zone" shall have
11            the meaning ascribed to them by PJM
12            Interconnection, LLC.
13                "RTO" means regional transmission
14            organization.
15            (C) No later than 45 days after June 1, 2017 (the
16        effective date of Public Act 99-906), the Agency shall
17        publish its proposed zero emission standard
18        procurement plan. The plan shall be consistent with
19        the provisions of this paragraph (1) and shall provide
20        that winning bids shall be selected based on public
21        interest criteria that include, but are not limited
22        to, minimizing carbon dioxide emissions that result
23        from electricity consumed in Illinois and minimizing
24        sulfur dioxide, nitrogen oxide, and particulate matter
25        emissions that adversely affect the citizens of this
26        State. In particular, the selection of winning bids

 

 

10200HB1747ham001- 86 -LRB102 12090 SPS 23532 a

1        shall take into account the incremental environmental
2        benefits resulting from the procurement, such as any
3        existing environmental benefits that are preserved by
4        the procurements held under Public Act 99-906 and
5        would cease to exist if the procurements were not
6        held, including the preservation of zero emission
7        facilities. The plan shall also describe in detail how
8        each public interest factor shall be considered and
9        weighted in the bid selection process to ensure that
10        the public interest criteria are applied to the
11        procurement and given full effect.
12            For purposes of developing the plan, the Agency
13        shall consider any reports issued by a State agency,
14        board, or commission under House Resolution 1146 of
15        the 98th General Assembly and paragraph (4) of
16        subsection (d) of this Section, as well as publicly
17        available analyses and studies performed by or for
18        regional transmission organizations that serve the
19        State and their independent market monitors.
20            Upon publishing of the zero emission standard
21        procurement plan, copies of the plan shall be posted
22        and made publicly available on the Agency's website.
23        All interested parties shall have 10 days following
24        the date of posting to provide comment to the Agency on
25        the plan. All comments shall be posted to the Agency's
26        website. Following the end of the comment period, but

 

 

10200HB1747ham001- 87 -LRB102 12090 SPS 23532 a

1        no more than 60 days later than June 1, 2017 (the
2        effective date of Public Act 99-906), the Agency shall
3        revise the plan as necessary based on the comments
4        received and file its zero emission standard
5        procurement plan with the Commission.
6            If the Commission determines that the plan will
7        result in the procurement of cost-effective zero
8        emission credits, then the Commission shall, after
9        notice and hearing, but no later than 45 days after the
10        Agency filed the plan, approve the plan or approve
11        with modification. For purposes of this subsection
12        (d-5), "cost effective" means the projected costs of
13        procuring zero emission credits from zero emission
14        facilities do not cause the limit stated in paragraph
15        (2) of this subsection to be exceeded.
16            (C-5) As part of the Commission's review and
17        acceptance or rejection of the procurement results,
18        the Commission shall, in its public notice of
19        successful bidders:
20                (i) identify how the winning bids satisfy the
21            public interest criteria described in subparagraph
22            (C) of this paragraph (1) of minimizing carbon
23            dioxide emissions that result from electricity
24            consumed in Illinois and minimizing sulfur
25            dioxide, nitrogen oxide, and particulate matter
26            emissions that adversely affect the citizens of

 

 

10200HB1747ham001- 88 -LRB102 12090 SPS 23532 a

1            this State;
2                (ii) specifically address how the selection of
3            winning bids takes into account the incremental
4            environmental benefits resulting from the
5            procurement, including any existing environmental
6            benefits that are preserved by the procurements
7            held under Public Act 99-906 and would have ceased
8            to exist if the procurements had not been held,
9            such as the preservation of zero emission
10            facilities;
11                (iii) quantify the environmental benefit of
12            preserving the resources identified in item (ii)
13            of this subparagraph (C-5), including the
14            following:
15                    (aa) the value of avoided greenhouse gas
16                emissions measured as the product of the zero
17                emission facilities' output over the contract
18                term multiplied by the U.S. Environmental
19                Protection Agency eGrid subregion carbon
20                dioxide emission rate and the U.S. Interagency
21                Working Group on Social Cost of Carbon's price
22                in the August 2016 Technical Update using a 3%
23                discount rate, adjusted for inflation for each
24                delivery year; and
25                    (bb) the costs of replacement with other
26                zero carbon dioxide resources, including wind

 

 

10200HB1747ham001- 89 -LRB102 12090 SPS 23532 a

1                and photovoltaic, based upon the simple
2                average of the following:
3                        (I) the price, or if there is more
4                    than one price, the average of the prices,
5                    paid for renewable energy credits from new
6                    utility-scale wind projects in the
7                    procurement events specified in item (i)
8                    of subparagraph (G) of paragraph (1) of
9                    subsection (c) of this Section; and
10                        (II) the price, or if there is more
11                    than one price, the average of the prices,
12                    paid for renewable energy credits from new
13                    utility-scale solar projects and
14                    brownfield site photovoltaic projects in
15                    the procurement events specified in item
16                    (ii) of subparagraph (G) of paragraph (1)
17                    of subsection (c) of this Section and,
18                    after January 1, 2015, renewable energy
19                    credits from photovoltaic distributed
20                    generation projects in procurement events
21                    held under subsection (c) of this Section.
22            Each utility shall enter into binding contractual
23        arrangements with the winning suppliers.
24            The procurement described in this subsection
25        (d-5), including, but not limited to, the execution of
26        all contracts procured, shall be completed no later

 

 

10200HB1747ham001- 90 -LRB102 12090 SPS 23532 a

1        than May 10, 2017. Based on the effective date of
2        Public Act 99-906, the Agency and Commission may, as
3        appropriate, modify the various dates and timelines
4        under this subparagraph and subparagraphs (C) and (D)
5        of this paragraph (1). The procurement and plan
6        approval processes required by this subsection (d-5)
7        shall be conducted in conjunction with the procurement
8        and plan approval processes required by subsection (c)
9        of this Section and Section 16-111.5 of the Public
10        Utilities Act, to the extent practicable.
11        Notwithstanding whether a procurement event is
12        conducted under Section 16-111.5 of the Public
13        Utilities Act, the Agency shall immediately initiate a
14        procurement process on June 1, 2017 (the effective
15        date of Public Act 99-906).
16            (D) Following the procurement event described in
17        this paragraph (1) and consistent with subparagraph
18        (B) of this paragraph (1), the Agency shall calculate
19        the payments to be made under each contract for the
20        next delivery year based on the market price index for
21        that delivery year. The Agency shall publish the
22        payment calculations no later than May 25, 2017 and
23        every May 25 thereafter.
24            (E) Notwithstanding the requirements of this
25        subsection (d-5), the contracts executed under this
26        subsection (d-5) shall provide that the zero emission

 

 

10200HB1747ham001- 91 -LRB102 12090 SPS 23532 a

1        facility may, as applicable, suspend or terminate
2        performance under the contracts in the following
3        instances:
4                (i) A zero emission facility shall be excused
5            from its performance under the contract for any
6            cause beyond the control of the resource,
7            including, but not restricted to, acts of God,
8            flood, drought, earthquake, storm, fire,
9            lightning, epidemic, war, riot, civil disturbance
10            or disobedience, labor dispute, labor or material
11            shortage, sabotage, acts of public enemy,
12            explosions, orders, regulations or restrictions
13            imposed by governmental, military, or lawfully
14            established civilian authorities, which, in any of
15            the foregoing cases, by exercise of commercially
16            reasonable efforts the zero emission facility
17            could not reasonably have been expected to avoid,
18            and which, by the exercise of commercially
19            reasonable efforts, it has been unable to
20            overcome. In such event, the zero emission
21            facility shall be excused from performance for the
22            duration of the event, including, but not limited
23            to, delivery of zero emission credits, and no
24            payment shall be due to the zero emission facility
25            during the duration of the event.
26                (ii) A zero emission facility shall be

 

 

10200HB1747ham001- 92 -LRB102 12090 SPS 23532 a

1            permitted to terminate the contract if legislation
2            is enacted into law by the General Assembly that
3            imposes or authorizes a new tax, special
4            assessment, or fee on the generation of
5            electricity, the ownership or leasehold of a
6            generating unit, or the privilege or occupation of
7            such generation, ownership, or leasehold of
8            generation units by a zero emission facility.
9            However, the provisions of this item (ii) do not
10            apply to any generally applicable tax, special
11            assessment or fee, or requirements imposed by
12            federal law.
13                (iii) A zero emission facility shall be
14            permitted to terminate the contract in the event
15            that the resource requires capital expenditures in
16            excess of $40,000,000 that were neither known nor
17            reasonably foreseeable at the time it executed the
18            contract and that a prudent owner or operator of
19            such resource would not undertake.
20                (iv) A zero emission facility shall be
21            permitted to terminate the contract in the event
22            the Nuclear Regulatory Commission terminates the
23            resource's license.
24            (F) If the zero emission facility elects to
25        terminate a contract under subparagraph (E) of this
26        paragraph (1), then the Commission shall reopen the

 

 

10200HB1747ham001- 93 -LRB102 12090 SPS 23532 a

1        docket in which the Commission approved the zero
2        emission standard procurement plan under subparagraph
3        (C) of this paragraph (1) and, after notice and
4        hearing, enter an order acknowledging the contract
5        termination election if such termination is consistent
6        with the provisions of this subsection (d-5).
7        (2) For purposes of this subsection (d-5), the amount
8    paid per kilowatthour means the total amount paid for
9    electric service expressed on a per kilowatthour basis.
10    For purposes of this subsection (d-5), the total amount
11    paid for electric service includes, without limitation,
12    amounts paid for supply, transmission, distribution,
13    surcharges, and add-on taxes.
14        Notwithstanding the requirements of this subsection
15    (d-5), the contracts executed under this subsection (d-5)
16    shall provide that the total of zero emission credits
17    procured under a procurement plan shall be subject to the
18    limitations of this paragraph (2). For each delivery year,
19    the contractual volume receiving payments in such year
20    shall be reduced for all retail customers based on the
21    amount necessary to limit the net increase that delivery
22    year to the costs of those credits included in the amounts
23    paid by eligible retail customers in connection with
24    electric service to no more than 1.65% of the amount paid
25    per kilowatthour by eligible retail customers during the
26    year ending May 31, 2009. The result of this computation

 

 

10200HB1747ham001- 94 -LRB102 12090 SPS 23532 a

1    shall apply to and reduce the procurement for all retail
2    customers, and all those customers shall pay the same
3    single, uniform cents per kilowatthour charge under
4    subsection (k) of Section 16-108 of the Public Utilities
5    Act. To arrive at a maximum dollar amount of zero emission
6    credits to be paid for the particular delivery year, the
7    resulting per kilowatthour amount shall be applied to the
8    actual amount of kilowatthours of electricity delivered by
9    the electric utility in the delivery year immediately
10    prior to the procurement, to all retail customers in its
11    service territory. Unpaid contractual volume for any
12    delivery year shall be paid in any subsequent delivery
13    year in which such payments can be made without exceeding
14    the amount specified in this paragraph (2). The
15    calculations required by this paragraph (2) shall be made
16    only once for each procurement plan year. Once the
17    determination as to the amount of zero emission credits to
18    be paid is made based on the calculations set forth in this
19    paragraph (2), no subsequent rate impact determinations
20    shall be made and no adjustments to those contract amounts
21    shall be allowed. All costs incurred under those contracts
22    and in implementing this subsection (d-5) shall be
23    recovered by the electric utility as provided in this
24    Section.
25        No later than June 30, 2019, the Commission shall
26    review the limitation on the amount of zero emission

 

 

10200HB1747ham001- 95 -LRB102 12090 SPS 23532 a

1    credits procured under this subsection (d-5) and report to
2    the General Assembly its findings as to whether that
3    limitation unduly constrains the procurement of
4    cost-effective zero emission credits.
5        (3) Six years after the execution of a contract under
6    this subsection (d-5), the Agency shall determine whether
7    the actual zero emission credit payments received by the
8    supplier over the 6-year period exceed the Average ZEC
9    Payment. In addition, at the end of the term of a contract
10    executed under this subsection (d-5), or at the time, if
11    any, a zero emission facility's contract is terminated
12    under subparagraph (E) of paragraph (1) of this subsection
13    (d-5), then the Agency shall determine whether the actual
14    zero emission credit payments received by the supplier
15    over the term of the contract exceed the Average ZEC
16    Payment, after taking into account any amounts previously
17    credited back to the utility under this paragraph (3). If
18    the Agency determines that the actual zero emission credit
19    payments received by the supplier over the relevant period
20    exceed the Average ZEC Payment, then the supplier shall
21    credit the difference back to the utility. The amount of
22    the credit shall be remitted to the applicable electric
23    utility no later than 120 days after the Agency's
24    determination, which the utility shall reflect as a credit
25    on its retail customer bills as soon as practicable;
26    however, the credit remitted to the utility shall not

 

 

