|
Rep. Lawrence "Larry" Walsh, Jr.
Filed: 4/16/2024
| | 10300HB5546ham001 | | LRB103 38732 SPS 72477 a |
|
|
1 | | AMENDMENT TO HOUSE BILL 5546
|
2 | | AMENDMENT NO. ______. Amend House Bill 5546 by replacing |
3 | | everything after the enacting clause with the following: |
4 | | "Section 5. The Illinois Underground Utility Facilities |
5 | | Damage Prevention Act is amended by changing Sections 1, 2, 3, |
6 | | 4, 6, 7, 8, 9, 10, 11, 11.3, 11.5, 12, 13, and 14 and by adding |
7 | | Sections 4.1, 5.1, 5.2, 5.3, 5.4, and 7.5 as follows: |
8 | | (220 ILCS 50/1) (from Ch. 111 2/3, par. 1601) |
9 | | Sec. 1. This Act shall be known , and may be cited , as the |
10 | | Illinois Underground Utility Facilities Damage Prevention Act, |
11 | | and for the purposes of participating in the State of Illinois |
12 | | Joint Purchasing Program, the State-Wide One-Call Notice |
13 | | System, commonly referred to as "JULIE, Inc.", shall be |
14 | | considered as created by this Act. |
15 | | (Source: P.A. 96-714, eff. 1-1-10.) |
|
| | 10300HB5546ham001 | - 2 - | LRB103 38732 SPS 72477 a |
|
|
1 | | (220 ILCS 50/2) (from Ch. 111 2/3, par. 1602) |
2 | | Sec. 2. Definitions. As used in this Act, unless the |
3 | | context clearly otherwise requires, the terms specified in |
4 | | this Section Sections 2.1 through 2.11 have the meanings |
5 | | ascribed to them in this Section in those Sections . |
6 | | "Approximate location" means the location of the marked |
7 | | facility that lies entirely within the tolerance zone. |
8 | | Circumstances that are "beyond the reasonable control" of |
9 | | a party include, but are not limited to, severe weather, |
10 | | unforeseen mechanical issues, or site conditions. As used in |
11 | | Section 11, "beyond the reasonable control" also includes, but |
12 | | is not limited to, notice volumes or dig site notification |
13 | | areas that exceed historical averages, as determined by the |
14 | | reasonable control measurement, created as a result of |
15 | | underground utility facility owners or operators or their |
16 | | contractors or subcontractors' non-emergency requests for |
17 | | utility excavation work for underground utility facility |
18 | | owners or operators, that is not part of a large project that |
19 | | has provided at least 60 days notice, and only applies to the |
20 | | requests submitted by underground utility facility owners or |
21 | | operators or their contractors or subcontractors' |
22 | | non-emergency utility excavation work for underground utility |
23 | | facility owners or operators. |
24 | | "Damage" means the contact or dislocation of a facility |
25 | | during excavation or demolition that necessitates immediate or |
26 | | subsequent repair by the underground utility facility owner or |
|
| | 10300HB5546ham001 | - 3 - | LRB103 38732 SPS 72477 a |
|
|
1 | | operator due to any partial or complete destruction of the |
2 | | facility, including, but not limited to, the protective |
3 | | coating, tracer wire, lateral support, cathodic protection, or |
4 | | housing for the line or device of the facility. |
5 | | "Damage notification" means a notification through JULIE |
6 | | to the underground utility facility owner or operator that |
7 | | damage to a facility has occurred in the area of the excavation |
8 | | or demolition. |
9 | | "Day" means any day, beginning at 12:00 a.m. and ending at |
10 | | 11:59 p.m. "Day" does not include holidays recognized by |
11 | | JULIE, Saturdays, Sundays, and the day of the actual notice. |
12 | | "Demolition" means the wrecking, razing, rending, moving, |
13 | | or removing of a structure by means of any power tool, power |
14 | | equipment (exclusive of transportation equipment), or |
15 | | explosives. |
16 | | "Emergency request" means a request involving a condition |
17 | | (1) that constitutes an imminent danger to life, health, or |
18 | | property or a utility service outage (2) and that requires |
19 | | repair or action before the expiration of 2 days. |
20 | | "Excavation" means: |
21 | | (1) any operation in which earth, rock, or other |
22 | | material in or on the ground is moved, removed, or |
23 | | otherwise displaced by means of any tools, power equipment |
24 | | or explosives, and includes, without limitation, grading, |
25 | | trenching, digging, ditching, drilling, augering, boring, |
26 | | tunneling, scraping, cable or pipe plowing, saw cutting or |
|
| | 10300HB5546ham001 | - 4 - | LRB103 38732 SPS 72477 a |
|
|
1 | | roadway surface milling when penetrating into the base or |
2 | | subbase of a paved surface, and driving, but does not |
3 | | include: |
4 | | (A) farm tillage operations; |
5 | | (B) railroad right-of-way maintenance; |
6 | | (C) coal mining operations regulated under the |
7 | | federal Surface Mining Control and Reclamation Act of |
8 | | 1977 or any State law or rules or regulations adopted |
9 | | under the federal statute; |
10 | | (D) land surveying operations as defined in the |
11 | | Illinois Professional Land Surveyor Act of 1989 when |
12 | | not using power equipment; |
13 | | (E) roadway surface milling; |
14 | | (F) manually inserting, without the use of power |
15 | | equipment, a temporary round-tipped ground or probe |
16 | | rod as part of facility locating; |
17 | | (G) manually inserting, without the use of power |
18 | | equipment, a temporary round-tipped probe rod for bar |
19 | | holing to determine the area of a potential leak from a |
20 | | facility transporting hazardous gases or liquids; or |
21 | | (H) manually inserting, without the use of power |
22 | | equipment, a round-tipped ground rod for the purpose |
23 | | of grounding utility equipment when an emergency |
24 | | exists and no other ground source is available. |
25 | | (2) An exclusion to this Section in no way prohibits a |
26 | | request from being made for the marking of facilities. |
|
| | 10300HB5546ham001 | - 5 - | LRB103 38732 SPS 72477 a |
|
|
1 | | (3) Any exception to excavation contained within this |
2 | | Section is not intended to remove liability that may be |
3 | | imposed against an individual or entity because of damage |
4 | | caused to a facility. |
5 | | "Excavator" means any person or legal entity, public or |
6 | | private, that engages in excavation or demolition work. |
7 | | "Exposed notification" means a notification through JULIE |
8 | | to the underground utility facility owner or operator that an |
9 | | unmarked facility has been exposed in the area of the |
10 | | excavation or demolition but has not been damaged. |
11 | | "Extension" means a request made by an excavator, to |
12 | | extend the expiration date of a normal notice to allow |
13 | | additional time to continue or complete the excavation or |
14 | | demolition project. |
15 | | (1) An extension request may be made no earlier than |
16 | | the 20th day from the initial normal notice request or |
17 | | latest extension request. |
18 | | (2) An extension request shall extend the expiration |
19 | | of the initial normal notice request or latest extension |
20 | | request by 25 days. |
21 | | (3) An extension request may not be made simply to |
22 | | keep a prior notice open without continued excavation |
23 | | occurring within the period of that subsequent notice. |
24 | | "Geographic information system data" means data to be |
25 | | applied to JULIE software to facilitate a more clearly defined |
26 | | notification area for notices sent to the system underground |
|
| | 10300HB5546ham001 | - 6 - | LRB103 38732 SPS 72477 a |
|
|
1 | | utility facility owners or operators. "Geographic information |
2 | | system data" includes, but is not limited to: |
3 | | (1) address points with site addresses; |
4 | | (2) parcels with site addresses; |
5 | | (3) road center lines with names and address range; |
6 | | (4) city limits with names; |
7 | | (5) political townships with names; |
8 | | (6) railroads with names; |
9 | | (7) streams with names; and |
10 | | (8) water bodies with names. |
11 | | "Historical averages" are used to determine benchmark |
12 | | notice volumes or dig site notification areas for a particular |
13 | | place. The notice volume is calculated for new and updated |
14 | | requests requiring an underground utility facility owner or |
15 | | operator response. It shall not include notices with a header |
16 | | of noshow, incomplete, or noremark. The dig site notification |
17 | | area is calculated using the dig site polygon on the notice. |
18 | | The 7 day look back shall be calculated once daily at the |
19 | | conclusion of the previous calendar day. "Historic averages" |
20 | | shall be determined by comparing notice volumes or dig site |
21 | | notification areas over the immediate past 7 calendar days to |
22 | | the same 7 calendar day period for the past 5 years. A 5-year |
23 | | trimmed mean, removing the highest and lowest years, and |
24 | | averaging the remaining 3 years, shall be the final |
25 | | determinate of this measurement. The official measurement of |
26 | | the notice volumes or dig site notification areas shall be |
|
| | 10300HB5546ham001 | - 7 - | LRB103 38732 SPS 72477 a |
|
|
1 | | provided by JULIE. |
2 | | "Incomplete request" means a notice initiated by an |
3 | | excavator through JULIE to the underground utility facility |
4 | | owners or operators notified in a prior request that such |
5 | | underground utility facility owners or operators, as |
6 | | identified by the excavator and confirmed, through the |
7 | | positive response system once implemented, in accordance with |
8 | | subsection (a) of Section 5.1, did not completely mark the |
9 | | entire extent or the entire segment of the proposed |
10 | | excavation, as identified on the prior notice or as previously |
11 | | documented and mutually agreed upon. |
12 | | "Joint meet notification" means a notice of a meeting held |
13 | | prior to the excavation phase to discuss projects that cannot |
14 | | be adequately communicated within a normal notice request. The |
15 | | meeting is intended to allow the exchange of maps, plans, or |
16 | | schedules. It is not a locating session and shall be held at or |
17 | | near the excavation site, or through electronic means, if |
18 | | available and agreed to by all parties. "Joint meet |
19 | | notification" are not to be used in lieu of valid normal notice |
20 | | requests and are required for, but not limited to, large |
21 | | projects. |
22 | | "JULIE, Inc." or "JULIE" means the communication system |
23 | | known as "JULIE, Inc." or "JULIE", utilized by excavators, |
24 | | designers, or any other entities covered by this Act to notify |
25 | | underground utility facility owners or operators of their |
26 | | intent to perform excavation or demolition or similar work as |
|
| | 10300HB5546ham001 | - 8 - | LRB103 38732 SPS 72477 a |
|
|
1 | | defined by this Act and shall include all underground utility |
2 | | facilities owned or operated outside the city limits of the |
3 | | City of Chicago. |
4 | | "Large project" means a single excavation that exceeds the |
5 | | expiration date of a normal notice request, or involves a |
6 | | series of repetitive, related-scope excavations. |
7 | | "Normal notice request" means a notification made by an |
8 | | excavator, through JULIE, in advance of a planned excavation |
9 | | or demolition. |
10 | | (1) The notification shall be made at least 2 days, |
11 | | but no more than 10 days, before beginning the planned |
12 | | excavation or demolition. |
13 | | (2) Excavation or demolition on a normal notice |
14 | | request is valid for 25 days from the date of the initial |
15 | | request unless a subsequent extension request is made. |
16 | | (3) Normal notice requests shall be limited to one |
17 | | quarter of a contiguous mile within a municipality and one |
18 | | contiguous mile within any unincorporated area, which |
19 | | includes townships. |
20 | | (4) Normal notice requests are valid for a single |
21 | | right-of-way with an exception for intersecting |
22 | | rights-of-way of 250 feet in all directions. Any |
