Illinois General Assembly

  Bills & Resolutions  
  Compiled Statutes  
  Public Acts  
  Legislative Reports  
  IL Constitution  
  Legislative Guide  
  Legislative Glossary  

 Search By Number
 (example: HB0001)
Search Tips

Search By Keyword

Illinois Compiled Statutes

 ILCS Listing   Public Acts  Search   Guide   Disclaimer

Information maintained by the Legislative Reference Bureau
Updating the database of the Illinois Compiled Statutes (ILCS) is an ongoing process. Recent laws may not yet be included in the ILCS database, but they are found on this site as Public Acts soon after they become law. For information concerning the relationship between statutes and Public Acts, refer to the Guide.

Because the statute database is maintained primarily for legislative drafting purposes, statutory changes are sometimes included in the statute database before they take effect. If the source note at the end of a Section of the statutes includes a Public Act that has not yet taken effect, the version of the law that is currently in effect may have already been removed from the database and you should refer to that Public Act to see the changes made to the current law.

220 ILCS 50/5.1

    (220 ILCS 50/5.1)
    (This Section may contain text from a Public Act with a delayed effective date)
    Sec. 5.1. Positive response system.
    (a) Beginning January 1, 2026, an excavator shall confirm through the positive response system prior to excavation or demolition that all underground utility facility owners or operators that are identified on the notice have provided a status update, responded, or marked or provided an all-clear notification.
    (b) Beginning January 1, 2026, an underground utility facility owner or operator shall respond through the positive response system by the dig start date and time on the notice with an appropriate and accurate system code. A minimal delay not to exceed one hour or when the marking of the facilities is complete, whichever is longer, in reporting a system code in response to an emergency request shall not be a violation of this Section.
    (c) If an underground utility facility owner or operator fails to respond or provide a status update through the positive response system by the dig start date and time on the notice, or a later time as otherwise agreed upon and submitted through the positive response system, JULIE shall transmit an additional notification to that underground utility facility owner or operator and shall continue to send out daily notifications until the positive response system receives a response confirming compliance with this Section.
    (d) If an underground utility facility owner or operator fails to respond or provide a status update to the positive response system, the excavator may proceed after providing a no show or incomplete request through JULIE. The notified underground utility facility owners or operators shall respond by the dig start date and time on the notice.
    (e) If all notified underground utility facility owners or operators have responded as "marked" or "clear" prior to the expiration of the dig start date and time on the notice, the wait time shall be considered expired and no additional wait time is required prior to commencing with the excavation or demolition work listed on the notice.
(Source: P.A. 103-614, eff. 1-1-25.)