10200HB1747ham001- 96 -LRB102 12090 SPS 23532 a

1    exceed the total amount of payments received by the
2    facility under its contract.
3        For purposes of this Section, the Average ZEC Payment
4    shall be calculated by multiplying the quantity of zero
5    emission credits delivered under the contract times the
6    average contract price. The average contract price shall
7    be determined by subtracting the amount calculated under
8    subparagraph (B) of this paragraph (3) from the amount
9    calculated under subparagraph (A) of this paragraph (3),
10    as follows:
11            (A) The average of the Social Cost of Carbon, as
12        defined in subparagraph (B) of paragraph (1) of this
13        subsection (d-5), during the term of the contract.
14            (B) The average of the market price indices, as
15        defined in subparagraph (B) of paragraph (1) of this
16        subsection (d-5), during the term of the contract,
17        minus the baseline market price index, as defined in
18        subparagraph (B) of paragraph (1) of this subsection
19        (d-5).
20        If the subtraction yields a negative number, then the
21    Average ZEC Payment shall be zero.
22        (4) Cost-effective zero emission credits procured from
23    zero emission facilities shall satisfy the applicable
24    definitions set forth in Section 1-10 of this Act.
25        (5) The electric utility shall retire all zero
26    emission credits used to comply with the requirements of

 

 

10200HB1747ham001- 97 -LRB102 12090 SPS 23532 a

1    this subsection (d-5).
2        (6) Electric utilities shall be entitled to recover
3    all of the costs associated with the procurement of zero
4    emission credits through an automatic adjustment clause
5    tariff in accordance with subsection (k) and (m) of
6    Section 16-108 of the Public Utilities Act, and the
7    contracts executed under this subsection (d-5) shall
8    provide that the utilities' payment obligations under such
9    contracts shall be reduced if an adjustment is required
10    under subsection (m) of Section 16-108 of the Public
11    Utilities Act.
12        (7) This subsection (d-5) shall become inoperative on
13    January 1, 2028.
14    (e) The draft procurement plans are subject to public
15comment, as required by Section 16-111.5 of the Public
16Utilities Act.
17    (f) The Agency shall submit the final procurement plan to
18the Commission. The Agency shall revise a procurement plan if
19the Commission determines that it does not meet the standards
20set forth in Section 16-111.5 of the Public Utilities Act.
21    (g) The Agency shall assess fees to each affected utility
22to recover the costs incurred in preparation of the annual
23procurement plan for the utility.
24    (h) The Agency shall assess fees to each bidder to recover
25the costs incurred in connection with a competitive
26procurement process.

 

 

10200HB1747ham001- 98 -LRB102 12090 SPS 23532 a

1    (i) A renewable energy credit, carbon emission credit, or
2zero emission credit can only be used once to comply with a
3single portfolio or other standard as set forth in subsection
4(c), subsection (d), or subsection (d-5) of this Section,
5respectively. A renewable energy credit, carbon emission
6credit, or zero emission credit cannot be used to satisfy the
7requirements of more than one standard. If more than one type
8of credit is issued for the same megawatt hour of energy, only
9one credit can be used to satisfy the requirements of a single
10standard. After such use, the credit must be retired together
11with any other credits issued for the same megawatt hour of
12energy.
13(Source: P.A. 100-863, eff. 8-14-18; 101-81, eff. 7-12-19;
14101-113, eff. 1-1-20.)
 
15    Section 10. The Public Utilities Act is amended by
16changing Sections 16-108, 16-111.5, and 16-115D as follows:
 
17    (220 ILCS 5/16-108)
18    Sec. 16-108. Recovery of costs associated with the
19provision of delivery and other services.
20    (a) An electric utility shall file a delivery services
21tariff with the Commission at least 210 days prior to the date
22that it is required to begin offering such services pursuant
23to this Act. An electric utility shall provide the components
24of delivery services that are subject to the jurisdiction of

 

 

10200HB1747ham001- 99 -LRB102 12090 SPS 23532 a

1the Federal Energy Regulatory Commission at the same prices,
2terms and conditions set forth in its applicable tariff as
3approved or allowed into effect by that Commission. The
4Commission shall otherwise have the authority pursuant to
5Article IX to review, approve, and modify the prices, terms
6and conditions of those components of delivery services not
7subject to the jurisdiction of the Federal Energy Regulatory
8Commission, including the authority to determine the extent to
9which such delivery services should be offered on an unbundled
10basis. In making any such determination the Commission shall
11consider, at a minimum, the effect of additional unbundling on
12(i) the objective of just and reasonable rates, (ii) electric
13utility employees, and (iii) the development of competitive
14markets for electric energy services in Illinois.
15    (b) The Commission shall enter an order approving, or
16approving as modified, the delivery services tariff no later
17than 30 days prior to the date on which the electric utility
18must commence offering such services. The Commission may
19subsequently modify such tariff pursuant to this Act.
20    (c) The electric utility's tariffs shall define the
21classes of its customers for purposes of delivery services
22charges. Delivery services shall be priced and made available
23to all retail customers electing delivery services in each
24such class on a nondiscriminatory basis regardless of whether
25the retail customer chooses the electric utility, an affiliate
26of the electric utility, or another entity as its supplier of

 

 

10200HB1747ham001- 100 -LRB102 12090 SPS 23532 a

1electric power and energy. Charges for delivery services shall
2be cost based, and shall allow the electric utility to recover
3the costs of providing delivery services through its charges
4to its delivery service customers that use the facilities and
5services associated with such costs. Such costs shall include
6the costs of owning, operating and maintaining transmission
7and distribution facilities. The Commission shall also be
8authorized to consider whether, and if so to what extent, the
9following costs are appropriately included in the electric
10utility's delivery services rates: (i) the costs of that
11portion of generation facilities used for the production and
12absorption of reactive power in order that retail customers
13located in the electric utility's service area can receive
14electric power and energy from suppliers other than the
15electric utility, and (ii) the costs associated with the use
16and redispatch of generation facilities to mitigate
17constraints on the transmission or distribution system in
18order that retail customers located in the electric utility's
19service area can receive electric power and energy from
20suppliers other than the electric utility. Nothing in this
21subsection shall be construed as directing the Commission to
22allocate any of the costs described in (i) or (ii) that are
23found to be appropriately included in the electric utility's
24delivery services rates to any particular customer group or
25geographic area in setting delivery services rates.
26    (d) The Commission shall establish charges, terms and

 

 

10200HB1747ham001- 101 -LRB102 12090 SPS 23532 a

1conditions for delivery services that are just and reasonable
2and shall take into account customer impacts when establishing
3such charges. In establishing charges, terms and conditions
4for delivery services, the Commission shall take into account
5voltage level differences. A retail customer shall have the
6option to request to purchase electric service at any delivery
7service voltage reasonably and technically feasible from the
8electric facilities serving that customer's premises provided
9that there are no significant adverse impacts upon system
10reliability or system efficiency. A retail customer shall also
11have the option to request to purchase electric service at any
12point of delivery that is reasonably and technically feasible
13provided that there are no significant adverse impacts on
14system reliability or efficiency. Such requests shall not be
15unreasonably denied.
16    (e) Electric utilities shall recover the costs of
17installing, operating or maintaining facilities for the
18particular benefit of one or more delivery services customers,
19including without limitation any costs incurred in complying
20with a customer's request to be served at a different voltage
21level, directly from the retail customer or customers for
22whose benefit the costs were incurred, to the extent such
23costs are not recovered through the charges referred to in
24subsections (c) and (d) of this Section.
25    (f) An electric utility shall be entitled but not required
26to implement transition charges in conjunction with the

 

 

10200HB1747ham001- 102 -LRB102 12090 SPS 23532 a

1offering of delivery services pursuant to Section 16-104. If
2an electric utility implements transition charges, it shall
3implement such charges for all delivery services customers and
4for all customers described in subsection (h), but shall not
5implement transition charges for power and energy that a
6retail customer takes from cogeneration or self-generation
7facilities located on that retail customer's premises, if such
8facilities meet the following criteria:
9        (i) the cogeneration or self-generation facilities
10    serve a single retail customer and are located on that
11    retail customer's premises (for purposes of this
12    subparagraph and subparagraph (ii), an industrial or
13    manufacturing retail customer and a third party contractor
14    that is served by such industrial or manufacturing
15    customer through such retail customer's own electrical
16    distribution facilities under the circumstances described
17    in subsection (vi) of the definition of "alternative
18    retail electric supplier" set forth in Section 16-102,
19    shall be considered a single retail customer);
20        (ii) the cogeneration or self-generation facilities
21    either (A) are sized pursuant to generally accepted
22    engineering standards for the retail customer's electrical
23    load at that premises (taking into account standby or
24    other reliability considerations related to that retail
25    customer's operations at that site) or (B) if the facility
26    is a cogeneration facility located on the retail

 

 

10200HB1747ham001- 103 -LRB102 12090 SPS 23532 a

1    customer's premises, the retail customer is the thermal
2    host for that facility and the facility has been designed
3    to meet that retail customer's thermal energy requirements
4    resulting in electrical output beyond that retail
5    customer's electrical demand at that premises, comply with
6    the operating and efficiency standards applicable to
7    "qualifying facilities" specified in title 18 Code of
8    Federal Regulations Section 292.205 as in effect on the
9    effective date of this amendatory Act of 1999;
10        (iii) the retail customer on whose premises the
11    facilities are located either has an exclusive right to
12    receive, and corresponding obligation to pay for, all of
13    the electrical capacity of the facility, or in the case of
14    a cogeneration facility that has been designed to meet the
15    retail customer's thermal energy requirements at that
16    premises, an identified amount of the electrical capacity
17    of the facility, over a minimum 5-year period; and
18        (iv) if the cogeneration facility is sized for the
19    retail customer's thermal load at that premises but
20    exceeds the electrical load, any sales of excess power or
21    energy are made only at wholesale, are subject to the
22    jurisdiction of the Federal Energy Regulatory Commission,
23    and are not for the purpose of circumventing the
24    provisions of this subsection (f).
25If a generation facility located at a retail customer's
26premises does not meet the above criteria, an electric utility

 

 

10200HB1747ham001- 104 -LRB102 12090 SPS 23532 a

1implementing transition charges shall implement a transition
2charge until December 31, 2006 for any power and energy taken
3by such retail customer from such facility as if such power and
4energy had been delivered by the electric utility. Provided,
5however, that an industrial retail customer that is taking
6power from a generation facility that does not meet the above
7criteria but that is located on such customer's premises will
8not be subject to a transition charge for the power and energy
9taken by such retail customer from such generation facility if
10the facility does not serve any other retail customer and
11either was installed on behalf of the customer and for its own
12use prior to January 1, 1997, or is both predominantly fueled
13by byproducts of such customer's manufacturing process at such
14premises and sells or offers an average of 300 megawatts or
15more of electricity produced from such generation facility
16into the wholesale market. Such charges shall be calculated as
17provided in Section 16-102, and shall be collected on each
18kilowatt-hour delivered under a delivery services tariff to a
19retail customer from the date the customer first takes
20delivery services until December 31, 2006 except as provided
21in subsection (h) of this Section. Provided, however, that an
22electric utility, other than an electric utility providing
23service to at least 1,000,000 customers in this State on
24January 1, 1999, shall be entitled to petition for entry of an
25order by the Commission authorizing the electric utility to
26implement transition charges for an additional period ending

 

 

10200HB1747ham001- 105 -LRB102 12090 SPS 23532 a

1no later than December 31, 2008. The electric utility shall
2file its petition with supporting evidence no earlier than 16
3months, and no later than 12 months, prior to December 31,
42006. The Commission shall hold a hearing on the electric
5utility's petition and shall enter its order no later than 8
6months after the petition is filed. The Commission shall
7determine whether and to what extent the electric utility
8shall be authorized to implement transition charges for an
9additional period. The Commission may authorize the electric
10utility to implement transition charges for some or all of the
11additional period, and shall determine the mitigation factors
12to be used in implementing such transition charges; provided,
13that the Commission shall not authorize mitigation factors
14less than 110% of those in effect during the 12 months ended
15December 31, 2006. In making its determination, the Commission
16shall consider the following factors: the necessity to
17implement transition charges for an additional period in order
18to maintain the financial integrity of the electric utility;
19the prudence of the electric utility's actions in reducing its
20costs since the effective date of this amendatory Act of 1997;
21the ability of the electric utility to provide safe, adequate
22and reliable service to retail customers in its service area;
23and the impact on competition of allowing the electric utility
24to implement transition charges for the additional period.
25    (g) The electric utility shall file tariffs that establish
26the transition charges to be paid by each class of customers to

 

 

