3 | | Sec. 15A-10. Definitions. As used in this Article: |
4 | | "Delivery system" means the design and construction |
5 | | approach used to develop and construct a project. |
6 | | "Design-build" means a delivery system that provides |
7 | | responsibility within a single contract for the furnishing of |
8 | | architecture, engineering, land surveying, and related |
9 | | services, as required, and the labor, materials, equipment, |
10 | | and other construction services for the project. |
11 | | "Design-build contract" means a contract for a public |
12 | | project under this Article between a school district and a |
13 | | design-build entity to furnish: architecture, engineering, |
14 | | land surveying, public art or interpretive exhibits, and |
15 | | related services, as required, and the labor, materials, |
16 | | equipment, and other construction services for the project. |
17 | | "Design-build entity" means an individual, sole |
18 | | proprietorship, firm, partnership, joint venture, corporation, |
19 | | professional corporation, or other entity that proposes to |
20 | | design and construct any public project under this Article. |
21 | | "Design professional" means an individual, sole |
22 | | proprietorship, firm, partnership, joint venture, corporation, |
23 | | professional corporation, or other entity that offers services |
24 | | under the Illinois Architecture Practice Act of 1989, the |
25 | | Professional Engineering Practice Act of 1989, the Structural
|
|
| | 10300SB1570ham001 | - 3 - | LRB103 05684 RJT 60871 a |
|
|
1 | | Engineering Practice Act of 1989, or the Illinois Professional |
2 | | Land Surveyor Act of 1989. |
3 | | "Evaluation criteria" means the requirements for the |
4 | | separate phases of the selection process as set forth in this |
5 | | Article and may include the specialized experience, technical |
6 | | qualifications and competence, capacity to perform, past |
7 | | performance, experience with similar projects, assignment of
|
8 | | personnel to the project, and other appropriate factors. |
9 | | "Proposal" means the offer to enter into a design-build |
10 | | contract as submitted by a design-build entity in accordance |
11 | | with this Article. |
12 | | "Public art designer" means an individual, sole |
13 | | proprietorship, firm, partnership, joint venture, corporation, |
14 | | professional corporation, or other entity that has |
15 | | demonstrated experience with the design and fabrication of |
16 | | public art, including any media that has been planned and |
17 | | executed with the intention of being staged in the physical |
18 | | public domain outside and accessible to all or any art that is |
19 | | exhibited in a public space, including publicly accessible |
20 | | buildings, or interpretive exhibits, including communication |
21 | | media that is designed to engage, excite, inform, relate, or |
22 | | reveal the intrinsic nature or indispensable quality of a |
23 | | topic or story being presented. |
24 | | "Request for proposal" means the document used by the |
25 | | school district to solicit proposals for a design-build |
26 | | contract. |
|
| | 10300SB1570ham001 | - 4 - | LRB103 05684 RJT 60871 a |
|
|
1 | | "Scope and performance criteria" means the requirements |
2 | | for the public project, such as the intended usage, capacity, |
3 | | size, scope, quality and performance standards, life-cycle |
4 | | costs, and other programmatic criteria that are expressed in |
5 | | performance-oriented and quantifiable specifications and |
6 | | drawings that can be reasonably inferred and are suited to |
7 | | allow a design-build entity to develop a proposal. |
8 | | (105 ILCS 5/15A-15 new) |
9 | | Sec. 15A-15. Solicitation of proposals. |
10 | | (a) A school district may enter into design-build |
11 | | contracts. In addition to the requirements set forth by the |
12 | | school board, if the school district elects to use the |
13 | | design-build delivery method, it must issue a notice of intent |
14 | | to receive proposals for the project at least 14 days before |
15 | | issuing the request for the proposal. The school district must |
16 | | publish the advance notice in the manner prescribed by the |
17 | | school board, which must include posting the advance notice |
18 | | online on its website. The school district may publish the |
19 | | notice in construction industry publications or post the |
20 | | notice on construction industry websites. A brief description |
21 | | of the proposed procurement must be included in the notice. |
22 | | The school district must provide a copy of the request for |
23 | | proposal to any party requesting a copy. |
24 | | (b) The request for proposal must be prepared for each |
25 | | project and must contain, without limitation, the following |
|
| | 10300SB1570ham001 | - 5 - | LRB103 05684 RJT 60871 a |
|
|
1 | | information: |
2 | | (1) The name of the school district. |
3 | | (2) A preliminary schedule for the completion of the |
4 | | contract. |
5 | | (3) The proposed budget for the project, the source of |
6 | | funds, and the currently available funds at the time the |
7 | | request for proposal is submitted. |
8 | | (4) Prequalification criteria for design-build |
9 | | entities wishing to submit proposals. The school district |
