(630 ILCS 10/50)
    (Section scheduled to be repealed on July 1, 2032)
    Sec. 50. Construction Manager/General Contractor contract.
    (a) The Construction Manager/General Contractor contract shall divide the Construction Manager/General Contractor services into 2 phases. The first phase shall address preconstruction services and the procedures the parties shall follow to finalize the contract terms for the second phase. The second phase shall address the Construction Manager/General Contractor's construction of the transportation facility for a lump sum or a guaranteed maximum price.
    (b) A Construction Manager/General Contractor contract shall include provisions regarding the following:
        (1) the Construction Manager/General Contractor's
    
provision of preconstruction services during the first phase of the contract, including the Construction Manager/General Contractor's compensation for those services;
        (2) a requirement that, during the first phase of
    
the contract, the Construction Manager/General Contractor shall use a competitive bidding process to procure subcontracts for at least the minimum percentage of construction work specified in the request for proposals, provided that:
            (A) compliance with this requirement shall be
        
based on an estimated cost for the construction work approved by the Transportation Agency before the start of the competitive bidding process; and
            (B) the Construction Manager/General Contractor
        
may not use subcontracts with its wholly or partially owned subsidiaries, parent companies, or affiliates to satisfy this obligation;
        (3) the process the Transportation Agency and the
    
Construction Manager/General Contractor shall use to determine a lump sum or guaranteed maximum price for the construction work, including a requirement that the Transportation Agency conduct an independent cost estimate for the construction work; and
        (4) grounds for termination of the Construction
    
Manager/General Contractor contract, including the Transportation Agency's right to terminate the contract and not proceed with the construction phase of the project if the Transportation Agency and the Construction Manager/General Contractor are unable to negotiate a lump sum or guaranteed maximum price for the construction work.
    (c) In addition to the provisions under subsection (b) of this Section, a Construction Manager/General Contractor contract may include any other provisions the Transportation Agency determines are necessary or appropriate, including, but not limited to, provisions regarding the following:
        (1) liability for damages and nonperformance;
        (2) events of default and the rights and remedies
    
available to the Construction Manager/General Contractor and the Transportation Agency in the event of a default or delay;
        (3) the identification of any technical
    
specifications that the Construction Manager/General Contractor must comply with when aiding the Transportation Agency with developing plans or performing construction work;
        (4) required performance and payment security for
    
the construction phase of the contract;
        (5) the terms and conditions of indemnification and
    
minimum insurance requirements; and
        (6) any other terms and conditions the
    
Transportation Agency deems necessary.
    (d) If the Construction Manager/General Contractor contract is terminated for any reason, the Transportation Agency, in its sole discretion, may readvertise the Construction Manager/General Contractor contract under this Act or use any other authorized procurement method to complete the transportation facility or any portion of the transportation facility. Once the contract is terminated, the Transportation Agency may use any work product developed by the Construction Manager/General Contractor to complete the transportation facility.
(Source: P.A. 102-1094, eff. 6-15-22.)