10200HB1747ham001- 106 -LRB102 12090 SPS 23532 a

1the electric utility in conjunction with the provision of
2delivery services. The electric utility's tariffs shall define
3the classes of its customers for purposes of calculating
4transition charges. The electric utility's tariffs shall
5provide for the calculation of transition charges on a
6customer-specific basis for any retail customer whose average
7monthly maximum electrical demand on the electric utility's
8system during the 6 months with the customer's highest monthly
9maximum electrical demands equals or exceeds 3.0 megawatts for
10electric utilities having more than 1,000,000 customers, and
11for other electric utilities for any customer that has an
12average monthly maximum electrical demand on the electric
13utility's system of one megawatt or more, and (A) for which
14there exists data on the customer's usage during the 3 years
15preceding the date that the customer became eligible to take
16delivery services, or (B) for which there does not exist data
17on the customer's usage during the 3 years preceding the date
18that the customer became eligible to take delivery services,
19if in the electric utility's reasonable judgment there exists
20comparable usage information or a sufficient basis to develop
21such information, and further provided that the electric
22utility can require customers for which an individual
23calculation is made to sign contracts that set forth the
24transition charges to be paid by the customer to the electric
25utility pursuant to the tariff.
26    (h) An electric utility shall also be entitled to file

 

 

10200HB1747ham001- 107 -LRB102 12090 SPS 23532 a

1tariffs that allow it to collect transition charges from
2retail customers in the electric utility's service area that
3do not take delivery services but that take electric power or
4energy from an alternative retail electric supplier or from an
5electric utility other than the electric utility in whose
6service area the customer is located. Such charges shall be
7calculated, in accordance with the definition of transition
8charges in Section 16-102, for the period of time that the
9customer would be obligated to pay transition charges if it
10were taking delivery services, except that no deduction for
11delivery services revenues shall be made in such calculation,
12and usage data from the customer's class shall be used where
13historical usage data is not available for the individual
14customer. The customer shall be obligated to pay such charges
15on a lump sum basis on or before the date on which the customer
16commences to take service from the alternative retail electric
17supplier or other electric utility, provided, that the
18electric utility in whose service area the customer is located
19shall offer the customer the option of signing a contract
20pursuant to which the customer pays such charges ratably over
21the period in which the charges would otherwise have applied.
22    (i) An electric utility shall be entitled to add to the
23bills of delivery services customers charges pursuant to
24Sections 9-221, 9-222 (except as provided in Section 9-222.1),
25and Section 16-114 of this Act, Section 5-5 of the Electricity
26Infrastructure Maintenance Fee Law, Section 6-5 of the

 

 

10200HB1747ham001- 108 -LRB102 12090 SPS 23532 a

1Renewable Energy, Energy Efficiency, and Coal Resources
2Development Law of 1997, and Section 13 of the Energy
3Assistance Act.
4    (j) If a retail customer that obtains electric power and
5energy from cogeneration or self-generation facilities
6installed for its own use on or before January 1, 1997,
7subsequently takes service from an alternative retail electric
8supplier or an electric utility other than the electric
9utility in whose service area the customer is located for any
10portion of the customer's electric power and energy
11requirements formerly obtained from those facilities
12(including that amount purchased from the utility in lieu of
13such generation and not as standby power purchases, under a
14cogeneration displacement tariff in effect as of the effective
15date of this amendatory Act of 1997), the transition charges
16otherwise applicable pursuant to subsections (f), (g), or (h)
17of this Section shall not be applicable in any year to that
18portion of the customer's electric power and energy
19requirements formerly obtained from those facilities,
20provided, that for purposes of this subsection (j), such
21portion shall not exceed the average number of kilowatt-hours
22per year obtained from the cogeneration or self-generation
23facilities during the 3 years prior to the date on which the
24customer became eligible for delivery services, except as
25provided in subsection (f) of Section 16-110.
26    (k) The electric utility shall be entitled to recover

 

 

10200HB1747ham001- 109 -LRB102 12090 SPS 23532 a

1through tariffed charges all of the costs associated with the
2purchase of zero emission credits from zero emission
3facilities to meet the requirements of subsection (d-5) of
4Section 1-75 of the Illinois Power Agency Act. Such costs
5shall include the costs of procuring the zero emission
6credits, as well as the reasonable costs that the utility
7incurs as part of the procurement processes and to implement
8and comply with plans and processes approved by the Commission
9under such subsection (d-5). The costs shall be allocated
10across all retail customers through a single, uniform cents
11per kilowatt-hour charge applicable to all retail customers,
12which shall appear as a separate line item on each customer's
13bill. Beginning June 1, 2017, the electric utility shall be
14entitled to recover through tariffed charges all of the costs
15associated with the purchase of renewable energy resources to
16meet the renewable energy resource standards of subsection (c)
17of Section 1-75 of the Illinois Power Agency Act, under
18procurement plans as approved in accordance with that Section
19and Section 16-111.5 of this Act. Such costs shall include the
20costs of procuring the renewable energy resources, as well as
21the reasonable costs that the utility incurs as part of the
22procurement processes and to implement and comply with plans
23and processes approved by the Commission under such Sections.
24The costs associated with the purchase of renewable energy
25resources shall be allocated across all retail customers in
26proportion to the amount of renewable energy resources the

 

 

10200HB1747ham001- 110 -LRB102 12090 SPS 23532 a

1utility procures for such customers through a single, uniform
2cents per kilowatt-hour charge applicable to such retail
3customers, which shall appear as a separate line item on each
4such customer's bill; however, the electric utility shall
5include an additional separate line item credit on the monthly
6bills of self-directing retail customers in the same amount to
7fully rebate to self-directing retail customers the costs
8associated with the purchase of renewable energy resources.
9    Notwithstanding whether the Commission has approved the
10initial long-term renewable resources procurement plan as of
11June 1, 2017, an electric utility shall place new tariffed
12charges into effect beginning with the June 2017 monthly
13billing period, to the extent practicable, to begin recovering
14the costs of procuring renewable energy resources, as those
15charges are calculated under the limitations described in
16subparagraph (E) of paragraph (1) of subsection (c) of Section
171-75 of the Illinois Power Agency Act. Notwithstanding the
18date on which the utility places such new tariffed charges
19into effect, the utility shall be permitted to collect the
20charges under such tariff as if the tariff had been in effect
21beginning with the first day of the June 2017 monthly billing
22period. For the delivery years commencing June 1, 2017, June
231, 2018, and June 1, 2019, the electric utility shall deposit
24into a separate interest bearing account of a financial
25institution the monies collected under the tariffed charges.
26Any interest earned shall be credited back to retail customers

 

 

10200HB1747ham001- 111 -LRB102 12090 SPS 23532 a

1under the reconciliation proceeding provided for in this
2subsection (k), provided that the electric utility shall first
3be reimbursed from the interest for the administrative costs
4that it incurs to administer and manage the account. Any taxes
5due on the funds in the account, or interest earned on it, will
6be paid from the account or, if insufficient monies are
7available in the account, from the monies collected under the
8tariffed charges to recover the costs of procuring renewable
9energy resources. Monies deposited in the account shall be
10subject to the review, reconciliation, and true-up process
11described in this subsection (k) that is applicable to the
12funds collected and costs incurred for the procurement of
13renewable energy resources.
14    The electric utility shall be entitled to recover all of
15the costs identified in this subsection (k) through automatic
16adjustment clause tariffs applicable to all of the utility's
17retail customers that allow the electric utility to adjust its
18tariffed charges consistent with this subsection (k). The
19determination as to whether any excess funds were collected
20during a given delivery year for the purchase of renewable
21energy resources, and the crediting of any excess funds back
22to retail customers, shall not be made until after the close of
23the delivery year, which will ensure that the maximum amount
24of funds is available to implement the approved long-term
25renewable resources procurement plan during a given delivery
26year. The electric utility's collections under such automatic

 

 

10200HB1747ham001- 112 -LRB102 12090 SPS 23532 a

1adjustment clause tariffs to recover the costs of renewable
2energy resources and zero emission credits from zero emission
3facilities shall be subject to separate annual review,
4reconciliation, and true-up against actual costs by the
5Commission under a procedure that shall be specified in the
6electric utility's automatic adjustment clause tariffs and
7that shall be approved by the Commission in connection with
8its approval of such tariffs. The procedure shall provide that
9any difference between the electric utility's collections
10under the automatic adjustment charges for an annual period
11and the electric utility's actual costs of renewable energy
12resources and zero emission credits from zero emission
13facilities for that same annual period shall be refunded to or
14collected from, as applicable, the electric utility's retail
15customers in subsequent periods.
16    Nothing in this subsection (k) is intended to affect,
17limit, or change the right of the electric utility to recover
18the costs associated with the procurement of renewable energy
19resources for periods commencing before, on, or after June 1,
202017, as otherwise provided in the Illinois Power Agency Act.
21    Notwithstanding anything to the contrary, the Commission
22shall not conduct an annual review, reconciliation, and
23true-up associated with renewable energy resources'
24collections and costs for the delivery years commencing June
251, 2017, June 1, 2018, June 1, 2019, and June 1, 2020, and
26shall instead conduct a single review, reconciliation, and

 

 

10200HB1747ham001- 113 -LRB102 12090 SPS 23532 a

1true-up associated with renewable energy resources'
2collections and costs for the 4-year period beginning June 1,
32017 and ending May 31, 2021, provided that the review,
4reconciliation, and true-up shall not be initiated until after
5August 31, 2021. During the 4-year period, the utility shall
6be permitted to collect and retain funds under this subsection
7(k) and to purchase renewable energy resources under an
8approved long-term renewable resources procurement plan using
9those funds regardless of the delivery year in which the funds
10were collected during the 4-year period.
11    If the amount of funds collected during the delivery year
12commencing June 1, 2017, exceeds the costs incurred during
13that delivery year, then up to half of this excess amount, as
14calculated on June 1, 2018, may be used to fund the programs
15under subsection (b) of Section 1-56 of the Illinois Power
16Agency Act in the same proportion the programs are funded
17under that subsection (b). However, any amount identified
18under this subsection (k) to fund programs under subsection
19(b) of Section 1-56 of the Illinois Power Agency Act shall be
20reduced if it exceeds the funding shortfall. For purposes of
21this Section, "funding shortfall" means the difference between
22$200,000,000 and the amount appropriated by the General
23Assembly to the Illinois Power Agency Renewable Energy
24Resources Fund during the period that commences on the
25effective date of this amendatory act of the 99th General
26Assembly and ends on August 1, 2018.

 

 

10200HB1747ham001- 114 -LRB102 12090 SPS 23532 a

1    If the amount of funds collected during the delivery year
2commencing June 1, 2018, exceeds the costs incurred during
3that delivery year, then up to half of this excess amount, as
4calculated on June 1, 2019, may be used to fund the programs
5under subsection (b) of Section 1-56 of the Illinois Power
6Agency Act in the same proportion the programs are funded
7under that subsection (b). However, any amount identified
8under this subsection (k) to fund programs under subsection
9(b) of Section 1-56 of the Illinois Power Agency Act shall be
10reduced if it exceeds the funding shortfall.
11    If the amount of funds collected during the delivery year
12commencing June 1, 2019, exceeds the costs incurred during
13that delivery year, then up to half of this excess amount, as
14calculated on June 1, 2020, may be used to fund the programs
15under subsection (b) of Section 1-56 of the Illinois Power
16Agency Act in the same proportion the programs are funded
17under that subsection (b). However, any amount identified
18under this subsection (k) to fund programs under subsection
19(b) of Section 1-56 of the Illinois Power Agency Act shall be
20reduced if it exceeds the funding shortfall.
21    The funding available under this subsection (k), if any,
22for the programs described under subsection (b) of Section
231-56 of the Illinois Power Agency Act shall not reduce the
24amount of funding for the programs described in subparagraph
25(O) of paragraph (1) of subsection (c) of Section 1-75 of the
26Illinois Power Agency Act. If funding is available under this

 

 

10200HB1747ham001- 115 -LRB102 12090 SPS 23532 a

1subsection (k) for programs described under subsection (b) of
2Section 1-56 of the Illinois Power Agency Act, then the
3long-term renewable resources plan shall provide for the
4Agency to procure contracts in an amount that does not exceed
5the funding, and the contracts approved by the Commission
6shall be executed by the applicable utility or utilities.
7    (l) A utility that has terminated any contract executed
8under subsection (d-5) of Section 1-75 of the Illinois Power
9Agency Act shall be entitled to recover any remaining balance
10associated with the purchase of zero emission credits prior to
11such termination, and such utility shall also apply a credit
12to its retail customer bills in the event of any
13over-collection.
14        (m)(1) An electric utility that recovers its costs of
15    procuring zero emission credits from zero emission
16    facilities through a cents-per-kilowatthour charge under
17    to subsection (k) of this Section shall be subject to the
18    requirements of this subsection (m). Notwithstanding
19    anything to the contrary, such electric utility shall,
20    beginning on April 30, 2018, and each April 30 thereafter
21    until April 30, 2026, calculate whether any reduction must
22    be applied to such cents-per-kilowatthour charge that is
23    paid by retail customers of the electric utility that are
24    exempt from subsections (a) through (j) of Section 8-103B
25    of this Act under subsection (l) of Section 8-103B. Such
26    charge shall be reduced for such customers for the next

 

 