10 | | must include, at a minimum, its normal qualifications, |
11 | | licensing, registration, and other requirements; however, |
12 | | nothing precludes the use of additional prequalification |
13 | | criteria by the school district. |
14 | | (5) Material requirements of the contract, such as the |
15 | | proposed terms and conditions, required performance and |
16 | | payment bonds, insurance, and the entity's plan to comply |
17 | | with the utilization goals for business enterprises |
18 | | established in the Business Enterprise for Minorities, |
19 | | Women, and Persons with Disabilities Act and with Section |
20 | | 2-105 of the Illinois
Human Rights Act. |
21 | | (6) The performance criteria. |
22 | | (7) The evaluation criteria for each phase of the |
23 | | solicitation. Price may not be used as a factor in the |
24 | | evaluation of Phase I proposals. |
25 | | (8) The number of entities that will be considered for |
26 | | the technical and cost evaluation phase. |
|
| | 10300SB1570ham001 | - 6 - | LRB103 05684 RJT 60871 a |
|
|
1 | | (c) The school district may include any other relevant |
2 | | information that it chooses to supply. The design-build entity |
3 | | may rely upon the accuracy of this documentation in the |
4 | | development of its proposal. |
5 | | (d) The date that proposals are due must be at least 21 |
6 | | calendar days after the date of the issuance of the request for |
7 | | proposal. If the cost of the project is estimated to exceed |
8 | | $12,000,000, then the proposal due date must be at least 28 |
9 | | calendar days after the date of the issuance of the request for |
10 | | proposal. The school district must include in the request for |
11 | | proposal a minimum of 30 days to develop the Phase II |
12 | | submissions after the selection of entities from the Phase I |
13 | | evaluation is completed. |
14 | | (105 ILCS 5/15A-20 new) |
15 | | Sec. 15A-20. Development of scope and performance |
16 | | criteria. |
17 | | (a) The school district must develop, with the assistance |
18 | | of a licensed design professional or public art designer, a |
19 | | request for proposal, which must include scope and performance |
20 | | criteria. The scope and performance criteria must be in |
21 | | sufficient detail and contain adequate information to |
22 | | reasonably apprise the qualified design-build entities of the |
23 | | school district's overall programmatic needs and goals, |
24 | | including criteria, general budget parameters, schedule, and |
25 | | delivery
requirements. |
|
| | 10300SB1570ham001 | - 7 - | LRB103 05684 RJT 60871 a |
|
|
1 | | (b) Each request for proposal must also include a |
2 | | description of the level of design to be provided in the |
3 | | proposals. This description must include the scope and type of |
4 | | renderings, drawings, and specifications that, at a minimum, |
5 | | will be required by the school district to be produced by the |
6 | | design-build entities. |
7 | | (c) The scope and performance criteria must be prepared by |
8 | | a design professional or public art designer who is an |
9 | | employee of the school district, or the school district may |
10 | | contract with an independent design professional or public art |
11 | | designer selected under the Local Government Professional |
12 | | Services Selection Act to provide these services. |
13 | | (d) The design professional or public art designer that |
14 | | prepares the scope and performance criteria is prohibited from |
15 | | participating in any design-build entity proposal for the |
16 | | project. |
17 | | (e) The design-build contract may be conditioned upon |
18 | | subsequent refinements in scope and price and may allow the |
19 | | school district to make modifications in the project scope |
20 | | without invalidating the design-build contract. |
21 | | (105 ILCS 5/15A-25 new) |
22 | | Sec. 15A-25. Procedures for selection. |
23 | | (a) The school district must use a 2-phase procedure for |
24 | | the selection of the successful design-build entity. Phase I |
25 | | of the procedure must evaluate and shortlist the design-build |
|
| | 10300SB1570ham001 | - 8 - | LRB103 05684 RJT 60871 a |
|
|
1 | | entities based on qualifications, and Phase II must evaluate |
2 | | the technical and cost proposals. |
3 | | (b) The school district must include in the request for |
4 | | proposal the evaluating factors to be used in Phase I. These |
5 | | factors are in addition to any prequalification requirements |
6 | | of design-build entities that the school district has set |
7 | | forth. Each request for proposal must establish the relative |
8 | | importance assigned to each evaluation factor and subfactor, |
9 | | including any weighting of criteria to be employed by the |
10 | | school district. The school district must maintain a record of |
11 | | the evaluation scoring to be disclosed in event of a protest |
12 | | regarding the solicitation. |
13 | | The school district must include the following criteria in |
14 | | every Phase I evaluation of design-build entities: |
15 | | (1) experience of personnel; |
16 | | (2) successful experience with similar project types; |
17 | | (3) financial capability; |
18 | | (4) timeliness of past performance; |
19 | | (5) experience with similarly sized projects; |