23 | | excavation continuing beyond 250 feet on a connecting |
24 | | right-of-way shall require an additional request. |
25 | | "No show request" means a notice initiated by an excavator |
26 | | through JULIE to the underground utility facility owners or |
|
| | 10300HB5546ham001 | - 9 - | LRB103 38732 SPS 72477 a |
|
|
1 | | operators notified in the prior notice that such underground |
2 | | utility facility owners or operators, as identified by the |
3 | | excavator and confirmed, once implemented, in accordance with |
4 | | subsection (a) of Section 5.1, either failed to mark their |
5 | | facilities or to communicate their non-involvement with the |
6 | | excavation prior to the dig start date and time on the notice. |
7 | | "Notice" means any record transmitted to an underground |
8 | | utility facility owner or operator of JULIE which shall |
9 | | include, but not be limited to, cancel, damage, emergency, |
10 | | exposed, extension, incomplete, joint meet, no show, normal, |
11 | | planning design, or re-mark. |
12 | | "Open cut utility locate" means a method of locating |
13 | | facilities that requires excavation by the underground utility |
14 | | facility owner or operator, or their contractor or |
15 | | subcontractor. |
16 | | "Place" means any incorporated city, village or town, or |
17 | | unincorporated township or road district, listed within the |
18 | | JULIE database. |
19 | | "Planning design request" means the process prior to the |
20 | | excavation phase of a project where information is gathered |
21 | | and decisions are made regarding the route or location of a |
22 | | proposed excavation. The use of the information that is |
23 | | obtainable pursuant to this Section is intended to minimize |
24 | | delays of future construction projects and not for imminent |
25 | | excavation. The underground utility facility owner or operator |
26 | | may indicate any portion of the information that is |
|
| | 10300HB5546ham001 | - 10 - | LRB103 38732 SPS 72477 a |
|
|
1 | | proprietary and require the planner or designer to protect the |
2 | | proprietary information. |
3 | | "Positive response system" means an automated system |
4 | | facilitated by JULIE allowing underground utility facility |
5 | | owners or operators to communicate to an excavator the |
6 | | presence, absence, or response status of any conflict between |
7 | | the existing facilities in or near the area of excavation or |
8 | | demolition on each notice received. |
9 | | "Pre-mark" means the use of white paint, chalk, lathe, |
10 | | whiskers, flags, or electronic white lining using lines or |
11 | | polygons to delineate the work area at the site of the proposed |
12 | | excavation or demolition. Unless otherwise stated on the |
13 | | request, all pre-marks are considered a request for a 5-foot |
14 | | radius of an above ground fixed structure or single point |
15 | | pre-mark, or a 10-foot-wide path for linear work. |
16 | | (1) Physical pre-marking for the area of the planned |
17 | | excavation or demolition shall be accomplished prior to |
18 | | notifying JULIE if the area of excavation cannot be |
19 | | clearly and adequately identified in the normal notice |
20 | | request. |
21 | | (2) Electronic white lining may be used when |
22 | | available. Electronic white lining provides an alternative |
23 | | method where an excavator may indicate their defined dig |
24 | | area visually by electronic data entry, including lines or |
25 | | polygons, without the need for a physical site visit. The |
26 | | technology allows the excavator to identify for the |
|
| | 10300HB5546ham001 | - 11 - | LRB103 38732 SPS 72477 a |
|
|
1 | | underground utility facility owner or operator a clear |
2 | | delineation of their proposed excavation area. |
3 | | (3) A verbal or written pre-mark is adequate when the |
4 | | scope requested to be marked is narrow and explicit enough |
5 | | to prevent marking beyond the actual area of excavation or |
6 | | demolition. An existing above ground fixed structure may |
7 | | be referenced as a verbal or written pre-mark. |
8 | | "Project owner" means the person or legal entity, public |
9 | | or private, that is financially responsible for the |
10 | | undertaking of a project that involves excavation or |
11 | | demolition. |
12 | | "Reasonable control measurement" shall use the historical |
13 | | averages and add to the calculation either of the following |
14 | | conditions that shall be met for the place to be considered |
15 | | beyond the reasonable control of the underground utility |
16 | | facility owner or operator: |
17 | | (1) the total notice volume count over the previous 7 |
18 | | calendar days shall increase by more than 15% of the |
19 | | historic average, and increase by not less than 25 |
20 | | additional notices over the previous 7 calendar days; or |
21 | | (2) the total dig site notification area over the |
22 | | previous 7 calendar days shall increase by more than 15% |
23 | | of the historic average, and not less than 0.4 additional |
24 | | square miles over the previous 7 calendar days. |
25 | | The official measurement shall be provided by JULIE. |
26 | | "Residential property owner" means any individual or |
|
| | 10300HB5546ham001 | - 12 - | LRB103 38732 SPS 72477 a |
|
|
1 | | entity that owns or leases real property that is used by the |
2 | | individual or entity as its residence or dwelling. Residential |
3 | | property owner does not include any persons who own or lease |
4 | | residential property for the purpose of holding or developing |
5 | | such property or for any other business or commercial |
6 | | purposes. |
7 | | "Roadway surface milling" means the removal of a uniform |
8 | | pavement section by rotomilling, grinding, saw cutting, or |
9 | | other means that does not penetrate into the roadway base or |
10 | | subbase. |
11 | | "Service lateral" means underground facilities located in |
12 | | a public right-of-way or utility easement that connects an end |
13 | | user's building or property to an underground utility facility |
14 | | owner's or operator's facility. |
15 | | "Submerged" means any facility installed below the surface |
16 | | of a lake, river, or navigable waterway. |
17 | | "Tolerance zone" means: |
18 | | (1) if the diameter of the underground utility |
19 | | facility is indicated, the distance of one-half of the |
20 | | known diameter plus one and one-half feet on either side |
21 | | of the designated center line of the underground utility |
22 | | facility marking; |
23 | | (2) if the diameter of the underground utility |
24 | | facility is not indicated, one and one-half feet on either |
25 | | side of the outside edge of the underground utility |
26 | | facility marking; or |
|
| | 10300HB5546ham001 | - 13 - | LRB103 38732 SPS 72477 a |
|
|
1 | | (3) if submerged, a distance of 30 feet on either side |
2 | | of the indicated facility. |
3 | | The underground utility facility markings provided |
4 | | shall not indicate that the width of the marked |
5 | | underground utility facility is any greater than the |
6 | | actual width of the underground utility facility or 2 |
7 | | inches, whichever is greater. The tolerance zone shall |
8 | | also apply to visible utility structures, including, but |
9 | | not limited to, poles with overhead to underground |
10 | | transitions, pedestals, transformers, meters, hydrants, |
11 | | and valve boxes. There shall be a one and one-half foot |
12 | | tolerance zone horizontally around such facilities. |
13 | | "Underground utility facility" or "facility" means and |
14 | | includes wires, ducts, fiber optic cable, conduits, pipes, |
15 | | sewers, and cables and their connected appurtenances installed |
16 | | or existing beneath the surface of the ground or submerged and |
17 | | either owned, operated, or controlled by: |
18 | | (1) a public utility as defined in the Public |
19 | | Utilities Act; |
20 | | (2) a municipally owned or mutually owned utility |
21 | | providing a similar utility service; |
22 | | (3) a pipeline entity transporting gases, crude oil, |
23 | | petroleum products, or other hydrocarbon materials within |
24 | | the State; |
25 | | (4) a telecommunications carrier as defined in the |
26 | | Universal Telephone Service Protection Law of 1985, or by |
|
| | 10300HB5546ham001 | - 14 - | LRB103 38732 SPS 72477 a |
|
|
1 | | a company described in Section 1 of the Telephone Company |
2 | | Act; |
3 | | (5) a community antenna television system, as defined |
4 | | in the Illinois Municipal Code or the Counties Code; |
5 | | (6) a holder or broadband service, as those terms are |
6 | | defined in the Cable and Video Competition Law of 2007; |
7 | | (7) any other entity owning or operating underground |
8 | | facilities that transport or generate electrical power to |
9 | | other utility owners or operators; |
10 | | (8) an electric cooperative as defined in the Public |
11 | | Utilities Act; and |
12 | | (9) any other active member of JULIE. |
13 | | (Source: P.A. 94-623, eff. 8-18-05.) |
14 | | (220 ILCS 50/3) (from Ch. 111 2/3, par. 1603) |
15 | | Sec. 3. JULIE Membership. The owners or operators of |
16 | | underground utility facilities are required to be members of |
17 | | JULIE. JULIE shall require that all facility information |
18 | | needed to operate JULIE within each underground utility |
19 | | facility owner's or operator's domain be identified and |
20 | | provided by the underground utility facility owner or operator |
21 | | to JULIE or CATS facilities that are not currently |
22 | | participants in the State-Wide One-Call Notice System shall, |
23 | | within 6 months of the effective date of this Act, join the |
24 | | State-Wide One-Call Notice System. This Section shall not |
25 | | apply to utilities operating facilities or CATS facilities |
|
| | 10300HB5546ham001 | - 15 - | LRB103 38732 SPS 72477 a |
|
|
1 | | exclusively within the boundaries of a municipality with a |
2 | | population of at least one million persons . |
3 | | (Source: P.A. 86-674.) |
4 | | (220 ILCS 50/4) (from Ch. 111 2/3, par. 1604) |
5 | | Sec. 4. Required activities. Every excavator person who |
6 | | engages in nonemergency excavation or demolition shall: |
7 | | (a) take reasonable action to inform the excavator |
8 | | himself of the location of any underground utility |
9 | | facilities in and near the area for which such operation |
10 | | is to be conducted; |
11 | | (b) plan the excavation or demolition to avoid or |
12 | | minimize interference with underground utility facilities |
13 | | within the tolerance zone by utilizing such precautions |
14 | | that include, but are not limited to, hand or excavation, |
15 | | vacuum excavation methods to the depth of the proposed |
16 | | excavation or demolition , and visually inspecting the |
17 | | excavation while in progress until clear of the |
18 | | approximate location of the existing marked facility; |
19 | | (c) pre-mark the area of excavation if practical, use |
20 | | white paint, flags, stakes, or both, to outline the dig |
21 | | site ; |
22 | | (d) provide notice not less than 2 days 48 hours but no |
23 | | more than 10 14 calendar days in advance of the start of |
24 | | the excavation or demolition to the owners or operators of |
25 | | the underground utility facilities at or in and near the |
|
| | 10300HB5546ham001 | - 16 - | LRB103 38732 SPS 72477 a |
|
|
1 | | excavation or demolition area through JULIE the State-Wide |
2 | | One-Call Notice System or, in the case of nonemergency |
3 | | excavation or demolition within the boundaries of a |
4 | | municipality of at least one million persons which |
5 | | operates its own one-call notice system, through the |
6 | | one-call notice system which operates in that |
7 | | municipality . |
8 | | At a minimum, the notice required under this |
9 | | subsection (d) shall provide: |
10 | | (1) the excavator's person's name, address, phone |
11 | | number at which the excavator a person can be reached, |