10200HB1747ham001- 116 -LRB102 12090 SPS 23532 a

1    delivery year commencing on June 1 based on the amount
2    necessary, if any, to limit the annual estimated average
3    net increase for the prior calendar year due to the future
4    energy investment costs to no more than 1.3% of 5.98 cents
5    per kilowatt-hour, which is the average amount paid per
6    kilowatthour for electric service during the year ending
7    December 31, 2015 by Illinois industrial retail customers,
8    as reported to the Edison Electric Institute.
9        The calculations required by this subsection (m) shall
10    be made only once for each year, and no subsequent rate
11    impact determinations shall be made.
12        (2) For purposes of this Section, "future energy
13    investment costs" shall be calculated by subtracting the
14    cents-per-kilowatthour charge identified in subparagraph
15    (A) of this paragraph (2) from the sum of the
16    cents-per-kilowatthour charges identified in subparagraph
17    (B) of this paragraph (2):
18            (A) The cents-per-kilowatthour charge identified
19        in the electric utility's tariff placed into effect
20        under Section 8-103 of the Public Utilities Act that,
21        on December 1, 2016, was applicable to those retail
22        customers that are exempt from subsections (a) through
23        (j) of Section 8-103B of this Act under subsection (l)
24        of Section 8-103B.
25            (B) The sum of the following
26        cents-per-kilowatthour charges applicable to those

 

 

10200HB1747ham001- 117 -LRB102 12090 SPS 23532 a

1        retail customers that are exempt from subsections (a)
2        through (j) of Section 8-103B of this Act under
3        subsection (l) of Section 8-103B, provided that if one
4        or more of the following charges has been in effect and
5        applied to such customers for more than one calendar
6        year, then each charge shall be equal to the average of
7        the charges applied over a period that commences with
8        the calendar year ending December 31, 2017 and ends
9        with the most recently completed calendar year prior
10        to the calculation required by this subsection (m):
11                (i) the cents-per-kilowatthour charge to
12            recover the costs incurred by the utility under
13            subsection (d-5) of Section 1-75 of the Illinois
14            Power Agency Act, adjusted for any reductions
15            required under this subsection (m); and
16                (ii) the cents-per-kilowatthour charge to
17            recover the costs incurred by the utility under
18            Section 16-107.6 of the Public Utilities Act.
19            If no charge was applied for a given calendar year
20        under item (i) or (ii) of this subparagraph (B), then
21        the value of the charge for that year shall be zero.
22        (3) If a reduction is required by the calculation
23    performed under this subsection (m), then the amount of
24    the reduction shall be multiplied by the number of years
25    reflected in the averages calculated under subparagraph
26    (B) of paragraph (2) of this subsection (m). Such

 

 

10200HB1747ham001- 118 -LRB102 12090 SPS 23532 a

1    reduction shall be applied to the cents-per-kilowatthour
2    charge that is applicable to those retail customers that
3    are exempt from subsections (a) through (j) of Section
4    8-103B of this Act under subsection (l) of Section 8-103B
5    beginning with the next delivery year commencing after the
6    date of the calculation required by this subsection (m).
7        (4) The electric utility shall file a notice with the
8    Commission on May 1 of 2018 and each May 1 thereafter until
9    May 1, 2026 containing the reduction, if any, which must
10    be applied for the delivery year which begins in the year
11    of the filing. The notice shall contain the calculations
12    made pursuant to this Section. By October 1 of each year
13    beginning in 2018, each electric utility shall notify the
14    Commission if it appears, based on an estimate of the
15    calculation required in this subsection (m), that a
16    reduction will be required in the next year.
17(Source: P.A. 99-906, eff. 6-1-17.)
 
18    (220 ILCS 5/16-111.5)
19    Sec. 16-111.5. Provisions relating to procurement.
20    (a) An electric utility that on December 31, 2005 served
21at least 100,000 customers in Illinois shall procure power and
22energy for its eligible retail customers in accordance with
23the applicable provisions set forth in Section 1-75 of the
24Illinois Power Agency Act and this Section. Beginning with the
25delivery year commencing on June 1, 2017, such electric

 

 

10200HB1747ham001- 119 -LRB102 12090 SPS 23532 a

1utility shall also procure zero emission credits from zero
2emission facilities in accordance with the applicable
3provisions set forth in Section 1-75 of the Illinois Power
4Agency Act, and, for years beginning on or after June 1, 2017,
5the utility shall procure renewable energy resources in
6accordance with the applicable provisions set forth in Section
71-75 of the Illinois Power Agency Act and this Section, but
8shall not procure renewable energy resources for
9self-directing retail customers. A small multi-jurisdictional
10electric utility that on December 31, 2005 served less than
11100,000 customers in Illinois may elect to procure power and
12energy for all or a portion of its eligible Illinois retail
13customers in accordance with the applicable provisions set
14forth in this Section and Section 1-75 of the Illinois Power
15Agency Act. This Section shall not apply to a small
16multi-jurisdictional utility until such time as a small
17multi-jurisdictional utility requests the Illinois Power
18Agency to prepare a procurement plan for its eligible retail
19customers. "Eligible retail customers" for the purposes of
20this Section means those retail customers that purchase power
21and energy from the electric utility under fixed-price bundled
22service tariffs, other than those retail customers whose
23service is declared or deemed competitive under Section 16-113
24and those other customer groups specified in this Section,
25including self-generating customers, customers electing hourly
26pricing, or those customers who are otherwise ineligible for

 

 

10200HB1747ham001- 120 -LRB102 12090 SPS 23532 a

1fixed-price bundled tariff service. For those customers that
2are excluded from the procurement plan's electric supply
3service requirements, and the utility shall procure any supply
4requirements, including capacity, ancillary services, and
5hourly priced energy, in the applicable markets as needed to
6serve those customers, provided that the utility may include
7in its procurement plan load requirements for the load that is
8associated with those retail customers whose service has been
9declared or deemed competitive pursuant to Section 16-113 of
10this Act to the extent that those customers are purchasing
11power and energy during one of the transition periods
12identified in subsection (b) of Section 16-113 of this Act.
13    (b) A procurement plan shall be prepared for each electric
14utility consistent with the applicable requirements of the
15Illinois Power Agency Act and this Section. For purposes of
16this Section, Illinois electric utilities that are affiliated
17by virtue of a common parent company are considered to be a
18single electric utility. Small multi-jurisdictional utilities
19may request a procurement plan for a portion of or all of its
20Illinois load. Each procurement plan shall analyze the
21projected balance of supply and demand for those retail
22customers to be included in the plan's electric supply service
23requirements over a 5-year period, with the first planning
24year beginning on June 1 of the year following the year in
25which the plan is filed. The plan shall specifically identify
26the wholesale products to be procured following plan approval,

 

 

10200HB1747ham001- 121 -LRB102 12090 SPS 23532 a

1and shall follow all the requirements set forth in the Public
2Utilities Act and all applicable State and federal laws,
3statutes, rules, or regulations, as well as Commission orders.
4Nothing in this Section precludes consideration of contracts
5longer than 5 years and related forecast data. Unless
6specified otherwise in this Section, in the procurement plan
7or in the implementing tariff, any procurement occurring in
8accordance with this plan shall be competitively bid through a
9request for proposals process. Approval and implementation of
10the procurement plan shall be subject to review and approval
11by the Commission according to the provisions set forth in
12this Section. A procurement plan shall include each of the
13following components:
14        (1) Hourly load analysis. This analysis shall include:
15            (i) multi-year historical analysis of hourly
16        loads;
17            (ii) switching trends and competitive retail
18        market analysis;
19            (iii) known or projected changes to future loads;
20        and
21            (iv) growth forecasts by customer class.
22        (2) Analysis of the impact of any demand side and
23    renewable energy initiatives. This analysis shall include:
24            (i) the impact of demand response programs and
25        energy efficiency programs, both current and
26        projected; for small multi-jurisdictional utilities,

 

 

10200HB1747ham001- 122 -LRB102 12090 SPS 23532 a

1        the impact of demand response and energy efficiency
2        programs approved pursuant to Section 8-408 of this
3        Act, both current and projected; and
4            (ii) supply side needs that are projected to be
5        offset by purchases of renewable energy resources, if
6        any.
7        (3) A plan for meeting the expected load requirements
8    that will not be met through preexisting contracts. This
9    plan shall include:
10            (i) definitions of the different Illinois retail
11        customer classes for which supply is being purchased;
12            (ii) the proposed mix of demand-response products
13        for which contracts will be executed during the next
14        year. For small multi-jurisdictional electric
15        utilities that on December 31, 2005 served fewer than
16        100,000 customers in Illinois, these shall be defined
17        as demand-response products offered in an energy
18        efficiency plan approved pursuant to Section 8-408 of
19        this Act. The cost-effective demand-response measures
20        shall be procured whenever the cost is lower than
21        procuring comparable capacity products, provided that
22        such products shall:
23                (A) be procured by a demand-response provider
24            from those retail customers included in the plan's
25            electric supply service requirements;
26                (B) at least satisfy the demand-response

 

 

10200HB1747ham001- 123 -LRB102 12090 SPS 23532 a

1            requirements of the regional transmission
2            organization market in which the utility's service
3            territory is located, including, but not limited
4            to, any applicable capacity or dispatch
5            requirements;
6                (C) provide for customers' participation in
7            the stream of benefits produced by the
8            demand-response products;
9                (D) provide for reimbursement by the
10            demand-response provider of the utility for any
11            costs incurred as a result of the failure of the
12            supplier of such products to perform its
13            obligations thereunder; and
14                (E) meet the same credit requirements as apply
15            to suppliers of capacity, in the applicable
16            regional transmission organization market;
17            (iii) monthly forecasted system supply
18        requirements, including expected minimum, maximum, and
19        average values for the planning period;
20            (iv) the proposed mix and selection of standard
21        wholesale products for which contracts will be
22        executed during the next year, separately or in
23        combination, to meet that portion of its load
24        requirements not met through pre-existing contracts,
25        including but not limited to monthly 5 x 16 peak period
26        block energy, monthly off-peak wrap energy, monthly 7

 

 

10200HB1747ham001- 124 -LRB102 12090 SPS 23532 a

1        x 24 energy, annual 5 x 16 energy, annual off-peak wrap
2        energy, annual 7 x 24 energy, monthly capacity, annual
3        capacity, peak load capacity obligations, capacity
4        purchase plan, and ancillary services;
5            (v) proposed term structures for each wholesale
6        product type included in the proposed procurement plan
7        portfolio of products; and
8            (vi) an assessment of the price risk, load
9        uncertainty, and other factors that are associated
10        with the proposed procurement plan; this assessment,
11        to the extent possible, shall include an analysis of
12        the following factors: contract terms, time frames for
13        securing products or services, fuel costs, weather
14        patterns, transmission costs, market conditions, and
15        the governmental regulatory environment; the proposed
16        procurement plan shall also identify alternatives for
17        those portfolio measures that are identified as having
18        significant price risk.
19        (4) Proposed procedures for balancing loads. The
20    procurement plan shall include, for load requirements
21    included in the procurement plan, the process for (i)
22    hourly balancing of supply and demand and (ii) the
23    criteria for portfolio re-balancing in the event of
24    significant shifts in load.
25        (5) Long-Term Renewable Resources Procurement Plan.
26    The Agency shall prepare a long-term renewable resources

 

 

10200HB1747ham001- 125 -LRB102 12090 SPS 23532 a

1    procurement plan for the procurement of renewable energy
2    credits under Sections 1-56 and 1-75 of the Illinois Power
3    Agency Act for delivery beginning in the 2017 delivery
4    year.
5            (i) The initial long-term renewable resources
6        procurement plan and all subsequent revisions shall be
7        subject to review and approval by the Commission. For
8        the purposes of this Section, "delivery year" has the
9        same meaning as in Section 1-10 of the Illinois Power
10        Agency Act. For purposes of this Section, "Agency"
11        shall mean the Illinois Power Agency.
12            (ii) The long-term renewable resources planning
13        process shall be conducted as follows:
14                (A) Electric utilities shall provide a range
15            of load forecasts to the Illinois Power Agency
16            within 45 days of the Agency's request for
17            forecasts, which request shall specify the length
18            and conditions for the forecasts including, but
19            not limited to, the quantity of distributed
20            generation expected to be interconnected for each
21            year.
22                (B) The Agency shall publish for comment the
23            initial long-term renewable resources procurement
24            plan no later than 120 days after the effective
25            date of this amendatory Act of the 99th General
26            Assembly and shall review, and may revise, the

 

 

10200HB1747ham001- 126 -LRB102 12090 SPS 23532 a

1            plan at least every 2 years thereafter. To the
2            extent practicable, the Agency shall review and
3            propose any revisions to the long-term renewable
4            energy resources procurement plan in conjunction
5            with the Agency's other planning and approval
6            processes conducted under this Section. The
7            initial long-term renewable resources procurement
8            plan shall:
9                    (aa) Identify the procurement programs and
10                competitive procurement events consistent with
11                the applicable requirements of the Illinois
12                Power Agency Act and shall be designed to
13                achieve the goals set forth in subsection (c)
14                of Section 1-75 of that Act.
15                    (bb) Include a schedule for procurements
16                for renewable energy credits from
17                utility-scale wind projects, utility-scale
18                solar projects, and brownfield site
19                photovoltaic projects consistent with
20                subparagraph (G) of paragraph (1) of
21                subsection (c) of Section 1-75 of the Illinois
22                Power Agency Act.
23                    (cc) Identify the process whereby the
24                Agency will submit to the Commission for
25                review and approval the proposed contracts to
26                implement the programs required by such plan.