20 | | (6) successful reference checks of the firm; |
21 | | (7) commitment to assign personnel for the duration of |
22 | | the project and qualifications of the entity's |
23 | | consultants; and |
24 | | (8) ability or past performance in meeting or |
25 | | exhausting good faith efforts to meet the utilization |
26 | | goals for business enterprises established in the Business |
|
| | 10300SB1570ham001 | - 9 - | LRB103 05684 RJT 60871 a |
|
|
1 | | Enterprise for Minorities, Women, and Persons with |
2 | | Disabilities Act and with Section 2-105 of the Illinois |
3 | | Human Rights Act. |
4 | | The school district may include any additional, relevant
|
5 | | criteria in Phase I that it deems necessary for a proper |
6 | | qualification review. |
7 | | The school district may not consider a design-build entity |
8 | | for evaluation or an award if the entity has any pecuniary |
9 | | interest in the project or has other relationships or |
10 | | circumstances, such as long-term leasehold, mutual |
11 | | performance, or development contracts with the school |
12 | | district, that may give the design-build entity a financial or |
13 | | tangible advantage over other design-build entities in the |
14 | | preparation, evaluation, or performance of the design-build |
15 | | contract or that create the appearance of impropriety. A |
16 | | design-build entity shall not be disqualified under this |
17 | | Section solely due to having previously been awarded a project |
18 | | or projects under any applicable public procurement law of the |
19 | | State. No proposal may be considered that does not include an |
20 | | entity's plan to comply with the requirements established in |
21 | | the Business Enterprise for Minorities, Women, and Persons |
22 | | with Disabilities Act, for both the design and construction |
23 | | areas of performance, and with Section 2-105 of the Illinois |
24 | | Human Rights Act. |
25 | | Upon completion of the qualification evaluation, the |
26 | | school district must create a shortlist of the most highly |
|
| | 10300SB1570ham001 | - 10 - | LRB103 05684 RJT 60871 a |
|
|
1 | | qualified design-build entities. The school district, in its |
2 | | discretion, is not required to shortlist the maximum number of |
3 | | entities as identified for Phase II evaluation if no less than |
4 | | 2 design-build entities nor more than 6 are selected to submit |
5 | | Phase II proposals. If a school district receives one response |
6 | | to Phase I, nothing herein shall prohibit the school district |
7 | | from proceeding with a Phase II evaluation of the single |
8 | | respondent, if the school district, in its discretion, finds |
9 | | proceeding to be in its best interest. |
10 | | The school district must notify the entities selected for |
11 | | the shortlist in writing. This notification must commence the |
12 | | period for the preparation of the Phase II technical and cost |
13 | | evaluations. The school district must allow sufficient time |
14 | | for the shortlist entities to prepare their Phase II |
15 | | submittals considering the scope and detail requested by the |
16 | | school district. |
17 | | (c) The school district must include in the request for |
18 | | proposal the evaluating factors to be used in the technical |
19 | | and cost submission components of Phase II. Each request for |
20 | | proposal must establish, for both the technical and cost |
21 | | submission components of Phase II, the relative importance |
22 | | assigned to each evaluation factor and subfactor, including |
23 | | any weighting of criteria to be employed by the school |
24 | | district. The school district must maintain a record of the |
25 | | evaluation scoring to be disclosed in event of a protest |
26 | | regarding the solicitation. |
|
| | 10300SB1570ham001 | - 11 - | LRB103 05684 RJT 60871 a |
|
|
1 | | The school district must include the following criteria in |
2 | | every Phase II technical evaluation of design-build entities: |
3 | | (1) compliance with objectives of the project; |
4 | | (2) compliance of proposed services to the request for |
5 | | proposal requirements; |
6 | | (3) quality of products or materials proposed; |
7 | | (4) quality of design parameters; |
8 | | (5) design concepts; |
9 | | (6) innovation in meeting the scope and performance |
10 | | criteria; and |
11 | | (7) constructability of the proposed project. |
12 | | The school district may include any additional relevant |
13 | | technical evaluation factors it deems necessary for proper |
14 | | selection. |
15 | | The school district must include the following criteria in |
16 | | every Phase II cost evaluation: the total project cost, the |
17 | | construction costs, and the time of completion. The school |
18 | | district may include any additional relevant technical |
19 | | evaluation factors it deems necessary for proper selection. |
20 | | The total project cost criteria weighting factor may not |
21 | | exceed 30%. |
22 | | The school district must directly employ or retain a |
23 | | licensed design professional or a public art designer to |
24 | | evaluate the technical and cost submissions to determine if |
25 | | the technical submissions are in accordance with generally |
26 | | accepted industry standards.
