(30 ILCS 538/1-55)
    (Section scheduled to be repealed on January 1, 2027)
    Sec. 1-55. Transition to design-bid-build. At the completion of design development, the progressive design-build entity must provide a firm fixed price. The State construction agency reserves the right to transition the project to the design-bid-build method if the fixed price exceeds the project budget, the progressive design-build entity's proposed schedule is unreasonable, or if transitioning to the design-bid-build method is in the best interests of the State.
(Source: P.A. 103-865, eff. 8-9-24.)