 

 

10200HB1747ham001- 127 -LRB102 12090 SPS 23532 a

1                Copies of the initial long-term renewable
2            resources procurement plan and all subsequent
3            revisions shall be posted and made publicly
4            available on the Agency's and Commission's
5            websites, and copies shall also be provided to
6            each affected electric utility. An affected
7            utility and other interested parties shall have 45
8            days following the date of posting to provide
9            comment to the Agency on the initial long-term
10            renewable resources procurement plan and all
11            subsequent revisions. All comments submitted to
12            the Agency shall be specific, supported by data or
13            other detailed analyses, and, if objecting to all
14            or a portion of the procurement plan, accompanied
15            by specific alternative wording or proposals. All
16            comments shall be posted on the Agency's and
17            Commission's websites. During this 45-day comment
18            period, the Agency shall hold at least one public
19            hearing within each utility's service area that is
20            subject to the requirements of this paragraph (5)
21            for the purpose of receiving public comment.
22            Within 21 days following the end of the 45-day
23            review period, the Agency may revise the long-term
24            renewable resources procurement plan based on the
25            comments received and shall file the plan with the
26            Commission for review and approval.

 

 

10200HB1747ham001- 128 -LRB102 12090 SPS 23532 a

1                (C) Within 14 days after the filing of the
2            initial long-term renewable resources procurement
3            plan or any subsequent revisions, any person
4            objecting to the plan may file an objection with
5            the Commission. Within 21 days after the filing of
6            the plan, the Commission shall determine whether a
7            hearing is necessary. The Commission shall enter
8            its order confirming or modifying the initial
9            long-term renewable resources procurement plan or
10            any subsequent revisions within 120 days after the
11            filing of the plan by the Illinois Power Agency.
12                (D) The Commission shall approve the initial
13            long-term renewable resources procurement plan and
14            any subsequent revisions, including expressly the
15            forecast used in the plan and taking into account
16            that funding will be limited to the amount of
17            revenues actually collected by the utilities, if
18            the Commission determines that the plan will
19            reasonably and prudently accomplish the
20            requirements of Section 1-56 and subsection (c) of
21            Section 1-75 of the Illinois Power Agency Act. The
22            Commission shall also approve the process for the
23            submission, review, and approval of the proposed
24            contracts to procure renewable energy credits or
25            implement the programs authorized by the
26            Commission pursuant to a long-term renewable

 

 

10200HB1747ham001- 129 -LRB102 12090 SPS 23532 a

1            resources procurement plan approved under this
2            Section.
3            (iii) The Agency or third parties contracted by
4        the Agency shall implement all programs authorized by
5        the Commission in an approved long-term renewable
6        resources procurement plan without further review and
7        approval by the Commission. Third parties shall not
8        begin implementing any programs or receive any payment
9        under this Section until the Commission has approved
10        the contract or contracts under the process authorized
11        by the Commission in item (D) of subparagraph (ii) of
12        paragraph (5) of this subsection (b) and the third
13        party and the Agency or utility, as applicable, have
14        executed the contract. For those renewable energy
15        credits subject to procurement through a competitive
16        bid process under the plan or under the initial
17        forward procurements for wind and solar resources
18        described in subparagraph (G) of paragraph (1) of
19        subsection (c) of Section 1-75 of the Illinois Power
20        Agency Act, the Agency shall follow the procurement
21        process specified in the provisions relating to
22        electricity procurement in subsections (e) through (i)
23        of this Section.
24            (iv) An electric utility shall recover its costs
25        associated with the procurement of renewable energy
26        credits under this Section through an automatic

 

 

10200HB1747ham001- 130 -LRB102 12090 SPS 23532 a

1        adjustment clause tariff under subsection (k) of
2        Section 16-108 of this Act. A utility shall not be
3        required to advance any payment or pay any amounts
4        under this Section that exceed the actual amount of
5        revenues collected by the utility under paragraph (6)
6        of subsection (c) of Section 1-75 of the Illinois
7        Power Agency Act and subsection (k) of Section 16-108
8        of this Act, and contracts executed under this Section
9        shall expressly incorporate this limitation.
10            (v) For the public interest, safety, and welfare,
11        the Agency and the Commission may adopt rules to carry
12        out the provisions of this Section on an emergency
13        basis immediately following the effective date of this
14        amendatory Act of the 99th General Assembly.
15            (vi) On or before July 1 of each year, the
16        Commission shall hold an informal hearing for the
17        purpose of receiving comments on the prior year's
18        procurement process and any recommendations for
19        change.
20    (c) The procurement process set forth in Section 1-75 of
21the Illinois Power Agency Act and subsection (e) of this
22Section shall be administered by a procurement administrator
23and monitored by a procurement monitor.
24        (1) The procurement administrator shall:
25            (i) design the final procurement process in
26        accordance with Section 1-75 of the Illinois Power

 

 

10200HB1747ham001- 131 -LRB102 12090 SPS 23532 a

1        Agency Act and subsection (e) of this Section
2        following Commission approval of the procurement plan;
3            (ii) develop benchmarks in accordance with
4        subsection (e)(3) to be used to evaluate bids; these
5        benchmarks shall be submitted to the Commission for
6        review and approval on a confidential basis prior to
7        the procurement event;
8            (iii) serve as the interface between the electric
9        utility and suppliers;
10            (iv) manage the bidder pre-qualification and
11        registration process;
12            (v) obtain the electric utilities' agreement to
13        the final form of all supply contracts and credit
14        collateral agreements;
15            (vi) administer the request for proposals process;
16            (vii) have the discretion to negotiate to
17        determine whether bidders are willing to lower the
18        price of bids that meet the benchmarks approved by the
19        Commission; any post-bid negotiations with bidders
20        shall be limited to price only and shall be completed
21        within 24 hours after opening the sealed bids and
22        shall be conducted in a fair and unbiased manner; in
23        conducting the negotiations, there shall be no
24        disclosure of any information derived from proposals
25        submitted by competing bidders; if information is
26        disclosed to any bidder, it shall be provided to all

 

 

10200HB1747ham001- 132 -LRB102 12090 SPS 23532 a

1        competing bidders;
2            (viii) maintain confidentiality of supplier and
3        bidding information in a manner consistent with all
4        applicable laws, rules, regulations, and tariffs;
5            (ix) submit a confidential report to the
6        Commission recommending acceptance or rejection of
7        bids;
8            (x) notify the utility of contract counterparties
9        and contract specifics; and
10            (xi) administer related contingency procurement
11        events.
12        (2) The procurement monitor, who shall be retained by
13    the Commission, shall:
14            (i) monitor interactions among the procurement
15        administrator, suppliers, and utility;
16            (ii) monitor and report to the Commission on the
17        progress of the procurement process;
18            (iii) provide an independent confidential report
19        to the Commission regarding the results of the
20        procurement event;
21            (iv) assess compliance with the procurement plans
22        approved by the Commission for each utility that on
23        December 31, 2005 provided electric service to at
24        least 100,000 customers in Illinois and for each small
25        multi-jurisdictional utility that on December 31, 2005
26        served less than 100,000 customers in Illinois;

 

 

10200HB1747ham001- 133 -LRB102 12090 SPS 23532 a

1            (v) preserve the confidentiality of supplier and
2        bidding information in a manner consistent with all
3        applicable laws, rules, regulations, and tariffs;
4            (vi) provide expert advice to the Commission and
5        consult with the procurement administrator regarding
6        issues related to procurement process design, rules,
7        protocols, and policy-related matters; and
8            (vii) consult with the procurement administrator
9        regarding the development and use of benchmark
10        criteria, standard form contracts, credit policies,
11        and bid documents.
12    (d) Except as provided in subsection (j), the planning
13process shall be conducted as follows:
14        (1) Beginning in 2008, each Illinois utility procuring
15    power pursuant to this Section shall annually provide a
16    range of load forecasts to the Illinois Power Agency by
17    July 15 of each year, or such other date as may be required
18    by the Commission or Agency. The load forecasts shall
19    cover the 5-year procurement planning period for the next
20    procurement plan and shall include hourly data
21    representing a high-load, low-load, and expected-load
22    scenario for the load of those retail customers included
23    in the plan's electric supply service requirements. The
24    utility shall provide supporting data and assumptions for
25    each of the scenarios.
26        (2) Beginning in 2008, the Illinois Power Agency shall

 

 

10200HB1747ham001- 134 -LRB102 12090 SPS 23532 a

1    prepare a procurement plan by August 15th of each year, or
2    such other date as may be required by the Commission. The
3    procurement plan shall identify the portfolio of
4    demand-response and power and energy products to be
5    procured. Cost-effective demand-response measures shall be
6    procured as set forth in item (iii) of subsection (b) of
7    this Section. Copies of the procurement plan shall be
8    posted and made publicly available on the Agency's and
9    Commission's websites, and copies shall also be provided
10    to each affected electric utility. An affected utility
11    shall have 30 days following the date of posting to
12    provide comment to the Agency on the procurement plan.
13    Other interested entities also may comment on the
14    procurement plan. All comments submitted to the Agency
15    shall be specific, supported by data or other detailed
16    analyses, and, if objecting to all or a portion of the
17    procurement plan, accompanied by specific alternative
18    wording or proposals. All comments shall be posted on the
19    Agency's and Commission's websites. During this 30-day
20    comment period, the Agency shall hold at least one public
21    hearing within each utility's service area for the purpose
22    of receiving public comment on the procurement plan.
23    Within 14 days following the end of the 30-day review
24    period, the Agency shall revise the procurement plan as
25    necessary based on the comments received and file the
26    procurement plan with the Commission and post the

 

 

10200HB1747ham001- 135 -LRB102 12090 SPS 23532 a

1    procurement plan on the websites.
2        (3) Within 5 days after the filing of the procurement
3    plan, any person objecting to the procurement plan shall
4    file an objection with the Commission. Within 10 days
5    after the filing, the Commission shall determine whether a
6    hearing is necessary. The Commission shall enter its order
7    confirming or modifying the procurement plan within 90
8    days after the filing of the procurement plan by the
9    Illinois Power Agency.
10        (4) The Commission shall approve the procurement plan,
11    including expressly the forecast used in the procurement
12    plan, if the Commission determines that it will ensure
13    adequate, reliable, affordable, efficient, and
14    environmentally sustainable electric service at the lowest
15    total cost over time, taking into account any benefits of
16    price stability.
17    (e) The procurement process shall include each of the
18following components:
19        (1) Solicitation, pre-qualification, and registration
20    of bidders. The procurement administrator shall
21    disseminate information to potential bidders to promote a
22    procurement event, notify potential bidders that the
23    procurement administrator may enter into a post-bid price
24    negotiation with bidders that meet the applicable
25    benchmarks, provide supply requirements, and otherwise
26    explain the competitive procurement process. In addition

 

 

10200HB1747ham001- 136 -LRB102 12090 SPS 23532 a

1    to such other publication as the procurement administrator
2    determines is appropriate, this information shall be
3    posted on the Illinois Power Agency's and the Commission's
4    websites. The procurement administrator shall also
5    administer the prequalification process, including
6    evaluation of credit worthiness, compliance with
7    procurement rules, and agreement to the standard form
8    contract developed pursuant to paragraph (2) of this
9    subsection (e). The procurement administrator shall then
10    identify and register bidders to participate in the
11    procurement event.
12        (2) Standard contract forms and credit terms and
13    instruments. The procurement administrator, in
14    consultation with the utilities, the Commission, and other
15    interested parties and subject to Commission oversight,
16    shall develop and provide standard contract forms for the
17    supplier contracts that meet generally accepted industry
18    practices. Standard credit terms and instruments that meet
19    generally accepted industry practices shall be similarly
20    developed. The procurement administrator shall make
21    available to the Commission all written comments it
22    receives on the contract forms, credit terms, or
23    instruments. If the procurement administrator cannot reach
24    agreement with the applicable electric utility as to the
25    contract terms and conditions, the procurement
26    administrator must notify the Commission of any disputed

 

 

10200HB1747ham001- 137 -LRB102 12090 SPS 23532 a

1    terms and the Commission shall resolve the dispute. The
2    terms of the contracts shall not be subject to negotiation
3    by winning bidders, and the bidders must agree to the
4    terms of the contract in advance so that winning bids are
5    selected solely on the basis of price.
6        (3) Establishment of a market-based price benchmark.
7    As part of the development of the procurement process, the
8    procurement administrator, in consultation with the
9    Commission staff, Agency staff, and the procurement
10    monitor, shall establish benchmarks for evaluating the
11    final prices in the contracts for each of the products
12    that will be procured through the procurement process. The
13    benchmarks shall be based on price data for similar
14    products for the same delivery period and same delivery
15    hub, or other delivery hubs after adjusting for that
16    difference. The price benchmarks may also be adjusted to
17    take into account differences between the information
18    reflected in the underlying data sources and the specific
19    products and procurement process being used to procure
20    power for the Illinois utilities. The benchmarks shall be
21    confidential but shall be provided to, and will be subject
22    to Commission review and approval, prior to a procurement
23    event.
24        (4) Request for proposals competitive procurement
25    process. The procurement administrator shall design and
26    issue a request for proposals to supply electricity in