Upon completion of the technical |
|
| | 10300SB1570ham001 | - 12 - | LRB103 05684 RJT 60871 a |
|
|
1 | | submissions and cost submissions evaluation, the school |
2 | | district may award the design-build contract to the highest |
3 | | overall ranked entity. |
4 | | (105 ILCS 5/15A-30 new) |
5 | | Sec. 15A-30. Small projects. In any case in which the |
6 | | total overall cost of the project is estimated to be |
7 | | $12,000,000 or less, the school district may combine the |
8 | | 2-phase procedure for selection described in Section 15A-25 |
9 | | into one combined step if all the requirements of evaluation |
10 | | are performed in accordance with Section 15A-25. |
11 | | (105 ILCS 5/15A-35 new) |
12 | | Sec. 15A-35. Submission of proposals. Proposals must be |
13 | | properly identified and sealed. Proposals may not be reviewed |
14 | | until after the deadline for submission has passed as set |
15 | | forth in the request for proposal. |
16 | | Proposals must include a bid bond in the form and security |
17 | | as designated in the request for proposal. Proposals must also |
18 | | contain a separate sealed envelope with the cost information |
19 | | within the overall proposal submission. Proposals must include |
20 | | a list of all design professionals, public art
designers, and |
21 | | other entities to which any work may be subcontracted during |
22 | | the performance of the contract. |
23 | | Proposals must meet all material requirements of the |
24 | | request for proposal, or they may be rejected as |
|
| | 10300SB1570ham001 | - 13 - | LRB103 05684 RJT 60871 a |
|
|
1 | | nonresponsive. The school district may reject any and all |
2 | | proposals. |
3 | | The drawings and specifications of the proposal may remain |
4 | | the property of the design-build entity. |
5 | | The school district must review the proposals for |
6 | | compliance with the performance criteria and evaluation |
7 | | factors. |
8 | | Proposals may be withdrawn prior to evaluation for any |
9 | | cause. After evaluation begins by the school district, clear |
10 | | and convincing evidence of error is required for withdrawal. |
11 | | After a response to a request for qualifications or a |
12 | | request for proposal has been submitted under this Section, a |
13 | | design-build entity may not replace, remove, or otherwise |
14 | | modify any firm identified as a member of the proposer's team |
15 | | unless authorized to do so by the school district. |
16 | | (105 ILCS 5/15A-40 new) |
17 | | Sec. 15A-40. Award; performance. The school district may |
18 | | award the contract to the highest overall ranked design-build |
19 | | entity. Notice of award must be made in writing. Unsuccessful |
20 | | design-build entities must also be notified in writing. The |
21 | | school district may not request a best and final offer after |
22 | | the receipt of proposals of all qualified design-build |
23 | | entities. The school district may negotiate with the selected |
24 | | design-build entity after the award, but prior to contract |
25 | | execution, for the purpose of securing better terms than |
|
| | 10300SB1570ham001 | - 14 - | LRB103 05684 RJT 60871 a |
|
|
1 | | originally proposed if the salient features of the request for |
2 | | proposal are not diminished. |
3 | | A design-build entity and associated design professionals |
4 | | must
conduct themselves in accordance with the relevant laws |
5 | | of this State and the related provisions of the Illinois |
6 | | Administrative Code. |
7 | | (105 ILCS 5/15A-45 new) |
8 | | Sec. 15A-45. Evaluation and report. At the end of every |
9 | | 6-month period following the contract award, and again prior |
10 | | to final contract payout and closure, a selected design-build |
11 | | entity must detail, in a written report submitted to the |
12 | | school district, its efforts and success in implementing the |
13 | | entity's plan to comply with the utilization goals for |
14 | | business enterprises established in the Business Enterprise |
15 | | for Minorities, Women, and Persons with Disabilities Act and |
16 | | the provisions of Section 2-105 of the Illinois Human Rights |
17 | | Act. |
18 | | (105 ILCS 5/15A-50 new) |
19 | | Sec. 15A-50. Exception. Nothing in this Article prevents a |
20 | | school district from using a qualification-based selection |
21 | | process for design professionals or construction managers for |
22 | | design-build projects. |
23 | | (105 ILCS 5/15A-90 new) |