12 | | and fax number , if available , a fax number and email |
13 | | address ; |
14 | | (2) the start date and time of the planned |
15 | | excavation or demolition; |
16 | | (3) the county and place or places all counties, |
17 | | cities, or townships, or any combination thereof, |
18 | | where the proposed excavation shall take place; |
19 | | (4) the address or location at which the |
20 | | excavation or demolition shall take place; |
21 | | (5) the type of work, and extent , and description |
22 | | of the area where the excavation or demolition is to |
23 | | occur of the work involved ; and |
24 | | (6) the section or quarter sections when the |
25 | | information in items (1) through (5) of this |
26 | | subsection (d) does not allow JULIE the State-Wide |
|
| | 10300HB5546ham001 | - 17 - | LRB103 38732 SPS 72477 a |
|
|
1 | | One-Call Notice System to determine the appropriate |
2 | | excavation or demolition site. This item (6) does not |
3 | | apply to residential property owners; |
4 | | (7) an indication of whether directional boring or |
5 | | horizontal directional drilling will be used; |
6 | | (8) an indication of whether the excavation will |
7 | | exceed 7 feet in depth; |
8 | | (9) an indication of how the proposed excavation |
9 | | or demolition has been pre-marked; |
10 | | (10) the identity of the project owner; and |
11 | | (11) the latitude and longitude of the relevant |
12 | | area, if available. |
13 | | The information specified in items (1) through (10) is |
14 | | still required when providing latitude and longitude; |
15 | | (e) provide, during and following excavation or |
16 | | demolition, such support for existing underground utility |
17 | | facilities in and near the excavation or demolition area |
18 | | as may be reasonably necessary for the protection of such |
19 | | facilities and known service laterals unless otherwise |
20 | | agreed to by the owner or operator of the underground |
21 | | facility or owners of any known service laterals ; |
22 | | (f) backfill all excavations in such manner and with |
23 | | such materials as may be reasonably necessary for the |
24 | | protection of existing underground utility facilities in |
25 | | and near the excavation or demolition area; |
26 | | (g) after February 29, 2004, when the excavation or |
|
| | 10300HB5546ham001 | - 18 - | LRB103 38732 SPS 72477 a |
|
|
1 | | demolition project will extend past 28 calendar days from |
2 | | the 25-day expiration date of the original notice provided |
3 | | under clause (d) or a subsequent extension notice, if |
4 | | marks are requested, the excavator shall pre-mark prior to |
5 | | requesting any subsequent extension notice , the excavator |
6 | | shall provide a subsequent notice to the owners or |
7 | | operators of the underground utility facilities in and |
8 | | near the excavation or demolition area through the |
9 | | State-Wide One-Call Notice System or, in the case of |
10 | | excavation or demolition within the boundaries of a |
11 | | municipality having a population of at least 1,000,000 |
12 | | inhabitants that operates its own one-call notice system, |
13 | | through the one-call notice system that operates in that |
14 | | municipality informing utility owners and operators that |
15 | | additional time to complete the excavation or demolition |
16 | | project will be required. The notice will provide the |
17 | | excavator with an additional 28 calendar days from the |
18 | | date of the subsequent notification to continue or |
19 | | complete the excavation or demolition project ; |
20 | | (h) exercise due care at all times to protect |
21 | | underground utility facilities and known service laterals . |
22 | | If, after proper notification through JULIE the State-Wide |
23 | | One-Call Notice System and upon arrival at the site of the |
24 | | proposed excavation, the excavator observes clear evidence |
25 | | of the presence of an unmarked or incompletely marked |
26 | | facility utility in the area of the proposed excavation, |
|
| | 10300HB5546ham001 | - 19 - | LRB103 38732 SPS 72477 a |
|
|
1 | | the excavator shall provide subsequent notice through |
2 | | JULIE of the unmarked or incompletely marked area and |
3 | | shall not begin excavating until all affected facilities |
4 | | have been marked or 2 hours , whichever is shorter, unless |
5 | | a greater time is provided by the excavator through JULIE |
6 | | after an additional call is made to the State-Wide |
7 | | One-Call Notice System for the area . The underground |
8 | | utility facility owner or operator of the facility utility |
9 | | shall respond within 2 hours unless a greater time is |
10 | | provided by the excavator through JULIE of the excavator's |
11 | | call to the State-Wide One-Call Notice System ; and |
12 | | (i) when factors, including, but not limited to, |
13 | | weather, construction activity, or vandalism, at the |
14 | | excavation site have caused the facility utility markings |
15 | | to become faded or indistinguishable, the excavator shall |
16 | | pre-mark again and provide a re-mark request an additional |
17 | | notice through JULIE the State-Wide One-Call Notice System |
18 | | requesting that only the affected areas where excavation |
19 | | or demolition is to continue be re-marked. Underground |
20 | | utility facility Facility owners or operators must respond |
21 | | to the notice to re-mark by the dig start date and time on |
22 | | the notice; and according to the requirements of Section |
23 | | 10 of this Act. |
24 | | (j) for informational and planning purposes only, |
25 | | prior notice of large projects may be provided to |
26 | | underground utility facility owners or operators through |
|
| | 10300HB5546ham001 | - 20 - | LRB103 38732 SPS 72477 a |
|
|
1 | | JULIE greater than 10 days in advance of the large project |
2 | | commencing. |
3 | | Nothing in this Section prohibits the use of any method of |
4 | | excavation if conducted in a manner that would avoid |
5 | | interference with underground utility facilities. |
6 | | (Source: P.A. 96-714, eff. 1-1-10.) |
7 | | (220 ILCS 50/4.1 new) |
8 | | Sec. 4.1. Watch and protect. |
9 | | (a) If, upon notice from JULIE, an underground utility |
10 | | facility owner or operator determines that the facility is |
11 | | within the proposed excavation area and the underground |
12 | | utility facility owner or operator desires to have an |
13 | | authorized representative present during excavation near the |
14 | | facility, the underground utility facility owner or operator |
15 | | shall contact the excavator prior to the dig start date and |
16 | | time provided on the notice to schedule a date and time for the |
17 | | underground utility facility owner or operator to be present |
18 | | when excavation will occur near the facility. |
19 | | (b) All excavators shall comply with the underground |
20 | | utility facility owner's or operator's request to be present |
21 | | during excavation near a owner or operator's facilities. In |
22 | | lieu of having an authorized representative present, the |
23 | | underground utility facility owner or operator may choose to |
24 | | perform an open cut utility locate of the facility to expose |
25 | | its location. The underground utility facility owner or |
|
| | 10300HB5546ham001 | - 21 - | LRB103 38732 SPS 72477 a |
|
|
1 | | operator shall comply with the excavator's schedule for when |
2 | | excavation will occur near the facility. |
3 | | (c) After excavation has started, if excavation near the |
4 | | underground utility facilities stops by more than one day and |
5 | | then recommences, the excavator shall establish direct contact |
6 | | with the underground utility facility owner or operator not |
7 | | less than one day prior to the excavation, each time the |
8 | | excavation is to occur, to advise the underground utility |
9 | | facility owner or operator of the excavation taking place. |
10 | | (d) Nothing in this Section shall prohibit an excavator |
11 | | from excavating prudently and carefully near the underground |
12 | | utility facility without the underground utility facility |
13 | | owner or operator present if the underground utility facility |
14 | | owner or operator waives the request to be present or to |
15 | | complete an open cut utility locate exposing the facility or |
16 | | is unable to comply with the excavator's schedule. |
17 | | (220 ILCS 50/5.1 new) |
18 | | Sec. 5.1. Positive response system. |
19 | | (a) Beginning January 1, 2026, an excavator shall confirm |
20 | | through the positive response system prior to excavation or |
21 | | demolition that all underground utility facility owners or |
22 | | operators that are identified on the notice have provided a |
23 | | status update, responded, or marked or provided an all-clear |
24 | | notification. |
25 | | (b) Beginning January 1, 2026, an underground utility |
|
| | 10300HB5546ham001 | - 22 - | LRB103 38732 SPS 72477 a |
|
|
1 | | facility owner or operator shall respond through the positive |
2 | | response system by the dig start date and time on the notice |
3 | | with an appropriate and accurate system code. A minimal delay |
4 | | not to exceed one hour or when the marking of the facilities is |
5 | | complete, whichever is longer, in reporting a system code in |
6 | | response to an emergency request shall not be a violation of |
7 | | this Section. |
8 | | (c) If an underground utility facility owner or operator |
9 | | fails to respond or provide a status update through the |
10 | | positive response system by the dig start date and time on the |
11 | | notice, or a later time as otherwise agreed upon and submitted |
12 | | through the positive response system, JULIE shall transmit an |
13 | | additional notification to that underground utility facility |
14 | | owner or operator and shall continue to send out daily |
15 | | notifications until the positive response system receives a |
16 | | response confirming compliance with this Section. |
17 | | (d) If an underground utility facility owner or operator |
18 | | fails to respond or provide a status update to the positive |
19 | | response system, the excavator may proceed after providing a |
20 | | no show or incomplete request through JULIE. The notified |
21 | | underground utility facility owners or operators shall respond |
22 | | by the dig start date and time on the notice. |
23 | | (e) If all notified underground utility facility owners or |
24 | | operators have responded as "marked" or "clear" prior to the |
25 | | expiration of the dig start date and time on the notice, the |
26 | | wait time shall be considered expired and no additional wait |
|
| | 10300HB5546ham001 | - 23 - | LRB103 38732 SPS 72477 a |
|
|
1 | | time is required prior to commencing with the excavation or |
2 | | demolition work listed on the notice. |
3 | | (220 ILCS 50/5.2 new) |
4 | | Sec. 5.2. Planning design request. |
5 | | (a) An underground utility facility owner or operator |
6 | | shall have the following responsibilities: |
7 | | (1) respond to a valid planning design request within |
8 | | 10 days after receiving the request or by such other date |
9 | | as shall be mutually agreed upon between the underground |
10 | | utility facility owner or operator and the designer or |
11 | | planner. The underground utility facility owner or |
12 | | operator shall provide information regarding the location, |
13 | | size, if greater than 1.5 inches in diameter, which shall |
14 | | be generically listed as communication, electric, gas, |
15 | | water, sewer, streetlight, or traffic control and if |
16 | | direct buried or in conduit or a duct package, of |
17 | | facilities based on the best information available to the |
18 | | underground utility facility owner or operator within the |
19 | | scope of the proposed project; |
20 | | (2) respond to a planning design request in one of the |
21 | | following methods: |
22 | | (A) provide the most current digital, KMZ file or |
23 | | shapefile, or paper drawings or prints, that are drawn |