 

 

10200HB1747ham001- 138 -LRB102 12090 SPS 23532 a

1    accordance with each utility's procurement plan, as
2    approved by the Commission. The request for proposals
3    shall set forth a procedure for sealed, binding commitment
4    bidding with pay-as-bid settlement, and provision for
5    selection of bids on the basis of price.
6        (5) A plan for implementing contingencies in the event
7    of supplier default or failure of the procurement process
8    to fully meet the expected load requirement due to
9    insufficient supplier participation, Commission rejection
10    of results, or any other cause.
11            (i) Event of supplier default: In the event of
12        supplier default, the utility shall review the
13        contract of the defaulting supplier to determine if
14        the amount of supply is 200 megawatts or greater, and
15        if there are more than 60 days remaining of the
16        contract term. If both of these conditions are met,
17        and the default results in termination of the
18        contract, the utility shall immediately notify the
19        Illinois Power Agency that a request for proposals
20        must be issued to procure replacement power, and the
21        procurement administrator shall run an additional
22        procurement event. If the contracted supply of the
23        defaulting supplier is less than 200 megawatts or
24        there are less than 60 days remaining of the contract
25        term, the utility shall procure power and energy from
26        the applicable regional transmission organization

 

 

10200HB1747ham001- 139 -LRB102 12090 SPS 23532 a

1        market, including ancillary services, capacity, and
2        day-ahead or real time energy, or both, for the
3        duration of the contract term to replace the
4        contracted supply; provided, however, that if a needed
5        product is not available through the regional
6        transmission organization market it shall be purchased
7        from the wholesale market.
8            (ii) Failure of the procurement process to fully
9        meet the expected load requirement: If the procurement
10        process fails to fully meet the expected load
11        requirement due to insufficient supplier participation
12        or due to a Commission rejection of the procurement
13        results, the procurement administrator, the
14        procurement monitor, and the Commission staff shall
15        meet within 10 days to analyze potential causes of low
16        supplier interest or causes for the Commission
17        decision. If changes are identified that would likely
18        result in increased supplier participation, or that
19        would address concerns causing the Commission to
20        reject the results of the prior procurement event, the
21        procurement administrator may implement those changes
22        and rerun the request for proposals process according
23        to a schedule determined by those parties and
24        consistent with Section 1-75 of the Illinois Power
25        Agency Act and this subsection. In any event, a new
26        request for proposals process shall be implemented by

 

 

10200HB1747ham001- 140 -LRB102 12090 SPS 23532 a

1        the procurement administrator within 90 days after the
2        determination that the procurement process has failed
3        to fully meet the expected load requirement.
4            (iii) In all cases where there is insufficient
5        supply provided under contracts awarded through the
6        procurement process to fully meet the electric
7        utility's load requirement, the utility shall meet the
8        load requirement by procuring power and energy from
9        the applicable regional transmission organization
10        market, including ancillary services, capacity, and
11        day-ahead or real time energy, or both; provided,
12        however, that if a needed product is not available
13        through the regional transmission organization market
14        it shall be purchased from the wholesale market.
15        (6) The procurement process described in this
16    subsection is exempt from the requirements of the Illinois
17    Procurement Code, pursuant to Section 20-10 of that Code.
18    (f) Within 2 business days after opening the sealed bids,
19the procurement administrator shall submit a confidential
20report to the Commission. The report shall contain the results
21of the bidding for each of the products along with the
22procurement administrator's recommendation for the acceptance
23and rejection of bids based on the price benchmark criteria
24and other factors observed in the process. The procurement
25monitor also shall submit a confidential report to the
26Commission within 2 business days after opening the sealed

 

 

10200HB1747ham001- 141 -LRB102 12090 SPS 23532 a

1bids. The report shall contain the procurement monitor's
2assessment of bidder behavior in the process as well as an
3assessment of the procurement administrator's compliance with
4the procurement process and rules. The Commission shall review
5the confidential reports submitted by the procurement
6administrator and procurement monitor, and shall accept or
7reject the recommendations of the procurement administrator
8within 2 business days after receipt of the reports.
9    (g) Within 3 business days after the Commission decision
10approving the results of a procurement event, the utility
11shall enter into binding contractual arrangements with the
12winning suppliers using the standard form contracts; except
13that the utility shall not be required either directly or
14indirectly to execute the contracts if a tariff that is
15consistent with subsection (l) of this Section has not been
16approved and placed into effect for that utility.
17    (h) The names of the successful bidders and the load
18weighted average of the winning bid prices for each contract
19type and for each contract term shall be made available to the
20public at the time of Commission approval of a procurement
21event. The Commission, the procurement monitor, the
22procurement administrator, the Illinois Power Agency, and all
23participants in the procurement process shall maintain the
24confidentiality of all other supplier and bidding information
25in a manner consistent with all applicable laws, rules,
26regulations, and tariffs. Confidential information, including

 

 

10200HB1747ham001- 142 -LRB102 12090 SPS 23532 a

1the confidential reports submitted by the procurement
2administrator and procurement monitor pursuant to subsection
3(f) of this Section, shall not be made publicly available and
4shall not be discoverable by any party in any proceeding,
5absent a compelling demonstration of need, nor shall those
6reports be admissible in any proceeding other than one for law
7enforcement purposes.
8    (i) Within 2 business days after a Commission decision
9approving the results of a procurement event or such other
10date as may be required by the Commission from time to time,
11the utility shall file for informational purposes with the
12Commission its actual or estimated retail supply charges, as
13applicable, by customer supply group reflecting the costs
14associated with the procurement and computed in accordance
15with the tariffs filed pursuant to subsection (l) of this
16Section and approved by the Commission.
17    (j) Within 60 days following August 28, 2007 (the
18effective date of Public Act 95-481), each electric utility
19that on December 31, 2005 provided electric service to at
20least 100,000 customers in Illinois shall prepare and file
21with the Commission an initial procurement plan, which shall
22conform in all material respects to the requirements of the
23procurement plan set forth in subsection (b); provided,
24however, that the Illinois Power Agency Act shall not apply to
25the initial procurement plan prepared pursuant to this
26subsection. The initial procurement plan shall identify the

 

 

10200HB1747ham001- 143 -LRB102 12090 SPS 23532 a

1portfolio of power and energy products to be procured and
2delivered for the period June 2008 through May 2009, and shall
3identify the proposed procurement administrator, who shall
4have the same experience and expertise as is required of a
5procurement administrator hired pursuant to Section 1-75 of
6the Illinois Power Agency Act. Copies of the procurement plan
7shall be posted and made publicly available on the
8Commission's website. The initial procurement plan may include
9contracts for renewable resources that extend beyond May 2009.
10        (i) Within 14 days following filing of the initial
11    procurement plan, any person may file a detailed objection
12    with the Commission contesting the procurement plan
13    submitted by the electric utility. All objections to the
14    electric utility's plan shall be specific, supported by
15    data or other detailed analyses. The electric utility may
16    file a response to any objections to its procurement plan
17    within 7 days after the date objections are due to be
18    filed. Within 7 days after the date the utility's response
19    is due, the Commission shall determine whether a hearing
20    is necessary. If it determines that a hearing is
21    necessary, it shall require the hearing to be completed
22    and issue an order on the procurement plan within 60 days
23    after the filing of the procurement plan by the electric
24    utility.
25        (ii) The order shall approve or modify the procurement
26    plan, approve an independent procurement administrator,

 

 

10200HB1747ham001- 144 -LRB102 12090 SPS 23532 a

1    and approve or modify the electric utility's tariffs that
2    are proposed with the initial procurement plan. The
3    Commission shall approve the procurement plan if the
4    Commission determines that it will ensure adequate,
5    reliable, affordable, efficient, and environmentally
6    sustainable electric service at the lowest total cost over
7    time, taking into account any benefits of price stability.
8    (k) (Blank).
9    (k-5) (Blank).
10    (l) An electric utility shall recover its costs incurred
11under this Section, including, but not limited to, the costs
12of procuring power and energy demand-response resources under
13this Section. The utility shall file with the initial
14procurement plan its proposed tariffs through which its costs
15of procuring power that are incurred pursuant to a
16Commission-approved procurement plan and those other costs
17identified in this subsection (l), will be recovered. The
18tariffs shall include a formula rate or charge designed to
19pass through both the costs incurred by the utility in
20procuring a supply of electric power and energy for the
21applicable customer classes with no mark-up or return on the
22price paid by the utility for that supply, plus any just and
23reasonable costs that the utility incurs in arranging and
24providing for the supply of electric power and energy. The
25formula rate or charge shall also contain provisions that
26ensure that its application does not result in over or under

 

 

10200HB1747ham001- 145 -LRB102 12090 SPS 23532 a

1recovery due to changes in customer usage and demand patterns,
2and that provide for the correction, on at least an annual
3basis, of any accounting errors that may occur. A utility
4shall recover through the tariff all reasonable costs incurred
5to implement or comply with any procurement plan that is
6developed and put into effect pursuant to Section 1-75 of the
7Illinois Power Agency Act and this Section, including any fees
8assessed by the Illinois Power Agency, costs associated with
9load balancing, and contingency plan costs. The electric
10utility shall also recover its full costs of procuring
11electric supply for which it contracted before the effective
12date of this Section in conjunction with the provision of full
13requirements service under fixed-price bundled service tariffs
14subsequent to December 31, 2006. All such costs shall be
15deemed to have been prudently incurred. The pass-through
16tariffs that are filed and approved pursuant to this Section
17shall not be subject to review under, or in any way limited by,
18Section 16-111(i) of this Act. All of the costs incurred by the
19electric utility associated with the purchase of zero emission
20credits in accordance with subsection (d-5) of Section 1-75 of
21the Illinois Power Agency Act and, beginning June 1, 2017, all
22of the costs incurred by the electric utility associated with
23the purchase of renewable energy resources in accordance with
24Sections 1-56 and 1-75 of the Illinois Power Agency Act, shall
25be recovered through the electric utility's tariffed charges
26applicable to all of its retail customers, as specified in

 

 

10200HB1747ham001- 146 -LRB102 12090 SPS 23532 a

1subsection (k) of Section 16-108 of this Act, and shall not be
2recovered through the electric utility's tariffed charges for
3electric power and energy supply to its eligible retail
4customers.
5    (m) The Commission has the authority to adopt rules to
6carry out the provisions of this Section. For the public
7interest, safety, and welfare, the Commission also has
8authority to adopt rules to carry out the provisions of this
9Section on an emergency basis immediately following August 28,
102007 (the effective date of Public Act 95-481).
11    (n) Notwithstanding any other provision of this Act, any
12affiliated electric utilities that submit a single procurement
13plan covering their combined needs may procure for those
14combined needs in conjunction with that plan, and may enter
15jointly into power supply contracts, purchases, and other
16procurement arrangements, and allocate capacity and energy and
17cost responsibility therefor among themselves in proportion to
18their requirements.
19    (o) On or before June 1 of each year, the Commission shall
20hold an informal hearing for the purpose of receiving comments
21on the prior year's procurement process and any
22recommendations for change.
23    (p) An electric utility subject to this Section may
24propose to invest, lease, own, or operate an electric
25generation facility as part of its procurement plan, provided
26the utility demonstrates that such facility is the least-cost

 

 

10200HB1747ham001- 147 -LRB102 12090 SPS 23532 a

1option to provide electric service to those retail customers
2included in the plan's electric supply service requirements.
3If the facility is shown to be the least-cost option and is
4included in a procurement plan prepared in accordance with
5Section 1-75 of the Illinois Power Agency Act and this
6Section, then the electric utility shall make a filing
7pursuant to Section 8-406 of this Act, and may request of the
8Commission any statutory relief required thereunder. If the
9Commission grants all of the necessary approvals for the
10proposed facility, such supply shall thereafter be considered
11as a pre-existing contract under subsection (b) of this
12Section. The Commission shall in any order approving a
13proposal under this subsection specify how the utility will
14recover the prudently incurred costs of investing in, leasing,
15owning, or operating such generation facility through just and
16reasonable rates charged to those retail customers included in
17the plan's electric supply service requirements. Cost recovery
18for facilities included in the utility's procurement plan
19pursuant to this subsection shall not be subject to review
20under or in any way limited by the provisions of Section
2116-111(i) of this Act. Nothing in this Section is intended to
22prohibit a utility from filing for a fuel adjustment clause as
23is otherwise permitted under Section 9-220 of this Act.
24    (q) If the Illinois Power Agency filed with the
25Commission, under Section 16-111.5 of this Act, its proposed
26procurement plan for the period commencing June 1, 2017, and

