(70 ILCS 1505/26.10-9) Sec. 26.10-9. Small design-build projects. In any case where the total overall cost of the
project is estimated to be less than $12,000,000, the Chicago Park District
may combine
the two-phase procedure for design-build selection described in Section 26.10-8 into one combined
step, provided that all the requirements of evaluation are performed in
accordance with Section 26.10-8.
(Source: P.A. 96-777, eff. 8-28-09.) |