24 | | to scale, when available, and include visible utility |
25 | | structures, including measurements from back of curb, |
|
| | 10300HB5546ham001 | - 24 - | LRB103 38732 SPS 72477 a |
|
|
1 | | sidewalk, edge of pavement, centerline of ditch, |
2 | | property lines, and other similar items; |
3 | | (B) request the proposed plans or drawings from |
4 | | the designer or planner and illustrate the location of |
5 | | the underground utility facility owner's or operator's |
6 | | facilities, drawn to scale, and, if available, provide |
7 | | the type and size, as described in paragraph (1), of |
8 | | the facilities, including visible structures on the |
9 | | plans; |
10 | | (C) locate and mark the underground utility |
11 | | facility owner's or operator's facilities within the |
12 | | scope of the proposed project, as agreed to with the |
13 | | planner or designer; |
14 | | (D) if the responding underground utility facility |
15 | | owner or operator is unable to comply with paragraph |
16 | | (A) or (B), then the underground utility facility |
17 | | owner or operator shall mark the facilities within the |
18 | | scope of the proposed project, as agreed to with the |
19 | | planner or designer; or |
20 | | (E) if marking of infrastructure is the preferred |
21 | | or required response of the underground utility |
22 | | facility owner or operator, the underground utility |
23 | | facility owner or operator need only mark main line |
24 | | facilities or any service lines that would otherwise |
25 | | be considered main line due to size or type, as |
26 | | described in paragraph (1); and |
|
| | 10300HB5546ham001 | - 25 - | LRB103 38732 SPS 72477 a |
|
|
1 | | (3) may charge a nominal fee to locate and mark the |
2 | | proposed project, as described in subparagraph (C) or (D) |
3 | | of paragraph (2). |
4 | | (b) The planner or designer shall have the following |
5 | | responsibilities: |
6 | | (1) follow the guidelines set forth in CI/ASCE 38-02 |
7 | | Standard Guidelines for the Collection and Depiction of |
8 | | Existing Subsurface Utility Data, as from time to time |
9 | | amended, when preparing plans or drawings; |
10 | | (2) illustrate on all appropriate documents the |
11 | | position, size, and type, as described in paragraph (1) of |
12 | | subsection (a), of all known facilities obtained in the |
13 | | planning design request process and include the valid |
14 | | planning design request number provided by JULIE on any |
15 | | plans or drawings; and |
16 | | (3) make all reasonable efforts to prepare the plans |
17 | | or drawings to minimize interference with known existing |
18 | | and proposed facilities in the proposed project area. |
19 | | (c) A planning design request shall include the following |
20 | | information: |
21 | | (1) name, address, telephone number, office and cell |
22 | | phone, and, if available, email address of the designated |
23 | | contact requesting the information; |
24 | | (2) name, address, telephone number, office and cell |
25 | | phone, and, if available, email address of the project |
26 | | owner; |
|
| | 10300HB5546ham001 | - 26 - | LRB103 38732 SPS 72477 a |
|
|
1 | | (3) the approximate date when the facility information |
2 | | is required; and |
3 | | (4) the specific area requiring facility information |
4 | | by one or more of the following means: |
5 | | (A) the county and place or places involved in the |
6 | | proposed project; |
7 | | (B) street names involved in the proposed project |
8 | | or the north, south, east, and west boundaries of the |
9 | | proposed project or the section number or numbers |
10 | | involved in the proposed project; |
11 | | (C) latitude and longitude coordinates of the |
12 | | outside edges of the proposed project; |
13 | | (D) digital data such as, but not limited to, |
14 | | shapefiles when technology and software allow; and |
15 | | (E) the type of work projected to take place |
16 | | within the proposed project. |
17 | | Any known site-specific facility information shall be made |
18 | | available to the project owner to be delivered to qualified |
19 | | bidders of the proposed project. |
20 | | (220 ILCS 50/5.3 new) |
21 | | Sec. 5.3. Joint meet notification. |
22 | | (a) A joint meet notification shall include the following |
23 | | information: |
24 | | (1) the excavator's name, address, phone number at |
25 | | which the excavator can be reached, and, if available, a |
|
| | 10300HB5546ham001 | - 27 - | LRB103 38732 SPS 72477 a |
|
|
1 | | fax number and email address; |
2 | | (2) the county and place or places where the work will |
3 | | be performed; |
4 | | (3) street names involved in the project or the north, |
5 | | south, east, and west boundaries of the project or the |
6 | | section number or numbers involved in the project; |
7 | | (4) the date, time, and location where the joint meet |
8 | | will take place, which shall be near the project site; and |
9 | | (5) a minimum advance notice of the joint meet of 2 |
10 | | days, but no more than 60 days prior to the planned start |
11 | | of excavation or demolition. |
12 | | (b) Upon the receipt of a joint meet notification, an |
13 | | underground utility facility owner or operator shall attend |
14 | | the joint meet, either in-person or remotely, at the specified |
15 | | time and location. If there is a conflict between joint meet |
16 | | notifications, an excavator that provided a joint meet |
17 | | notification may receive a communication from an underground |
18 | | utility facility owner or operator requesting an alternate |
19 | | meeting time or date. |
20 | | (c) When a joint meet notification occurs as part of a |
21 | | large project, the excavator shall notify the project owner |
22 | | and the designer or planner when and where the joint meet is to |
23 | | occur. |
24 | | (d) Multiple joint meets shall be required in the case of a |
25 | | large project that extends into multiple places. The excavator |
26 | | shall schedule, at a minimum, one joint meet per place to |
|
| | 10300HB5546ham001 | - 28 - | LRB103 38732 SPS 72477 a |
|
|
1 | | accommodate travel restrictions of responding underground |
2 | | utility facility owners or operators. A single electronic |
3 | | meeting covering multiple places is also acceptable. |
4 | | (e) Prior to the meeting, the excavator shall physically |
5 | | or electronically pre-mark the extent of the initial request |
6 | | for the proposed excavation area or route if normal notice |
7 | | requests are planned to be submitted with excavation beginning |
8 | | after the minimum advance notice of 2 days after the joint |
9 | | meet. The minimum advance notice for a large project is 5 days. |
10 | | (f) The individuals participating in the joint meet shall |
11 | | agree to their individual obligations consistent with the |
12 | | project. The underground utility facility owner or operator, |
13 | | along with the excavator involved, shall work in a cooperative |
14 | | manner to negotiate in good faith. These obligations may vary |
15 | | from project to project. The individuals participating at the |
16 | | joint meet shall have the flexibility to make decisions |
17 | | consistent with the project's parameters. The individuals |
18 | | participating in the joint meet are not required to set |
19 | | specific standards for all projects. |
20 | | (g) The scope of the project shall be defined at the joint |
21 | | meet and specific project details, including, but not limited |
22 | | to, the number of phases, and the number of excavation crews |
23 | | working for the contractor or subcontractors, to the extent |
24 | | that the information can be determined. |
25 | | (h) The size and number of normal notice requests agreed |
26 | | to be submitted at one time at the joint meet shall be |
|
| | 10300HB5546ham001 | - 29 - | LRB103 38732 SPS 72477 a |
|
|
1 | | documented by the excavator in the meeting notes and made |
2 | | available to those participating in the joint meet. Any |
3 | | mutually agreed upon initial or amended meeting notes shall, |
4 | | at a minimum, include: (1) the date and time of the |
5 | | interaction; (2) all names of the individuals involved, and |
6 | | (3) an acknowledgment by the individuals that agreed to the |
7 | | meeting notes. Meeting notes shall be retained by the |
8 | | excavator through JULIE, Inc., for at least 5 years after the |
9 | | date of the joint meet. |
10 | | (i) If an underground utility facility owner or operator |
11 | | fails to attend the joint meet and does not request an |
12 | | alternate time or date to meet prior to commencement of |
13 | | excavation, the excavator may proceed according to the |
14 | | agreement reached with those attending the meeting. |
15 | | (j) Within 60 days after the joint meet, the excavator |
16 | | shall submit the normal notice requests consistent with the |
17 | | agreements reached at the joint meet. |
18 | | (k) The initial normal notice requests submitted after the |
19 | | joint meet shall require a minimum of 2 days advance notice and |
20 | | 5 days advance notice for large projects. All remaining normal |
21 | | notice requests shall be submitted in agreement with the joint |
22 | | meet schedule and provide a minimum advance notice of 2 days. |
23 | | The excavator shall not submit normal notice requests until |
24 | | after the joint meet. |
25 | | (l) If the project start is delayed more than 60 days, or |
26 | | the scope of the project changes after the joint meet has been |
|
| | 10300HB5546ham001 | - 30 - | LRB103 38732 SPS 72477 a |
|
|
1 | | held and the locate schedule agreed to, a new joint meet |
2 | | notification shall be required. |
3 | | (m) If an excavator creates multiple normal notice |
4 | | requests for a single project without a joint meet being held, |
5 | | an affected underground utility facility owner or operator may |
6 | | contact the excavator and recommend the excavator follow the |
7 | | joint meet process to assist in working out a locate schedule. |
8 | | A notified excavator that fails to follow the joint meet |
9 | | process may realize delays in marking of facilities on their |
10 | | project. In accordance with subsection (e) of Section 10, a |
11 | | delay in marking is not necessarily deemed a violation of this |
12 | | Act. |
13 | | (220 ILCS 50/5.4 new) |
14 | | Sec. 5.4. Geographic information system data. Geographic |
15 | | information system data shall be provided to JULIE by any |
16 | | county or State agency that has provided substantially similar |
17 | | data to any other not-for-profit or State agency utilizing |
18 | | such data for public display of information or to be utilized |
19 | | by a not-for-profit or agency in the interest of public |
20 | | safety. This data shall be provided to JULIE at a cost not to |
21 | | exceed the actual cost of transmission of the data. |
22 | | (220 ILCS 50/6) (from Ch. 111 2/3, par. 1606) |
23 | | Sec. 6. Emergency excavation or demolition. |
24 | | (a) Every excavator person who engages in emergency |
|
| | 10300HB5546ham001 | - 31 - | LRB103 38732 SPS 72477 a |
|
|
1 | | excavation or demolition outside of the boundaries of a |
2 | | municipality of at least one million persons which operates |
3 | | its own one-call notice system shall take all reasonable |
4 | | precautions to avoid or minimize interference between the |
5 | | emergency work and existing underground utility facilities in |
6 | | and near the excavation or demolition area, through the |
7 | | State-Wide One-Call Notice System, and shall notify, as far in |
8 | | advance as possible, the underground utility facility owners |
9 | | or operators of such underground utility facilities in and |
10 | | near the emergency excavation or demolition area, through |
11 | | JULIE the State-Wide One-Call Notice System . At a minimum, the |
12 | | notice required under this subsection (a) shall provide: |
13 | | (1) the excavator's person's name, address, and (i) |
14 | | phone number at which the excavator with knowledge of the |
15 | | emergency excavation or demolition a person can be reached |