 

 

10200HB1747ham001- 148 -LRB102 12090 SPS 23532 a

1the Commission has not yet entered its final order approving
2the plan on or before the effective date of this amendatory Act
3of the 99th General Assembly, then the Illinois Power Agency
4shall file a notice of withdrawal with the Commission, after
5the effective date of this amendatory Act of the 99th General
6Assembly, to withdraw the proposed procurement of renewable
7energy resources to be approved under the plan, other than the
8procurement of renewable energy credits from distributed
9renewable energy generation devices using funds previously
10collected from electric utilities' retail customers that take
11service pursuant to electric utilities' hourly pricing tariff
12or tariffs and, for an electric utility that serves less than
13100,000 retail customers in the State, other than the
14procurement of renewable energy credits from distributed
15renewable energy generation devices. Upon receipt of the
16notice, the Commission shall enter an order that approves the
17withdrawal of the proposed procurement of renewable energy
18resources from the plan. The initially proposed procurement of
19renewable energy resources shall not be approved or be the
20subject of any further hearing, investigation, proceeding, or
21order of any kind.
22    This amendatory Act of the 99th General Assembly preempts
23and supersedes any order entered by the Commission that
24approved the Illinois Power Agency's procurement plan for the
25period commencing June 1, 2017, to the extent it is
26inconsistent with the provisions of this amendatory Act of the

 

 

10200HB1747ham001- 149 -LRB102 12090 SPS 23532 a

199th General Assembly. To the extent any previously entered
2order approved the procurement of renewable energy resources,
3the portion of that order approving the procurement shall be
4void, other than the procurement of renewable energy credits
5from distributed renewable energy generation devices using
6funds previously collected from electric utilities' retail
7customers that take service under electric utilities' hourly
8pricing tariff or tariffs and, for an electric utility that
9serves less than 100,000 retail customers in the State, other
10than the procurement of renewable energy credits for
11distributed renewable energy generation devices.
12(Source: P.A. 99-906, eff. 6-1-17.)
 
13    (220 ILCS 5/16-115D)
14    Sec. 16-115D. Renewable portfolio standard for alternative
15retail electric suppliers and electric utilities operating
16outside their service territories.
17    (a) An alternative retail electric supplier shall be
18responsible for procuring cost-effective renewable energy
19resources as required under item (5) of subsection (d) of
20Section 16-115 of this Act as outlined herein:
21        (1) The definition of renewable energy resources
22    contained in Section 1-10 of the Illinois Power Agency Act
23    applies to all renewable energy resources required to be
24    procured by alternative retail electric suppliers.
25        (2) Through May 31, 2017, the quantity of renewable

 

 

10200HB1747ham001- 150 -LRB102 12090 SPS 23532 a

1    energy resources shall be measured as a percentage of the
2    actual amount of metered electricity (megawatt-hours)
3    delivered by the alternative retail electric supplier to
4    Illinois retail customers during the 12-month period June
5    1 through May 31, commencing June 1, 2009, and the
6    comparable 12-month period in each year thereafter except
7    as provided in item (6) of this subsection (a).
8        (3) Through May 31, 2017, the quantity of renewable
9    energy resources shall be in amounts at least equal to the
10    annual percentages set forth in item (1) of subsection (c)
11    of Section 1-75 of the Illinois Power Agency Act. At least
12    60% of the renewable energy resources procured pursuant to
13    items (1) and (3) of subsection (b) of this Section shall
14    come from wind generation and, starting June 1, 2015, at
15    least 6% of the renewable energy resources procured
16    pursuant to items (1) and (3) of subsection (b) of this
17    Section shall come from solar photovoltaics. If, in any
18    given year, an alternative retail electric supplier does
19    not purchase at least these levels of renewable energy
20    resources, then the alternative retail electric supplier
21    shall make alternative compliance payments, as described
22    in subsection (d) of this Section.
23        (3.5) For the delivery year commencing June 1, 2017,
24    the quantity of renewable energy resources shall be at
25    least 13.0% of the uncovered amount of metered electricity
26    (megawatt-hours) delivered by the alternative retail

 

 

10200HB1747ham001- 151 -LRB102 12090 SPS 23532 a

1    electric supplier to Illinois retail customers during the
2    delivery year, which uncovered amount shall equal 50% of
3    such metered electricity delivered by the alternative
4    retail electric supplier. For the delivery year commencing
5    June 1, 2018, the quantity of renewable energy resources
6    shall be at least 14.5% of the uncovered amount of metered
7    electricity (megawatt-hours) delivered by the alternative
8    retail electric supplier to Illinois retail customers
9    during the delivery year, which uncovered amount shall
10    equal 25% of such metered electricity delivered by the
11    alternative retail electric supplier. At least 32% of the
12    renewable energy resources procured by the alternative
13    retail electric supplier for its uncovered portion under
14    this paragraph (3.5) shall come from wind or photovoltaic
15    generation. The renewable energy resources procured under
16    this paragraph (3.5) shall not include any resources from
17    a facility whose costs were being recovered through rates
18    regulated by any state or states on or after January 1,
19    2017.
20        (4) The quantity and source of renewable energy
21    resources shall be independently verified through the PJM
22    Environmental Information System Generation Attribute
23    Tracking System (PJM-GATS) or the Midwest Renewable Energy
24    Tracking System (M-RETS), which shall document the
25    location of generation, resource type, month, and year of
26    generation for all qualifying renewable energy resources

 

 

10200HB1747ham001- 152 -LRB102 12090 SPS 23532 a

1    that an alternative retail electric supplier uses to
2    comply with this Section. No later than June 1, 2009, the
3    Illinois Power Agency shall provide PJM-GATS, M-RETS, and
4    alternative retail electric suppliers with all information
5    necessary to identify resources located in Illinois,
6    within states that adjoin Illinois or within portions of
7    the PJM and MISO footprint in the United States that
8    qualify under the definition of renewable energy resources
9    in Section 1-10 of the Illinois Power Agency Act for
10    compliance with this Section 16-115D. Alternative retail
11    electric suppliers shall not be subject to the
12    requirements in item (3) of subsection (c) of Section 1-75
13    of the Illinois Power Agency Act.
14        (5) All renewable energy credits used to comply with
15    this Section shall be permanently retired.
16        (6) The required procurement of renewable energy
17    resources by an alternative retail electric supplier shall
18    apply to all metered electricity delivered to Illinois
19    retail customers by the alternative retail electric
20    supplier pursuant to contracts executed or extended after
21    March 15, 2009.
22    (b) Compliance obligations.
23        (1) Through May 31, 2017, an alternative retail
24    electric supplier shall comply with the renewable energy
25    portfolio standards by making an alternative compliance
26    payment, as described in subsection (d) of this Section,

 

 

10200HB1747ham001- 153 -LRB102 12090 SPS 23532 a

1    to cover at least one-half of the alternative retail
2    electric supplier's compliance obligation for the period
3    prior to June 1, 2017.
4        (2) For the delivery years beginning June 1, 2017 and
5    June 1, 2018, an alternative retail electric supplier need
6    not make any alternative compliance payment to meet any
7    portion of its compliance obligation, as set forth in
8    paragraph (3.5) of subsection (a) of this Section.
9        (3) An alternative retail electric supplier shall use
10    any one or combination of the following means to cover the
11    remainder of the alternative retail electric supplier's
12    compliance obligation, as set forth in paragraphs (3) and
13    (3.5) of subsection (a) of this Section, not covered by an
14    alternative compliance payment made under paragraphs (1)
15    and (2) of this subsection (b) of this Section:
16            (A) Generating electricity using renewable energy
17        resources identified pursuant to item (4) of
18        subsection (a) of this Section.
19            (B) Purchasing electricity generated using
20        renewable energy resources identified pursuant to item
21        (4) of subsection (a) of this Section through an
22        energy contract.
23            (C) Purchasing renewable energy credits from
24        renewable energy resources identified pursuant to item
25        (4) of subsection (a) of this Section.
26            (D) Making an alternative compliance payment as

 

 

10200HB1747ham001- 154 -LRB102 12090 SPS 23532 a

1        described in subsection (d) of this Section.
2    (c) Use of renewable energy credits.
3        (1) Renewable energy credits that are not used by an
4    alternative retail electric supplier to comply with a
5    renewable portfolio standard in a compliance year may be
6    banked and carried forward up to 2 12-month compliance
7    periods after the compliance period in which the credit
8    was generated for the purpose of complying with a
9    renewable portfolio standard in those 2 subsequent
10    compliance periods. For the 2009-2010 and 2010-2011
11    compliance periods, an alternative retail electric
12    supplier may use renewable credits generated after
13    December 31, 2008 and before June 1, 2009 to comply with
14    this Section.
15        (2) An alternative retail electric supplier is
16    responsible for demonstrating that a renewable energy
17    credit used to comply with a renewable portfolio standard
18    is derived from a renewable energy resource and that the
19    alternative retail electric supplier has not used, traded,
20    sold, or otherwise transferred the credit.
21        (3) The same renewable energy credit may be used by an
22    alternative retail electric supplier to comply with a
23    federal renewable portfolio standard and a renewable
24    portfolio standard established under this Act. An
25    alternative retail electric supplier that uses a renewable
26    energy credit to comply with a renewable portfolio

 

 

10200HB1747ham001- 155 -LRB102 12090 SPS 23532 a

1    standard imposed by any other state may not use the same
2    credit to comply with a renewable portfolio standard
3    established under this Act.
4    (d) Alternative compliance payments.
5        (1) The Commission shall establish and post on its
6    website, within 5 business days after entering an order
7    approving a procurement plan pursuant to Section 1-75 of
8    the Illinois Power Agency Act, maximum alternative
9    compliance payment rates, expressed on a per kilowatt-hour
10    basis, that will be applicable in the first compliance
11    period following the plan approval. A separate maximum
12    alternative compliance payment rate shall be established
13    for the service territory of each electric utility that is
14    subject to subsection (c) of Section 1-75 of the Illinois
15    Power Agency Act. Each maximum alternative compliance
16    payment rate shall be equal to the maximum allowable
17    annual estimated average net increase due to the costs of
18    the utility's purchase of renewable energy resources
19    included in the amounts paid by eligible retail customers
20    in connection with electric service, as described in item
21    (2) of subsection (c) of Section 1-75 of the Illinois
22    Power Agency Act for the compliance period, and as
23    established in the approved procurement plan. Following
24    each procurement event through which renewable energy
25    resources are purchased for one or more of these utilities
26    for the compliance period, the Commission shall establish

 

 

10200HB1747ham001- 156 -LRB102 12090 SPS 23532 a

1    and post on its website estimates of the alternative
2    compliance payment rates, expressed on a per kilowatt-hour
3    basis, that shall apply for that compliance period.
4    Posting of the estimates shall occur no later than 10
5    business days following the procurement event, however,
6    the Commission shall not be required to establish and post
7    such estimates more often than once per calendar month. By
8    July 1 of each year, the Commission shall establish and
9    post on its website the actual alternative compliance
10    payment rates for the preceding compliance year. For
11    compliance years beginning prior to June 1, 2014, each
12    alternative compliance payment rate shall be equal to the
13    total amount of dollars that the utility contracted to
14    spend on renewable resources, excepting the additional
15    incremental cost attributable to solar resources, for the
16    compliance period divided by the forecasted load of
17    eligible retail customers, at the customers' meters, as
18    previously established in the Commission-approved
19    procurement plan for that compliance year. For compliance
20    years commencing on or after June 1, 2014, each
21    alternative compliance payment rate shall be equal to the
22    total amount of dollars that the utility contracted to
23    spend on all renewable resources for the compliance period
24    divided by the forecasted load of retail customers for
25    which the utility is procuring renewable energy resources
26    in a given delivery year, at the customers' meters, as

 

 

10200HB1747ham001- 157 -LRB102 12090 SPS 23532 a

1    previously established in the Commission-approved
2    procurement plan for that compliance year. The actual
3    alternative compliance payment rates may not exceed the
4    maximum alternative compliance payment rates established
5    for the compliance period. For purposes of this subsection
6    (d), the term "eligible retail customers" has the same
7    meaning as found in Section 16-111.5 of this Act.
8        (2) In any given compliance year, an alternative
9    retail electric supplier may elect to use alternative
10    compliance payments to comply with all or a part of the
11    applicable renewable portfolio standard. In the event that
12    an alternative retail electric supplier elects to make
13    alternative compliance payments to comply with all or a
14    part of the applicable renewable portfolio standard, such
15    payments shall be made by September 1, 2010 for the period
16    of June 1, 2009 to May 1, 2010 and by September 1 of each
17    year thereafter for the subsequent compliance period, in
18    the manner and form as determined by the Commission. Any
19    election by an alternative retail electric supplier to use
20    alternative compliance payments is subject to review by
21    the Commission under subsection (e) of this Section.
22        (3) An alternative retail electric supplier's
23    alternative compliance payments shall be computed
24    separately for each electric utility's service territory
25    within which the alternative retail electric supplier
26    provided retail service during the compliance period,

