(735 ILCS 30/25-7-103.91)
(was 735 ILCS 5/7-103.91)
Sec. 25-7-103.91. Quick-take; Madison County. Quick-take proceedings under Article 20 may be used
for a period of 12 months after July 30, 1999,
by Madison County, for the acquisition of
property necessary for the purpose of approximately 2.4 miles of roadwork
commencing at the intersection of Illinois Route 143 northerly over, adjacent
to, and near the location of County Highway 19 (locally known as Birch Drive)
to the intersection of Buchts Road, traversing through land sections 19, 20,
29, 30, and 31 of Ft. Russell Township, the work to consist of excavation, fill
placement, concrete structures, and an aggregate and bituminous base with
bituminous binder and surfacing.
(Source: P.A. 94-1055, eff. 1-1-07.)
|