16 | | and (ii) fax number , if available , a fax number and email |
17 | | address ; |
18 | | (2) the start date and time of the planned emergency |
19 | | excavation or demolition; |
20 | | (3) the address or location at which the emergency |
21 | | excavation or demolition will take place; and |
22 | | (4) the type of work, extent, and description of the |
23 | | area where the emergency excavation or demolition is to |
24 | | occur; and |
25 | | (5) the county and place or places where the emergency |
26 | | excavation or demolition will take place and extent of the |
|
| | 10300HB5546ham001 | - 32 - | LRB103 38732 SPS 72477 a |
|
|
1 | | work involved . |
2 | | (b) There is a minimum wait time of 2 hours or the date and |
3 | | time requested on the notice, whichever is longer, after an |
4 | | emergency locate notification request is made through JULIE |
5 | | the State-Wide One-Call Notice System . If the conditions at |
6 | | the site dictate an earlier start than the date and time on the |
7 | | notice required wait time , it is the responsibility of the |
8 | | excavator to demonstrate that site conditions warranted this |
9 | | earlier start time. |
10 | | (c) Upon notice by the excavator person engaged in |
11 | | emergency excavation or demolition, the underground utility |
12 | | facility owner or operator owner or operator of an underground |
13 | | utility facility in or near the excavation or demolition area |
14 | | shall communicate with the excavator person engaged in |
15 | | emergency excavation or demolition within 2 hours or by the |
16 | | date and time requested on the notice, whichever is longer by : |
17 | | (1) marking the approximate location of underground |
18 | | facilities; |
19 | | (2) advising the excavator person excavating that |
20 | | their underground facilities are not in conflict with the |
21 | | emergency excavation or demolition ; or |
22 | | (3) notifying the excavator person excavating that the |
23 | | underground utility facility owner or operator shall be |
24 | | delayed in marking because of conditions as referenced in |
25 | | subsection (g) of Section 11 of this Act. |
26 | | (d) The notice by the underground utility facility owner |
|
| | 10300HB5546ham001 | - 33 - | LRB103 38732 SPS 72477 a |
|
|
1 | | or operator to the excavator shall be provided utilizing the |
2 | | positive response system, in accordance with Section 5.1, and |
3 | | prior to January 1, 2026 may also person engaged in emergency |
4 | | excavation or demolition may be provided by phone or phone |
5 | | message or by marking the excavation or demolition area. The |
6 | | underground utility facility owner or operator has discharged |
7 | | the underground utility facility owner's or operator's |
8 | | obligation to provide notice under this Section if the |
9 | | underground utility facility owner or operator attempts to |
10 | | provide notice by positive response or by telephone but is |
11 | | unable to do so because the excavator person engaged in the |
12 | | emergency excavation or demolition does not answer the his or |
13 | | her telephone or does not have an answering machine , or |
14 | | answering service , or voicemail to receive the telephone call |
15 | | or positive response, in accordance with Section 5.1 . If the |
16 | | underground utility facility owner or operator attempts to |
17 | | provide additional notice by telephone or by facsimile but |
18 | | receives a busy signal, that attempt shall not discharge the |
19 | | underground utility facility owner or operator from the |
20 | | obligation to provide notice under this Section. |
21 | | (b) Every person who engages in emergency excavation or |
22 | | demolition within the boundaries of a municipality of at least |
23 | | one million persons which operates its own one-call notice |
24 | | system shall take all reasonable precautions to avoid or |
25 | | minimize interference between the emergency work and existing |
26 | | underground utility facilities in and near the excavation or |
|
| | 10300HB5546ham001 | - 34 - | LRB103 38732 SPS 72477 a |
|
|
1 | | demolition area, through the municipality's one-call notice |
2 | | system, and shall notify, as far in advance as possible, the |
3 | | owners and operators of underground utility facilities in and |
4 | | near the emergency excavation or demolition area, through the |
5 | | municipality's one-call notice system. |
6 | | (e) (c) The reinstallation of traffic control devices |
7 | | shall be deemed an emergency for purposes of this Section. |
8 | | (f) (d) An open cut utility locate shall be deemed an |
9 | | emergency for purposes of this Section. |
10 | | (g) During an emergency situation, where the underground |
11 | | utility facility owner or operator has a widespread emergency |
12 | | situation beyond the equipment or personnel capabilities to |
13 | | facilitate a timely repair or correction of the emergency, the |
14 | | underground utility facility owner or operator may utilize |
15 | | subcontractors to facilitate the work without a separate |
16 | | emergency notice by the subcontractor. The underground utility |
17 | | facility owner or operator shall be responsible for the |
18 | | actions of the subcontractor, unless the subcontractor has |
19 | | obtained the subcontractor's own emergency notice. |
20 | | (h) Emergency notices provided through JULIE shall expire |
21 | | 10 days after the date of the notice. |
22 | | (Source: P.A. 96-714, eff. 1-1-10.) |
23 | | (220 ILCS 50/7) (from Ch. 111 2/3, par. 1607) |
24 | | Sec. 7. Damage or dislocation. |
25 | | (a) In the event of any damage to or dislocation of any |
|
| | 10300HB5546ham001 | - 35 - | LRB103 38732 SPS 72477 a |
|
|
1 | | underground utility facilities in connection with any |
2 | | excavation or demolition, emergency or nonemergency, the |
3 | | excavator person responsible for the excavation or demolition |
4 | | operations shall immediately notify the affected underground |
5 | | utility facility owner or operator and JULIE utility and the |
6 | | State-Wide One-Call Notice System and cease excavation in the |
7 | | area of the damage when the damaged facility is a threat to |
8 | | life or property or if otherwise required by law or, in the |
9 | | case of damage or dislocation in connection with any |
10 | | excavation or demolition within the boundaries of a |
11 | | municipality having a population of at least 1,000,000 |
12 | | inhabitants that operates its own one-call notice system, |
13 | | notify the affected utility and the one-call notice system |
14 | | that operates in that municipality . |
15 | | (b) The excavator person responsible for the excavation or |
16 | | demolition shall not attempt to repair, clamp, or constrict |
17 | | the damaged utility facility unless under the direct |
18 | | supervision or advisement of the underground utility facility |
19 | | owner or operator. At no time shall an excavator a person under |
20 | | this Act be required by an underground a utility facility |
21 | | owner or operator to attempt to repair, clamp, or constrict a |
22 | | damaged utility facility. In the event of any damage to any |
23 | | underground utility facility that results in the escape of any |
24 | | flammable, toxic, or corrosive gas or liquid, the excavator |
25 | | person responsible for the excavation or demolition shall call |
26 | | 9-1-1 and notify authorities of the damage. |
|
| | 10300HB5546ham001 | - 36 - | LRB103 38732 SPS 72477 a |
|
|
1 | | (c) Underground utility facility owners Owners and |
2 | | operators of underground utility facilities that are damaged , |
3 | | and the excavator involved , shall work in a cooperative and |
4 | | expeditious manner to repair the affected facility utility . |
5 | | (d) The underground utility facility owner or operator |
6 | | shall provide to JULIE a phone number with a dedicated |
7 | | extension, if applicable, that can be provided to the |
8 | | excavator allowing immediate notification by the excavator to |
9 | | the underground utility facility owner or operator of the |
10 | | potential damage. |
11 | | (e) At a minimum, the notice required under this Section |
12 | | shall provide: |
13 | | (1) a reference to the original excavation or |
14 | | demolition notice, if one exists; |
15 | | (2) the type of facility damaged, if known; |
16 | | (3) the name of the affected underground utility |
17 | | facility owner or operator, if known; and |
18 | | (4) the location of the damaged facility at the |
19 | | excavation or demolition site. |
20 | | (Source: P.A. 96-714, eff. 1-1-10.) |
21 | | (220 ILCS 50/7.5 new) |
22 | | Sec. 7.5. Exposed facility. |
23 | | (a) If any previously unmarked facility is exposed during |
24 | | excavation or demolition, emergency or nonemergency, the |
25 | | excavator responsible for the excavation or demolition |
|
| | 10300HB5546ham001 | - 37 - | LRB103 38732 SPS 72477 a |
|
|
1 | | operations shall immediately notify JULIE. |
2 | | (b) At a minimum, the notice required under this Section |
3 | | shall provide: |
4 | | (1) a reference to the original excavation or |
5 | | demolition notice, if one exists; |
6 | | (2) the type of exposed facility, if known; |
7 | | (3) the name of the affected underground utility |
8 | | facility owner or operator, if known; and |
9 | | (4) the location of the exposed facility at the |
10 | | excavation or demolition site. |
11 | | (220 ILCS 50/8) (from Ch. 111 2/3, par. 1608) |
12 | | Sec. 8. Liability or financial responsibility. |
13 | | (a) Nothing in this Act shall be deemed to affect or |
14 | | determine the financial responsibility for any operation under |
15 | | this Act or liability of any entity or individual person for |
16 | | any damages that occur unless specifically stated otherwise. |
17 | | (b) Nothing in this Act shall be deemed to provide for |
18 | | liability or financial responsibility of the Department of |
19 | | Transportation, its officers and employees concerning any |
20 | | underground utility facility or CATS facility located on |
21 | | highway right-of-way by permit issued under the provisions of |
22 | | Section 9-113 of the Illinois Highway Code. It is not the |
23 | | intent of this Act to change any remedies in law regarding the |
24 | | duty of providing lateral support. |
25 | | (c) Neither JULIE the State-Wide One-Call Notice System |
|
| | 10300HB5546ham001 | - 38 - | LRB103 38732 SPS 72477 a |
|
|
1 | | nor any of its officers, agents, or employees shall be liable |
2 | | for damages for injuries or death to persons or damage to |
3 | | property caused by acts or omissions in the receipt, |
4 | | recording, or transmission of notices locate requests or other |
5 | | information in the performance of its duties as JULIE the |
6 | | State-Wide One-Call Notice System , unless the act or omission |
7 | | was the result of willful and wanton misconduct. |
8 | | (d) Any residential property owner who fails to comply |
9 | | with any provision of this Act and damages underground utility |
10 | | facilities or CATS facilities while engaging in excavation or |
11 | | demolition on such residential property shall not be subject |
12 | | to a penalty under this Act, but shall be liable for the damage |
13 | | caused to the underground utility facility owners or operators |
14 | | owner or operator of the damaged underground utility |
15 | | facilities or CATS facilities . |
16 | | (Source: P.A. 92-179, eff. 7-1-02.) |
17 | | (220 ILCS 50/9) (from Ch. 111 2/3, par. 1609) |
18 | | Sec. 9. Negligence. |
19 | | (a) When it is shown by competent evidence in any action |
20 | | for damages to underground utility facilities or CATS |
21 | | facilities that such damages resulted from excavation or |
22 | | demolition and that the excavator person engaged in such |
23 | | excavation or demolition failed to comply with the provisions |
24 | | of this Act, that excavator person shall be deemed prima facie |
25 | | guilty of negligence. |
|
| | 10300HB5546ham001 | - 39 - | LRB103 38732 SPS 72477 a |
|
|
