(605 ILCS 5/6-406) (from Ch. 121, par. 6-406)
Sec. 6-406.
When a joint contract has been made in accordance with Section
6-402, and if the commissioner of either of such road districts, after
reasonable notice in writing from the commissioner of any other road
district, neglects or refuses to construct or repair any bridge or culvert,
the commissioner so giving notice, after constructing or repairing the
same, may recover by suit such amount as may have been contracted for in
accordance with Section 6-402 of this Code, of the expense of so
constructing or repairing such bridge or culvert together with costs of
suit and interest from time of completion thereof, from the road district
so neglecting or refusing.
(Source: P.A. 84-962.)
|