Amends the Illinois Municipal Code. Defines "underground" and "undergrounding". Provides that public utilities shall underground specified electric transmission lines under certain conditions. Provides that the Illinois Commerce Commission shall allow a public utility to recover from all retail customers in its service territory all reasonable and prudent costs that it incurs related to the undergrounding of such transmission lines. Provides that a public utility shall record and defer such costs as a regulatory asset to be included in the public utility's total rate base and amortized over a reasonable period that is equal to the expected life of such transmission line. Effective immediately.
|
| |
| | | FISCAL NOTE ACT MAY APPLY | |
| | A BILL FOR |
|
|
| | HB2372 | | LRB102 14303 AWJ 19655 b |
|
|
1 | | AN ACT concerning local government.
|
2 | | Be it enacted by the People of the State of Illinois,
|
3 | | represented in the General Assembly:
|
4 | | Section 5. The Illinois Municipal Code is amended by |
5 | | adding Division 15.5 to Article 11 as follows: |
6 | | (65 ILCS 5/Art. 11 Div. 15.5 heading new) |
7 | | DIVISION 15.5. UNDERGROUNDING UTILITY FACILITIES |
8 | | (65 ILCS 5/11-15.5-5 new) |
9 | | Sec. 11-15.5-5. Definitions. As used in this Division and |
10 | | unless the context requires otherwise, "underground" or |
11 | | "undergrounding" means routing and constructing electric |
12 | | transmission lines and their associated components below |
13 | | ground, consistent with sound engineering and utility |
14 | | practices. |
15 | | (65 ILCS 5/11-15.5-10 new) |
16 | | Sec. 11-15.5-10. Undergrounding utility facilities. |
17 | | (a) In the interest of public health and safety, |
18 | | reliability, and electric grid security, a public utility, as |
19 | | defined by Section 3-105 of the Public Utilities Act, shall |
20 | | underground any 138 kilowatt or greater electric transmission |
21 | | line constructed after the effective date of this amendatory |
|
| | HB2372 | - 2 - | LRB102 14303 AWJ 19655 b |
|
|
1 | | Act of the 102nd General Assembly where: |
2 | | (1) such transmission line or any portion thereof is |
3 | | to be located within 26,000 feet of an airport that is |
4 | | located in and owned by a municipality with a population |
5 | | greater than 70,000 and less than 80,000 located in or |
6 | | contiguous to a county with a population in excess of |
7 | | 1,000,000 inhabitants; or |
8 | | (2) such transmission line is to be located in 4 or |
9 | | more contiguous municipalities with a population density |
10 | | of 1,000 per square mile or more as of the most recent |
11 | | federal decennial census. |
12 | | (b) The costs for undergrounding a new transmission line |
13 | | shall not be allocated solely to the municipality or |
14 | | municipalities in which it is underground; instead, the |
15 | | Illinois Commerce Commission shall allow a public utility to |
16 | | fully recover from all retail customers in its service |
17 | | territory all reasonable and prudent costs that it incurs |
18 | | related to the undergrounding of transmission lines. The |
19 | | public utility shall record and defer such costs as a |
20 | | regulatory asset to be included in the public utility's total |
21 | | rate base and amortized over a reasonable period that is equal |
22 | | to the expected life of the transmission line. Such regulatory |
23 | | assets shall be collected from all ratepayers system-wide, and |
24 | | not only from ratepayers in the corporate limits of the |
25 | | municipality or municipalities within which the transmission |
26 | | line is constructed.
|