1 | | (b) When it is shown by competent evidence in any action |
2 | | for damages to excavators persons , material , or equipment |
3 | | brought by excavators persons undertaking excavation or |
4 | | demolition acting in compliance with the provisions of this |
5 | | Act that such damages resulted from the failure of underground |
6 | | utility facility owners or and operators of underground |
7 | | facilities or CATS facilities to comply with the provisions of |
8 | | this Act, those underground utility facility owners or and |
9 | | operators shall be deemed prima facie guilty of negligence. |
10 | | (Source: P.A. 86-674.) |
11 | | (220 ILCS 50/10) (from Ch. 111 2/3, par. 1610) |
12 | | Sec. 10. Record of notice; marking of facilities. |
13 | | (a) Upon notice by the excavator person engaged in |
14 | | excavation or demolition , the underground utility facility |
15 | | owners or operators person owning or operating underground |
16 | | utility facilities in or near the excavation or demolition |
17 | | area shall cause a written record to be made of the notice and |
18 | | shall mark, within 48 hours of receipt of notice or by the dig |
19 | | start requested date and time indicated on the notice, |
20 | | whichever is later, the approximate locations of such |
21 | | facilities so as to enable the excavator person excavating or |
22 | | demolishing to establish the location of the underground |
23 | | utility facilities. |
24 | | For submerged facilities, when the owner or operator of |
25 | | the submerged facilities determines that a proposed excavation |
|
| | 10300HB5546ham001 | - 40 - | LRB103 38732 SPS 72477 a |
|
|
1 | | or demolition which could include anchoring, pile driving, |
2 | | dredging, or any other water bottom contact for any means |
3 | | performed is in proximity to or in conflict with, submerged |
4 | | facilities located under a lake, river, or navigable waterway, |
5 | | the owner or operator of the submerged facilities shall |
6 | | identify the estimated horizontal route of the submerged |
7 | | facilities, within 15 days or by a date and time mutually |
8 | | agreed to, using marking buoys, other suitable devices, or GPS |
9 | | location data unless directed otherwise by an agency having |
10 | | jurisdiction over the waters under which the submerged |
11 | | facilities are located. |
12 | | (b) Underground utility facility owners or Owners and |
13 | | operators of underground sewer facilities that are located |
14 | | outside the boundaries of a municipality having a population |
15 | | of at least 1,000,000 inhabitants shall be required to respond |
16 | | and mark the approximate location of those sewer facilities |
17 | | when the excavator indicates, in the notice required in |
18 | | Section 4, that the excavation or demolition project will |
19 | | exceed a depth of 7 feet. "Depth", in this case, is defined as |
20 | | the distance measured vertically from the surface of the |
21 | | ground to the top of the sewer facility. |
22 | | (c) Underground utility facility owners or operators of |
23 | | Owners and operators of underground sewer facilities that are |
24 | | located outside the boundaries of a municipality having a |
25 | | population of at least 1,000,000 inhabitants shall be required |
26 | | at all times to mark locate the approximate location of those |
|
| | 10300HB5546ham001 | - 41 - | LRB103 38732 SPS 72477 a |
|
|
1 | | sewer facilities when: |
2 | | (1) directional boring is the indicated type of |
3 | | excavation work being performed within the notice; |
4 | | (2) the underground sewer facilities owned are |
5 | | non-gravity, pressurized force mains; or |
6 | | (3) the excavation indicated will occur in the |
7 | | immediate proximity of known underground sewer facilities |
8 | | that are less than 7 feet deep. |
9 | | (d) Underground utility facility owners Owners or |
10 | | operators of underground sewer facilities that are located |
11 | | outside the boundaries of a municipality having a population |
12 | | of at least 1,000,000 inhabitants shall not hold an excavator |
13 | | liable for damages that occur to sewer facilities that were |
14 | | not required to be marked under this Section, provided that |
15 | | prompt notice of known the damage is made to JULIE the |
16 | | State-Wide One-Call Notice System and the underground utility |
17 | | facility owners or operators utility owner as required in |
18 | | Section 7. |
19 | | (e) All entities persons subject to the requirements of |
20 | | this Act shall plan and conduct their work consistent with |
21 | | reasonable business practices. |
22 | | (1) Conditions may exist making it unreasonable to |
23 | | request that locations be marked by the dig start within |
24 | | 48 hours or by the requested date and time indicated on the |
25 | | notice , whichever is later . |
26 | | (A) In such situations, the excavator and the |
|
| | 10300HB5546ham001 | - 42 - | LRB103 38732 SPS 72477 a |
|
|
1 | | underground utility facility owner or operator shall |
2 | | interact in good faith to establish a mutually |
3 | | agreeable date and time for the completion of the |
4 | | request. |
5 | | (B) All mutually agreed upon modifications to the |
6 | | dig start date and time shall be fully documented by |
7 | | the underground utility facility owner or operator and |
8 | | include, at a minimum, the date and time of the |
9 | | interaction, the names of the individuals involved, |
10 | | and acknowledgment by the individuals that agreed to |
11 | | the modification and the new dig start date and time |
12 | | that was mutually agreed upon by both parties. The |
13 | | underground utility facility owner or operator shall |
14 | | retain through JULIE, Inc., the documentation for at |
15 | | least 5 years after the date of the expiration of the |
16 | | notice. |
17 | | (2) It is unreasonable to request underground utility |
18 | | facility owners or and operators of underground utility |
19 | | facilities to mark locate all of their facilities in an |
20 | | affected area upon short notice in advance of a large or |
21 | | extensive nonemergency project . , or |
22 | | (3) It is unreasonable to request extensive notices |
23 | | locates in excess of a reasonable excavation or demolition |
24 | | work schedule . , or |
25 | | (4) It is unreasonable to request notices locates |
26 | | under conditions where a repeat request is likely to be |
|
| | 10300HB5546ham001 | - 43 - | LRB103 38732 SPS 72477 a |
|
|
1 | | made because of the passage of time or adverse job |
2 | | conditions. |
3 | | (5) During periods where the notice volumes or dig |
4 | | site notification areas exceed the historical averages as |
5 | | determined by the reasonable control measurements for the |
6 | | place, only those additional non-emergency requests that |
7 | | are not part of a large project, when that large project |
8 | | has been submitted at least 60 days in advance of the start |
9 | | of the large project by underground utility facility |
10 | | owners or operators or their contractors or subcontractors |
11 | | for excavation work for the underground utility facility |
12 | | owners or operators within the place, may be subject to a |
13 | | request from the underground utility facility owner or |
14 | | operator or the owner or operator's locate contractors or |
15 | | subcontractors for an additional wait time of up to 2 days |
16 | | for the underground utility facility owner or operator, |
17 | | whether utilizing in-house or contract locators, to |
18 | | respond to locate and mark, or provide a no conflict |
19 | | response. It is the responsibility of the requesting |
20 | | underground utility facility owner or operator to document |
21 | | any modification as outlined in paragraph (1) of |
22 | | subsection (e) of Section 10. |
23 | | (f) Underground utility facility owners or Owners and |
24 | | operators , whether utilizing in-house or contract locators, |
25 | | and the owner or operator's locate contractors or |
26 | | subcontractors of underground utility facilities must |
|
| | 10300HB5546ham001 | - 44 - | LRB103 38732 SPS 72477 a |
|
|
1 | | reasonably anticipate seasonal fluctuations in the number of |
2 | | notices locate requests and staff accordingly. |
3 | | Seasonal fluctuations shall not be considered within the |
4 | | reasonable control of underground utility facility owners or |
5 | | operators and the owner or operator's locate contractors or |
6 | | subcontractors within a place or places, when the notice |
7 | | volumes exceed the historical averages as determined by the |
8 | | reasonable control measurement, for non-emergency requests for |
9 | | utility excavation work for underground utility facility |
10 | | owners or operators, that is not part of a large project that |
11 | | has provided at least a 60 day advance notice. |
12 | | Only utility excavators when doing utility work may be |
13 | | impacted by this subsection and may incur an additional wait |
14 | | time of up to 2 days. |
15 | | (g) If an underground utility facility owner or operator a |
16 | | person owning or operating underground utility facilities |
17 | | receives a notice under this Section but does not own or |
18 | | operate any underground utility facilities within the proposed |
19 | | excavation or demolition area described in the notice, that |
20 | | underground utility facility owner or operator, by the dig |
21 | | start date and time on the notice person, within 48 hours or by |
22 | | the requested date and time indicated on the notice, whichever |
23 | | is later, after receipt of the notice , shall so notify the |
24 | | excavator who initiated the notice in accordance with Section |
25 | | 5.1, and prior to January 1, 2026, may person engaged in |
26 | | excavation or demolition who initiated the notice, unless the |
|
| | 10300HB5546ham001 | - 45 - | LRB103 38732 SPS 72477 a |
|
|
1 | | person who initiated the notice expressly waives the right to |
2 | | be notified that no facilities are located within the |
3 | | excavation or demolition area. The notification by the owner |
4 | | or operator of underground utility facilities to the person |
5 | | engaged in excavation or demolition may be provided in any |
6 | | reasonable manner including, but not limited to, notification |
7 | | in any one of the following ways: |
8 | | (1) by face-to-face communication; |
9 | | (2) by phone or phone message; |
10 | | (3) by facsimile or email ; |
11 | | (4) by posting in the excavation or demolition area; |
12 | | or |
13 | | (5) by marking the excavation or demolition area. |
14 | | (h) The underground utility facility owner or operator of |
15 | | those facilities has discharged the underground utility |
16 | | facility owner's or operator's obligation to provide notice |
17 | | under this Section if the underground utility facility owner |
18 | | or operator attempts to provide notice utilizing the positive |
19 | | response system, in accordance with Section 5.1, and prior to |
20 | | January 1, 2026, by : |
21 | | (1) telephone or by facsimile, if the person has |
22 | | supplied a facsimile number , but is unable to do so |
23 | | because the excavator person engaged in the excavation or |
24 | | demolition does not answer the his or her telephone and or |
25 | | does not have the ability to receive telephone messages; |
26 | | (2) facsimile, if the excavator has supplied a |
|
| | 10300HB5546ham001 | - 46 - | LRB103 38732 SPS 72477 a |
|
|
1 | | facsimile number and does not have a facsimile machine in |
2 | | operation to receive the facsimile transmission; or |
3 | | (3) email, if the excavator has supplied an email |
4 | | address and the message is electronically undeliverable an |
5 | | answering machine or answering service to receive the |
6 | | telephone call or does not have a facsimile machine in |
7 | | operation to receive the facsimile transmission . |
8 | | If the underground utility facility owner or operator |
9 | | attempts to provide additional notice by telephone or by |