 

 

10200HB1747ham001- 158 -LRB102 12090 SPS 23532 a

1    provided that the electric utility was subject to
2    subsection (c) of Section 1-75 of the Illinois Power
3    Agency Act. For each service territory, the alternative
4    retail electric supplier's alternative compliance payment
5    shall be equal to (i) the actual alternative compliance
6    payment rate established in item (1) of this subsection
7    (d), multiplied by (ii) the actual amount of metered
8    electricity delivered by the alternative retail electric
9    supplier to retail customers for which the supplier has a
10    compliance obligation within the service territory during
11    the compliance period, multiplied by (iii) the result of
12    one minus the ratios of the quantity of renewable energy
13    resources used by the alternative retail electric supplier
14    to comply with the requirements of this Section within the
15    service territory to the product of the percentage of
16    renewable energy resources required under item (3) or
17    (3.5) of subsection (a) of this Section and the actual
18    amount of metered electricity delivered by the alternative
19    retail electrical supplier to retail customers for which
20    the supplier has a compliance obligation within the
21    service territory during the compliance period.
22        (4) Through May 31, 2017, all alternative compliance
23    payments by alternative retail electric suppliers shall be
24    deposited in the Illinois Power Agency Renewable Energy
25    Resources Fund and used to purchase renewable energy
26    credits, in accordance with Section 1-56 of the Illinois

 

 

10200HB1747ham001- 159 -LRB102 12090 SPS 23532 a

1    Power Agency Act. Beginning April 1, 2012 and by April 1 of
2    each year thereafter, the Illinois Power Agency shall
3    submit an annual report to the General Assembly, the
4    Commission, and alternative retail electric suppliers that
5    shall include, but not be limited to:
6            (A) the total amount of alternative compliance
7        payments received in aggregate from alternative retail
8        electric suppliers by planning year for all previous
9        planning years in which the alternative compliance
10        payment was in effect;
11            (B) the amount of those payments utilized to
12        purchased renewable energy credits itemized by the
13        date of each procurement in which the payments were
14        utilized; and
15            (C) the unused and remaining balance in the Agency
16        Renewable Energy Resources Fund attributable to those
17        payments.
18        (4.5) Beginning with the delivery year commencing June
19    1, 2017, all alternative compliance payments by
20    alternative retail electric suppliers shall be remitted to
21    the applicable electric utility. To facilitate this
22    remittance, each electric utility shall file a tariff with
23    the Commission no later than 30 days following the
24    effective date of this amendatory Act of the 99th General
25    Assembly, which the Commission shall approve, after notice
26    and hearing, no later than 45 days after its filing. The

 

 

10200HB1747ham001- 160 -LRB102 12090 SPS 23532 a

1    Illinois Power Agency shall use such payments to increase
2    the amount of renewable energy resources otherwise to be
3    procured under subsection (c) of Section 1-75 of the
4    Illinois Power Agency Act.
5        (5) The Commission, in consultation with the Illinois
6    Power Agency, shall establish a process or proceeding to
7    consider the impact of a federal renewable portfolio
8    standard, if enacted, on the operation of the alternative
9    compliance mechanism, which shall include, but not be
10    limited to, developing, to the extent permitted by the
11    applicable federal statute, an appropriate methodology to
12    apportion renewable energy credits retired as a result of
13    alternative compliance payments made in accordance with
14    this Section. The Commission shall commence any such
15    process or proceeding within 35 days after enactment of a
16    federal renewable portfolio standard.
17    (d-5) Self directing retail customers.
18        (1) Beginning June 1, 2022, alternative retail
19    electric suppliers may procure renewable energy resources
20    from a renewable energy generator located in Illinois for
21    self-directing retail customers, as defined in Section
22    1-10 of the Illinois Power Agency Act.
23        (2) In order to qualify as a self-directing retail
24    customer:
25            (A) a notice must be provided to the electric
26        utility and the Illinois Power Agency that the retail

 

 

10200HB1747ham001- 161 -LRB102 12090 SPS 23532 a

1        customer has entered into a self-supply renewable
2        portfolio standard agreement, as defined in Section
3        1-10 of the Illinois Power Agency Act, with an
4        alternative retail electric supplier;
5            (B) the alternative retail electric supplier must
6        certify to the Illinois Power Agency that over the
7        term of the self-supply renewable portfolio standard
8        agreement: (i) it will procure renewable energy
9        resources from renewable energy generators located in
10        Illinois for at least 25% of the metered electricity
11        delivered by the alternative retail electric supplier
12        to the retail customer; (ii) it will deliver the
13        energy from those renewable energy generators to the
14        retail customer and retire the renewable energy
15        credits from those renewable energy generators; and
16        (iii) it will not use, trade, sell, or otherwise
17        transfer those renewable energy credits from those
18        renewable energy generators; and
19            (C) the renewable energy generator must certify to
20        the Illinois Power Agency that: (i) its facility is
21        located in Illinois; (ii) not less than the prevailing
22        wage was or will be paid to employees engaged in
23        construction activities associated with the facility;
24        (iii) at a minimum at least 25% of all construction
25        related activities associated with the facility,
26        including, but not limited to legal work, accounting,

 

 

10200HB1747ham001- 162 -LRB102 12090 SPS 23532 a

1        catering, and equipment rental were or are provided by
2        businesses owned by minority persons, women, or
3        persons with disabilities; and (iv) the costs for its
4        facility were not recovered through rates regulated by
5        any state or states on or after January 1, 2017.
6        "Prevailing wage" has the same meaning as defined in
7        subparagraph (F) of paragraph (3) of subsection (a) of
8        Section 5.5 of the Illinois Enterprise Zone Act. The
9        terms "minority persons", "women", and "persons with
10        disabilities" have the same meaning as provided in
11        subsection (A) of Section 2 of the Business Enterprise
12        for Minorities, Women, and Persons with Disabilities
13        Act.
14        (3) The electric utility shall be entitled to recover
15    reasonable costs incurred in complying with this
16    subsection from all retail customers.
17        (4) The self-supply renewable portfolio standard
18    agreement, and any renewal of such agreement, shall be for
19    a minimum duration of one year for residential retail
20    customers and small commercial retail customers; a minimum
21    duration of one year for corporate authorities, township
22    boards, and county boards entering into such agreements
23    under a government aggregation program adopted in
24    accordance with Section 1-92 of the Illinois Power Agency
25    Act; and a minimum duration of 5 years for all other
26    non-residential retail customers.

 

 

10200HB1747ham001- 163 -LRB102 12090 SPS 23532 a

1        (5) The notice provided pursuant to paragraph (2) of
2    this subsection shall be given by the alternative retail
3    electric supplier at least 60 days prior to the effective
4    date of the self-supply renewable portfolio standard
5    agreement and shall identify: (i) the retail customer's
6    name, address, and account number; (ii) the duration of
7    the self-supply renewable portfolio standard agreement;
8    and (iii) the name and location of the renewable energy
9    generator that will be supplying the renewable energy
10    resources. The alternative retail electric supplier also
11    shall provide a notice to the electric utility and the
12    Illinois Power Agency at least 60 days prior to the end of
13    the term of the self-supply renewable portfolio standard
14    agreement detailing whether and for what duration the
15    self-supply renewable portfolio standard agreement has
16    been renewed, and shall promptly notify the electric
17    utility and the Illinois Power Agency if the self-supply
18    renewable portfolio standard agreement is terminated for
19    any reason prior to the end of the term.
20    (e) Each alternative retail electric supplier shall, by
21September 1, 2010 and by September 1 of each year thereafter,
22prepare and submit to the Commission a report, in a format to
23be specified by the Commission, that provides information
24certifying compliance by the alternative retail electric
25supplier with this Section, including copies of all PJM-GATS
26and M-RETS reports, and documentation relating to banking,

 

 

10200HB1747ham001- 164 -LRB102 12090 SPS 23532 a

1retiring renewable energy credits, and any other information
2that the Commission determines necessary to ensure compliance
3with this Section.
4    An alternative retail electric supplier may file
5commercially or financially sensitive information or trade
6secrets with the Commission as provided under the rules of the
7Commission. To be filed confidentially, the information shall
8be accompanied by an affidavit that sets forth both the
9reasons for the confidentiality and a public synopsis of the
10information.
11    (f) The Commission may initiate a contested case to review
12allegations that the alternative retail electric supplier has
13violated this Section, including an order issued or rule
14promulgated under this Section. In any such proceeding, the
15alternative retail electric supplier shall have the burden of
16proof. If the Commission finds, after notice and hearing, that
17an alternative retail electric supplier has violated this
18Section, then the Commission shall issue an order requiring
19the alternative retail electric supplier to:
20        (1) immediately comply with this Section; and
21        (2) if the violation involves a failure to procure the
22    requisite quantity of renewable energy resources or pay
23    the applicable alternative compliance payment by the
24    annual deadline, the Commission shall require the
25    alternative retail electric supplier to double the
26    applicable alternative compliance payment that would

 

 

10200HB1747ham001- 165 -LRB102 12090 SPS 23532 a

1    otherwise be required to bring the alternative retail
2    electric supplier into compliance with this Section.
3    If an alternative retail electric supplier fails to comply
4with the renewable energy resource portfolio requirement in
5this Section more than once in a 5-year period, then the
6Commission shall revoke the alternative electric supplier's
7certificate of service authority. The Commission shall not
8accept an application for a certificate of service authority
9from an alternative retail electric supplier that has lost
10certification under this subsection (f), or any corporate
11affiliate thereof, for at least one year after the date of
12revocation.
13    (g) All of the provisions of this Section apply to
14electric utilities operating outside their service area except
15under item (2) of subsection (a) of this Section the quantity
16of renewable energy resources shall be measured as a
17percentage of the actual amount of electricity
18(megawatt-hours) supplied in the State outside of the
19utility's service territory during the 12-month period June 1
20through May 31, commencing June 1, 2009, and the comparable
2112-month period in each year thereafter except as provided in
22item (6) of subsection (a) of this Section.
23    If any such utility fails to procure the requisite
24quantity of renewable energy resources by the annual deadline,
25then the Commission shall require the utility to double the
26alternative compliance payment that would otherwise be

 

 

10200HB1747ham001- 166 -LRB102 12090 SPS 23532 a

1required to bring the utility into compliance with this
2Section.
3    If any such utility fails to comply with the renewable
4energy resource portfolio requirement in this Section more
5than once in a 5-year period, then the Commission shall order
6the utility to cease all sales outside of the utility's
7service territory for a period of at least one year.
8    (h) The provisions of this Section and the provisions of
9subsection (d) of Section 16-115 of this Act relating to
10procurement of renewable energy resources shall not apply to
11an alternative retail electric supplier that operates a
12combined heat and power system in this State or that has a
13corporate affiliate that operates such a combined heat and
14power system in this State that supplies electricity primarily
15to or for the benefit of: (i) facilities owned by the supplier,
16its subsidiary, or other corporate affiliate; (ii) facilities
17electrically integrated with the electrical system of
18facilities owned by the supplier, its subsidiary, or other
19corporate affiliate; or (iii) facilities that are adjacent to
20the site on which the combined heat and power system is
21located.
22    (i) The obligations of alternative retail electric
23suppliers and electric utilities operating outside their
24service territories to procure renewable energy resources,
25make alternative compliance payments, and file annual reports,
26and the obligations of the Commission to determine and post

 

 

10200HB1747ham001- 167 -LRB102 12090 SPS 23532 a

1alternative compliance payment rates, shall terminate after
2May 31, 2019, provided that alternative retail electric
3suppliers and electric utilities operating outside their
4service territories shall be obligated to make all alternative
5compliance payments that they were obligated to pay for
6periods through and including May 31, 2019, but were not paid
7as of that date. The Commission shall continue to enforce the
8payment of unpaid alternative compliance payments in
9accordance with subsections (f) and (g) of this Section. All
10alternative compliance payments made after May 31, 2016 shall
11be remitted to the applicable electric utility and used to
12purchase renewable energy credits, in accordance with Section
131-75 of the Illinois Power Agency Act.
14    This subsection (i) is intended to accommodate the
15transition to the procurement of renewable energy resources
16for all retail customers in the amounts specified under
17subsection (c) of Section 1-75 of the Illinois Power Agency
18Act and Section 16-111.5 of this Act, including but not
19limited to the transition to a single charge applicable to all
20retail customers to recover the costs of these resources. Each
21alternative retail electric supplier shall certify in its
22annual reports filed pursuant to subsection (e) of this
23Section after May 31, 2019, that its retail customers are not
24paying the costs of alternative compliance payments or
25renewable energy resources that the alternative retail
26electric supplier is not required to remit or purchase under

 

 

10200HB1747ham001- 168 -LRB102 12090 SPS 23532 a

1this Section. The Commission shall have the authority to
2initiate an emergency rulemaking to adopt rules regarding such
3certification.
4(Source: P.A. 99-906, eff. 6-1-17.)".