10 | | facsimile but receives a busy signal, that attempt shall not |
11 | | serve to discharge the underground utility facility owner or |
12 | | operator of the obligation to provide notice under this |
13 | | Section. |
14 | | (i) Any excavator or legal entity, public or private, who, |
15 | | on or after January 1, 2026, installs a nonconductive service |
16 | | lateral shall ensure that the installation is locatable by |
17 | | electromagnetic means or other equally effective means for |
18 | | marking the location of the service lateral. This subsection |
19 | | does not apply to minor repairs to, or partial replacements |
20 | | of, service laterals installed prior to January 1, 2026. |
21 | | A person engaged in excavation or demolition may expressly |
22 | | waive the right to notification from the owner or operator of |
23 | | underground utility facilities that the owner or operator has |
24 | | no facilities located in the proposed excavation or demolition |
25 | | area. Waiver of notice is only permissible in the case of |
26 | | regular or nonemergency locate requests. The waiver must be |
|
| | 10300HB5546ham001 | - 47 - | LRB103 38732 SPS 72477 a |
|
|
1 | | made at the time of the notice to the State-Wide One-Call |
2 | | Notice System. A waiver made under this Section is not |
3 | | admissible as evidence in any criminal or civil action that |
4 | | may arise out of, or is in any way related to, the excavation |
5 | | or demolition that is the subject of the waiver. |
6 | | (j) For the purposes of this Act, the following color |
7 | | coding shall be used to mark the approximate location of |
8 | | facilities by the underground utility facility owners or |
9 | | operators who underground facility operators may utilize a |
10 | | combination of flags, lathe with colored ribbon, chalk, |
11 | | whiskers, or stakes, and paint as when possible on non-paved |
12 | | surfaces and when dig site and seasonal conditions warrant. If |
13 | | the approximate location of an underground utility facility is |
14 | | marked with stakes or other physical means, the following |
15 | | color coding shall be employed: |
|
16 | | Underground Facility type Identification Color |
|
|
17 | | Underground utility facility owner or | 18 | | operator or contract locator use only | | |
19 | | Facility Owner or Agent Use Only | | | 20 | | | |
21 | | Electric Power, Distribution and | | |
22 | | Transmission ........................ | Safety Red | |
23 | | Municipal Electric Systems .............. | Safety Red | |
|
|
| | 10300HB5546ham001 | - 48 - | LRB103 38732 SPS 72477 a |
|
|
1 | | Gas Distribution and Transmission ....... | High Visibility Safety Yellow | |
2 | | Oil Distribution and Transmission ....... | High Visibility Safety Yellow | |
3 | | Communication Systems . | Safety Alert Orange | |
4 | | Telephone and Telegraph Systems ......... | Safety Alert Orange | |
5 | | Community Antenna Television Systems .... | Safety Alert Orange | |
6 | | Water Systems ........................... | Safety Precaution Blue | |
7 | | Sewer Systems ........................... | Safety Green | |
8 | | Non-potable Water and Slurry Lines ...... | Safety Purple | | 9 | | | |
10 | | Excavator Use Only | | | 11 | | | |
12 | | Temporary Survey ........................ | Safety Pink | |
13 | | Proposed Excavation ..................... | 14 | | | Safety White (Black when snow is on the ground) |
|
15 | | (Source: P.A. 96-714, eff. 1-1-10 .) |
16 | | (220 ILCS 50/11) (from Ch. 111 2/3, par. 1611) |
17 | | Sec. 11. Penalties; liability; fund. |
18 | | (a) Every excavator person who, while engaging in |
19 | | excavation or demolition, willfully wilfully fails to comply |
20 | | with the Act by failing to provide the notice to the |
21 | | underground utility facility owners or operators in and of the |
|
| | 10300HB5546ham001 | - 49 - | LRB103 38732 SPS 72477 a |
|
|
1 | | underground facilities near the excavation or demolition area |
2 | | through JULIE the State-Wide One-Call Notice System as |
3 | | required by Section 4 , 5, or 6 of this Act shall be subject to |
4 | | a penalty of not more than up to $5,000 for each separate |
5 | | offense and shall be liable for the damage caused to the |
6 | | underground utility facility owners or operators of the |
7 | | facility . Every excavator person who fails to provide notice |
8 | | and willfully fails to comply with other provisions of this |
9 | | Act shall be subject to additional penalties of not more than |
10 | | up to $2,500 for each separate offense and shall be liable for |
11 | | the damage caused to the underground utility facility owners |
12 | | or operators of the facility . |
13 | | (b) Every excavator person who has provided the notice to |
14 | | the underground utility facility owners or operators of the |
15 | | underground utility facilities in and near the excavation or |
16 | | demolition area through JULIE the State-Wide One-Call Notice |
17 | | System as required by Section 4 or 6 of this Act, but otherwise |
18 | | willfully wilfully fails to comply with this Act, shall be |
19 | | subject to a penalty of not more than up to $2,500 for each |
20 | | separate offense and shall be liable for the damage caused to |
21 | | the underground utility facility owners or operators of the |
22 | | facility . |
23 | | (c) Every excavator person who, while engaging in |
24 | | excavation or demolition, has provided the notice to the |
25 | | underground utility facility owners or operators of the |
26 | | underground utility facilities in and near the excavation or |
|
| | 10300HB5546ham001 | - 50 - | LRB103 38732 SPS 72477 a |
|
|
1 | | demolition area through JULIE the State-Wide One-Call Notice |
2 | | System as required by Section 4 or 6 of this Act, but |
3 | | otherwise, while acting reasonably, damages any underground |
4 | | utility facilities, shall not be subject to a penalty, but |
5 | | shall be liable for the damage caused to the underground |
6 | | utility facility owners or operators of the facility provided |
7 | | the underground utility facility is properly marked as |
8 | | provided in Section 10 of this Act. |
9 | | (d) Every excavator person who provides notice to the |
10 | | underground utility facility owners or operators of the |
11 | | underground utility facilities through JULIE the State-Wide |
12 | | One-Call Notice System as a no show, incomplete, or an |
13 | | emergency locate request and the locate request is not a no |
14 | | show, incomplete, or an emergency locate request as defined in |
15 | | Section 2.6 of this Act shall be subject to a penalty of not |
16 | | more than up to $2,500 for each separate offense. |
17 | | (e) Underground utility facility owners or operators |
18 | | Owners and operators of underground utility facilities who |
19 | | willfully fail to comply with this Act , unless otherwise |
20 | | stated in this Section, shall be subject to a penalty of not |
21 | | more than $2,500 for each separate offense. A by a failure to |
22 | | respond or mark the approximate location of facilities by the |
23 | | dig start date and time on the notice an underground utility as |
24 | | required by subsection (h) of Section 4, subsection (c) (a) of |
25 | | Section 6, or Section 10 of this Act after being notified of |
26 | | planned or emergency excavation or demolition through JULIE |
|
| | 10300HB5546ham001 | - 51 - | LRB103 38732 SPS 72477 a |
|
|
1 | | the State-Wide One-Call Notice System , shall be subject to a |
2 | | penalty of not more than up to $5,000 for each separate |
3 | | offense. |
4 | | (1) Underground utility facility owners or operators |
5 | | who fail to provide a response to the positive response |
6 | | system by the dig start date and time on the notice, as |
7 | | required in subsection (b) of Section 5.1, on more than |
8 | | 10% of their weekly required responses for 4 or more |
9 | | consecutive weeks, shall be subject to a penalty of not |
10 | | more than $250 for each separate offense. |
11 | | (2) Underground utility facility owners or operators |
12 | | shall not be subject to a penalty where a delay in |
13 | | responding through the positive response system is caused |
14 | | by conditions beyond the reasonable control of such |
15 | | underground utility facility owners or operators. |
16 | | (f) As provided in Section 3 of this Act, all underground |
17 | | utility facility owners or operators of underground utility |
18 | | facilities who fail to join JULIE the State-Wide One-Call |
19 | | Notice System by January 1, 2003 shall be subject to a penalty |
20 | | of $100 per day for each separate offense. Every day an |
21 | | underground utility facility owner or operator fails to join |
22 | | JULIE the State-Wide One-Call Notice System is a separate |
23 | | offense. This subsection (f) does not apply to utilities |
24 | | operating facilities exclusively within the boundaries of a |
25 | | municipality with a population of at least 1,000,000 persons. |
26 | | (g) No underground utility facility owner or operator of |
|
| | 10300HB5546ham001 | - 52 - | LRB103 38732 SPS 72477 a |
|
|
1 | | underground utility facilities shall be subject to a penalty |
2 | | where a delay in marking or a failure to mark or properly mark |
3 | | the location of a facility an underground utility is caused by |
4 | | conditions beyond the reasonable control of such underground |
5 | | utility facility owner or operator. It is the responsibility |
6 | | of the underground utility facility owners or operators to |
7 | | demonstrate how the condition affected their ability to |
8 | | respond and caused it to become beyond the reasonable control. |
9 | | Each underground utility facility owner or operator shall |
10 | | staff in a manner that such underground utility facility owner |
11 | | or operator can respond by the dig start date and time on the |
12 | | notices within the underground utility facility owner's or |
13 | | operator's reasonable control. |
14 | | (h) Any entity that person who is neither an agent, |
15 | | employee, or authorized locating contractor of the underground |
16 | | utility facility owner or operator of the underground utility |
17 | | facility nor an excavator involved in the excavation or |
18 | | demolition activity that who removes, alters, or otherwise |
19 | | damages markings, flags, lathe with color ribbon, chalk, |
20 | | whiskers, or paint or stakes used to mark the location of |
21 | | facilities an underground utility other than during the course |
22 | | of the excavation or demolition for which the markings were |
23 | | made or before completion of the project shall be subject to a |
24 | | penalty up to $1,000 for each separate offense. |
25 | | (i) (Blank). |
26 | | (i-5) All parties who submit alleged violations to the |
|
| | 10300HB5546ham001 | - 53 - | LRB103 38732 SPS 72477 a |
|
|
1 | | Illinois Commerce Commission shall use the forms provided and |
2 | | should submit not later than 65 days after the discovery of the |
3 | | alleged violation. Any alleged violation submission received |
4 | | after the 65-day period shall be subject to a penalty of not |
5 | | more than $500 but not less than $100 per occurrence. |
6 | | Excavators shall not be subject to a penalty under this |
7 | | subsection when their decision to submit an alleged violation |
8 | | form later than the 65-day period is a result of receiving a |
9 | | damage claim from an underground utility facility owner or |
10 | | operator after the expiration of the excavator's 65-day period |
11 | | for submitting an alleged violation. |
12 | | (j) The Illinois Commerce Commission shall have the power |
13 | | and jurisdiction to, and shall, enforce the provisions of this |
14 | | Act. The Illinois Commerce Commission may impose |
15 | | administrative penalties as provided in this Section. The |
16 | | Illinois Commerce Commission may promulgate rules and develop |
17 | | enforcement policies in the manner provided by the Public |
18 | | Utilities Act in order to implement compliance with this Act. |
19 | | When a penalty is warranted, the following criteria shall be |
20 | | used in determining the magnitude of the penalty: |
21 | | (1) gravity of noncompliance; |
22 | | (2) culpability of offender; |
23 | | (3) history of noncompliance for the 18 months prior |
24 | | to the date of the incident; however, when determining |
25 | | noncompliance non-compliance the alleged violator's roles |
26 | | as underground utility facility operator or owner and the |
|
| | 10300HB5546ham001 | - 54 - | LRB103 38732 SPS 72477 a |
|
|
1 | | excavator person engaged in excavating shall be treated |
2 | | separately; |
3 | | (4) (blank); ability to pay penalty; |
4 | | (5) show of good faith of offender; |
5 | | (6) (blank); and ability to continue business; and |
6 | | (7) other special circumstances. |
7 | | (k) There is hereby created in the State treasury a |
8 | | special fund to be known as the Illinois Underground Utility |
9 | | Facilities Damage Prevention Fund. All penalties recovered by |
10 | | the Illinois Commerce Commission in any action under this |
11 | | Section shall be paid into the Fund and shall be distributed |
12 | | annually as a grant to JULIE the State-Wide One-Call Notice |
13 | | System to be used in safety and informational programs to |
14 | | reduce the number of incidents of damage to underground |
15 | | utility facilities in Illinois. The distribution shall be made |
16 | | during January of each calendar year based on the balance in |
17 | | the Illinois Underground Utility Facilities Damage Prevention |
18 | | Fund as of December 31 of the previous calendar year. In all |
19 | | such actions under this Section, the procedure and rules of |
20 | | evidence shall conform with the Code of Civil Procedure, and |
21 | | with rules of courts governing civil trials. |
22 | | (l) The Illinois Commerce Commission shall establish an |
23 | | Advisory Committee consisting of a representative from each of |
24 | | the following: utility operator, JULIE, excavator, |
25 | | municipality, and the general public , and a nonmunicipal |
26 | | public body . The Advisory Committee shall serve as a peer |
|
| | 10300HB5546ham001 | - 55 - | LRB103 38732 SPS 72477 a |
|
|
1 | | review panel for any contested penalties resulting from the |
2 | | enforcement of this Act. |
3 | | The members of the Advisory Committee shall be immune, |
4 | | individually and jointly, from civil liability for any act or |
5 | | omission done or made in performance of their duties while |
6 | | serving as members of such Advisory Committee, unless the act |
7 | | or omission was the result of willful and wanton misconduct. |
8 | | (m) If, after the Advisory Committee has considered a |
9 | | particular contested penalty and performed its review |
10 | | functions under this Act and the Illinois Commerce |
11 | | Commission's rules, there remains a dispute as to whether the |
12 | | Illinois Commerce Commission should impose a penalty under |
13 | | this Act, the matter shall proceed in the manner set forth in |
14 | | Article X of the Public Utilities Act, including the |
15 | | provisions governing judicial review. |
16 | | (Source: P.A. 96-714, eff. 1-1-10.) |
17 | | (220 ILCS 50/11.3) |
18 | | Sec. 11.3. Emergency telephone system outages; |
19 | | reimbursement. Any excavator person who negligently damages a |
20 | | an underground facility or CATS facility causing an emergency |
21 | | telephone system outage must reimburse the public safety |
22 | | agency that provides personnel to answer calls or to maintain |
23 | | or operate an emergency telephone system during the outage for |
24 | | the agency's costs associated with answering calls or |
25 | | maintaining or operating the system during the outage. For the |
|
| | 10300HB5546ham001 | - 56 - | LRB103 38732 SPS 72477 a |
|
|
1 | | purposes of this Section, "public safety agency" means the |
2 | | same as in Section 2.02 of the Emergency Telephone System Act. |
3 | | (Source: P.A. 92-149, eff. 1-1-02.) |
4 | | (220 ILCS 50/11.5) |
5 | | Sec. 11.5. Limitation on liability. |
6 | | (a) In joining JULIE the State-Wide One-Call Notice |
7 | | System , a municipality's liability, under any membership |
8 | | agreement rules and regulations, for the indemnification of |
9 | | (i) the entity that is in charge of or managing JULIE the |
10 | | System or any officer, agent, or employee of JULIE that entity |
11 | | or (ii) an underground utility facility owner or operator of |
12 | | JULIE a member of the System or any officer, agent, or employee |
13 | | of an underground utility facility owner or operator of JULIE |
14 | | a member of the System shall be limited to claims arising as a |
15 | | result of the acts or omissions of the municipality or its |
16 | | officers, agents, or employees or arising out of the |
17 | | operations of the municipality's underground utility |
18 | | facilities. |
19 | | (b) Subsection (a) shall not be construed to create any |
20 | | additional liability for a municipality in relation to any |
21 | | underground utility facility owner or operator of JULIE member |
22 | | of the System with which the municipality may have entered |
23 | | into a franchise agreement. If a municipality's liability for |
24 | | indemnification under a franchise agreement is narrower than |
25 | | under this Section, the franchise agreement controls. |
|
| | 10300HB5546ham001 | - 57 - | LRB103 38732 SPS 72477 a |
|
|
1 | | (Source: P.A. 90-481, eff. 8-17-97.) |
2 | | (220 ILCS 50/12) (from Ch. 111 2/3, par. 1612) |
3 | | Sec. 12. Noncompliance and enforcement action time frames. |
4 | | No action may be brought by the Illinois Commerce Commission |
5 | | under Section 11 of this Act unless commenced within 2 years |
6 | | after the date of the alleged violation of this Act. |
7 | | Beginning January 1, 2025, all parties submitting alleged |
8 | | violations to the Illinois Commerce Commission shall use the |
9 | | forms provided and shall submit no later than 65 days after the |
10 | | discovery of the alleged violation. Any report of an alleged |
11 | | violation received later than 65 days after the discovery of |
12 | | the alleged violation shall be subject to a penalty as |
13 | | provided for in Section 11. |
14 | | Beginning January 1, 2025, the Illinois Commerce |
15 | | Commission shall provide notice of investigation to the |
16 | | parties involved in the alleged violation report within 20 |
17 | | days after the receipt of the alleged violation report. |
18 | | Once a notice of investigation has been sent for all |
19 | | alleged violations reported on or after January 1, 2025, no |
20 | | further action may be brought by the Illinois Commerce |
21 | | Commission under Section 11 unless the notice of violation has |
22 | | been provided by the Illinois Commerce Commission staff to the |
23 | | entity determined to be in violation within 195 days after the |
24 | | date of the notice of investigation. For alleged violations |
25 | | that involve utility damage, personal injury or death, or |
|
| | 10300HB5546ham001 | - 58 - | LRB103 38732 SPS 72477 a |
|
|
1 | | property damage, an additional 130 days shall be allowed for |
2 | | the Illinois Commerce Commission staff to determine if the |
3 | | alleged entity was in violation. |
4 | | Beginning July 1, 2025, the Illinois Commerce Commission |
5 | | shall provide for public review a monthly report listing all |
6 | | of the reports of alleged violations it received in the prior |
7 | | month. The listing shall be available by the end of the |
8 | | violations report. The listing shall be available by the end |
9 | | of second full week for all reports from the previous month. |
10 | | The listing shall, at a minimum, include: (1) the name of the |
11 | | party submitting the alleged violation; (2) the name of the |
12 | | party and the name of the project owner that is alleged to be |
13 | | in violation; (3) the date the alleged violation report is |
14 | | submitted; and (4) the Section or Sections of the Act |
15 | | applicable to the submitted alleged violation. |
16 | | JULIE, Inc., may submit reports to the Illinois Commerce |
17 | | Commission for alleged violations of Section 5.1. |
18 | | (Source: P.A. 86-674.) |
19 | | (220 ILCS 50/13) (from Ch. 111 2/3, par. 1613) |
20 | | Sec. 13. Mandamus or injunction. Where public safety or |
21 | | the preservation of uninterrupted, necessary facilities |
22 | | utility service or community antenna television system service |
23 | | is endangered by any excavator person engaging in excavation |
24 | | or demolition in a negligent or unsafe manner which has |
25 | | resulted in or is likely to result in damage to underground |
|
| | 10300HB5546ham001 | - 59 - | LRB103 38732 SPS 72477 a |
|
|
1 | | utility facilities or CATS facilities or proposing to use |
2 | | procedures for excavation or demolition which are likely to |
3 | | result in damage to underground utility facilities or CATS |
4 | | facilities, or where the underground utility facility owner or |
5 | | operator of underground utility facilities or CATS facilities |
6 | | endangers an excavator by willfully failing to respond to a |
7 | | notice locate request , the underground utility facility owner |
8 | | or operator of such facilities or the excavator or the State's |
9 | | Attorney or the Illinois Commerce Commission at the request of |
10 | | the underground utility facility owner or operator of such |
11 | | facilities or the excavator may commence an action in the |
12 | | circuit court for the county in which the excavation or |
13 | | demolition is occurring or is to occur, or in which the person |
14 | | or entity complained of has its his principal place of |
15 | | business or resides, for the purpose of having such negligent |
16 | | or unsafe excavation or demolition stopped and prevented or to |
17 | | compel the marking of underground utilities facilities or CATS |
18 | | facilities, either by mandamus or injunction. |
19 | | (Source: P.A. 92-179, eff. 7-1-02.) |
20 | | (220 ILCS 50/14) (from Ch. 111 2/3, par. 1614) |
21 | | Sec. 14. Home rule. The regulation of underground utility |
22 | | facilities and CATS facilities damage prevention, as provided |
23 | | for in this Act, is an exclusive power and function of the |
24 | | State. A home rule unit may not regulate underground utility |
25 | | facilities and CATS facilities damage prevention, as provided |
|
| | 10300HB5546ham001 | - 60 - | LRB103 38732 SPS 72477 a |
|
|
1 | | for in this Act. All units of local government, including home |
2 | | rule units that are not municipalities of more than 1,000,000 |
3 | | persons operating its own One-Call Notice System , must comply |
4 | | with the provisions of this Act. To this extent, this Section |
5 | | is a denial and limitation of home rule powers and functions |
6 | | under subsection (h) of Section 6 of Article VII of the |
7 | | Illinois Constitution. A home rule municipality of more than |
8 | | 1,000,000 persons may regulate underground utility facilities |
9 | | and CATS facilities damage prevention. |
10 | | (Source: P.A. 99-121, eff. 7-23-15.) |
11 | | (220 ILCS 50/2.1 rep.) |
12 | | (220 ILCS 50/2.1.3 rep.) |
13 | | (220 ILCS 50/2.1.4 rep.) |
14 | | (220 ILCS 50/2.1.5 rep.) |
15 | | (220 ILCS 50/2.1.6 rep.) |
16 | | (220 ILCS 50/2.1.9 rep.) |
17 | | (220 ILCS 50/2.1.10 rep.) |
18 | | (220 ILCS 50/2.2 rep.) |
19 | | (220 ILCS 50/2.3 rep.) |
20 | | (220 ILCS 50/2.4 rep.) |
21 | | (220 ILCS 50/2.5 rep.) |
22 | | (220 ILCS 50/2.6 rep.) |
23 | | (220 ILCS 50/2.7 rep.) |
24 | | (220 ILCS 50/2.8 rep.) |
25 | | (220 ILCS 50/2.9 rep.) |
|
| | 10300HB5546ham001 | - 61 - | LRB103 38732 SPS 72477 a |
|
|
1 | | (220 ILCS 50/2.10 rep.) |
2 | | (220 ILCS 50/2.11 rep.) |
3 | | (220 ILCS 50/5 rep.) |
4 | | Section 10. The Illinois Underground Utility Facilities |
5 | | Damage Prevention Act is amended by repealing Sections 2.1, |
6 | | 2.1.3, 2.1.4, 2.1.5, 2.1.6, 2.1.9, 2.1.10, 2.2, 2.3, 2.4, 2.5, |
7 | | 2.6, 2.7, 2.8, 2.9, 2.10, 2.11, and 5. |
8 | | Section 99. Effective date. This Act takes effect January |
9 | | 1, 2025.". |